ADDENDUM #1 DATE: PROJECT NO: PROJECT:...

129
ADDENDUM #1 DATE: January 22, 2018 PROJECT NO: 17471 PROJECT: Fairfield Junior High Air Conditioning The following revision, additions, deletions, and/or items of clarification shall hereby be included as an integral part of the Contract Documents for the above-listed project and shall be fully binding. All other requirements shall remain in effect of the original plans and specification. DIVISION – 22, 23 & 26 GENERAL 1. Add flow meter to the 3” copper main water building supply. Tie into the building BMS system. Main water supply line is located in the boiler storage room. 2. DRAWINGS SHEET - A100 1. Change title block to print black and white. See attached SHEET - A101 1. Clean up overlapping text. See attached 2. Change title block to print black and white and change school location. SHEET - M401 1. There is an existing 6” roof drain line running east to west through the fan room that will need to be rerouted around the new AH-4. 2. There is an existing 6” roof drain line running east to west through the fan room that will need to be rerouted around the new AH-1. SHEET - MD402 1. ADD TO KEYED NOTE 2: Salvage back to Owner. SHEET - M601 1. Add gravity damper schedule. See attached SPECIFICATIONS SECTION - DIVISION 26 ELECTRICAL SPECIFICATIONS 1. SEE ATTACHED DIVISION 26 SPECIFICATIONS

Transcript of ADDENDUM #1 DATE: PROJECT NO: PROJECT:...

ADDENDUM #1

DATE: January 22, 2018

PROJECT NO: 17471

PROJECT: Fairfield Junior High Air Conditioning

The following revision, additions, deletions, and/or items of clarification shall hereby be included as an integral part of the Contract Documents for the above-listed project and shall be fully binding. All other requirements shall remain in effect of the original plans and specification.

DIVISION – 22, 23 & 26

GENERAL1. Add flow meter to the 3” copper main water building supply. Tie into the building BMS system. Main water

supply line is located in the boiler storage room. 2.

DRAWINGS

SHEET - A1001. Change title block to print black and white. See attached

SHEET - A1011. Clean up overlapping text. See attached2. Change title block to print black and white and change school location.

SHEET - M4011. There is an existing 6” roof drain line running east to west through the fan room that will need to be

rerouted around the new AH-4.2. There is an existing 6” roof drain line running east to west through the fan room that will need to be

rerouted around the new AH-1.

SHEET - MD4021. ADD TO KEYED NOTE 2: Salvage back to Owner.

SHEET - M6011. Add gravity damper schedule. See attached

SPECIFICATIONS

SECTION - DIVISION 26 ELECTRICAL SPECIFICATIONS1. SEE ATTACHED DIVISION 26 SPECIFICATIONS

Page 2 of 2Addendum #1

SECTION - T.O.C1. Delete 230800 Commissioning of HVAC

SECTION - 23 34231. Section 23 3423 2.2 Delete Multiple Fan Arrays. Multiple fan arrays are specified in 23 7313 and are part

of the air handling unit.

SECTION - 23 7313 Custom Factory Fabricated Pump House1. 23 7313 2.2 J1 – Change “Wire all circuits to a common main panel terminal block for a single point

connection of power to the unit” to: “Wire all circuits to an electrical panel. Provide electrical panel which complies with Specification Section 26 2416 and as sized and scheduled on the electrical drawings for a single point connection”.

PRIOR APPROVALS

The following manufacturers, trade names and products are allowed to bid on a name brand only basis with the provision that they completely satisfy all and every requirement of the drawings, specifications and all addenda shall conform to the design, quality and standards specified, established and required for the complete and satisfactory installation and performance of the building and all its respective parts.

Item Manufacturer Comments

Control Dampers GreenheckEvaporative Coolers Premier, NeptronicVibration and Seismic Controls SRSPump House Kysor Panel SystemsPumps TigerflowWall Exhaust Fans CarnesLouvers CESCO

GENERAL NOTES

SECTION 323133 - CHAIN LINK FENCES AND GATES

PART 1 - GENERAL

1.1 RELATED DOCUMENTSA. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specifcation Sections, apply to this Section.

1.2 SUMMARYA. This Section includes the following:

1. Chain-Link Fences: Industrial2. Gates: Horizontal slide and swing.

B. Related Sections include the following:1. Section 033000 "Cast-in-Place Concrete" for concrete2. Section 312000 "Earth Moving" for site excavation, fill, and backfill where chainlink fence and gates are located.

1.3 SUBMITTALSA. Product Data: Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for chain-link fences and gates.

1. Fence and gate posts, rails, and fittings.2. Chain-link fabric, reinforcements, and attachments.3. Gates and hardware.4. Accessories: Privacy slats, if used

B. Shop drawings: show locations of fences, gates, posts, rails, tension wires, details of extended posts, extension arms, gate swing, or other operation, hardware, and accessories. Indicate materials, dimensions, sizes, weights, and finishes of components. Include plans, gate elevations, sections, details of post anchorage, attachment, bracing, and other required installation and operational clearances.

1.4 QUALITY ASSURANCEA. Installer Qualifications: Engage an experienced Installer who has at least three years' experience and has completed at least five chain link fence projects with same material and of similar scope to that indicated for this Project with a successful construction record of in-service performance.B. Single-Source Responsibility: Obtain chain link fences and gates, including accessories, fittings, and fastenings, from a single source.

1.5 PROJECT CONDITIONSA. Field Measurements: Verify layout information for fences and gates shown on the Drawings in relation to the property survey and existing structures.

Verify dimensions by field measurements.

PART 2 - PRODUCTS

2.1 INDUSTRIAL FENCEA. Selvage: Knuckled at one selvage and twisted at the other for 2-inch and 2-1/8-inch mesh sizes and heights above 60 inches.B. Steel Chain-Link Fence Fabric: Fabricated in one-piece widths for fencing 12 feet and less in height to comply with Chain Link Fence Manufactures Institute (CLFMI) "Product Manual" and with requirements indicated:

1. Mesh and Wire Size: 2-inch mesh, 0.148-inch diameter (9 gage)2. Coating: ASTM A 817, Type 2, Class 1, Zinc-coated (Galvanized) applied after weaving.

2.2 FRAMINGA. Selvage: Knuckled at one selvage and twisted at the other for 2-inch and 2-1/8- inch mesh sizes and heights above 60 inches.

Actual NPS Trade OD Size Size

1.660 1-1/4 1.900 1-1/2 2 2.375 2 2-1/2 2.875 2-1/2 3 3.500 3 3-1/2 4.000 3-1/2 4

B. Type I Round Posts: Standard weight (schedule 40) galvanized-steel pipe conforming to ASTM F 1083, according to heavy industrial requirements of ASTM F 669, Group IA, with minimum yield strength of 25,000 psi, not less than 1.8 oz. of zinc per sq. ft. Type A coating inside and outside according to ASTM F 1234, as determined by ASTM A 90, and weights per foot as follows:

Actual NPS Trade OD Size Size

1.660 2.27 1-1/4 1.900 2.72 1-1/2 3.500 7.58 3 4.000 9.11 3-1/2

A. Roll-Formed Steel: Rolled form steel shapes produced from structural-quality steel conforming to ASTM A 570, grade 45, or ASTM A 446, grade D, galvanized, conforming to heavy industrial requirements of ASTM F 669, Group II, with a minimum yield strength of 45,000 psi. Protective coating system according to ASTM F 1234, Type A, hot-dip galvanized with a minimum of 2.0 oz. of zinc per sq. ft. according to ASTM A 123, 4.0 oz. of zinc per sq. ft. according to ASTM A 525.B. Top Rail: Manufacturer's longest lengths (17-21 feet) with swedged-end or expansion-type coupling, approximately 6 inches long for joining. Provide rail ends or other means for attaching top rail securely to each gate corner, pull, and end post.

1. Round Steel: 1.660-inch OD Type I or II steel pipe.

C. Steel posts for fabric heights 6 feet and higher:1. Round Line or Intermediate Posts: 2.375-inch OD Type I or II steel pipe.2. Round End, Corner, and Pull Posts: 2.875-inch OD Type I or II steel pipe.

D. Material: Comply with ASTM F 626. Mill-finished aluminum or galvanized iron or steel to suit manufacturer's standards.E. Post and Line Caps: Provide weathertight closure cap for each post. Provide line post caps with loop to recieve or top rail.F. Post Brace Assembly: Manufacturer's standard adjustable brace. Use material specified below for brace, and truss to line posts with 3/8-inch diameter rod and adjustable tightener. Provide manufacturer's standard galvanized-steel, for each end.

1. Round Steel: 1.660-inch OD Type I or II steel pipe.

G. Tension Wire: 0.177-inch diameter metallic-coated steel marcelled tension wire conforming to ASTM A 824 with finish to match fabric. (If shown on plans.)

1. Coating Type II zinc in the following class as determined by ASTM A 90.a. Class 2, with a minimum coating weight of 1.20 oz. per sq. ft. of uncoated wire surface.

H. Tie Wires: 0.106-inch diameter (12-gage) galvanized steel with a minimum of 0.80 oz. per sq. ft. of zinc coating according to ASTM A 641, or equal, to match fabric wire.

2.3 INDUSTRIAL SWING GATESA. General: Comply with ASTM F 900 for single or double swing gate types.

1. Metal Pipe and Tubing : Galvanized steel. Comply with ASTM F 1043 and ASTM F 1083 for materials and protective coatings.

B. Frames and Bracing: Fabricate members from round, galvanized steel tubing with outside dimension and weight according to ASTM F 900 and the following:

1. Gate Fabric Height: 2 inches (50mm) less than adjacent fence height.2. Leaf Width: As indicated.3. Frame Members:

a. Tubular Steel 1.90 inches (48mm) round.C. Frame Corner Construction:

1. Welded 3/8-inch diameter, adjustable truss rods for panels 5 feet (1.52m) wide or wider.

D. Hardware: Latches permitting operation from both sides of gate, hinges, center gate stops and keepers for each gate leaf more than 5 feet (1.52m) wide.

1. Single: Fork Latch.2. Double: Plunger type drop rod.

2.4 INDUSTRIAL HORIZONTAL-SLIDE GATESA. General: Comply with ASTM F 1184 for single slide gate types.

1. Classification: Type II Cantilever Slide, Class 1 with external roller assemblies.2. Metal Pipe and Tubing: Galvanized steel. Comply with ASTM F 1184 for materials and protective coatings.

B. Frames and Bracing: Fabricate members from round, galvanized steel tubing with outside dimension and weight according to ASTM F 1184 and the following:1. Gate Fabric Height: As indicated on drawings.2. Gate Opening Width: As indicated on drawings.3. Frame members:

a. Tubular Steel: 2.375 inches (60.32mm) round.4. Bracing Members:

a. Tubular Steel: 1.90 inches (48mm) round.C. Frame Corner Construction:

1. Welded frame.D. Roller Guards: As required per ASTM F 1184 for Type II, Class 1 gates.E. Hardware: Latches permitting operation from both sides of gate, roll gate latch.

2.5 CONCRETEA. Conrete: Provide conrete consisting of portland cement per ASTM C 150, aggregates per ASTM C 33, and potable water. Mix materials to obtain concrete with a minimum 28-day compressive strength of 3000 psi. Use at least four sacks of cement per cu. yd., 1-inch maximum size aggregate, 3-inch slump.B. Packaged Concrete Mix: Mix dry-packaged normal-weight concrete conforming to ASTM C 387 with clean water to obtain a 2- to 3-inch slump.

PART 3 - EXECUTION

3.1 EXAMINATIONA. Examine areas and conditions, with Installer present, for compliance with requirements for site clearing, earthwork, pavement work and other conditions affecting performance.

1. Do not begin installation before final grading is completed, unless otherwise permitted by Architect.2. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERALA. General: Install fence to comply with ASTM F 567. Do not begin installation and erection before final grading is completed, unless otherwise permitted.

1. Apply fabric to outside of framework. Install fencing on boundary lines linside property line established by survey.

3.3 CHAIN LINK FENCE INSTALLATIONA. Excavation: Drill or hand-excavate (using post-hole digger) holes for posts and spacings indicated, in firm, undisturbed or compacted soil.

1. If not indicated on Drawings, excavate holes for each post to minimum diameter recommened by fence manufacturer, but not less than four times the largest cross section of post.2. Unless otherwise indicated, excavate hole depths approximately 3 inches lower than post bottom, with bottom of posts set not less than 36 inches below finish grade surface.

B. Setting Posts: Center and align posts in holes 3 inches above bottom of excavation. Space a maximum of 10 feet o.c., unless otherwise indicated.

1. Protect portion of posts above ground from concrete splatter. Place concrete around posts and vibrate or tamp for consolidation. Check each post for vertical and top alignment, and hold in position during placement and finishing operations.

a. Unless otherwise indicated, extend concrete footings 2 inches above grade and trowel to a crown to shed water.

C. Top Rails: Run rail continuously through line post caps, bending to radius for curved runs and at other posts terminating into rail end attached to posts or post caps fabricated to receive rail. Provide expansion couplings as recommended by fencing manufacturer.D. Brace Assemblies: Install braces at end and gate posts and at both sides of corner and pull posts. Locate horizontal braces at midheight of fabric on fences with top rail and at two thirds fabric height on fences without top rail. Install so posts are plumb when diagonal rod is under proper tension. (If shown on plans.)E. Bottom Tension Wire: Install tension wire within 6 inches of bottom of fabric before stretching fabric and tie to each post with not less than same gage ond type of wire. Pull wire taut, without sags. Fasten fabric to tension wire with .120-inch diameter (11-gage) hog rings of same material and finish as fabric wire, spaced a maximum of 24 inches o.c.F. Fabric: Leave approximately 2 inches between finish grade and bottom selvage unless otherwise indicated. Pull fabric taut and tie to posts,rails, and tension wires. Install fabric on security side of fence, and anchor to framework so that fabric remains under tension after pulling force is released.G. Tie Wires: Use wire of proper length to secure fabric firmly to posts and rails. Bend ends of wire to minimize hazard to persons or clothing.

2. Maximum Spacing: Tie fabric to line posts 12 inches o.c. and to rails and braces 24 inches o.c.H. Fasteners: Install nuts for tension bands and carriage bolts on the side of the fence opposite the fabric side. Peen ends of bolts or score threads to prevent removal of nuts for added security.I. Privacy Slats: Install slats in direction indicated, securely locked in place. (If shown on plans.)

1. Vertically.

3.4 GATE INSTALLATIONA. Install gates according to manufacturer's written instructions, level, plumb, and secure for full opening without interference. Attach fabric as for fencing. Attach hardware using tamperresistant or concealed means. Install ground-set items in concrete for anchorage. Adjust hardware for smooth operation and lubricate where necessary.

3.5 ADJUSTINGA. Gate: Adjust gate to operate smoothly, easily, and quietly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range. Confirm that latches and locks engage accurately and securely without forcing or binding.

EXTERIOR

1. Contractor to verify all dimensions on drawings for layout prior to construction with actual field conditions. Contractor to report any discrepancies to Architect and or Mechanical Engineer.

2. Contractor to coordinate and review with district for all staging, construction zones, barricade, parking and temporary fencing. Coordinate with district to maintain existing access for school deliveries, public andstudent safety access and exiting during all construction phases.

3. General contractor to retain soils engineers approved by School District for verification of soils bearing capacity for a minimum 2,000 lbs per foot.Selected soils engineer shall approve all undisturbed soils below all interior /exterior concrete slabs and footings typical, unless otherwise noted.Contractor to provide 6” free draining gravel under all slabs. If soils mediation / imports are required, soils engineer shall approve new imported engineered fill.Fill installed in 8” lifts, compacted to 95% maximum relative density for all soils bearing conditions. Imported fill to be type 1 Pit run gravel underneath all footings typical, unless otherwise noted, or as per soilsengineer's approval.

4. Contractor to verify existing gas piping routing in lawn area where new chiller enclosure is to be located, prior to excavation. Refer to plumbing drawings for notes.

5. Contractor to verify and work with district personnel for location of all irrigation piping, valve boxes, and heads prior to commencement of work impacted by new construction.Contractor to re-route, adjust and cap abandon lines not used. Contractor to provide new layout for fully functional irrigation system maintaining existing zone for this area impactedby new construction. Contractor to review type and manufacture of all irrigation heads replacement with district standards.

6. Contractor to provide rough grading free of large rocks and or construction debris for new landscaping. Provide the placement of 2 ” imported and amended topsoil for the placement of new lawn sod. New sodarea within existing curbs area left after construction of new chiller enclosure. Provide one (1) mowing after installing new or replacing existing sod.

7. Contractor to provide earth bank shoring, wall bracing or form bracing and other shoring work for all permanent concrete members as required. Shoring for the construction of footings, foundation walls, retainingwalls, sidewalks and other structures for the protection and safetyshall be the responsibility of the contractor. Back filling shall not take place until all connection are complete and structurally sound.

8. Contractor shall be responsible for the location of all existing utilities in the area of construction for location. Report all conflicts to owner and or engineer for district clarification and direction prior toconstruction.

INTERIOR

1. Remove and store all demolished fixtures and equipment for Owner review and approval prior to disposal.

2. Remove all ceilings, grids, or fixtures necessary to perform the required work. Replace all damaged materials after installation of equipment with new assemblies matching adjacent existing assemblies.

3. The contractor shall protect all existing finishes to remain from construction damage.

4. All penetrations through rated assemblies shall be fire stopped with a District approved material which maintains the original assembly rating.

A.

B.

C.

D.

1.E.

A.

B.

C.

D.

E.1.

2.

3.

4.

5.6.

7.

8.

9.

A.

B.

A.

1.2.

3.

A.

B.

A.

POLYVINYL-CHLORIDE (PVC) ROOFING –CURB/PIPE ADDITIONS

PART 1 - GENERAL

1.1 PERFORMANCE REQUIREMENTSGeneral Performance: Installed membrane roofing and base flashings shall withstandspecified uplift pressures, thermally induced movement, and exposure to weatherwithout failure due to defective manufacture, fabrication, installation, or other defectsin construction. Membrane roofing and base flashings shall remain watertight.Material Compatibility: Provide roofing materials that are compatible with one anotherunder conditions of service and application required, and demonstrated by membraneroofing manufacturer based on testing and field experience.Roofing System Design: Provide membrane roofing system that is identical to systemsthat have been successfully tested by a qualified testing and inspecting agency toresist uplift pressure calculated according to ASCE/SEI 7.FM Approvals Listing: Provide membrane roofing, base flashings, and componentmaterials that comply with requirements in FM Approvals 4450 and FM Approvals 4470as part of a membrane roofing system. Identify materials with FM Approvals markings.

Fire/Windstorm Classification: Class 1A-90.Energy Performance: Provide roofing system that is listed on the DOE ’s ENERGY STAR“Roof Products Qualified Product List ” for low-slope roof products.

1.2 QUALITY ASSURANCEManufacturer Qualifications: A qualified manufacturer that is UL listed for membraneroofing system identical to that used for this Project.Installer Qualifications: Installer shall have five (5) years minimum experienceinstalling the proposed membrane with an elite status with manufacture, unless priorapproval from Architect, Owner, and General Manager has been made.Source Limitations: Obtain components including fasteners for membrane roofingsystem approved by Owner and or membrane roofing manufacturer.Exterior Fire-Test Exposure: ASTM E 108, Class A; for application and roof slopesindicated, as determined by testing identical membrane roofing materials by a qualifiedtesting agency. Materials shall be identified with appropriate markings of applicabletesting agency.Pre-installation Roofing Conference: Conduct conference at Project site.

Meet with Owner, Architect, Owner ’s insurer if applicable, testing and inspectingagency representative, roofing installer, roofing system manufacturer ’srepresentative, deck installer, and installers whose work interfaces with or affectsroofing, including installers of roof accessories and roof-mounted equipment. Review methods and procedures related to roofing installation, includingmanufacturer’s written instructions.Review and finalize construction schedule and verify availability of materials,Installer’s personnel, equipment, and facilities needed to make progress and avoiddelays.Examine deck substrate conditions and finishes for compliance with requirements,including flatness and fastening.Review structural loading limitations of roof deck during and after roofing.Review base flashings, special roofing details, roof drainage, roof penetrations,equipment curbs, and condition of other construction that will affect roofingsystem.Review governing regulations and requirements for insurance and certificates ifapplicable.Review temporary protection requirements for roofing system during and afterinstallation.Review roof observation and repair procedures after roofing installation.

1.3 DELIVERY, STORAGE, AND HANDLINGDeliver roofing materials to Project site in original containers with seals unbroken andlabeled with manufacturer ’s name, product brand name and type, date of manufacture,approval or listing agency markings, and directions for storing and mixing with othercomponents.Store liquid materials n their original undamaged containers in a clean, dry, protectedlocation and within the temperature range required by roofing system manufacturer.Protect stored liquid material from direct sunlight.

1. Discard and legally dispose of liquid material that cannot be applied within its statedshelf life.C. Handle and store roofing materials and place equipment in a manner to avoid permanentdeflection of deck.

1.4 PROJECT CONDITIONSA. Weather Limitations: Proceed with installation only when existing and forecastedweather conditions permit roofing system to be installed according to manufacturer ’swritten instructions and warranty requirements.

1.5 WARRANTYA. Special Warranty: Manufacturer ’s standard or customized form, without monetarylimitation, inwhich manufacturer agrees to repair or replace components of membrane roofing systemthat fail in materials or workmanship within specified warranty period.

No exclusions for ponding water.Special warranty includes membrane roofing, base flashings, fasteners, substrateboard, roofing accessories, and other components of membrane roofing system.Warranty Period: Keep existing warranty in place and valid.

B. Special Project Warranty: Submit roofing Installer ’s warranty, on warranty formapproved by Owner, signed by Installer, covering the Work of this Section, including allcomponents of membrane roofing system such as membrane roofing, base flashing,fasteners, substrate boards, and walkway products, for the following warranty period:1. Warranty Period: Two years from date of Substantial Completion.PART 2 - PRODUCTS

2.1 PVC MEMBRANE ROOFINGA. PVC Sheet: ASTM D 4434, Type lll, fabric reinforced. Match existing roof membrane.

1. 60 mils nominal.

1. The components of this roof system are to be products of one manufacturer. Productsnot supplied by primary roof membrane manufacturer, shall be identified as beingcompatible, acceptable and under warranty by the membrane manufacturer.

Acceptable Manufacturer and roof membrane for use on this project shallcomply to the following requirements:

Curb Flasings- G410, .060 minimum thickness, glass fiber reinforcedPolyvinyl Chloride membrane. Color:Energy Smart White.Pipe Flashings- Standard pre-formed pipe boots or field fabricatedwraps as warranted by manufacturer.

2. Membrane adhesive shall be supplied by the membrane manufacturer.Acceptable adhesive shall include:

A. Solvent based 2170 adhesive meeting current VOC requirements.B. As required by Membrane manufacturer.

3. Membrane Cleaner, Bonding Cement, Multi-purpose Sealant, Flashing,termination Bars, Mechanical Fastener ’s, Water Cut off Mastic and pourable sealeras manufactured and supplied by the membrane manufacturer.

4. Membrane Flashing:

A. Inside/outside corners or vent stacks shall be fieldfabricated fiberglass reinforced membrane in the same color asfield membrane. Supplied by the membrane manufacturer.

5. Fasteners : #12 steel painted screw for insulation or hard board attachment.

6. Membrane Cleaner:

A solvent cleaner for removal of adhesives from lap areas and for removalof contaminants from the roofing membrane as supplied by themembrane manufacturer.

7. Sealants:

Caulking / sealants which are provided will be accepted for use with thisinstallation based on chemical compatibility with the specifiedmembranes:

Multi purpose sealant tape or sealant in caulking tubes. Assupplied by membrane manufacturer.

A.

A.

A.

A.

1.2.

A.

1.

2.

B.

A.

B.C.

D.

A.

B.

A.

A.

B.

C.

D.

E.

A.

A.

B.

A.

B.

C.

8. Coated Metal25 gauge galvanized PVC coated steel sheets. Color to match roofmembrane color or as directed by owner. Membrane cover strips tomatch colored metal shall be provided by manufacturer as part of theflashing package. Steel flashing shall be formed to meet projecttermination and flashing requirements. Supplied and warranted bymembrane manufacturer.

2.2 AUXILIARY MEMBRANE ROOFING MATERIALSGeneral: Auxiliary membrane roofing materials recommended by roofing systemmanufacturer for intended use, and compatible with membrane roofing.

1. Liquid-type auxiliary materials shall comply with VOC limits of authorities havingjurisdiction.B. Sheet Flashing: Manufacturer ’s standard sheet flashing of same material, type,thickness, and color, as PVC sheet membrane.C. Bonding Adhesive: Manufacturer ’s standard.D. Metal Termination Bars: Manufacturer ’s standard, predrilled stainless-steel oraluminum bars, approximately 1 by 1/8 inch thick; with anchors.E. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying withcorrosion-resistance provisions in FM Approvals 4470, designed for fastening membrane tosubstrate, and acceptable to membrane roofing system manufacturer.F. Coated Flashings: Manufacturer ’s standard coated metal flashings in thickness asrecommended by manufacturer for indicated use and complying with performancerequirements, but with metal thickness not less than 0.028 inches.G. Miscellaneous Accessories: Provide cone and vent sheet flashings, inside and outsidecorner sheet flashings, T-joint covers, termination reglets, and other accessories.

2.3 INSULATION MATERIALSSubstrate Board: Rigid polyisocyanurate with black mat facers 4 ’x8’ installed in twolayers to meet desired r-value.

2.4 WALKWAYSFlexible Walkways: Factory-formed, heavy-duty, slip-resisting, surface-texturedwalkway pads, approximately 3/16 inch thick and acceptable to membrane roofingsystem manufacturer.

Size: 3'-0" wide by lengths indicated or as graphically shown on the roof plans.Provide around roof access hatch, at high roof drip edge and around mechanicalequipment as indicated on the drawings.

3.1 EXAMINATIONExamine substrates, areas, and conditions, with Installer present, for compliance withthe following requirements and other conditions affecting performance of roofingsystem:

Verify that roof openings and penetrations are in place and curbs are set andbraced.Verify that wood blocking, curbs, and nailers are securely anchored to roof deck atpenetrations.

Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATIONClean substrate of dust, debris, moisture, and other substances detrimental to roofinginstallation according to roofing system manufacturer ’s written instructions. Removesharp projections.Prevent materials from spilling or migrating onto surfaces of other construction.Complete terminations and base flashings and provide temporary seals to prevent waterfrom entering completed sections of roofing system at the end of the workday or whenrain is in the forecast. Remove and discard temporary seals before beginning wok onadjoining roofing.Do not begin installation in inclement weather and lonely install as much insulation in aday as can be covered with the roof membrane.

3.3 INSULATION (SUBSTRATE) BOARDSInstall substrate board with long joints in continuous straight lines, perpendicular toroof slopes with end joints staggered between rows. Tightly butt substrate boardstogether.Install second layer with end and side joints offset one-foot minimum from joints in firstlayer.

3.4 MECHANICALLY FASTENED MEMBRANE ROOFING INSTALLATIONMechanically fasten membrane roofing over area to receive roofing and installaccording to roofing system manufacturer ’s written instructions.

1. Install sheet according to ASTM D 5082.B. Start installation of membrane roofing in presence of roofing system manufacturer ’stechnical personnel.C. Accurately align membrane roofing and maintain uniform side and end laps of minimumdimensions required by manufacturer. Stagger end laps.D. Mechanically fasten or adhere membrane roofing securely at terminations,penetrations, and perimeter of roofing.E. Apply membrane roofing with side laps shingled with slope of roof deck where possible.F. Seams: Clean seam areas, overlap membrane roofing, and hot-air weld side and endlaps of membrane roofing and sheet flashings according to manufacturer ’s writteninstructions to ensure a watertight seam installation.

1. Test lap edges to prove and verify seam weld continuity.2. Verify field strength of seams a minimum of twice daily and repair seam sample

areas.3. Repair tears, voids, and lapped seams in roofing that does not comply with

requirements.

3.5 BASE FLASHING INSTALLATIONInstall sheet flashings and preformed flashing accessories and adhere to substratesaccording to membrane roofing system manufacturer ’s written instructions.Apply bonding adhesive to substrate and underside of sheet flashing at required rateand allow to partially dry. Do not apply to seam area of flashing.Flash penetrations and field-formed inside and outside corners with cured or uncuredsheet flashing.Clean seam areas, overlap, and firmly roll sheet flashings into the adhesive. Hot-airweld side and end laps to ensure a watertight seam installation.Terminate and seal top of sheet flashings.

3.7 WALKWAY INSTALLATIONFlexible Walkways: Install walkway products in locations indicated. Heat weld tosubstrate or adhere walkway products to substrate with compatible adhesive accordingto roofing system manufacturer ’s written instructions.

1. Install walkways around all sides of mechanical rooftop equipment, at roof accesshatches and under eaves of high roof along drip line.

3.8 FIELD QUALITY CONTROLRepair or remove and replace components of membrane roofing system whereinspections indicate that they do not comply with specified requirements.Additional inspections, at contractor ’s expense, will be performed to determinecompliance of replaced or additional work with specified requirements.

3.9 PROTECTING AND CLEANINGProtect membrane roofing system from damage and wear during remainder ofconstruction period. When remaining construction will not affect or endanger roofing,inspect roofing for deterioration and damage, describing its nature and extent in awritten report, with copies to Architect and Owner.Correct deficiencies in or remove membrane roofing system that does not comply withrequirements; repair substrates; and repair or reinstall membrane roofing system to acondition free of damage and deterioration at time of Substantial Completion andaccording to warranty requirements.Clean overspray and spillage from adjacent construction using cleaning agents andprocedures recommended by manufacturer of affected construction.

BUILT-UP ROOFING (BUR) NEW PENETRATION OR MECH. CURB

A. Thoroughly clean roof surface of dirt, debris, loose granules and contaminates at andaround location of new penetrations or curbs. Spread the gravel back from the edge of thenew penetration or curb 12-inches minimum. Prime area and allow to dry.B. Provide new flashing vertically 8-inches minimum at pipe or curb. Provide 4-incheshorizontal flange at flashing, prime both sides with asphalt primer and let dry. Set horizontalflange over top ply of field roofing in approximately 1/8-inch-thick layer of manufacturer ’sapproved utility cement.C. Strip-in horizontal flange with fiberglass mesh with a coat of plastic-roofing cement.Apply additional coats of plastic-roofing cement extending cement to cover joint betweenthe felt and flashing. Slope flashing to shed water.D. Coat plastic-roofing cement with aluminum roof coating.E. Provide 22-gauge galvanized rain collar at top of pipe penetration. Secure collar withstainless steel draw band set in urethane sealant. Seal top of rain collar.

BL

BD

01.15.2018

A

B

D

E

1 2 3 4 5

17471

C

6

FA

IR

FIE

LD

JH

S

A/C

95

1 N

F

AIR

FIE

LD

S

T. K

AY

SV

IL

LE

, U

T. 8

40

37

A101A1

6"1'-

0"

8"

6"

1" C

LR.

19'-4"4'-7"

6'-1"

4'-10" 53'-10" 6'-0"

7'-0"7'-3"

9'-8"

A4A101

D4A101D4

A101

6"1'-

0"

8"

1" C

LR.

8'4'2'0'

N 1" = 50'-0"D1 OVERALL SITE PLAN 1" = 1'-0"D4 SLAB EDGE AT EQUIPMENT

8'4'2'0'

N 1/8" = 1'-0"A1 ENLARGED ENCLOSURE PLAN 1 1/2" = 1'-0"A4 SIDEWALK AT SLAB EDGE

BL

BD

01.15.2018

A

B

D

E

1 2 3 4 5

17471

C

6

FA

IR

FIE

LD

JH

S

A/C

95

1 N

F

AIR

FIE

LD

S

T. K

AY

SV

IL

LE

, U

T. 8

40

37

BL

BD

01.15.2018

A

B

D

E

1 2 3 4 5

17471

C

6

FA

IR

FIE

LD

JH

S

A/C

95

1 N

F

AIR

FIE

LD

S

T. K

AY

SV

IL

LE

, U

T. 8

40

37

LIC

ENSE

D P

ROFE SS I ONAL ENGIN

EER

No. 172628-2202

S TA T E O F U TAH

WADE W.BENNION

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 1

SECTION 26 0100 – ELECTRICAL REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. All sections of Division 26, 27, & 28 shall comply with this section. The standards established in this section as to quality of materials and equipment, the type and quality of workmanship, mode of operations, safety rules, code requirements, etc., shall apply to all sections of this Division as though they were repeated in each Division.

C. Architectural, Mechanical, Civil, Structural, and other applicable documents also apply to work of this section.

1.2 SUMMARY

A. Provide all labor, materials, and equipment as required for a complete operating and tested electrical system as described in the contract documents

B. Related Requirements, including but not limited to:

1. Section 02 "Existing Conditions”.2. Section 03 “Concrete”.3. Section 05 “Metals”.4. Section 06 “Woods Plastics, and Composites”.5. Section 07 “Thermal and Moisture Protection:6. Section 08 “Openings”.7. Section 09 “Finishes”.8. Section 31 “Earthwork”.

1.3 CODES & ORDINANCES

A. All work shall be executed in accordance with all underwriters, public utilities, local and state codes, rules, and regulations applicable to the trade affected. Where work required by the drawings or specifications exceeds the codes rules, and regulations, it shall be done according to the documents. Where conflicts occur, the most stringent requirements shall apply.

B. Applicable codes: Work shall comply with currently adopted Edition:

1. International Building code 2. International Fire Code3. International Energy Code4. National Electrical Code

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 2

5. International Mechanical Code6. International Plumbing Code.

1.4 INDUSTRY STANDARDS

A. All work and equipment shall comply with the following standards. These standards refer to the latest adopted or published edition. Where conflicts occur, the most stringent requirement shall apply.

1. ETL Testing Laboratories (ETL)2. Institute of Electrical and Electronic Engineers (IEEE)3. National Fire Protection Association (NFPA)4. National Electrical Manufacturers Association (NEMA)5. National Electrical Safety code (NESC)6. Utah Safety Standard (OSHA), Utah State Industrial Council.7. Underwriters Laboratories (UL)8. Illuminating Engineering Society (IES)1. Certified Ballast Manufacturers (CBM) 2. American Society for testing Materials (ASTM)3. Insulated Cable Engineers Association (ICEA)9. American National Standards Institute (ANSI)10. EIA/TIA

B. Compliance Verification:

1. Manufactured equipment which is represented by a UL classification and/or listing, shall bear the UL or equivalent ETL label.

1.5 INTERPRETATION OF DRAWINGS

A. Carefully review the documents prior to bid. Submit requests for clarification to the Architect/Engineer in writing prior to final addendum.

B. Electric equipment is shown at a small scale, and is shown at its approximate location only. The drawings shall not be scaled for roughing in measurements, except where dimensions are specifically shown. Refer to the Architectural and Mechanical drawings, and coordinate with applicable shop drawings of other trades, to locate electrical equipment. Coordinate with other trades to avoid interferences, and to provide sufficient space for the installation of all equipment. Where conflicts occur, notify the Architect in writing, for clarification.

C. Visit the site prior to bid to determine how existing conditions shall affect the electrical installation. Include all costs required due to existing site conditions in the bid.

1.6 DEFINITIONS

A. Provide: Furnish, install, and connect, unless noted otherwise.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 3

B. Furnish: Purchase and deliver to the site. Include all essential items for performing the function.

C. Install: Physically install the equipment per industry standards, codes, and Contract Documents.

D. Connect: Make final connections to the equipment, and place into operation per manufacturer’s instructions.

1.7 SAFETY REGULATION

A. Comply with all local, State, Federal, and OSHA safety requirements in performance with this work. Refer to the General Conditions. Provide equipment, supervision, construction, procedures, and all other necessary items to assure safety to life and property.

1.8 UTILITIES & FEES

A. Include all fees for permits, inspections, and utility connections required by work of this Division, unless noted otherwise. The Contractor shall obtain the necessary permits to perform the work unless noted otherwise,

B. Provide connections to new and existing utilities, as shown on the documents.

1.9 SUBMITTALS AND SHOP DRAWINGS

A. As soon as possible after the contract is awarded, the Contractor shall submit to the Architect, the manufacturer’s data on products and materials, and shop drawings, to be used in the installation of electrical systems for this project. Review of the submitted data will require a minimum of 14 days. The first day starts after the day they are received in the Engineer’s office. If the Contractors schedule requires return of submitted literature in less than the allotted time, the Contractor shall accelerate his submittal delivery date. The Contractor shall resubmit all items requiring re-review within 14 days of returned submittals. Refer to each specification section for items requiring submittal review.

B. Written approval of the Owner's Representative shall be obtained before installing any equipment or materials for the project. Review of the submittals by the Owner’s Representative is for general conformance with the Contract Documents and shall not relieve the Contractor from compliance with the Contract Documents.

C. Verify all dimensional information to insure proper clearance for installation of equipment. Submitted literature shall bear the Contractor's stamp, indicating that he has reviewed all equipment being submitted; that each item will fit within the available space. Notify the Architect, in writing, for additional instructions where proposed equipment is found to be in conflict with available space.

D. By description, catalog number, and manufacturer's names, standards of quality have been established by the Architect and the Engineer for certain manufactured equipment items and specialties that are to be furnished by this Division. Alternate products and equipment may be

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 4

proposed for use only if specifically named in the specifications, or if given written prior approval in published addenda. Design equipment is the equipment listed on the drawings, or if not listed on the drawings is the equipment first named in the specifications.

E. If the Engineer is required to do additional design work to incorporate changes caused by submitting equipment or products, different than the design equipment specified, as defined above, the contractor shall reimburse the engineer for additional time and expenses at the engineer’s current, recognized, hourly rates.

F. Submittal Format: Unless noted otherwise in the General Conditions, the project submittals may be submitted in electronic format as noted below. Partial submittals will not be reviewed until the complete submittal is received. Provide copies of the descriptive literature covering products and materials to be used in the installation of electrical systems for this project for review.

1. Electronic Submittal Format: Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single specification section and transmittal form with links enabling navigation to each item. Name file with submittal number or other unique identifier, including revision identifier. Electronic file shall be completely electronically searchable or it will be rejected. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by the Architect

2. The title sheet of the submittal shall contain the project name, date of submission, Architect, Contractor, Sub Contractors, Suppliers, specification section number and title.

3. Provide a statement on the title sheet that the shop drawings comply with, and are submitted in accordance with the contract documents.

4. Provide manufacturer’s equipment cut sheets, brochures, and drawings which describe the proposed equipment. All relevant information shall be identified.

5. Submit electrical room layouts for all electrical rooms showing equipment dimensions and required clearances.

6. The drawings shall not be scaled for roughing in measurements nor shall they be used as shop drawings. Where drawings are required for these purposes or where drawings must be made from field measurements, the Contractor shall take the necessary measurements and prepare the drawings. Shop drawings of the various subcontractors shall be coordinated to eliminate all interferences and to provide sufficient space for the installation of all equipment.

1.10 OPERATING AND MAINTENANCE MANUALS

A. Unless noted otherwise in the General Conditions, submit one (1) copy in PDF format. Follow same compilation format as listed for Electronic Submittal Format.

B. Provide manufacturer's operating and maintenance instructions. Provide vendor's name, address, and phone number. List model and serial number for each piece of equipment. Include list of replacement parts and service schedules. Provide wiring diagrams and manufacturer’s warranties.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 5

1.11 RECORD DRAWINGS

A. Refer to the General Conditions for As-Built Drawing submission requirements.

B. Keep one complete hard copy set of the contract documents on site. Record on a daily basis, any modifications to the documents due to addendums, changes, and field conditions. Show dimensions for concealed work including conduits buried below slab or below grade, concrete ductbanks, direct burial cable, utility lines, etc.

1.12 WARRANTY

A. In addition to the requirements of the General Conditions, warranty the complete electrical installation to be in accordance with the contract documents, to be free from defects and in proper working order. Repair or replace any defective equipment or installation for a period of one (1) year from the date of final acceptance, or as noted otherwise. Defective lamps shall be replaced for a period of two (2) months from the date of final acceptance.

B. Submit written warranties and guarantees. List the Project name and the Contractor’s business name and contact information.

C. Submit warranty information for each product including name, address, and telephone number of warranty service. Include procedures for filing a claim.

PART 2 - PRODUCTS

2.1 GENERAL

A. All materials shall be new unless specifically noted otherwise.

2.2 SUBSTITUTIONS:

A. Substitutions of specified products, approved installers, etc. may be considered prior to bid. Submit proposed substitutions a minimum of eight (8) working days prior to the bid date. Provide complete information for proposed equipment including catalog cut sheets. Certify that the proposed equipment is equal to the specified equipment. Where substitution of a proposed installer is requested, submit company/installer’s resume indicating years of experience, certifications, etc. Any allowed substitutions shall be included in the addendum. Do not bid unapproved equipment or work by unapproved installers.

B. Provide samples as requested by the Architect/Engineer for review of proposed equipment prior to bid.

C. Substituted equipment shall comply with the intent of the contract documents. The Contactor shall bear all costs arising from conflicts arising due to the use of substituted equipment.

D. Value engineering substitutions shall not be offered by the Contractor without a request from the Architect/Engineer. Vendors offering value engineered product substitutions, without the

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 6

permission and involvement of the Architect/Engineer, shall be forfeited from bidding future projects.

2.3 SPARE PARTS

A. Provide spare parts as specified in Divisions 26, 27, and 28 sections. Deliver spare parts to the Owner's Representative prior to substantial completion. Obtain written receipt and include with as-built drawing submission.

PART 3 - EXECUTION

3.1 CUTTING AND PATCHING

A. No cutting or drilling of structural members shall be done without written approval of the Architect. The work shall be carefully laid out in advance, and cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings, or other surfaces necessary for the electrical work shall be carefully done. Any damage to building, piping, or equipment shall be repaired by professional plasterers, masons, concrete workers, etc., and all such work shall be paid for as work of this Division.

B. When concrete, asphalt, grading landscaping, etc., is disturbed, it shall be restored to original condition as described in the applicable Division of this Specification.

C. Provide roof jacks and flange extending a minimum of 9 inches under roofing materials, for raceways and cables which penetrate the roof. Seal opening with approved sealant. Provide drip loop for cables, and weather head on raceway, which penetrates the roof. Coordinate installation requirements with Division 7.

D. Seal and caulk as required to waterproof all conduit penetrations. Any penetrations through vapor barriers shall be made vapor tight. See Division 7, Thermal and Moisture Protection for material and installation requirements.

3.2 EXCAVATION AND BACKFILLING

A. All necessary excavations and backfilling for the electrical work shall be provided as work of this Division. Trenches for all underground raceways and ductbanks shall be excavated to the required depths. The bottom of trenches shall be compacted hard and graded to obtain required fall. Backfill shall be placed in horizontal layers, not exceeding 12 inches in thickness, and properly moistened. Each layer shall be compacted, by suitable equipment, to a density of not less than 95 percent as determined by ASTM D-1557. After raceways have been, inspected, and approved, the trench shall be backfilled with selected material. Excess earth shall be hauled from the job site. Fill materials approved by the Architect shall be provided as work of this Division.

B. Locate and protect existing utilities and other underground work prior to excavation. Insure that damage or service interruption will not result from excavation and backfilling.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 7

C. No trenches shall be cut near or under any footings without consultation first with the Architect's office. Any trenches or excavations more than 30 inches deep shall be tapered, shored, covered, or otherwise made absolutely safe so that no vehicle or persons can be injured by falling into such excavations, or in any way be harmed by cave-ins, shifting earth, rolling rocks, or by drowning. This protection shall be extended to all persons approaching excavation related to this work whether or not such persons are authorized to be in the vicinity of the construction.

D. Provide safety equipment at excavations such as barricades, warning signs, and illumination to protect against injury.

3.3 ACCESS

A. Provide access doors in walls, ceilings and floors for access to electrical equipment such as junction boxes, pull boxes, cable trays, etc. Refer to Division 8 for door specifications. All access doors shall be 24" x 24" unless noted otherwise. Coordinate location of doors with the Architect prior to installation. If doors are not specified in Division 8, provide the following: Doors in ceilings and wall shall be equal to JR Smith No. 4760 bonderized and painted. Doors in tile walls shall be equal to JR Smith No. 4730 chrome plated. Doors in floors shall be equal to JR Smith No. 4910.

B. Provide block-outs, sleeves, demolition work, etc., required for installation of work specified in this Division.

3.4 CLEANING AND PAINTING

A. Upon completion of all tests and adjustments, and all systems have been pronounced satisfactory for permanent operation, clean all exposed raceway, junction boxes, pullboxes, fixtures, etc. and leave them ready for painting. Refinish any damaged finish, and leave everything in proper working order.

B. Remove all stains, finger marks, and grease marks on walls, floors, glass, hardware, fixtures, or elsewhere, caused by work of this Division. Clean light fixtures and interior and exterior of all electrical equipment.

C. Painting of exposed raceway, junction boxes, pullboxes, surface metal raceway, etc., is work of Division 9, Painting.

D. All equipment which is indicated to be furnished in factory prefinished conditions, and painted by the Electrical Contractor shall be left without mark, scratch, or impairment to finish upon completion of job. Any necessary refinishing to match original shall be done. Do not paint over nameplates, serial numbers, or other identifying marks.

E. Upon completion of work of this Division, remove all surplus material and rubbish resulting from this work, and leave the premises in a clean and orderly condition.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 8

3.5 PROTECTION AGAINST WEATHER AND STORING OF MATERIALS

A. All equipment and materials shall be properly stored and protected against damage, theft, moisture, dust, and wind. Coverings or other protection shall be used on all items that may be damaged or rusted or may have performance impaired by adverse weather or moisture conditions. Damage or defect developing before acceptance of the work shall be made good at the Contractor's expense.

3.6 POWER OUTAGES:

A. Power outages, as required for installation of electrical work, shall be scheduled with the Owner a minimum of (7) days prior to outages, and shall be performed during non-standard working hours, unless noted otherwise. Include all costs in bid for overtime hours and utility company disconnection and reconnection fees.

3.7 EQUIPMENT STARTUP AND TESTING:

A. Each major piece of equipment shall be started and tested by an authorized representative of the equipment manufacturer. A certificate indicating the equipment is operating to the satisfaction of the manufacturer shall be provided, and shall be included with the Warranty.

B. Notify Architect/Engineer prior to all testing for this Division, a minimum of three (3) business days prior to testing. Engineer shall observe all tests to insure the proper operation of the electrical system.

C. The Manufacturer’s Representative shall provide instructions to the owner's maintenance personnel for operation and maintenance of the equipment.

3.8 FINAL REVIEW:

A. The Project Forman shall accompany the Engineer and remove coverplates, panelboard covers, access panels, etc. as requested, to allow review of the entire electrical system.

END OF SECTION 26 0100

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 1

SECTION 26 0519 - CONDUCTORS AND CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Building wires and cables rated 600 V and less.2. Connectors, splices, and terminations rated 600 V and less.

1.3 SUBMITTALS

A. Product Data: For each type of product.

1.4 QUALITY ASSURANCE

A. Testing Agency Qualifications: Member company of NETA or an NRTL.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

PART 2 - PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Belden Inc.2. Cooper Industries, Inc.3. General Cable Technologies Corporation.4. General Cable; General Cable Corporation.5. Senator Wire & Cable Company.6. Southwire Company.7. Thomas & Betts Corporation, A Member of the ABB Group.

B. Conductors: Comply with NEMA WC 70/ICEA S-95-658.

C. Conductor Insulation: Comply with NEMA WC 70/ICEA S-95-658.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 2

2.2 CONNECTORS AND SPLICES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. 3M.2. AFC Cable Systems; a part of Atkore International.3. Hubbell Power Systems, Inc.4. Ideal Industries, Inc.5. ILSCO.6. O-Z/Gedney; a brand of Emerson Industrial Automation.

B. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

2.3 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

PART 3 - EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Stranded for No. 12 AWG and larger.

3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING METHODS

A. Feeders: Type THHN/THWN-2 for 400 KCMIL and below, and Type XHHW-2, for 500 KCMIL and larger.

B. Branch Circuits, Type THHN/THWN-2. Provide minimum #12 AWG.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Conceal cables in finished walls, ceilings, and floors unless otherwise indicated.

B. Complete raceway installation between conductor and cable termination points according to Section 260533 "Raceways and Boxes for Electrical Systems" prior to pulling conductors and cables.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 3

C. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

D. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

E. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours where possible.

F. Support cables according to Section 260529 "Hangers and Supports for Electrical Systems."

G. Do not exceed three phase conductors in any conduit, unless noted otherwise.

H. Provide separate neutral conductor for each single phase branch circuit. Shared neutrals are not allowed, except where noted otherwise.

I. Voltage Drop: Increase branch circuit by one wire size when circuit length exceeds 100’ and by two wire sizes when circuit length exceeds 200’.

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.

B. Make splices, terminations, and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

C. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches of slack.

3.5 IDENTIFICATION

A. Identify and color-code conductors and cables according to Section 260553 "Identification for Electrical Systems."

B. Identify each spare conductor at each end with identity number and location of other end of conductor, and identify as spare conductor.

3.6 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Section 260544 "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 4

3.7 FIRESTOPPING

A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly according to Section 078413 "Penetration Firestopping."

3.8 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. After installing conductors and cables and before electrical circuitry has been energized, test service entrance and feeder conductors for compliance with requirements.

2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

B. Cables will be considered defective if they do not pass tests and inspections.

END OF SECTION 26 0519

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 1

SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes grounding and bonding systems and equipment.

1.3 QUALITY ASSURANCE

A. Testing Agency Qualifications: Member company of NETA or an NRTL.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Comply with UL 467 for grounding and bonding materials and equipment.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Burndy; Part of Hubbell Electrical Systems.2. ILSCO.3. O-Z/Gedney; a brand of Emerson Industrial Automation.4. Thomas & Betts Corporation, A Member of the ABB Group.

2.2 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with UL 467 for grounding and bonding materials and equipment.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 2

2.3 CONDUCTORS

A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

2.4 CONNECTORS

A. Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.

B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy.

PART 3 - EXECUTION

3.1 APPLICATIONS

A. Conductors:

1. Provide grounding conductors with stranding and insulation types to match phase conductors.

3.2 EQUIPMENT GROUNDING

A. Install insulated equipment grounding conductors with all feeders and branch circuits.

B. Install insulated equipment grounding conductors with the following items, in addition to those required by NFPA 70:

1. Feeders and branch circuits.2. Receptacle circuits.3. Single-phase motor and appliance branch circuits.4. Three-phase motor and appliance branch circuits.5. Flexible raceway runs.

3.3 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 3

1. After installing grounding system but before permanent electrical circuits have been energized, test for compliance with requirements.

2. Inspect physical and mechanical condition. Verify tightness of accessible, bolted, electrical connections with a calibrated torque wrench according to manufacturer's written instructions.

C. Grounding system will be considered defective if it does not pass tests and inspections.

END OF SECTION 26 0526

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 4

BLANK PAGE

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 1

SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Hangers and supports for electrical equipment and systems.2. Construction requirements for concrete bases.

B. Related Requirements:

1. Section 260548 "Seismic Controls for Electrical Systems" for products and installation requirements necessary for compliance with seismic criteria.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for the following:

a. Hangers.b. Steel slotted support systems.c. Trapeze hangers.d. Clamps.

2. Include rated capacities and furnished specialties and accessories.

B. Shop Drawings: Signed and sealed by a qualified professional engineer. For fabrication and installation details for electrical hangers and support systems.

1. Trapeze hangers. Include product data for components.2. Steel slotted-channel systems.3. Equipment supports.

C. Delegated-Design Submittal: For hangers and supports for electrical systems.

1. Include design calculations and details of trapeze hangers.2. Include design calculations for seismic restraints.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 2

D. Seismic Qualification Certificates: For hangers and supports for electrical equipment and systems, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

E. Welding certificates.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design hanger and support system.

B. Seismic Performance: Hangers and supports shall withstand the effects of earthquake motions determined according to ASCE/SEI 7.

1. The term "withstand" means "the supported equipment and systems will remain in place without separation of any parts when subjected to the seismic forces specified.

2. Retain "Surface-Burning Characteristics" Paragraph below for nonmetallic slotted-channel system and accessories.

C. Surface-Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1. Flame Rating: Class 1.2. Self-extinguishing according to ASTM D 635.

2.2 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS

A. Steel Slotted Support Systems: Comply with MFMA-4 factory-fabricated components for field assembly.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Allied Tube & Conduit; a part of Atkore International.b. B-line, an Eaton business.c. ERICO International Corporation.d. Flex-Strut Inc.e. GS Metals Corp.f. G-Strut.g. Haydon Corporation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 3

h. Metal Ties Innovation.i. Thomas & Betts Corporation; A Member of the ABB Group.j. Unistrut; Part of Atkore International.k. Wesanco, Inc.

2. Material: Galvanized steel. 3. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-

4.4. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating

applied according to MFMA-4.5. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-

4.6. Protect finishes on exposed surfaces from damage by applying a strippable, temporary

protective covering before shipping.7. Channel Dimensions: Selected for applicable load criteria.

B. Aluminum Slotted Support Systems: Comply with MFMA-4 factory-fabricated components for field assembly.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Cooper Industries, Inc.b. Flex-Strut Inc.c. Haydon Corporation.d. MKT Metal Manufacturing.e. Thomas & Betts Corporation; A Member of the ABB Group.f. Unistrut; Part of Atkore International.

2. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating applied according to MFMA-4.

3. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-4.

4. Protect finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

5. Channel Dimensions: Selected for applicable load criteria.

C. Conduit and Cable Support Devices: Steel hangers, clamps, and associated fittings, designed for types and sizes of raceway or cable to be supported.

D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for nonarmored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be made of malleable iron.

E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M steel plates, shapes, and bars; black and galvanized.

F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 4

1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Hilti, Inc.2) ITW Ramset/Red Head; Illinois Tool Works, Inc.3) MKT Fastening, LLC.4) Simpson Strong-Tie Co., Inc.

2. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel [stainless steel], for use in hardened portland cement concrete, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) B-line, an Eaton business.2) Empire Tool and Manufacturing Co., Inc.3) Hilti, Inc.4) ITW Ramset/Red Head; Illinois Tool Works, Inc.5) MKT Fastening, LLC.

3. Concrete Inserts: Steel or malleable-iron, slotted support system units are similar to MSS Type 18 units and comply with MFMA-4 or MSS SP-58.

4. Clamps for Attachment to Steel Structural Elements: MSS SP-58 units are suitable for attached structural element.

5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325.6. Toggle Bolts: All-steel springhead type.7. Hanger Rods: Threaded steel.

2.3 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES

A. Description: Welded or bolted structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

B. Materials: Comply with requirements in Section 055000 "Metal Fabrications" for steel shapes and plates.

PART 3 - EXECUTION

3.1 APPLICATION

A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems unless requirements in this Section are stricter.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 5

B. Comply with requirements for raceways and boxes specified in Section 260533 "Raceways and Boxes for Electrical Systems."

C. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMTs, IMCs, and RMCs as scheduled in NECA 1, where its Table 1 lists maximum spacings that are less than those stated in NFPA 70. Minimum rod size shall be 1/4 inch in diameter.

D. Space supports for raceways within 12 inches of each coupling, fitting, and box, at every 90 degree bend, and provide a minimum of two supports per ten foot run.

E. Multiple Raceways or Cables: Install trapeze-type supports fabricated with steel slotted support system, sized so capacity can be increased by at least 25 percent in future without exceeding specified design load limits.

1. Secure raceways and cables to these supports with single-bolt conduit clamps.

F. Spring-steel clamps designed for supporting single conduits without bolts may be used for 1-1/2-inch and smaller raceways serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports.

3.2 SUPPORT INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this article.

B. Raceway Support Methods: In addition to methods described in NECA 1, metal raceways may be supported by openings through structure members, according to NFPA 70.

C. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb.

D. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:

1. To Wood: Fasten with lag screws or through bolts.2. To New Concrete: Bolt to concrete inserts.3. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor

fasteners on solid masonry units.4. To Existing Concrete: Expansion anchor fasteners.5. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock

washers and nuts may be used in existing standard-weight concrete 4 inches (100 mm) thick or greater. Do not use for anchorage to lightweight-aggregate concrete or for slabs less than 4 inches thick.

6. To Steel: Beam clamps (MSS SP-58, Type 19, 21, 23, 25, or 27), complying with MSS SP-69.

7. To Light Steel: Sheet metal screws.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 6

8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches, control enclosures, pull and junction boxes, transformers, and other devices on slotted-channel racks attached to substrate by means that comply with seismic-restraint strength and anchorage requirements.

E. Drill holes for expansion anchors in concrete at locations and to depths that avoid the need for reinforcing bars.

3.3 INSTALLATION OF FABRICATED METAL SUPPORTS

A. Comply with installation requirements in Section 055000 "Metal Fabrications" for site-fabricated metal supports.

B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

C. Field Welding: Comply with AWS D1.1/D1.1M.

3.4 PAINTING

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils. Retain "Touchup" Paragraph below if a painting Section is in Project Manual.

B. Touchup: Comply with requirements in Section 09 for cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal.

C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780.

END OF SECTION 26 0529

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 1

SECTION 26 0533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Metal conduits, tubing, and fittings.2. Nonmetal conduits, and fittings.3. Metal wireways and auxiliary gutters.4. Boxes, enclosures, and cabinets.5. Surface raceway.6. Handholes and boxes for exterior underground cabling.

1.3 SUBMITTALS

A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

B. Shop Drawings: For custom enclosures and cabinets. Include plans, elevations, sections, and attachment details.

PART 2 - PRODUCTS

2.1 METAL CONDUITS, TUBING, AND FITTINGS

A. Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. GRC: Comply with ANSI C80.1 and UL 6.

C. IMC: Comply with ANSI C80.6 and UL 1242.

D. EMT: Comply with ANSI C80.3 and UL 797.

E. FMC: Comply with UL 1; zinc-coated steel.

F. LFMC: Flexible steel conduit with PVC jacket and complying with UL 360.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 2

G. Fittings for Metal Conduit: Comply with NEMA FB 1 and UL 514B.

1. Conduit Fittings for Hazardous (Classified) Locations: Comply with UL 886 and NFPA 70.

2. Fittings for EMT:

a. Material: Steel. b. Type: Setscrew.

3. Expansion Fittings: PVC or steel to match conduit type, complying with UL 651, rated for environmental conditions where installed, and including flexible external bonding jumper.

H. Joint Compound for IMC, or GRC: Approved, as defined in NFPA 70, by authorities having jurisdiction for use in conduit assemblies, and compounded for use to lubricate and protect threaded conduit joints from corrosion and to enhance their conductivity.

2.2 NONMETALLIC CONDUITS AND FITTINGS

A. Listing and Labeling: Nonmetallic conduits, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. RNC: Type EPC-40-PVC complying with NEMA TC 2 and UL 651 unless otherwise indicated.

C. Fittings for RNC: Comply with NEMA TC 3; match to conduit type and material.

2.3 METAL WIREWAYS AND AUXILIARY GUTTERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. B-line, an Eaton business.2. Hoffman; a brand of Pentair Equipment Protection.3. MonoSystems, Inc.4. Square D.

B. Description: Sheet metal, complying with UL 870 and NEMA 250, and sized according to NFPA 70.

1. Metal wireways installed outdoors shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Fittings and Accessories: Include covers, couplings, offsets, elbows, expansion joints, adapters, hold-down straps, end caps, and other fittings to match and mate with wireways as required for complete system.

D. Wireway Covers: Screw-cover type unless otherwise indicated.

E. Finish: Manufacturer's standard enamel finish.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 3

2.4 SURFACE RACEWAYS

A. Listing and Labeling: Surface raceways shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Surface Metal Raceways: Galvanized steel with snap-on covers complying with UL 5. Manufacturer's standard enamel finish in color selected by Architect.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Hubbell Incorporated; Wiring Device-Kellems.b. MonoSystems, Inc.c. Panduit Corp.d. Wiremold / Legrand.

C. Surface Nonmetallic Raceways: Two- or three-piece construction, complying with UL 5A, and manufactured of rigid PVC with texture and color selected by Architect from manufacturer's standard colors. Product shall comply with UL 94 V-0 requirements for self-extinguishing characteristics.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Hubbell Incorporated.b. MonoSystems, Inc.c. Panduit Corp.d. Wiremold / Legrand

2.5 BOXES, ENCLOSURES, AND CABINETS

A. General Requirements for Boxes, Enclosures, and Cabinets: Boxes, enclosures, and cabinets installed in wet locations shall be listed for use in wet locations.

B. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A.

C. Cast-Metal Outlet and Device Boxes: Comply with NEMA FB 1, [ferrous alloy] [aluminum], Type FD, with gasketed cover.

D. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1.

E. Cast-Metal Access, Pull, and Junction Boxes: Comply with NEMA FB 1 and UL 1773, galvanized, cast iron with gasketed cover.

F. Box extensions used to accommodate new building finishes shall be of same material as recessed box.

G. Device Box Dimensions: 4 inches square by 2-1/8 inches deep.

H. Gangable boxes are prohibited.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 4

I. Hinged-Cover Enclosures: Comply with UL 50 and NEMA 250, with continuous-hinge cover with flush latch unless otherwise indicated.

1. Metal Enclosures: Steel, finished inside and out with manufacturer's standard enamel.2. Interior Panels: Steel; all sides finished with manufacturer's standard enamel.

J. Cabinets:

1. NEMA 250, galvanized-steel box with removable interior panel and removable front, finished inside and out with manufacturer's standard enamel.

2. Hinged door in front cover with flush latch and concealed hinge.3. Key latch to match panelboards.4. Metal barriers to separate wiring of different systems and voltage.5. Accessory feet where required for freestanding equipment.

2.6 HANDHOLES AND BOXES FOR EXTERIOR UNDERGROUND WIRING

A. General Requirements for Handholes and Boxes:

1. Boxes and handholes for use in underground systems shall be designed and identified as defined in NFPA 70, for intended location and application.

2. Boxes installed in wet areas shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Polymer-Concrete Handholes and Boxes with Polymer-Concrete Cover: Molded of sand and aggregate, bound together with polymer resin, and reinforced with steel, fiberglass, or a combination of the two.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Oldcastle Precast, Inc.b. Quazite: Hubbell Power Systems, Inc.

2. Standard: Comply with SCTE 77.3. Configuration: Designed for flush burial with closed bottom unless otherwise indicated.4. Cover: Weatherproof, secured by tamper-resistant locking devices and having structural

load rating consistent with enclosure and handhole location.5. Cover Finish: Nonskid finish shall have a minimum coefficient of friction of 0.50.6. Cover Legend: Molded lettering, "ELECTRIC", or as noted otherwise.7. Conduit Entrance Provisions: Conduit-terminating fittings shall mate with entering ducts

for secure, fixed installation in enclosure wall.8. Handholes 12 Inches Wide by 24 Inches Long and Larger: Have inserts for cable racks

and pulling-in irons installed before concrete is poured.

2.7 SOURCE QUALITY CONTROL FOR UNDERGROUND ENCLOSURES

A. Handhole and Pull-Box Prototype Test: Test prototypes of handholes and boxes for compliance with SCTE 77. Strength tests shall be for specified tier ratings of products supplied.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 5

1. Tests of materials shall be performed by an independent testing agency.2. Strength tests of complete boxes and covers shall be by either an independent testing

agency or manufacturer. A qualified registered professional engineer shall certify tests by manufacturer.

3. Testing machine pressure gages shall have current calibration certification complying with ISO 9000 and ISO 10012 and traceable to NIST standards.

PART 3 - EXECUTION

3.1 RACEWAY APPLICATION

A. Outdoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed Conduit: GRC, IMC.2. Concealed Conduit, Aboveground: GRC, IMC, EMT.3. Underground Conduit: RNC, Type EPC-40-PVC. 4. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic,

Electric Solenoid, or Motor-Driven Equipment): LFMC.5. Boxes and Enclosures, Aboveground: NEMA 250, Type 3R.

B. Indoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed, Not Subject to Physical Damage: EMT. 2. Exposed, Not Subject to Severe Physical Damage: EMT. 3. Exposed and Subject to Severe Physical Damage: GRC, or IMC. Raceway locations

include the following:

a. Loading dock.b. Corridors used for traffic of mechanized carts, forklifts, and pallet-handling units.c. Mechanical rooms.d. Gymnasiums.

4. Concealed in Ceilings and Interior Walls and Partitions: EMT 5. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic,

Electric Solenoid, or Motor-Driven Equipment): FMC, except use LFMC in damp or wet locations.

6. Damp or Wet Locations: GRC or IMC.7. Boxes and Enclosures: NEMA 250, Type 1, except use NEMA 250, Type 4 stainless

steel in institutional and commercial kitchens and damp or wet locations.

C. Minimum Raceway Size: 3/4-inch trade size.

D. Raceway Fittings: Compatible with raceways and suitable for use and location.

1. Rigid and Intermediate Steel Conduit: Use threaded rigid steel conduit fittings unless otherwise indicated. Comply with NEMA FB 2.10.

2. PVC Externally Coated, Rigid Steel Conduits: Use only fittings listed for use with this type of conduit. Patch and seal all joints, nicks, and scrapes in PVC coating after

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 6

installing conduits and fittings. Use sealant recommended by fitting manufacturer and apply in thickness and number of coats recommended by manufacturer.

3. EMT: Use setscrew steel fittings. Comply with NEMA FB 2.10.4. Flexible Conduit: Use only fittings listed for use with flexible conduit. Comply with

NEMA FB 2.20.

E. Install surface raceways only where indicated on Drawings.

F. Do not install nonmetallic conduit where ambient temperature exceeds 120 deg F.

3.2 INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except where requirements on Drawings or in this article are stricter. Comply with NFPA 70 limitations for types of raceways allowed in specific occupancies and number of floors.

B. Keep raceways at least 6 inches away from parallel runs of flues and steam or hot-water pipes. Install horizontal raceway runs above water and steam piping.

C. Complete raceway installation before starting conductor installation.

D. Comply with requirements in Section 26 0529 "Hangers and Supports for Electrical Systems" for hangers and supports.

E. Arrange stub-ups so curved portions of bends are not visible above finished slab.

F. Install no more than the equivalent of three 90-degree bends in any conduit run except for control wiring conduits, for which fewer bends are allowed. Support within 12 inches of changes in direction.

G. Conceal conduit and EMT within finished walls, ceilings, and floors unless otherwise indicated. Install conduits parallel or perpendicular to building lines.

H. Support conduit within 12 inches of enclosures to which attached.

I. Raceways Embedded in Slabs:

1. Run conduit larger than 1-inch trade size, parallel or at right angles to main reinforcement. Where at right angles to reinforcement, place conduit close to slab support. Secure raceways to reinforcement at maximum 10-foot intervals.

2. Arrange raceways to cross building expansion joints at right angles with expansion fittings.

3. Arrange raceways to keep a minimum of 2 inches of concrete cover in all directions.4. Do not embed threadless fittings in concrete unless specifically approved by Architect for

each specific location.

J. Stub-ups to Above Recessed Ceilings:

1. Use EMT, IMC, or RMC for raceways.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 7

2. Use a conduit bushing or insulated fitting to terminate stub-ups not terminated in hubs or in an enclosure.

K. Threaded Conduit Joints, Exposed to Wet, Damp, Corrosive, or Outdoor Conditions: Apply listed compound to threads of raceway and fittings before making up joints. Follow compound manufacturer's written instructions.

L. Coat field-cut threads on PVC-coated raceway with a corrosion-preventing conductive compound prior to assembly.

M. Raceway Terminations at Locations Subject to Moisture or Vibration: Use insulating bushings to protect conductors including conductors smaller than No. 4 AWG.

N. Terminate threaded conduits into threaded hubs or with locknuts on inside and outside of boxes or cabinets. Install bushings on conduits up to 1-1/4-inch trade size and insulated throat metal bushings on 1-1/2-inch trade size and larger conduits terminated with locknuts. Install insulated throat metal grounding bushings on service conduits.

O. Install raceways square to the enclosure and terminate at enclosures with locknuts. Install locknuts hand tight plus 1/4 turn more.

P. Do not rely on locknuts to penetrate nonconductive coatings on enclosures. Remove coatings in the locknut area prior to assembling conduit to enclosure to assure a continuous ground path.

Q. Cut conduit perpendicular to the length. For conduits 2-inch trade size and larger, use roll cutter or a guide to make cut straight and perpendicular to the length.

R. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb tensile strength. Leave at least 12 inches of slack at each end of pull wire. Cap underground raceways designated as spare above grade alongside raceways in use.

S. Install raceway sealing fittings at accessible locations according to NFPA 70 and fill them with listed sealing compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing fittings according to NFPA 70.

T. Install devices to seal raceway interiors at accessible locations. Locate seals so no fittings or boxes are between the seal and the following changes of environments. Seal the interior of all raceways at the following points:

1. Where conduits pass from warm to cold locations, such as boundaries of refrigerated spaces.

2. Where an underground service raceway enters a building or structure.3. Where otherwise required by NFPA 70.

U. Comply with manufacturer's written instructions for solvent welding RNC and fittings.

V. Expansion-Joint Fittings:

1. Install in each run of aboveground RNC that is located where environmental temperature change may exceed 30 deg. F and that has straight-run length that exceeds 25 feet. Install

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 8

in each run of aboveground RMC, IMC, and EMT conduit that is located where environmental temperature change may exceed 100 deg F and that has straight-run length that exceeds 100 feet.

2. Install type and quantity of fittings that accommodate temperature change listed for each of the following locations:

a. Outdoor Locations Not Exposed to Direct Sunlight: 125 deg F temperature change.b. Outdoor Locations Exposed to Direct Sunlight: 155 deg F temperature change.c. Indoor Spaces Connected with Outdoors without Physical Separation: 125 deg F

temperature change.d. Attics: 135 deg temperature change.

3. Install fitting(s) that provide expansion and contraction for at least 0.00041 inch per foot of length of straight run per deg F of temperature change for PVC conduits. Install fitting(s) that provide expansion and contraction for at least 0.000078 inch per foot of length of straight run per deg F of temperature change for metal conduits.

4. Install expansion fittings at all locations where conduits cross building or structure expansion joints.

5. Install each expansion-joint fitting with position, mounting, and piston setting selected according to manufacturer's written instructions for conditions at specific location at time of installation. Install conduit supports to allow for expansion movement.

W. Flexible Conduit Connections: Comply with NEMA RV 3. Use a maximum of 72 inches of flexible conduit for recessed and semirecessed luminaires, equipment subject to vibration, noise transmission, or movement; and for transformers and motors.

1. Use LFMC in damp or wet locations subject to severe physical damage.2. Use LFMC in damp or wet locations not subject to severe physical damage.

X. Mount boxes at heights indicated on Drawings. If mounting heights of boxes are not individually indicated, give priority to ADA requirements. Install boxes with height measured to center of box unless otherwise indicated.

Y. Recessed Boxes in Masonry Walls: Saw-cut opening for box in center of cell of masonry block, and install box flush with surface of wall. Prepare block surfaces to provide a flat surface for a raintight connection between box and cover plate or supported equipment and box.

Z. Horizontally separate boxes mounted on opposite sides of walls so they are not in the same vertical channel.

AA. Locate boxes so that cover or plate will not span different building finishes.

BB. Support boxes of three gangs or more from more than one side by spanning two framing members or mounting on brackets specifically designed for the purpose.

CC. Fasten junction and pull boxes to or support from building structure. Do not support boxes by conduits.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 9

3.3 INSTALLATION OF UNDERGROUND CONDUIT

A. Direct-Buried Conduit:

1. Excavate trench bottom to provide firm and uniform support for conduit. Prepare trench bottom as specified in Section 312000 "Earth Moving" for pipe less than 6 inches in nominal diameter.

2. Install backfill as specified in Section 312000 "Earth Moving."3. After installing conduit, backfill and compact. Start at tie-in point, and work toward end

of conduit run, leaving conduit at end of run free to move with expansion and contraction as temperature changes during this process. Firmly hand tamp backfill around conduit to provide maximum supporting strength. After placing controlled backfill to within 12 inches of finished grade, make final conduit connection at end of run and complete backfilling with normal compaction as specified in Section 312000 "Earth Moving."

4. Install manufactured duct elbows for stub-ups at poles and equipment and at building entrances through floor unless otherwise indicated. Encase elbows for stub-up ducts throughout length of elbow.

5. Install manufactured rigid steel conduit elbows for stub-ups at poles and equipment and at building entrances through floor.

a. Couple steel conduits to ducts with adapters designed for this purpose, and encase coupling with 3 inches of concrete for a minimum of 12 inches on each side of the coupling.

b. For stub-ups at equipment mounted on outdoor concrete bases and where conduits penetrate building foundations, extend steel conduit horizontally a minimum of 60 inches from edge of foundation or equipment base. Install insulated grounding bushings on terminations at equipment.

6. Underground Warning Tape: Comply with requirements in Section 26 0553 "Identification for Electrical Systems."

3.4 INSTALLATION OF UNDERGROUND HANDHOLES AND BOXES

A. Install handholes and boxes level and plumb and with orientation and depth coordinated with connecting conduits to minimize bends and deflections required for proper entrances.

B. Unless otherwise indicated, support units on a level bed of crushed stone or gravel, graded from 1/2-inch sieve to No. 4 sieve and compacted to same density as adjacent undisturbed earth.

C. Elevation: In paved areas, set so cover surface will be flush with finished grade. Set covers of other enclosures 1 inch above finished grade.

D. Install handholes with bottom below frost line, below grade.

E. Install removable hardware, including pulling eyes, cable stanchions, cable arms, and insulators, as required for installation and support of cables and conductors and as indicated. Select arm lengths to be long enough to provide spare space for future cables but short enough to preserve adequate working clearances in enclosure.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 10

F. Field-cut openings for conduits according to enclosure manufacturer's written instructions. Cut wall of enclosure with a tool designed for material to be cut. Size holes for terminating fittings to be used, and seal around penetrations after fittings are installed.

3.5 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Section 260544 "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

3.6 FIRESTOPPING

A. Install firestopping at penetrations of fire-rated floor and wall assemblies. Comply with requirements in Section 078413 "Penetration Firestopping."

3.7 PROTECTION

A. Protect coatings, finishes, and cabinets from damage and deterioration.

1. Repair damage to galvanized finishes with zinc-rich paint recommended by manufacturer.

2. Repair damage to PVC coatings or paint finishes with matching touchup coating recommended by manufacturer.

END OF SECTION 26 0533

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 1

SECTION 26 0544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Sleeves for raceway and cable penetration of non-fire-rated construction walls and floors.2. Sleeve-seal systems.3. Sleeve-seal fittings.4. Grout.5. Silicone sealants.

B. Related Requirements:

1. Section 078413 "Penetration Firestopping" for penetration firestopping installed in fire-resistance-rated walls, horizontal assemblies, and smoke barriers, with and without penetrating items.

PART 2 - PRODUCTS

2.1 SLEEVES

A. Wall Sleeves:

1. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc coated, plain ends.

2. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop unless otherwise indicated.

B. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies: Galvanized-steel sheet; 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint, with tabs for screw-fastening the sleeve to the board.

C. PVC-Pipe Sleeves: ASTM D 1785, Schedule 40.

D. Molded-PVC Sleeves: With nailing flange for attaching to wooden forms.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 2

E. Molded-PE or -PP Sleeves: Removable, tapered-cup shaped, and smooth outer surface with nailing flange for attaching to wooden forms.

F. Sleeves for Rectangular Openings:

1. Material: Galvanized sheet steel.2. Minimum Metal Thickness:

a. For sleeve cross-section rectangle perimeter less than 50 inches and with no side larger than 16 inches, thickness shall be 0.052 inch.

b. For sleeve cross-section rectangle perimeter 50 inches or more and one or more sides larger than 16 inches, thickness shall be 0.138 inch.

2.2 SLEEVE-SEAL SYSTEMS

A. Description: Modular sealing device, designed for field assembly, to fill annular space between sleeve and raceway or cable.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Advance Products & Systems, Inc.b. CALPICO, Inc.c. Metraflex Company (The).d. Pipeline Seal and Insulator, Inc.e. Proco Products, Inc.

2. Sealing Elements: EPDM rubber interlocking links shaped to fit surface of pipe. Include type and number required for pipe material and size of pipe.

3. Pressure Plates: Carbon steel.4. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, of length

required to secure pressure plates to sealing elements.

2.3 SLEEVE-SEAL FITTINGS

A. Description: Manufactured plastic, sleeve-type, waterstop assembly made for embedding in concrete slab or wall. Unit shall have plastic or rubber waterstop collar with center opening to match piping OD.

1. Manufacturers: Subject to compliance with requirements, provide products by the following:

a. HOLDRITE.

2.4 GROUT

A. Description: Nonshrink; recommended for interior and exterior sealing openings in non-fire-rated walls or floors.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 3

B. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting, dry, hydraulic-cement grout.

C. Design Mix: 5000-psi, 28-day compressive strength.

D. Packaging: Premixed and factory packaged.

2.5 SILICONE SEALANTS

A. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric sealants of grade indicated below.

1. Grade: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces that are not fire rated.

2. Sealant shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

B. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, nonshrinking foam.

PART 3 - EXECUTION

3.1 SLEEVE INSTALLATION FOR NON-FIRE-RATED ELECTRICAL PENETRATIONS

A. Comply with NECA 1.

B. Comply with NEMA VE 2 for cable tray and cable penetrations.

C. Sleeves for Conduits Penetrating Above-Grade Non-Fire-Rated Concrete and Masonry-Unit Floors and Walls:

1. Interior Penetrations of Non-Fire-Rated Walls and Floors:

a. Seal annular space between sleeve and raceway or cable, using joint sealant appropriate for size, depth, and location of joint. Comply with requirements in Section 079200 "Joint Sealants."

b. Seal space outside of sleeves with mortar or grout. Pack sealing material solidly between sleeve and wall so no voids remain. Tool exposed surfaces smooth; protect material while curing.

2. Use pipe sleeves unless penetration arrangement requires rectangular sleeved opening.3. Size pipe sleeves to provide 1/4-inch annular clear space between sleeve and raceway or

cable unless sleeve seal is to be installed, or unless seismic criteria require different clearance.

4. Install sleeves for wall penetrations unless core-drilled holes or formed openings are used. Install sleeves during erection of walls. Cut sleeves to length for mounting flush with both surfaces of walls. Deburr after cutting.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 4

5. Install sleeves for floor penetrations. Extend sleeves installed in floors 2 inches above finished floor level. Install sleeves during erection of floors.

D. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies:

1. Use circular metal sleeves unless penetration arrangement requires rectangular sleeved opening.

2. Seal space outside of sleeves with approved joint compound for gypsum board assemblies.

E. Roof-Penetration Sleeves: Seal penetration of individual raceways and cables with flexible boot-type flashing units applied in coordination with roofing work.

F. Aboveground, Exterior-Wall Penetrations: Seal penetrations using steel pipe sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

G. Underground, Exterior-Wall and Floor Penetrations: Install cast-iron pipe sleeves. Size sleeves to allow for 1-inch annular clear space between raceway or cable and sleeve for installing sleeve-seal system.

3.2 SLEEVE-SEAL-SYSTEM INSTALLATION

A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at raceway entries into building.

B. Install type and number of sealing elements recommended by manufacturer for raceway or cable material and size. Position raceway or cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space between raceway or cable and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

3.3 SLEEVE-SEAL-FITTING INSTALLATION

A. Install sleeve-seal fittings in new walls and slabs as they are constructed.

B. Assemble fitting components of length to be flush with both surfaces of concrete slabs and walls. Position waterstop flange to be centered in concrete slab or wall.

C. Secure nailing flanges to concrete forms.

D. Using grout, seal the space around outside of sleeve-seal fittings.

END OF SECTION 26 0544

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 1

SECTION 26 0553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Identification for raceways.2. Identification of power and control cables.3. Identification for conductors.4. Underground-line warning tape.5. Warning labels and signs.6. Instruction signs.7. Equipment identification labels. Including, arc-flash warning labels.8. Miscellaneous identification products.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Brady Corporation.b. Panduit Corp.c. Seton Identification Productsd. Brother International Corporation.e. Ideal Industries, Inc.f. Carlton Industries, LP.g. Champion America.

2.2 PERFORMANCE REQUIREMENTS

A. Comply with NFPA 70, and NEC.

B. Comply with ANSI Z535.4 for safety signs and labels.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 2

2.3 COLOR AND LEGEND REQUIREMENTS

A. Raceways and Cables Carrying Circuits at 600 V or Less:

1. Legend: Indicate voltage and system or service type.

2.4 LABELS

A. Snap-Around Labels for Raceways and Cables Carrying Circuits at 600 V or Less: Slit, pretensioned, flexible, preprinted, color-coded acrylic sleeves, with diameters sized to suit diameters of raceways they identify, and that stay in place by gripping action.

B. Self-Adhesive Labels:

1. 3-mil- thick flexible label with acrylic pressure-sensitive adhesive.

2. Marker for Tags: Permanent, waterproof, black ink marker recommended by tag manufacturer.

2.5 TAPES AND STENCILS:

A. Marker Tapes: Vinyl or vinyl-cloth, self-adhesive wraparound type, with circuit identification legend machine printed by thermal transfer or equivalent process.

B. Self-Adhesive Vinyl Tape: Colored, heavy duty, waterproof, fade resistant; not less than 3 mils thick by 1 to 2 inches wide; compounded for outdoor use.

C. Underground-Line Warning Tape

1. Tape:

a. Recommended by manufacturer for the method of installation and suitable to identify and locate underground electrical and communications utility lines.

b. Printing on tape shall be permanent and shall not be damaged by burial operations.

c. Tape material and ink shall be chemically inert and not subject to degradation when exposed to acids, alkalis, and other destructive substances commonly found in soils.

2. Color and Printing:

a. Comply with ANSI Z535.1, ANSI Z535.2, ANSI Z535.3, ANSI Z535.4, and ANSI Z535.5.

b. Inscriptions for Red-Colored Tapes: "ELECTRIC LINE, HIGH VOLTAGE"

c. Inscriptions for Orange-Colored Tapes: "TELEPHONE CABLE, CATV CABLE, COMMUNICATIONS CABLE, OPTICAL FIBER CABLE".

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 3

2.6 Tags

A. Metal Tags: Brass or aluminum, 2 by 2 by 0.05 inch, with stamped legend, punched for use with self-locking cable tie fastener.

2.7 Signs

A. Baked-Enamel Signs:

1. Preprinted aluminum signs, punched or drilled for fasteners, with colors, legend, and size required for application.

2. 1/4-inch grommets in corners for mounting.3. Nominal Size: 7 by 10 inches

B. Laminated Acrylic or Melamine Plastic Signs:

1. Engraved legend.2. Thickness:

a. For signs up to 20 sq. inches, minimum 1/16-inch.b. For signs larger than 20 sq. inches, 1/8 inch thick.c. Engraved legend with white letters on black face. Provide white

letters on red face for emergency and life safety equipment. Provide white letters on blue face for UPS equipment.

d. Punched or drilled for mechanical fasteners/

2.8 CABLE TIES

A. Cable Ties: Fungus inert, self-extinguishing, one piece, self-locking, Type 6/6 nylon.

1. Minimum Width: 3/16 inch (5 mm).2. Color: Black, except where used for color-coding.

2.9 MISCELLANEOUS IDENTIFICATION PRODUCTS

A. Paint: Comply with requirements in painting Sections for paint materials and application requirements. Retain paint system applicable for surface material and location (exterior or interior).

B. Fasteners for Labels and Signs: Self-tapping, stainless-steel screws or stainless-steel machine screws with nuts and flat and lock washers.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 4

PART 3 - EXECUTION

3.1 PREPARATION

A. Self-Adhesive Identification Products: Before applying electrical identification products, clean substrates of substances that could impair bond, using materials and methods recommended by manufacturer of identification product.

3.2 INSTALLATION

A. Verify and coordinate identification names, abbreviations, colors, and other features with requirements in other Sections requiring identification applications, Drawings, Shop Drawings, manufacturer's wiring diagrams, and operation and maintenance manual. Use consistent designations throughout Project.

B. Install identifying devices before installing acoustical ceilings and similar concealment.

C. Verify identity of each item before installing identification products.

D. Install identification materials and devices at locations for most convenient viewing without interference with operation and maintenance of equipment. Install access doors or panels to provide view of identifying devices.

E. Apply identification devices to surfaces that require finish after completing finish work.

F. Attach signs and plastic labels that are not self-adhesive type with mechanical fasteners appropriate to the location and substrate.

G. Attach plastic raceway and cable labels that are not self-adhesive type with clear vinyl tape, with adhesive appropriate to the location and substrate.

H. Cable Ties: For attaching tags. Use general-purpose type, except as listed below:

1. Outdoors: UV-stabilized nylon.2. In Spaces Handling Environmental Air: Plenum rated.

I. Painted Identification: Comply with requirements in painting Sections for surface preparation and paint application.

J. Aluminum Wraparound Marker Labels and Metal Tags: Secure tight to surface of conductor or cable at a location with high visibility and accessibility.

K. System Identification Color-Coding Bands for Raceways and Cables: Each color-coding band shall completely encircle cable or conduit. Place adjacent bands of two-color markings in contact, side by side. Locate bands at changes in direction, at penetrations of walls and floors, at 40-foot maximum intervals in straight runs, and at 25-foot maximum intervals in congested areas.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 5

L. During backfilling of trenches, install continuous underground-line warning tape directly above cable or raceway at 6 to 8 inches below finished grade. Use multiple tapes where width of multiple lines installed in a common trench or concrete envelope exceeds 16 inches overall.

3.3 IDENTIFICATION SCHEDULE

A. Accessible Raceways, 600 V or Less, for Service, Feeder, and Branch Circuits.: Identify with self-adhesive vinyl tape applied in bands. Install labels at 30-foot maximum intervals.

B. Accessible Raceways and Cables within Buildings: Identify the covers of each junction and pull box of the following systems with self-adhesive vinyl labels containing the wiring system legend and system voltage. System legends shall be as follows:

1. "POWER."

C. Power-Circuit Conductor Identification, 600 V or Less: For conductors in vaults, pull and junction boxes, manholes, and handholes, use color-coding conductor tape to identify the phase.

1. Color-Coding for Phase and Voltage-Level Identification, 600 V or Less: Use colors listed below for ungrounded service, feeder, and branch circuit conductors.

a. Color shall be factory applied or field applied for sizes larger than No. 8 AWG if authorities having jurisdiction permit.

b. Colors for 208/120-V Circuits:

1) Phase A: Black.2) Phase B: Red.3) Phase C: Blue.

c. Field-Applied, Color-Coding Conductor Tape: Apply in half-lapped turns for a minimum distance of 6 inches from terminal points and in boxes where splices or taps are made. Apply last two turns of tape with no tension to prevent possible unwinding. Locate bands to avoid obscuring factory cable markings.

D. Control-Circuit Conductor Identification: For conductors and cables in pull and junction boxes, manholes, and handholes, use tags with the conductor or cable designation, origin, and destination.

E. Control-Circuit Conductor Termination Identification: For identification at terminations, provide labels with the conductor designation.

F. Conductors To Be Extended in the Future: Attach tags to conductors and list source.

G. Auxiliary Electrical Systems Conductor Identification: Identify field-installed alarm, control, and signal connections.

1. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, and pull points. Identify by system and circuit designation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 6

2. Use system of marker-tape designations that is uniform and consistent with system used by manufacturer for factory-installed connections.

3. Coordinate identification with Project Drawings, manufacturer's wiring diagrams, and operation and maintenance manual.

4. Label and paint the covers of the systems junction boxes as follows. Provide Kwal Howell colors as listed, or approved equal:

a. Fire Alarm Red Alert AC118R

H. Locations of Underground Lines: Identify with underground-line warning tape for power, lighting, communication, and control wiring and optical-fiber cable.

1. Install underground-line warning tape for direct-buried cables and cables in raceways.

I. Warning Labels for Indoor Cabinets, Boxes, and Enclosures for Power and Lighting,

1. Apply to exterior of door, cover, or other access.2. For equipment with multiple power or control sources, apply to door or cover of

equipment, including, but not limited to, the following:

a. Power-transfer switches.b. Controls with external control power connections.

J. Arc Flash Warning Labeling: Self-adhesive thermal transfer vinyl labels.

1. Comply with NFPA 70E and ANSI Z535.4.2. Comply with Section 260574 "Overcurrent Protective Device Arc-Flash Study"

requirements for arc-flash warning labels.

K. Operating Instruction Signs: Install instruction signs to facilitate proper operation and maintenance of electrical systems and items to which they connect. Install instruction signs with approved legend where instructions are needed for system or equipment operation.

L. Equipment Identification Labels: On each unit of equipment, install unique designation label that is consistent with wiring diagrams, schedules, and operation and maintenance manual. Apply labels to disconnect switches and protection equipment, central or master units, control panels, control stations, terminal cabinets, and racks of each system. Systems include power, lighting, control, communication, signal, monitoring, and alarm unless equipment is provided with its own identification.

1. Labeling Instructions:

a. Elevated Components: Increase sizes of labels and letters to those appropriate for viewing from the floor.

b. Fasten labels with appropriate mechanical fasteners that do not change the NEMA or NRTL rating of the enclosure.

c. Mark each device box and junction box with a permanent ink marker, indicating the circuit to which the device is connected: Example: LP1-12. Mark circuit number on exterior side of junction boxes located in accessible locations, and inside junction boxes in non-accessible locations.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 7

2. Equipment to be labeled with engraved, laminated acrylic or melamine plastic label, punched, or drilled for mechanical fasteners. Unless otherwise indicated, provide a single line of text with 1/2-inch high letters on 1-1/2-inch high label; where two lines of text are required, use labels 2 inches high:

a. Panelboards.b. Enclosures and electrical cabinets.c. Access doors and panels for concealed electrical items.d. Switchgear.e. Switchboards, including branch breakers or fusible switches.f. Variable-speed controllers.

S. Install Arc-flash hazard labels on the following equipment:

1. Service entrance equipment.2. Power distribution switchboards or panelboards.3. Branch panelboards.

END OF SECTION 26 0553

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 8

BLANK PAGE

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 1

SECTION 26 2416 - PANELBOARDS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Lighting and appliance branch-circuit panelboards.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of panelboard.

1. Include materials, switching and overcurrent protective devices, accessories, and components indicated.

2. Include dimensions and manufacturers' technical data on features, performance, electrical characteristics, ratings, and finishes.

B. Shop Drawings: For each panelboard and related equipment.

1. Include dimensioned plans, elevations, sections, and details.2. Show tabulations of installed devices with nameplates, conductor termination sizes,

equipment features, and ratings.3. Detail enclosure types including mounting and anchorage, environmental protection,

knockouts, corner treatments, covers and doors, gaskets, hinges, and locks.4. Detail bus configuration, current, and voltage ratings.5. Short-circuit current rating of panelboards and overcurrent protective devices.6. Detail features, characteristics, ratings, and factory settings of individual overcurrent

protective devices and auxiliary components.7. Include wiring diagrams for power, signal, and control wiring.8. Key interlock scheme drawing and sequence of operations.9. Include time-current coordination curves for each type and rating of overcurrent

protective device included in panelboards.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For panelboards and components to include in emergency, operation, and maintenance manuals. In addition to items specified in Section 01 "Operation and Maintenance Data," include the following:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 2

1. Manufacturer's written instructions for testing and adjusting overcurrent protective devices.

2. Time-current curves, including selectable ranges for each type of overcurrent protective device that allows adjustments.

1.5 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Keys: Two spares for each type of panelboard cabinet lock.2. Fuses for Fused Switches: Equal to 10 percent of quantity installed for each size and type,

but no fewer than three of each size and type.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: ISO 9001 or 9002 certified.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Remove loose packing and flammable materials from inside panelboards; install temporary electric heating (250 W per panelboard) to prevent condensation.

B. Handle and prepare panelboards for installation according to NECA 407 and NEMA PB 1.

1.8 FIELD CONDITIONS

A. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electric service according to requirements indicated:

1. Notify Owner no fewer than seven days in advance of proposed interruption of electric service.

2. Do not proceed with interruption of electric service without Owner's written permission.3. Comply with NFPA 70E.

1.9 WARRANTY

A. Manufacturer's Warranty: Manufacturer agrees to repair or replace panelboards that fail in materials or workmanship within specified warranty period.

1. Panelboard Warranty Period: 24 months from date of Substantial Completion.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 3

PART 2 - PRODUCTS

2.1 PANELBOARDS REQUIREMENTS

A. Fabricate and test panelboards according to IEEE 344 to withstand seismic forces defined in Section 26 0548 "Seismic Controls for Electrical Systems."

B. Product Selection for Restricted Space: Drawings indicate maximum dimensions for panelboards including clearances between panelboards and adjacent surfaces and other items. Comply with indicated maximum dimensions.

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

D. Comply with NEMA PB 1.

E. Comply with NFPA 70.

F. Enclosures: Flush and surface mounted, dead-front cabinets as indicated on the drawings.

1. Rated for environmental conditions at installed location.

a. Indoor Dry and Clean Locations: NEMA 250, Type 1.

2. Height: 84 inches maximum.3. Front: Secured to box with concealed trim clamps. For surface-mounted fronts, match

box dimensions; for flush-mounted fronts, overlap box. Trims shall cover all live parts and shall have no exposed hardware.

4. Hinged Front Cover: Entire front trim hinged to box and with standard door within hinged trim cover. Trims shall cover all live parts and shall have no exposed hardware.

5. Finishes:

a. Panels, back boxes, and Trim: Steel, or galvanized steel, factory finished immediately after cleaning and pretreating with manufacturer's standard two-coat, baked-on finish consisting of prime coat and thermosetting topcoat.

G. Incoming Mains:

1. Location: Convertible between top and bottom.2. Main Breaker: Main lug interiors up to 400 amperes shall be field convertible to main

breaker.

H. Phase, Neutral, and Ground Buses:

1. Material: Tin-plated aluminum, 98 percent conductivity.

a. Plating shall run entire length of bus.b. Bus shall be fully rated the entire length.

2. Interiors shall be factory assembled into a unit. Replacing switching and protective devices shall not disturb adjacent units or require removing the main bus connectors.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 4

3. Equipment Ground Bus: Adequate for feeder and branch-circuit equipment grounding conductors; bonded to box.

4. Full-Sized Neutral: Equipped with full-capacity bonding strap for service entrance applications. Mount electrically isolated from enclosure. Do not mount neutral bus in gutter.

I. Conductor Connectors: Suitable for use with conductor material and sizes.

1. Material: Tin-plated aluminum, 98 percent conductivity.2. Terminations shall allow use of 75 deg C rated conductors without derating.3. Size: Lugs suitable for indicated conductor sizes, with additional gutter space, if required,

for larger conductors.4. Main and Neutral Lugs: Mechanical type, with a lug on the neutral bar for each pole in

the panelboard.5. Ground Lugs and Bus-Configured Terminators: Mechanical type, with a lug on the bar

for each pole in the panelboard.6. Subfeed (Double) Lugs: Mechanical type suitable for use with conductor material. Locate

at same end of bus as incoming lugs or main device.

J. Future Devices: Panelboards shall have mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices.

K. Panelboard Short-Circuit Current Rating: Fully rated to interrupt symmetrical short-circuit current available at terminals. Assembly listed by an NRTL for 100 percent interrupting capacity.

1. Panelboards and overcurrent protective devices rated 240 V or less shall have short-circuit ratings as shown on Drawings, but not less than 10,000 A rms symmetrical.

2. Panelboards and overcurrent protective devices rated above 240 V and less than 600 V shall have short-circuit ratings as shown on Drawings, but not less than 14,000 A rms symmetrical.

2.2 POWER PANELBOARDS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company; GE Energy Management - Electrical Distribution.3. Siemens Energy.4. Square D; by Schneider Electric.

B. Panelboards: NEMA PB 1, distribution type.

C. Doors: Secured with vault-type latch with tumbler lock; keyed alike.

1. For doors more than 36 inches high, provide two latches, keyed alike.

D. Branch Overcurrent Protective Devices for Circuit-Breaker Frame Bolt-on circuit breakers..

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 5

2.3 DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company; GE Energy Management - Electrical Distribution.3. Siemens Energy.4. Square D; by Schneider Electric.

B. Fused Switch: NEMA KS 1, Type HD; clips to accommodate specified fuses; lockable handle.

1. Fused Switch Features and Accessories:

a. Standard ampere ratings and number of poles.b. Mechanical cover interlock with a manual interlock override, to prevent the

opening of the cover when the switch is in the on position. The interlock shall prevent the switch from being turned on with the cover open. The operating handle shall have lock-off means with provisions for three padlocks.

c. Auxiliary Contacts: Two normally open and normally closed contact(s) that operate with switch handle operation.

2.4 IDENTIFICATION

A. Panelboard Label: Manufacturer's name and trademark, voltage, amperage, number of phases, and number of poles shall be located on the interior of the panelboard door.

B. Breaker Labels: Faceplate shall list current rating, UL and IEC certification standards, and AIC rating.

C. Circuit Directory: Directory card inside panelboard door, mounted in metal frame with transparent protective cover.

1. Circuit directory shall identify specific purpose with detail sufficient to distinguish it from all other circuits.

D. Circuit Directory: Computer-generated circuit directory mounted inside panelboard door with transparent plastic protective cover.

1. Circuit directory shall identify specific purpose with detail sufficient to distinguish it from all other circuits.

2.5 ACCESSORY COMPONENTS AND FEATURES

A. Accessory Set: Include tools and miscellaneous items required for overcurrent protective device test, inspection, maintenance, and operation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 6

B. Portable Test Set: For testing functions of solid-state trip devices without removing from panelboard. Include relay and meter test plugs suitable for testing panelboard meters and switchboard class relays.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify actual conditions with field measurements prior to ordering panelboards to verify that equipment fits in allocated space in, and comply with, minimum required clearances specified in NFPA 70.

B. Receive, inspect, handle, and store panelboards according to NECA 407 and NEMA PB 1.1.

C. Examine panelboards before installation. Reject panelboards that are damaged, rusted, or have been subjected to water saturation.

D. Examine elements and surfaces to receive panelboards for compliance with installation tolerances and other conditions affecting performance of the Work.

E. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. Coordinate layout and installation of panelboards and components with other construction that penetrates walls or is supported by them, including electrical and other types of equipment, raceways, piping, encumbrances to workspace clearance requirements, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels.

B. Comply with NECA 1.

C. Install panelboards and accessories according to NECA 407 and NEMA PB 1.1.

D. Equipment Mounting:

1. Attach panelboard to the vertical finished or structural surface behind the panelboard.2. Comply with requirements for seismic control devices specified in Section 26 0548

"Seismic Controls for Electrical Systems."

E. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from panelboards.

F. Comply with mounting and anchoring requirements specified in Section 26 0548 "Seismic Controls for Electrical Systems."

G. Mount top of trim 90 inches above finished floor unless otherwise indicated.

H. Mount panelboard cabinet plumb and rigid without distortion of box.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 7

I. Mount recessed panelboards with fronts uniformly flush with wall finish and mating with back box.

J. Mounting panelboards with space behind is recommended for damp, wet, or dirty locations. The steel slotted supports in the following paragraph provide an even mounting surface and the recommended space behind to prevent moisture or dirt collection.

K. Mount surface-mounted panelboards to steel slotted supports a minimum of 5/8 inch in depth. Orient steel slotted supports vertically.

L. Install overcurrent protective devices and controllers not already factory installed.

1. Set field-adjustable, circuit-breaker trip ranges.2. Tighten bolted connections and circuit breaker connections using calibrated torque

wrench or torque screwdriver per manufacturer's written instructions.

M. Make grounding connections and bond neutral for services and separately derived systems to ground. Make connections to grounding electrodes, separate grounds for isolated ground bars, and connections to separate ground bars.

N. Install filler plates in unused spaces.

O. Stub six 1-inch empty conduits from panelboard into accessible ceiling space or space designated to be ceiling space in the future. Stub four 1-inch empty conduits into raised floor space or below slab not on grade.

P. Arrange conductors in gutters into groups and bundle and wrap with wire ties.

Q. Mount spare fuse cabinet in accessible location.

3.3 IDENTIFICATION

A. Identify field-installed conductors, interconnecting wiring, and components; install warning signs complying with requirements in Section 26 0553 "Identification for Electrical Systems."

B. Create a directory to indicate installed circuit loads; incorporate Owner's final room designations. Obtain approval before installing. Handwritten directories are not acceptable. Install directory inside panelboard door.

C. Panelboard Nameplates: Label each panelboard with a nameplate complying with requirements for identification specified in Section 26 0553 "Identification for Electrical Systems."

D. Device Nameplates: Label each branch circuit device in power panelboards with a nameplate complying with requirements for identification specified in Section 26 0553 "Identification for Electrical Systems."

E. Install warning signs complying with requirements in Section 26 0553 "Identification for Electrical Systems" identifying source of remote circuit.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 8

3.4 FIELD QUALITY CONTROL

A. Acceptance Testing Preparation:

1. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit.

2. Test continuity of each circuit.

B. Tests and Inspections:

1. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest.

C. Panelboards will be considered defective if they do not pass tests and inspections.

D. Prepare test and inspection reports, including a certified report that identifies panelboards included and that describes scanning results, with comparisons of the two scans. Include notation of deficiencies detected, remedial action taken, and observations after remedial action.

3.5 ADJUSTING

A. Adjust moving parts and operable components to function smoothly, and lubricate as recommended by manufacturer.

B. Set field-adjustable circuit-breaker trip ranges as indicated.

C. Circuit changes made during load balancing may negate color-coding of phases and circuits. If load balancing proves undesirable or is to be performed by others, delete "Load Balancing" Paragraph below.

D. Load Balancing: After Substantial Completion, but not more than 60 days after Final Acceptance, measure load balancing and make circuit changes. Prior to making circuit changes to achieve load balancing, inform Architect of effect on phase color coding.

1. Measure loads during period of normal facility operations.2. Perform circuit changes to achieve load balancing outside normal facility operation

schedule or at times directed by the Architect. Avoid disrupting services such as fax machines and on-line data processing, computing, transmitting, and receiving equipment.

3. After changing circuits to achieve load balancing, recheck loads during normal facility operations. Record load readings before and after changing circuits to achieve load balancing.

4. Tolerance: Maximum difference between phase loads, within a panelboard, shall not exceed 20 percent.

END OF SECTION 26 2416

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 1

SECTION 26 2726 - WIRING DEVICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Receptacles, receptacles with integral GFCI, and associated device plates.2. Weather-resistant receptacles.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton (Arrow Hart).2. Hubbell Incorporated; Wiring Device-Kellems.3. Leviton Manufacturing Co., Inc.4. Pass & Seymour/Legrand (Pass & Seymour).

B. Source Limitations: Obtain each type of wiring device and associated wall plate from single source from single manufacturer.

2.2 GENERAL WIRING-DEVICE REQUIREMENTS

A. Wiring Devices, Components, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

C. Devices that are manufactured for use with modular plug-in connectors may be substituted under the following conditions:

1. Connectors shall comply with UL 2459 and shall be made with stranding building wire.2. Devices shall comply with the requirements in this Section.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 2

2.3 STRAIGHT-BLADE RECEPTACLES

A. Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 Configuration 5-20R, UL 498, and FS W-C-596.

2.4 GFCI RECEPTACLES

A. General Description:

1. Straight blade, non-feed-through type.2. Comply with NEMA WD 1, NEMA WD 6, UL 498, UL 943 Class A, and FS W-C-596.3. Include indicator light that shows when the GFCI has malfunctioned and no longer

provides proper GFCI protection.

B. Duplex GFCI Convenience Receptacles, 125 V, 20 A.

C. Tamper-Resistant GFCI Convenience Receptacles, 125 V, 20 A.

D. Weather-Resistant GFCI Convenience Receptacles, 125 V, 20 A.

2.5 WALL PLATES

A. Single and combination types shall match corresponding wiring devices.

B. Wet-Location, Weatherproof Cover Plates: NEMA 250, complying with Type 3R, weather-resistant, die-cast aluminum with lockable cover.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with NECA 1, including mounting heights listed in that standard, unless otherwise indicated.

B. Coordination with Other Trades:

1. Protect installed devices and their boxes. Do not place wall finish materials over device boxes and do not cut holes for boxes with routers that are guided by riding against outside of boxes.

2. Keep outlet boxes free of plaster, drywall joint compound, mortar, cement, concrete, dust, paint, and other material that may contaminate the raceway system, conductors, and cables.

3. Install device boxes in brick or block walls so that the cover plate does not cross a joint unless the joint is troweled flush with the face of the wall.

4. Install wiring devices after all wall preparation, including painting, is complete.

C. Conductors:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 3

1. Do not strip insulation from conductors until right before they are spliced or terminated on devices.

2. Strip insulation evenly around the conductor using tools designed for the purpose. Avoid scoring or nicking of solid wire or cutting strands from stranded wire.

3. The length of free conductors at outlets for devices shall meet provisions of NFPA 70, Article 300, without pigtails.

4. Existing Conductors:

a. Cut back and pigtail, or replace all damaged conductors.b. Straighten conductors that remain and remove corrosion and foreign matter.c. Pigtailing existing conductors is permitted, provided the outlet box is large enough.

D. Device Installation:

1. Replace devices that have been in temporary use during construction and that were installed before building finishing operations were complete.

2. Keep each wiring device in its package or otherwise protected until it is time to connect conductors.

3. Do not remove surface protection, such as plastic film and smudge covers, until the last possible moment.

4. Connect devices to branch circuits using pigtails that are not less than 6 inches in length.

5. When there is a choice, use side wiring with binding-head screw terminals. Wrap solid conductor tightly clockwise, two-thirds to three-fourths of the way around terminal screw.

6. Use a torque screwdriver when a torque is recommended or required by manufacturer.7. When conductors larger than No. 12 AWG are installed on 15- or 20-A circuits, splice

No. 12 AWG pigtails for device connections.8. Tighten unused terminal screws on the device.9. When mounting into metal boxes, remove the fiber or plastic washers used to hold

device-mounting screws in yokes, allowing metal-to-metal contact.

3.2 IDENTIFICATION

A. Comply with Section 26 0553 "Identification for Electrical Systems."

B. Identify each receptacle with panelboard identification and circuit number. Use hot, stamped, or engraved machine printing with black -filled lettering on face of plate, and durable wire markers or tags inside outlet boxes.

3.3 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Test Instruments: Use instruments that comply with UL 1436.2. Test Instrument for Convenience Receptacles: Digital wiring analyzer with digital

readout or illuminated digital-display indicators of measurement.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 4

B. Tests for Convenience Receptacles:

1. Line Voltage: Acceptable range is 105 to 132 V.2. Percent Voltage Drop under 15-A Load: A value of 6 percent or higher is unacceptable.3. Ground Impedance: Values of up to 2 ohms are acceptable.4. GFCI Trip: Test for tripping values specified in UL 1436 and UL 943.5. Using the test plug, verify that the device and its outlet box are securely mounted.6. Tests shall be diagnostic, indicating damaged conductors, high resistance at the circuit

breaker, poor connections, inadequate fault current path, defective devices, or similar problems. Correct circuit conditions, remove malfunctioning units and replace with new ones, and retest as specified above.

C. Wiring device will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

END OF SECTION 26 2726

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 1

SECTION 26 2913 - MOTOR STARTERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes the following enclosed controllers rated 600 V and less:

1. Full-voltage manual.2. Full-voltage magnetic.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of enclosed controller. Include manufacturer's technical data on features, performance, electrical characteristics, ratings, and enclosure types and finishes.

B. Shop Drawings: For each enclosed controller. Include dimensioned plans, elevations, sections, details, and required clearances and service spaces around controller enclosures.

1. Show tabulations of the following:

a. Each installed unit's type and details.b. Factory-installed devices.c. Nameplate legends.d. Short-circuit current rating of integrated unit.e. Listed and labeled for integrated short-circuit current (withstand) rating of OCPDs

in combination controllers by an NRTL acceptable to authorities having jurisdiction.

f. Features, characteristics, ratings, and factory settings of individual OCPDs in combination controllers.

2. Wiring Diagrams: For power, signal, and control wiring.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

B. Load-Current and Overload-Relay Heater List: Compile after motors have been installed, and arrange to demonstrate that selection of heaters suits actual motor nameplate full-load currents.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 2

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For enclosed controllers to include in, operation, and maintenance manuals.

1. Routine maintenance requirements for enclosed controllers and installed components.2. Manufacturer's written instructions for testing, adjusting, and reprogramming reduced-

voltage solid-state controllers.

1.6 MATERIALS MAINTENANCE SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Fuses for Fused Switches: Equal to 10 percent of quantity installed for each size and type, but no fewer than three of each size and type.

1.7 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Store enclosed controllers indoors in clean, dry space with uniform temperature to prevent condensation. Protect enclosed controllers from exposure to dirt, fumes, water, corrosive substances, and physical damage.

1.9 PROJECT CONDITIONS

A. Environmental Limitations: Rate equipment for continuous operation under the following conditions unless otherwise indicated:

1. Ambient Temperature: Not less than minus 22 deg Fand not exceeding 104 deg F2. Altitude: Not exceeding 6600 feet.

1.10 COORDINATION

A. Coordinate layout and installation of enclosed controllers with other construction including conduit, piping, equipment, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels.

B. Coordinate installation of roof curbs, equipment supports, and roof penetrations.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 3

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company.3. Siemens Power Transmission & Distribution, Inc.4. Square D; by Schneider Electric.

B. Source Limitations: Obtain each enclosed controller type from single source from single manufacturer.

2.2 FULL-VOLTAGE CONTROLLERS

A. General Requirements for Full-Voltage Controllers: Comply with NEMA ICS 2, general purpose, Class A.

1. Configuration: Full Voltage Non reversing2. Red pilot light.

B. Fractional Horsepower Manual Starters: "Quick-make, quick-break" toggle or push-button action; marked to show whether unit is off, on, or tripped.

1. Overload Relays: Inverse-time-current characteristics; NEMA ICS 2, Class 10 tripping characteristics; heaters matched to nameplate full-load current of actual protected motor; external reset push button melting alloy type

2. Surface mounting.3. Green pilot light.

C. Integral Horsepower Manual Starters: "Quick-make, quick-break" toggle marked to show whether unit is off, on, or tripped.

1. Configuration: Non reversing 2. Overload Relays: Inverse-time-current characteristics; NEMA ICS 2, Class 10tripping

characteristics; heaters and sensors in each phase, matched to nameplate full-load current of actual protected motor and having appropriate adjustment for duty cycle; external reset push button melting alloy type

3. Surface mounting.4. Green pilot light.5. [N.O.] [N.C.] auxiliary contact.

D. Magnetic Starters: Full voltage, across the line, electrically held.

1. Configuration: Non reversing.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 4

2. Power Contacts: Totally enclosed, double-break, silver-cadmium oxide; assembled to allow inspection and replacement without disturbing line or load wiring.

3. Control Circuits: 120 V ac; obtained from integral CPT, with primary and secondary fuses with CPT of sufficient capacity to operate integral devices and remotely located pilot, indicating, and control devices.

4. Solid-State Overload Relay:

a. Switch or dial selectable for motor running overload protection.b. Sensors in each phase.c. Class 20 tripping characteristic selected to protect motor against voltage and

current unbalance and single phasing.

5. Provide (2) spare normally open (N.O.) and (2) spare normally closed (N.C.) contacts6. External overload reset push button.

E. Combination Magnetic Controller: Factory-assembled combination of magnetic controller, OCPD, and disconnecting means.

1. Fusible Disconnecting Means:

a. NEMA KS 1, heavy-duty, horsepower-rated, fusible switch with clips or bolt pads to accommodate Class R fuses.

b. Lockable Handle: Accepts three padlocks and interlocks with cover in closed position.

2. Auxiliary Contacts: (2) N.O./(2) N.C., arranged to activate before switch blades open.

2.3 ENCLOSURES

A. Enclosed Controllers: NEMA ICS 6, to comply with environmental conditions at installed location.

1. Dry and Clean Indoor Locations: Type 12. Outdoor Locations: Type 3R3. Other Wet or Damp Indoor Locations: Type 44. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Noncorrosive Liquids:

Type 12.

2.4 ACCESSORIES

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and surfaces to receive enclosed controllers, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 5

3.2 INSTALLATION

A. Wall-Mounted Controllers: Install enclosed controllers on walls with tops at uniform height unless otherwise indicated, and by bolting units to wall or mounting on lightweight structural-steel channels bolted to wall. For controllers not at walls, provide freestanding racks complying with Section 260529 "Hangers and Supports for Electrical Systems."

B. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from enclosures and components.

C. Install fuses in each fusible-switch enclosed controller.

D. Install fuses in control circuits if not factory installed. Install heaters in thermal overload relays. Select heaters based on actual nameplate full-load amperes after motors have been installed.

E. Install, connect, and fuse thermal-protector monitoring relays furnished with motor-driven equipment.

F. Comply with NECA 1.

3.3 IDENTIFICATION

A. Identify enclosed controllers, components, and control wiring. Comply with requirements for identification specified in Section 260553 "Identification for Electrical Systems."

1. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs.

2. Label each enclosure with engraved nameplate.3. Label each enclosure-mounted control and pilot device.

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Acceptance Testing Preparation:1. Test continuity of each circuit.

C. Tests and Inspections:

1. Inspect controllers, wiring, components, connections, and equipment installation2. Test insulation resistance for each enclosed-controller element, component, connecting

motor supply, feeder, and control circuits.3. Test continuity of each circuit.4. Verify that voltages at controller locations are within plus or minus 10 percent of motor

nameplate rated voltages. If outside this range for any motor, notify Architect Test each motor for proper phase rotation.

5. Perform each electrical test and visual and mechanical inspection stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 6

6. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest.

D. Enclosed controllers will be considered defective if they do not pass tests and inspections.

3.5 ADJUSTING

A. Set field-adjustable switches, auxiliary relays, time-delay relays, timers, and overload-relay pickup and trip ranges.

B. Adjust overload-relay heaters or settings if power factor correction capacitors are connected to the load side of the overload relays.

END OF SECTION 26 2913

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 1

SECTION 26 0100 – ELECTRICAL REQUIREMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. All sections of Division 26, 27, & 28 shall comply with this section. The standards established in this section as to quality of materials and equipment, the type and quality of workmanship, mode of operations, safety rules, code requirements, etc., shall apply to all sections of this Division as though they were repeated in each Division.

C. Architectural, Mechanical, Civil, Structural, and other applicable documents also apply to work of this section.

1.2 SUMMARY

A. Provide all labor, materials, and equipment as required for a complete operating and tested electrical system as described in the contract documents

B. Related Requirements, including but not limited to:

1. Section 02 "Existing Conditions”.2. Section 03 “Concrete”.3. Section 05 “Metals”.4. Section 06 “Woods Plastics, and Composites”.5. Section 07 “Thermal and Moisture Protection:6. Section 08 “Openings”.7. Section 09 “Finishes”.8. Section 31 “Earthwork”.

1.3 CODES & ORDINANCES

A. All work shall be executed in accordance with all underwriters, public utilities, local and state codes, rules, and regulations applicable to the trade affected. Where work required by the drawings or specifications exceeds the codes rules, and regulations, it shall be done according to the documents. Where conflicts occur, the most stringent requirements shall apply.

B. Applicable codes: Work shall comply with currently adopted Edition:

1. International Building code 2. International Fire Code3. International Energy Code4. National Electrical Code

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 2

5. International Mechanical Code6. International Plumbing Code.

1.4 INDUSTRY STANDARDS

A. All work and equipment shall comply with the following standards. These standards refer to the latest adopted or published edition. Where conflicts occur, the most stringent requirement shall apply.

1. ETL Testing Laboratories (ETL)2. Institute of Electrical and Electronic Engineers (IEEE)3. National Fire Protection Association (NFPA)4. National Electrical Manufacturers Association (NEMA)5. National Electrical Safety code (NESC)6. Utah Safety Standard (OSHA), Utah State Industrial Council.7. Underwriters Laboratories (UL)8. Illuminating Engineering Society (IES)1. Certified Ballast Manufacturers (CBM) 2. American Society for testing Materials (ASTM)3. Insulated Cable Engineers Association (ICEA)9. American National Standards Institute (ANSI)10. EIA/TIA

B. Compliance Verification:

1. Manufactured equipment which is represented by a UL classification and/or listing, shall bear the UL or equivalent ETL label.

1.5 INTERPRETATION OF DRAWINGS

A. Carefully review the documents prior to bid. Submit requests for clarification to the Architect/Engineer in writing prior to final addendum.

B. Electric equipment is shown at a small scale, and is shown at its approximate location only. The drawings shall not be scaled for roughing in measurements, except where dimensions are specifically shown. Refer to the Architectural and Mechanical drawings, and coordinate with applicable shop drawings of other trades, to locate electrical equipment. Coordinate with other trades to avoid interferences, and to provide sufficient space for the installation of all equipment. Where conflicts occur, notify the Architect in writing, for clarification.

C. Visit the site prior to bid to determine how existing conditions shall affect the electrical installation. Include all costs required due to existing site conditions in the bid.

1.6 DEFINITIONS

A. Provide: Furnish, install, and connect, unless noted otherwise.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 3

B. Furnish: Purchase and deliver to the site. Include all essential items for performing the function.

C. Install: Physically install the equipment per industry standards, codes, and Contract Documents.

D. Connect: Make final connections to the equipment, and place into operation per manufacturer’s instructions.

1.7 SAFETY REGULATION

A. Comply with all local, State, Federal, and OSHA safety requirements in performance with this work. Refer to the General Conditions. Provide equipment, supervision, construction, procedures, and all other necessary items to assure safety to life and property.

1.8 UTILITIES & FEES

A. Include all fees for permits, inspections, and utility connections required by work of this Division, unless noted otherwise. The Contractor shall obtain the necessary permits to perform the work unless noted otherwise,

B. Provide connections to new and existing utilities, as shown on the documents.

1.9 SUBMITTALS AND SHOP DRAWINGS

A. As soon as possible after the contract is awarded, the Contractor shall submit to the Architect, the manufacturer’s data on products and materials, and shop drawings, to be used in the installation of electrical systems for this project. Review of the submitted data will require a minimum of 14 days. The first day starts after the day they are received in the Engineer’s office. If the Contractors schedule requires return of submitted literature in less than the allotted time, the Contractor shall accelerate his submittal delivery date. The Contractor shall resubmit all items requiring re-review within 14 days of returned submittals. Refer to each specification section for items requiring submittal review.

B. Written approval of the Owner's Representative shall be obtained before installing any equipment or materials for the project. Review of the submittals by the Owner’s Representative is for general conformance with the Contract Documents and shall not relieve the Contractor from compliance with the Contract Documents.

C. Verify all dimensional information to insure proper clearance for installation of equipment. Submitted literature shall bear the Contractor's stamp, indicating that he has reviewed all equipment being submitted; that each item will fit within the available space. Notify the Architect, in writing, for additional instructions where proposed equipment is found to be in conflict with available space.

D. By description, catalog number, and manufacturer's names, standards of quality have been established by the Architect and the Engineer for certain manufactured equipment items and specialties that are to be furnished by this Division. Alternate products and equipment may be

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 4

proposed for use only if specifically named in the specifications, or if given written prior approval in published addenda. Design equipment is the equipment listed on the drawings, or if not listed on the drawings is the equipment first named in the specifications.

E. If the Engineer is required to do additional design work to incorporate changes caused by submitting equipment or products, different than the design equipment specified, as defined above, the contractor shall reimburse the engineer for additional time and expenses at the engineer’s current, recognized, hourly rates.

F. Submittal Format: Unless noted otherwise in the General Conditions, the project submittals may be submitted in electronic format as noted below. Partial submittals will not be reviewed until the complete submittal is received. Provide copies of the descriptive literature covering products and materials to be used in the installation of electrical systems for this project for review.

1. Electronic Submittal Format: Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single specification section and transmittal form with links enabling navigation to each item. Name file with submittal number or other unique identifier, including revision identifier. Electronic file shall be completely electronically searchable or it will be rejected. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by the Architect

2. The title sheet of the submittal shall contain the project name, date of submission, Architect, Contractor, Sub Contractors, Suppliers, specification section number and title.

3. Provide a statement on the title sheet that the shop drawings comply with, and are submitted in accordance with the contract documents.

4. Provide manufacturer’s equipment cut sheets, brochures, and drawings which describe the proposed equipment. All relevant information shall be identified.

5. Submit electrical room layouts for all electrical rooms showing equipment dimensions and required clearances.

6. The drawings shall not be scaled for roughing in measurements nor shall they be used as shop drawings. Where drawings are required for these purposes or where drawings must be made from field measurements, the Contractor shall take the necessary measurements and prepare the drawings. Shop drawings of the various subcontractors shall be coordinated to eliminate all interferences and to provide sufficient space for the installation of all equipment.

1.10 OPERATING AND MAINTENANCE MANUALS

A. Unless noted otherwise in the General Conditions, submit one (1) copy in PDF format. Follow same compilation format as listed for Electronic Submittal Format.

B. Provide manufacturer's operating and maintenance instructions. Provide vendor's name, address, and phone number. List model and serial number for each piece of equipment. Include list of replacement parts and service schedules. Provide wiring diagrams and manufacturer’s warranties.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 5

1.11 RECORD DRAWINGS

A. Refer to the General Conditions for As-Built Drawing submission requirements.

B. Keep one complete hard copy set of the contract documents on site. Record on a daily basis, any modifications to the documents due to addendums, changes, and field conditions. Show dimensions for concealed work including conduits buried below slab or below grade, concrete ductbanks, direct burial cable, utility lines, etc.

1.12 WARRANTY

A. In addition to the requirements of the General Conditions, warranty the complete electrical installation to be in accordance with the contract documents, to be free from defects and in proper working order. Repair or replace any defective equipment or installation for a period of one (1) year from the date of final acceptance, or as noted otherwise. Defective lamps shall be replaced for a period of two (2) months from the date of final acceptance.

B. Submit written warranties and guarantees. List the Project name and the Contractor’s business name and contact information.

C. Submit warranty information for each product including name, address, and telephone number of warranty service. Include procedures for filing a claim.

PART 2 - PRODUCTS

2.1 GENERAL

A. All materials shall be new unless specifically noted otherwise.

2.2 SUBSTITUTIONS:

A. Substitutions of specified products, approved installers, etc. may be considered prior to bid. Submit proposed substitutions a minimum of eight (8) working days prior to the bid date. Provide complete information for proposed equipment including catalog cut sheets. Certify that the proposed equipment is equal to the specified equipment. Where substitution of a proposed installer is requested, submit company/installer’s resume indicating years of experience, certifications, etc. Any allowed substitutions shall be included in the addendum. Do not bid unapproved equipment or work by unapproved installers.

B. Provide samples as requested by the Architect/Engineer for review of proposed equipment prior to bid.

C. Substituted equipment shall comply with the intent of the contract documents. The Contactor shall bear all costs arising from conflicts arising due to the use of substituted equipment.

D. Value engineering substitutions shall not be offered by the Contractor without a request from the Architect/Engineer. Vendors offering value engineered product substitutions, without the

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 6

permission and involvement of the Architect/Engineer, shall be forfeited from bidding future projects.

2.3 SPARE PARTS

A. Provide spare parts as specified in Divisions 26, 27, and 28 sections. Deliver spare parts to the Owner's Representative prior to substantial completion. Obtain written receipt and include with as-built drawing submission.

PART 3 - EXECUTION

3.1 CUTTING AND PATCHING

A. No cutting or drilling of structural members shall be done without written approval of the Architect. The work shall be carefully laid out in advance, and cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings, or other surfaces necessary for the electrical work shall be carefully done. Any damage to building, piping, or equipment shall be repaired by professional plasterers, masons, concrete workers, etc., and all such work shall be paid for as work of this Division.

B. When concrete, asphalt, grading landscaping, etc., is disturbed, it shall be restored to original condition as described in the applicable Division of this Specification.

C. Provide roof jacks and flange extending a minimum of 9 inches under roofing materials, for raceways and cables which penetrate the roof. Seal opening with approved sealant. Provide drip loop for cables, and weather head on raceway, which penetrates the roof. Coordinate installation requirements with Division 7.

D. Seal and caulk as required to waterproof all conduit penetrations. Any penetrations through vapor barriers shall be made vapor tight. See Division 7, Thermal and Moisture Protection for material and installation requirements.

3.2 EXCAVATION AND BACKFILLING

A. All necessary excavations and backfilling for the electrical work shall be provided as work of this Division. Trenches for all underground raceways and ductbanks shall be excavated to the required depths. The bottom of trenches shall be compacted hard and graded to obtain required fall. Backfill shall be placed in horizontal layers, not exceeding 12 inches in thickness, and properly moistened. Each layer shall be compacted, by suitable equipment, to a density of not less than 95 percent as determined by ASTM D-1557. After raceways have been, inspected, and approved, the trench shall be backfilled with selected material. Excess earth shall be hauled from the job site. Fill materials approved by the Architect shall be provided as work of this Division.

B. Locate and protect existing utilities and other underground work prior to excavation. Insure that damage or service interruption will not result from excavation and backfilling.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 7

C. No trenches shall be cut near or under any footings without consultation first with the Architect's office. Any trenches or excavations more than 30 inches deep shall be tapered, shored, covered, or otherwise made absolutely safe so that no vehicle or persons can be injured by falling into such excavations, or in any way be harmed by cave-ins, shifting earth, rolling rocks, or by drowning. This protection shall be extended to all persons approaching excavation related to this work whether or not such persons are authorized to be in the vicinity of the construction.

D. Provide safety equipment at excavations such as barricades, warning signs, and illumination to protect against injury.

3.3 ACCESS

A. Provide access doors in walls, ceilings and floors for access to electrical equipment such as junction boxes, pull boxes, cable trays, etc. Refer to Division 8 for door specifications. All access doors shall be 24" x 24" unless noted otherwise. Coordinate location of doors with the Architect prior to installation. If doors are not specified in Division 8, provide the following: Doors in ceilings and wall shall be equal to JR Smith No. 4760 bonderized and painted. Doors in tile walls shall be equal to JR Smith No. 4730 chrome plated. Doors in floors shall be equal to JR Smith No. 4910.

B. Provide block-outs, sleeves, demolition work, etc., required for installation of work specified in this Division.

3.4 CLEANING AND PAINTING

A. Upon completion of all tests and adjustments, and all systems have been pronounced satisfactory for permanent operation, clean all exposed raceway, junction boxes, pullboxes, fixtures, etc. and leave them ready for painting. Refinish any damaged finish, and leave everything in proper working order.

B. Remove all stains, finger marks, and grease marks on walls, floors, glass, hardware, fixtures, or elsewhere, caused by work of this Division. Clean light fixtures and interior and exterior of all electrical equipment.

C. Painting of exposed raceway, junction boxes, pullboxes, surface metal raceway, etc., is work of Division 9, Painting.

D. All equipment which is indicated to be furnished in factory prefinished conditions, and painted by the Electrical Contractor shall be left without mark, scratch, or impairment to finish upon completion of job. Any necessary refinishing to match original shall be done. Do not paint over nameplates, serial numbers, or other identifying marks.

E. Upon completion of work of this Division, remove all surplus material and rubbish resulting from this work, and leave the premises in a clean and orderly condition.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

ELECTRICAL REQUIREMENTS 26 0100 - 8

3.5 PROTECTION AGAINST WEATHER AND STORING OF MATERIALS

A. All equipment and materials shall be properly stored and protected against damage, theft, moisture, dust, and wind. Coverings or other protection shall be used on all items that may be damaged or rusted or may have performance impaired by adverse weather or moisture conditions. Damage or defect developing before acceptance of the work shall be made good at the Contractor's expense.

3.6 POWER OUTAGES:

A. Power outages, as required for installation of electrical work, shall be scheduled with the Owner a minimum of (7) days prior to outages, and shall be performed during non-standard working hours, unless noted otherwise. Include all costs in bid for overtime hours and utility company disconnection and reconnection fees.

3.7 EQUIPMENT STARTUP AND TESTING:

A. Each major piece of equipment shall be started and tested by an authorized representative of the equipment manufacturer. A certificate indicating the equipment is operating to the satisfaction of the manufacturer shall be provided, and shall be included with the Warranty.

B. Notify Architect/Engineer prior to all testing for this Division, a minimum of three (3) business days prior to testing. Engineer shall observe all tests to insure the proper operation of the electrical system.

C. The Manufacturer’s Representative shall provide instructions to the owner's maintenance personnel for operation and maintenance of the equipment.

3.8 FINAL REVIEW:

A. The Project Forman shall accompany the Engineer and remove coverplates, panelboard covers, access panels, etc. as requested, to allow review of the entire electrical system.

END OF SECTION 26 0100

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 1

SECTION 26 0519 - CONDUCTORS AND CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Building wires and cables rated 600 V and less.2. Connectors, splices, and terminations rated 600 V and less.

1.3 SUBMITTALS

A. Product Data: For each type of product.

1.4 QUALITY ASSURANCE

A. Testing Agency Qualifications: Member company of NETA or an NRTL.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

PART 2 - PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Belden Inc.2. Cooper Industries, Inc.3. General Cable Technologies Corporation.4. General Cable; General Cable Corporation.5. Senator Wire & Cable Company.6. Southwire Company.7. Thomas & Betts Corporation, A Member of the ABB Group.

B. Conductors: Comply with NEMA WC 70/ICEA S-95-658.

C. Conductor Insulation: Comply with NEMA WC 70/ICEA S-95-658.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 2

2.2 CONNECTORS AND SPLICES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. 3M.2. AFC Cable Systems; a part of Atkore International.3. Hubbell Power Systems, Inc.4. Ideal Industries, Inc.5. ILSCO.6. O-Z/Gedney; a brand of Emerson Industrial Automation.

B. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

2.3 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

PART 3 - EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Stranded for No. 12 AWG and larger.

3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING METHODS

A. Feeders: Type THHN/THWN-2 for 400 KCMIL and below, and Type XHHW-2, for 500 KCMIL and larger.

B. Branch Circuits, Type THHN/THWN-2. Provide minimum #12 AWG.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Conceal cables in finished walls, ceilings, and floors unless otherwise indicated.

B. Complete raceway installation between conductor and cable termination points according to Section 260533 "Raceways and Boxes for Electrical Systems" prior to pulling conductors and cables.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 3

C. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

D. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

E. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours where possible.

F. Support cables according to Section 260529 "Hangers and Supports for Electrical Systems."

G. Do not exceed three phase conductors in any conduit, unless noted otherwise.

H. Provide separate neutral conductor for each single phase branch circuit. Shared neutrals are not allowed, except where noted otherwise.

I. Voltage Drop: Increase branch circuit by one wire size when circuit length exceeds 100’ and by two wire sizes when circuit length exceeds 200’.

3.4 CONNECTIONS

A. Tighten electrical connectors and terminals according to manufacturer's published torque-tightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A-486B.

B. Make splices, terminations, and taps that are compatible with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

C. Wiring at Outlets: Install conductor at each outlet, with at least 6 inches of slack.

3.5 IDENTIFICATION

A. Identify and color-code conductors and cables according to Section 260553 "Identification for Electrical Systems."

B. Identify each spare conductor at each end with identity number and location of other end of conductor, and identify as spare conductor.

3.6 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Section 260544 "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

CONDUCTORS AND CABLES 26 0519 - 4

3.7 FIRESTOPPING

A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly according to Section 078413 "Penetration Firestopping."

3.8 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. After installing conductors and cables and before electrical circuitry has been energized, test service entrance and feeder conductors for compliance with requirements.

2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

B. Cables will be considered defective if they do not pass tests and inspections.

END OF SECTION 26 0519

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 1

SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes grounding and bonding systems and equipment.

1.3 QUALITY ASSURANCE

A. Testing Agency Qualifications: Member company of NETA or an NRTL.

1. Testing Agency's Field Supervisor: Certified by NETA to supervise on-site testing.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Comply with UL 467 for grounding and bonding materials and equipment.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Burndy; Part of Hubbell Electrical Systems.2. ILSCO.3. O-Z/Gedney; a brand of Emerson Industrial Automation.4. Thomas & Betts Corporation, A Member of the ABB Group.

2.2 SYSTEM DESCRIPTION

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with UL 467 for grounding and bonding materials and equipment.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 2

2.3 CONDUCTORS

A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

2.4 CONNECTORS

A. Listed and labeled by an NRTL acceptable to authorities having jurisdiction for applications in which used and for specific types, sizes, and combinations of conductors and other items connected.

B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy.

PART 3 - EXECUTION

3.1 APPLICATIONS

A. Conductors:

1. Provide grounding conductors with stranding and insulation types to match phase conductors.

3.2 EQUIPMENT GROUNDING

A. Install insulated equipment grounding conductors with all feeders and branch circuits.

B. Install insulated equipment grounding conductors with the following items, in addition to those required by NFPA 70:

1. Feeders and branch circuits.2. Receptacle circuits.3. Single-phase motor and appliance branch circuits.4. Three-phase motor and appliance branch circuits.5. Flexible raceway runs.

3.3 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 3

1. After installing grounding system but before permanent electrical circuits have been energized, test for compliance with requirements.

2. Inspect physical and mechanical condition. Verify tightness of accessible, bolted, electrical connections with a calibrated torque wrench according to manufacturer's written instructions.

C. Grounding system will be considered defective if it does not pass tests and inspections.

END OF SECTION 26 0526

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 0526 - 4

BLANK PAGE

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 1

SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Hangers and supports for electrical equipment and systems.2. Construction requirements for concrete bases.

B. Related Requirements:

1. Section 260548 "Seismic Controls for Electrical Systems" for products and installation requirements necessary for compliance with seismic criteria.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for the following:

a. Hangers.b. Steel slotted support systems.c. Trapeze hangers.d. Clamps.

2. Include rated capacities and furnished specialties and accessories.

B. Shop Drawings: Signed and sealed by a qualified professional engineer. For fabrication and installation details for electrical hangers and support systems.

1. Trapeze hangers. Include product data for components.2. Steel slotted-channel systems.3. Equipment supports.

C. Delegated-Design Submittal: For hangers and supports for electrical systems.

1. Include design calculations and details of trapeze hangers.2. Include design calculations for seismic restraints.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 2

D. Seismic Qualification Certificates: For hangers and supports for electrical equipment and systems, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

E. Welding certificates.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Delegated Design: Engage a qualified professional engineer, as defined in Section 014000 "Quality Requirements," to design hanger and support system.

B. Seismic Performance: Hangers and supports shall withstand the effects of earthquake motions determined according to ASCE/SEI 7.

1. The term "withstand" means "the supported equipment and systems will remain in place without separation of any parts when subjected to the seismic forces specified.

2. Retain "Surface-Burning Characteristics" Paragraph below for nonmetallic slotted-channel system and accessories.

C. Surface-Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1. Flame Rating: Class 1.2. Self-extinguishing according to ASTM D 635.

2.2 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS

A. Steel Slotted Support Systems: Comply with MFMA-4 factory-fabricated components for field assembly.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Allied Tube & Conduit; a part of Atkore International.b. B-line, an Eaton business.c. ERICO International Corporation.d. Flex-Strut Inc.e. GS Metals Corp.f. G-Strut.g. Haydon Corporation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 3

h. Metal Ties Innovation.i. Thomas & Betts Corporation; A Member of the ABB Group.j. Unistrut; Part of Atkore International.k. Wesanco, Inc.

2. Material: Galvanized steel. 3. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-

4.4. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating

applied according to MFMA-4.5. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-

4.6. Protect finishes on exposed surfaces from damage by applying a strippable, temporary

protective covering before shipping.7. Channel Dimensions: Selected for applicable load criteria.

B. Aluminum Slotted Support Systems: Comply with MFMA-4 factory-fabricated components for field assembly.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Cooper Industries, Inc.b. Flex-Strut Inc.c. Haydon Corporation.d. MKT Metal Manufacturing.e. Thomas & Betts Corporation; A Member of the ABB Group.f. Unistrut; Part of Atkore International.

2. Nonmetallic Coatings: Manufacturer's standard PVC, polyurethane, or polyester coating applied according to MFMA-4.

3. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-4.

4. Protect finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

5. Channel Dimensions: Selected for applicable load criteria.

C. Conduit and Cable Support Devices: Steel hangers, clamps, and associated fittings, designed for types and sizes of raceway or cable to be supported.

D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for nonarmored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be made of malleable iron.

E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M steel plates, shapes, and bars; black and galvanized.

F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 4

1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) Hilti, Inc.2) ITW Ramset/Red Head; Illinois Tool Works, Inc.3) MKT Fastening, LLC.4) Simpson Strong-Tie Co., Inc.

2. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel [stainless steel], for use in hardened portland cement concrete, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used.

a. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1) B-line, an Eaton business.2) Empire Tool and Manufacturing Co., Inc.3) Hilti, Inc.4) ITW Ramset/Red Head; Illinois Tool Works, Inc.5) MKT Fastening, LLC.

3. Concrete Inserts: Steel or malleable-iron, slotted support system units are similar to MSS Type 18 units and comply with MFMA-4 or MSS SP-58.

4. Clamps for Attachment to Steel Structural Elements: MSS SP-58 units are suitable for attached structural element.

5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325.6. Toggle Bolts: All-steel springhead type.7. Hanger Rods: Threaded steel.

2.3 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES

A. Description: Welded or bolted structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

B. Materials: Comply with requirements in Section 055000 "Metal Fabrications" for steel shapes and plates.

PART 3 - EXECUTION

3.1 APPLICATION

A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems unless requirements in this Section are stricter.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 5

B. Comply with requirements for raceways and boxes specified in Section 260533 "Raceways and Boxes for Electrical Systems."

C. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMTs, IMCs, and RMCs as scheduled in NECA 1, where its Table 1 lists maximum spacings that are less than those stated in NFPA 70. Minimum rod size shall be 1/4 inch in diameter.

D. Space supports for raceways within 12 inches of each coupling, fitting, and box, at every 90 degree bend, and provide a minimum of two supports per ten foot run.

E. Multiple Raceways or Cables: Install trapeze-type supports fabricated with steel slotted support system, sized so capacity can be increased by at least 25 percent in future without exceeding specified design load limits.

1. Secure raceways and cables to these supports with single-bolt conduit clamps.

F. Spring-steel clamps designed for supporting single conduits without bolts may be used for 1-1/2-inch and smaller raceways serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports.

3.2 SUPPORT INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this article.

B. Raceway Support Methods: In addition to methods described in NECA 1, metal raceways may be supported by openings through structure members, according to NFPA 70.

C. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb.

D. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:

1. To Wood: Fasten with lag screws or through bolts.2. To New Concrete: Bolt to concrete inserts.3. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor

fasteners on solid masonry units.4. To Existing Concrete: Expansion anchor fasteners.5. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock

washers and nuts may be used in existing standard-weight concrete 4 inches (100 mm) thick or greater. Do not use for anchorage to lightweight-aggregate concrete or for slabs less than 4 inches thick.

6. To Steel: Beam clamps (MSS SP-58, Type 19, 21, 23, 25, or 27), complying with MSS SP-69.

7. To Light Steel: Sheet metal screws.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 0529 - 6

8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches, control enclosures, pull and junction boxes, transformers, and other devices on slotted-channel racks attached to substrate by means that comply with seismic-restraint strength and anchorage requirements.

E. Drill holes for expansion anchors in concrete at locations and to depths that avoid the need for reinforcing bars.

3.3 INSTALLATION OF FABRICATED METAL SUPPORTS

A. Comply with installation requirements in Section 055000 "Metal Fabrications" for site-fabricated metal supports.

B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

C. Field Welding: Comply with AWS D1.1/D1.1M.

3.4 PAINTING

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils. Retain "Touchup" Paragraph below if a painting Section is in Project Manual.

B. Touchup: Comply with requirements in Section 09 for cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal.

C. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780.

END OF SECTION 26 0529

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 1

SECTION 26 0533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Metal conduits, tubing, and fittings.2. Nonmetal conduits, and fittings.3. Metal wireways and auxiliary gutters.4. Boxes, enclosures, and cabinets.5. Surface raceway.6. Handholes and boxes for exterior underground cabling.

1.3 SUBMITTALS

A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

B. Shop Drawings: For custom enclosures and cabinets. Include plans, elevations, sections, and attachment details.

PART 2 - PRODUCTS

2.1 METAL CONDUITS, TUBING, AND FITTINGS

A. Listing and Labeling: Metal conduits, tubing, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. GRC: Comply with ANSI C80.1 and UL 6.

C. IMC: Comply with ANSI C80.6 and UL 1242.

D. EMT: Comply with ANSI C80.3 and UL 797.

E. FMC: Comply with UL 1; zinc-coated steel.

F. LFMC: Flexible steel conduit with PVC jacket and complying with UL 360.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 2

G. Fittings for Metal Conduit: Comply with NEMA FB 1 and UL 514B.

1. Conduit Fittings for Hazardous (Classified) Locations: Comply with UL 886 and NFPA 70.

2. Fittings for EMT:

a. Material: Steel. b. Type: Setscrew.

3. Expansion Fittings: PVC or steel to match conduit type, complying with UL 651, rated for environmental conditions where installed, and including flexible external bonding jumper.

H. Joint Compound for IMC, or GRC: Approved, as defined in NFPA 70, by authorities having jurisdiction for use in conduit assemblies, and compounded for use to lubricate and protect threaded conduit joints from corrosion and to enhance their conductivity.

2.2 NONMETALLIC CONDUITS AND FITTINGS

A. Listing and Labeling: Nonmetallic conduits, and fittings shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. RNC: Type EPC-40-PVC complying with NEMA TC 2 and UL 651 unless otherwise indicated.

C. Fittings for RNC: Comply with NEMA TC 3; match to conduit type and material.

2.3 METAL WIREWAYS AND AUXILIARY GUTTERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. B-line, an Eaton business.2. Hoffman; a brand of Pentair Equipment Protection.3. MonoSystems, Inc.4. Square D.

B. Description: Sheet metal, complying with UL 870 and NEMA 250, and sized according to NFPA 70.

1. Metal wireways installed outdoors shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Fittings and Accessories: Include covers, couplings, offsets, elbows, expansion joints, adapters, hold-down straps, end caps, and other fittings to match and mate with wireways as required for complete system.

D. Wireway Covers: Screw-cover type unless otherwise indicated.

E. Finish: Manufacturer's standard enamel finish.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 3

2.4 SURFACE RACEWAYS

A. Listing and Labeling: Surface raceways shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Surface Metal Raceways: Galvanized steel with snap-on covers complying with UL 5. Manufacturer's standard enamel finish in color selected by Architect.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Hubbell Incorporated; Wiring Device-Kellems.b. MonoSystems, Inc.c. Panduit Corp.d. Wiremold / Legrand.

C. Surface Nonmetallic Raceways: Two- or three-piece construction, complying with UL 5A, and manufactured of rigid PVC with texture and color selected by Architect from manufacturer's standard colors. Product shall comply with UL 94 V-0 requirements for self-extinguishing characteristics.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Hubbell Incorporated.b. MonoSystems, Inc.c. Panduit Corp.d. Wiremold / Legrand

2.5 BOXES, ENCLOSURES, AND CABINETS

A. General Requirements for Boxes, Enclosures, and Cabinets: Boxes, enclosures, and cabinets installed in wet locations shall be listed for use in wet locations.

B. Sheet Metal Outlet and Device Boxes: Comply with NEMA OS 1 and UL 514A.

C. Cast-Metal Outlet and Device Boxes: Comply with NEMA FB 1, [ferrous alloy] [aluminum], Type FD, with gasketed cover.

D. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1.

E. Cast-Metal Access, Pull, and Junction Boxes: Comply with NEMA FB 1 and UL 1773, galvanized, cast iron with gasketed cover.

F. Box extensions used to accommodate new building finishes shall be of same material as recessed box.

G. Device Box Dimensions: 4 inches square by 2-1/8 inches deep.

H. Gangable boxes are prohibited.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 4

I. Hinged-Cover Enclosures: Comply with UL 50 and NEMA 250, with continuous-hinge cover with flush latch unless otherwise indicated.

1. Metal Enclosures: Steel, finished inside and out with manufacturer's standard enamel.2. Interior Panels: Steel; all sides finished with manufacturer's standard enamel.

J. Cabinets:

1. NEMA 250, galvanized-steel box with removable interior panel and removable front, finished inside and out with manufacturer's standard enamel.

2. Hinged door in front cover with flush latch and concealed hinge.3. Key latch to match panelboards.4. Metal barriers to separate wiring of different systems and voltage.5. Accessory feet where required for freestanding equipment.

2.6 HANDHOLES AND BOXES FOR EXTERIOR UNDERGROUND WIRING

A. General Requirements for Handholes and Boxes:

1. Boxes and handholes for use in underground systems shall be designed and identified as defined in NFPA 70, for intended location and application.

2. Boxes installed in wet areas shall be listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Polymer-Concrete Handholes and Boxes with Polymer-Concrete Cover: Molded of sand and aggregate, bound together with polymer resin, and reinforced with steel, fiberglass, or a combination of the two.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Oldcastle Precast, Inc.b. Quazite: Hubbell Power Systems, Inc.

2. Standard: Comply with SCTE 77.3. Configuration: Designed for flush burial with closed bottom unless otherwise indicated.4. Cover: Weatherproof, secured by tamper-resistant locking devices and having structural

load rating consistent with enclosure and handhole location.5. Cover Finish: Nonskid finish shall have a minimum coefficient of friction of 0.50.6. Cover Legend: Molded lettering, "ELECTRIC", or as noted otherwise.7. Conduit Entrance Provisions: Conduit-terminating fittings shall mate with entering ducts

for secure, fixed installation in enclosure wall.8. Handholes 12 Inches Wide by 24 Inches Long and Larger: Have inserts for cable racks

and pulling-in irons installed before concrete is poured.

2.7 SOURCE QUALITY CONTROL FOR UNDERGROUND ENCLOSURES

A. Handhole and Pull-Box Prototype Test: Test prototypes of handholes and boxes for compliance with SCTE 77. Strength tests shall be for specified tier ratings of products supplied.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 5

1. Tests of materials shall be performed by an independent testing agency.2. Strength tests of complete boxes and covers shall be by either an independent testing

agency or manufacturer. A qualified registered professional engineer shall certify tests by manufacturer.

3. Testing machine pressure gages shall have current calibration certification complying with ISO 9000 and ISO 10012 and traceable to NIST standards.

PART 3 - EXECUTION

3.1 RACEWAY APPLICATION

A. Outdoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed Conduit: GRC, IMC.2. Concealed Conduit, Aboveground: GRC, IMC, EMT.3. Underground Conduit: RNC, Type EPC-40-PVC. 4. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic,

Electric Solenoid, or Motor-Driven Equipment): LFMC.5. Boxes and Enclosures, Aboveground: NEMA 250, Type 3R.

B. Indoors: Apply raceway products as specified below unless otherwise indicated:

1. Exposed, Not Subject to Physical Damage: EMT. 2. Exposed, Not Subject to Severe Physical Damage: EMT. 3. Exposed and Subject to Severe Physical Damage: GRC, or IMC. Raceway locations

include the following:

a. Loading dock.b. Corridors used for traffic of mechanized carts, forklifts, and pallet-handling units.c. Mechanical rooms.d. Gymnasiums.

4. Concealed in Ceilings and Interior Walls and Partitions: EMT 5. Connection to Vibrating Equipment (Including Transformers and Hydraulic, Pneumatic,

Electric Solenoid, or Motor-Driven Equipment): FMC, except use LFMC in damp or wet locations.

6. Damp or Wet Locations: GRC or IMC.7. Boxes and Enclosures: NEMA 250, Type 1, except use NEMA 250, Type 4 stainless

steel in institutional and commercial kitchens and damp or wet locations.

C. Minimum Raceway Size: 3/4-inch trade size.

D. Raceway Fittings: Compatible with raceways and suitable for use and location.

1. Rigid and Intermediate Steel Conduit: Use threaded rigid steel conduit fittings unless otherwise indicated. Comply with NEMA FB 2.10.

2. PVC Externally Coated, Rigid Steel Conduits: Use only fittings listed for use with this type of conduit. Patch and seal all joints, nicks, and scrapes in PVC coating after

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 6

installing conduits and fittings. Use sealant recommended by fitting manufacturer and apply in thickness and number of coats recommended by manufacturer.

3. EMT: Use setscrew steel fittings. Comply with NEMA FB 2.10.4. Flexible Conduit: Use only fittings listed for use with flexible conduit. Comply with

NEMA FB 2.20.

E. Install surface raceways only where indicated on Drawings.

F. Do not install nonmetallic conduit where ambient temperature exceeds 120 deg F.

3.2 INSTALLATION

A. Comply with NECA 1 and NECA 101 for installation requirements except where requirements on Drawings or in this article are stricter. Comply with NFPA 70 limitations for types of raceways allowed in specific occupancies and number of floors.

B. Keep raceways at least 6 inches away from parallel runs of flues and steam or hot-water pipes. Install horizontal raceway runs above water and steam piping.

C. Complete raceway installation before starting conductor installation.

D. Comply with requirements in Section 26 0529 "Hangers and Supports for Electrical Systems" for hangers and supports.

E. Arrange stub-ups so curved portions of bends are not visible above finished slab.

F. Install no more than the equivalent of three 90-degree bends in any conduit run except for control wiring conduits, for which fewer bends are allowed. Support within 12 inches of changes in direction.

G. Conceal conduit and EMT within finished walls, ceilings, and floors unless otherwise indicated. Install conduits parallel or perpendicular to building lines.

H. Support conduit within 12 inches of enclosures to which attached.

I. Raceways Embedded in Slabs:

1. Run conduit larger than 1-inch trade size, parallel or at right angles to main reinforcement. Where at right angles to reinforcement, place conduit close to slab support. Secure raceways to reinforcement at maximum 10-foot intervals.

2. Arrange raceways to cross building expansion joints at right angles with expansion fittings.

3. Arrange raceways to keep a minimum of 2 inches of concrete cover in all directions.4. Do not embed threadless fittings in concrete unless specifically approved by Architect for

each specific location.

J. Stub-ups to Above Recessed Ceilings:

1. Use EMT, IMC, or RMC for raceways.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 7

2. Use a conduit bushing or insulated fitting to terminate stub-ups not terminated in hubs or in an enclosure.

K. Threaded Conduit Joints, Exposed to Wet, Damp, Corrosive, or Outdoor Conditions: Apply listed compound to threads of raceway and fittings before making up joints. Follow compound manufacturer's written instructions.

L. Coat field-cut threads on PVC-coated raceway with a corrosion-preventing conductive compound prior to assembly.

M. Raceway Terminations at Locations Subject to Moisture or Vibration: Use insulating bushings to protect conductors including conductors smaller than No. 4 AWG.

N. Terminate threaded conduits into threaded hubs or with locknuts on inside and outside of boxes or cabinets. Install bushings on conduits up to 1-1/4-inch trade size and insulated throat metal bushings on 1-1/2-inch trade size and larger conduits terminated with locknuts. Install insulated throat metal grounding bushings on service conduits.

O. Install raceways square to the enclosure and terminate at enclosures with locknuts. Install locknuts hand tight plus 1/4 turn more.

P. Do not rely on locknuts to penetrate nonconductive coatings on enclosures. Remove coatings in the locknut area prior to assembling conduit to enclosure to assure a continuous ground path.

Q. Cut conduit perpendicular to the length. For conduits 2-inch trade size and larger, use roll cutter or a guide to make cut straight and perpendicular to the length.

R. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb tensile strength. Leave at least 12 inches of slack at each end of pull wire. Cap underground raceways designated as spare above grade alongside raceways in use.

S. Install raceway sealing fittings at accessible locations according to NFPA 70 and fill them with listed sealing compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing fittings according to NFPA 70.

T. Install devices to seal raceway interiors at accessible locations. Locate seals so no fittings or boxes are between the seal and the following changes of environments. Seal the interior of all raceways at the following points:

1. Where conduits pass from warm to cold locations, such as boundaries of refrigerated spaces.

2. Where an underground service raceway enters a building or structure.3. Where otherwise required by NFPA 70.

U. Comply with manufacturer's written instructions for solvent welding RNC and fittings.

V. Expansion-Joint Fittings:

1. Install in each run of aboveground RNC that is located where environmental temperature change may exceed 30 deg. F and that has straight-run length that exceeds 25 feet. Install

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 8

in each run of aboveground RMC, IMC, and EMT conduit that is located where environmental temperature change may exceed 100 deg F and that has straight-run length that exceeds 100 feet.

2. Install type and quantity of fittings that accommodate temperature change listed for each of the following locations:

a. Outdoor Locations Not Exposed to Direct Sunlight: 125 deg F temperature change.b. Outdoor Locations Exposed to Direct Sunlight: 155 deg F temperature change.c. Indoor Spaces Connected with Outdoors without Physical Separation: 125 deg F

temperature change.d. Attics: 135 deg temperature change.

3. Install fitting(s) that provide expansion and contraction for at least 0.00041 inch per foot of length of straight run per deg F of temperature change for PVC conduits. Install fitting(s) that provide expansion and contraction for at least 0.000078 inch per foot of length of straight run per deg F of temperature change for metal conduits.

4. Install expansion fittings at all locations where conduits cross building or structure expansion joints.

5. Install each expansion-joint fitting with position, mounting, and piston setting selected according to manufacturer's written instructions for conditions at specific location at time of installation. Install conduit supports to allow for expansion movement.

W. Flexible Conduit Connections: Comply with NEMA RV 3. Use a maximum of 72 inches of flexible conduit for recessed and semirecessed luminaires, equipment subject to vibration, noise transmission, or movement; and for transformers and motors.

1. Use LFMC in damp or wet locations subject to severe physical damage.2. Use LFMC in damp or wet locations not subject to severe physical damage.

X. Mount boxes at heights indicated on Drawings. If mounting heights of boxes are not individually indicated, give priority to ADA requirements. Install boxes with height measured to center of box unless otherwise indicated.

Y. Recessed Boxes in Masonry Walls: Saw-cut opening for box in center of cell of masonry block, and install box flush with surface of wall. Prepare block surfaces to provide a flat surface for a raintight connection between box and cover plate or supported equipment and box.

Z. Horizontally separate boxes mounted on opposite sides of walls so they are not in the same vertical channel.

AA. Locate boxes so that cover or plate will not span different building finishes.

BB. Support boxes of three gangs or more from more than one side by spanning two framing members or mounting on brackets specifically designed for the purpose.

CC. Fasten junction and pull boxes to or support from building structure. Do not support boxes by conduits.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 9

3.3 INSTALLATION OF UNDERGROUND CONDUIT

A. Direct-Buried Conduit:

1. Excavate trench bottom to provide firm and uniform support for conduit. Prepare trench bottom as specified in Section 312000 "Earth Moving" for pipe less than 6 inches in nominal diameter.

2. Install backfill as specified in Section 312000 "Earth Moving."3. After installing conduit, backfill and compact. Start at tie-in point, and work toward end

of conduit run, leaving conduit at end of run free to move with expansion and contraction as temperature changes during this process. Firmly hand tamp backfill around conduit to provide maximum supporting strength. After placing controlled backfill to within 12 inches of finished grade, make final conduit connection at end of run and complete backfilling with normal compaction as specified in Section 312000 "Earth Moving."

4. Install manufactured duct elbows for stub-ups at poles and equipment and at building entrances through floor unless otherwise indicated. Encase elbows for stub-up ducts throughout length of elbow.

5. Install manufactured rigid steel conduit elbows for stub-ups at poles and equipment and at building entrances through floor.

a. Couple steel conduits to ducts with adapters designed for this purpose, and encase coupling with 3 inches of concrete for a minimum of 12 inches on each side of the coupling.

b. For stub-ups at equipment mounted on outdoor concrete bases and where conduits penetrate building foundations, extend steel conduit horizontally a minimum of 60 inches from edge of foundation or equipment base. Install insulated grounding bushings on terminations at equipment.

6. Underground Warning Tape: Comply with requirements in Section 26 0553 "Identification for Electrical Systems."

3.4 INSTALLATION OF UNDERGROUND HANDHOLES AND BOXES

A. Install handholes and boxes level and plumb and with orientation and depth coordinated with connecting conduits to minimize bends and deflections required for proper entrances.

B. Unless otherwise indicated, support units on a level bed of crushed stone or gravel, graded from 1/2-inch sieve to No. 4 sieve and compacted to same density as adjacent undisturbed earth.

C. Elevation: In paved areas, set so cover surface will be flush with finished grade. Set covers of other enclosures 1 inch above finished grade.

D. Install handholes with bottom below frost line, below grade.

E. Install removable hardware, including pulling eyes, cable stanchions, cable arms, and insulators, as required for installation and support of cables and conductors and as indicated. Select arm lengths to be long enough to provide spare space for future cables but short enough to preserve adequate working clearances in enclosure.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 0533 - 10

F. Field-cut openings for conduits according to enclosure manufacturer's written instructions. Cut wall of enclosure with a tool designed for material to be cut. Size holes for terminating fittings to be used, and seal around penetrations after fittings are installed.

3.5 SLEEVE AND SLEEVE-SEAL INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Install sleeves and sleeve seals at penetrations of exterior floor and wall assemblies. Comply with requirements in Section 260544 "Sleeves and Sleeve Seals for Electrical Raceways and Cabling."

3.6 FIRESTOPPING

A. Install firestopping at penetrations of fire-rated floor and wall assemblies. Comply with requirements in Section 078413 "Penetration Firestopping."

3.7 PROTECTION

A. Protect coatings, finishes, and cabinets from damage and deterioration.

1. Repair damage to galvanized finishes with zinc-rich paint recommended by manufacturer.

2. Repair damage to PVC coatings or paint finishes with matching touchup coating recommended by manufacturer.

END OF SECTION 26 0533

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 1

SECTION 26 0544 - SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Sleeves for raceway and cable penetration of non-fire-rated construction walls and floors.2. Sleeve-seal systems.3. Sleeve-seal fittings.4. Grout.5. Silicone sealants.

B. Related Requirements:

1. Section 078413 "Penetration Firestopping" for penetration firestopping installed in fire-resistance-rated walls, horizontal assemblies, and smoke barriers, with and without penetrating items.

PART 2 - PRODUCTS

2.1 SLEEVES

A. Wall Sleeves:

1. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc coated, plain ends.

2. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop unless otherwise indicated.

B. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies: Galvanized-steel sheet; 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint, with tabs for screw-fastening the sleeve to the board.

C. PVC-Pipe Sleeves: ASTM D 1785, Schedule 40.

D. Molded-PVC Sleeves: With nailing flange for attaching to wooden forms.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 2

E. Molded-PE or -PP Sleeves: Removable, tapered-cup shaped, and smooth outer surface with nailing flange for attaching to wooden forms.

F. Sleeves for Rectangular Openings:

1. Material: Galvanized sheet steel.2. Minimum Metal Thickness:

a. For sleeve cross-section rectangle perimeter less than 50 inches and with no side larger than 16 inches, thickness shall be 0.052 inch.

b. For sleeve cross-section rectangle perimeter 50 inches or more and one or more sides larger than 16 inches, thickness shall be 0.138 inch.

2.2 SLEEVE-SEAL SYSTEMS

A. Description: Modular sealing device, designed for field assembly, to fill annular space between sleeve and raceway or cable.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Advance Products & Systems, Inc.b. CALPICO, Inc.c. Metraflex Company (The).d. Pipeline Seal and Insulator, Inc.e. Proco Products, Inc.

2. Sealing Elements: EPDM rubber interlocking links shaped to fit surface of pipe. Include type and number required for pipe material and size of pipe.

3. Pressure Plates: Carbon steel.4. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, of length

required to secure pressure plates to sealing elements.

2.3 SLEEVE-SEAL FITTINGS

A. Description: Manufactured plastic, sleeve-type, waterstop assembly made for embedding in concrete slab or wall. Unit shall have plastic or rubber waterstop collar with center opening to match piping OD.

1. Manufacturers: Subject to compliance with requirements, provide products by the following:

a. HOLDRITE.

2.4 GROUT

A. Description: Nonshrink; recommended for interior and exterior sealing openings in non-fire-rated walls or floors.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 3

B. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting, dry, hydraulic-cement grout.

C. Design Mix: 5000-psi, 28-day compressive strength.

D. Packaging: Premixed and factory packaged.

2.5 SILICONE SEALANTS

A. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric sealants of grade indicated below.

1. Grade: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces that are not fire rated.

2. Sealant shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

B. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, nonshrinking foam.

PART 3 - EXECUTION

3.1 SLEEVE INSTALLATION FOR NON-FIRE-RATED ELECTRICAL PENETRATIONS

A. Comply with NECA 1.

B. Comply with NEMA VE 2 for cable tray and cable penetrations.

C. Sleeves for Conduits Penetrating Above-Grade Non-Fire-Rated Concrete and Masonry-Unit Floors and Walls:

1. Interior Penetrations of Non-Fire-Rated Walls and Floors:

a. Seal annular space between sleeve and raceway or cable, using joint sealant appropriate for size, depth, and location of joint. Comply with requirements in Section 079200 "Joint Sealants."

b. Seal space outside of sleeves with mortar or grout. Pack sealing material solidly between sleeve and wall so no voids remain. Tool exposed surfaces smooth; protect material while curing.

2. Use pipe sleeves unless penetration arrangement requires rectangular sleeved opening.3. Size pipe sleeves to provide 1/4-inch annular clear space between sleeve and raceway or

cable unless sleeve seal is to be installed, or unless seismic criteria require different clearance.

4. Install sleeves for wall penetrations unless core-drilled holes or formed openings are used. Install sleeves during erection of walls. Cut sleeves to length for mounting flush with both surfaces of walls. Deburr after cutting.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 0544 - 4

5. Install sleeves for floor penetrations. Extend sleeves installed in floors 2 inches above finished floor level. Install sleeves during erection of floors.

D. Sleeves for Conduits Penetrating Non-Fire-Rated Gypsum Board Assemblies:

1. Use circular metal sleeves unless penetration arrangement requires rectangular sleeved opening.

2. Seal space outside of sleeves with approved joint compound for gypsum board assemblies.

E. Roof-Penetration Sleeves: Seal penetration of individual raceways and cables with flexible boot-type flashing units applied in coordination with roofing work.

F. Aboveground, Exterior-Wall Penetrations: Seal penetrations using steel pipe sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

G. Underground, Exterior-Wall and Floor Penetrations: Install cast-iron pipe sleeves. Size sleeves to allow for 1-inch annular clear space between raceway or cable and sleeve for installing sleeve-seal system.

3.2 SLEEVE-SEAL-SYSTEM INSTALLATION

A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at raceway entries into building.

B. Install type and number of sealing elements recommended by manufacturer for raceway or cable material and size. Position raceway or cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space between raceway or cable and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

3.3 SLEEVE-SEAL-FITTING INSTALLATION

A. Install sleeve-seal fittings in new walls and slabs as they are constructed.

B. Assemble fitting components of length to be flush with both surfaces of concrete slabs and walls. Position waterstop flange to be centered in concrete slab or wall.

C. Secure nailing flanges to concrete forms.

D. Using grout, seal the space around outside of sleeve-seal fittings.

END OF SECTION 26 0544

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 1

SECTION 26 0553 - IDENTIFICATION FOR ELECTRICAL SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Identification for raceways.2. Identification of power and control cables.3. Identification for conductors.4. Underground-line warning tape.5. Warning labels and signs.6. Instruction signs.7. Equipment identification labels. Including, arc-flash warning labels.8. Miscellaneous identification products.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Brady Corporation.b. Panduit Corp.c. Seton Identification Productsd. Brother International Corporation.e. Ideal Industries, Inc.f. Carlton Industries, LP.g. Champion America.

2.2 PERFORMANCE REQUIREMENTS

A. Comply with NFPA 70, and NEC.

B. Comply with ANSI Z535.4 for safety signs and labels.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 2

2.3 COLOR AND LEGEND REQUIREMENTS

A. Raceways and Cables Carrying Circuits at 600 V or Less:

1. Legend: Indicate voltage and system or service type.

2.4 LABELS

A. Snap-Around Labels for Raceways and Cables Carrying Circuits at 600 V or Less: Slit, pretensioned, flexible, preprinted, color-coded acrylic sleeves, with diameters sized to suit diameters of raceways they identify, and that stay in place by gripping action.

B. Self-Adhesive Labels:

1. 3-mil- thick flexible label with acrylic pressure-sensitive adhesive.

2. Marker for Tags: Permanent, waterproof, black ink marker recommended by tag manufacturer.

2.5 TAPES AND STENCILS:

A. Marker Tapes: Vinyl or vinyl-cloth, self-adhesive wraparound type, with circuit identification legend machine printed by thermal transfer or equivalent process.

B. Self-Adhesive Vinyl Tape: Colored, heavy duty, waterproof, fade resistant; not less than 3 mils thick by 1 to 2 inches wide; compounded for outdoor use.

C. Underground-Line Warning Tape

1. Tape:

a. Recommended by manufacturer for the method of installation and suitable to identify and locate underground electrical and communications utility lines.

b. Printing on tape shall be permanent and shall not be damaged by burial operations.

c. Tape material and ink shall be chemically inert and not subject to degradation when exposed to acids, alkalis, and other destructive substances commonly found in soils.

2. Color and Printing:

a. Comply with ANSI Z535.1, ANSI Z535.2, ANSI Z535.3, ANSI Z535.4, and ANSI Z535.5.

b. Inscriptions for Red-Colored Tapes: "ELECTRIC LINE, HIGH VOLTAGE"

c. Inscriptions for Orange-Colored Tapes: "TELEPHONE CABLE, CATV CABLE, COMMUNICATIONS CABLE, OPTICAL FIBER CABLE".

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 3

2.6 Tags

A. Metal Tags: Brass or aluminum, 2 by 2 by 0.05 inch, with stamped legend, punched for use with self-locking cable tie fastener.

2.7 Signs

A. Baked-Enamel Signs:

1. Preprinted aluminum signs, punched or drilled for fasteners, with colors, legend, and size required for application.

2. 1/4-inch grommets in corners for mounting.3. Nominal Size: 7 by 10 inches

B. Laminated Acrylic or Melamine Plastic Signs:

1. Engraved legend.2. Thickness:

a. For signs up to 20 sq. inches, minimum 1/16-inch.b. For signs larger than 20 sq. inches, 1/8 inch thick.c. Engraved legend with white letters on black face. Provide white

letters on red face for emergency and life safety equipment. Provide white letters on blue face for UPS equipment.

d. Punched or drilled for mechanical fasteners/

2.8 CABLE TIES

A. Cable Ties: Fungus inert, self-extinguishing, one piece, self-locking, Type 6/6 nylon.

1. Minimum Width: 3/16 inch (5 mm).2. Color: Black, except where used for color-coding.

2.9 MISCELLANEOUS IDENTIFICATION PRODUCTS

A. Paint: Comply with requirements in painting Sections for paint materials and application requirements. Retain paint system applicable for surface material and location (exterior or interior).

B. Fasteners for Labels and Signs: Self-tapping, stainless-steel screws or stainless-steel machine screws with nuts and flat and lock washers.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 4

PART 3 - EXECUTION

3.1 PREPARATION

A. Self-Adhesive Identification Products: Before applying electrical identification products, clean substrates of substances that could impair bond, using materials and methods recommended by manufacturer of identification product.

3.2 INSTALLATION

A. Verify and coordinate identification names, abbreviations, colors, and other features with requirements in other Sections requiring identification applications, Drawings, Shop Drawings, manufacturer's wiring diagrams, and operation and maintenance manual. Use consistent designations throughout Project.

B. Install identifying devices before installing acoustical ceilings and similar concealment.

C. Verify identity of each item before installing identification products.

D. Install identification materials and devices at locations for most convenient viewing without interference with operation and maintenance of equipment. Install access doors or panels to provide view of identifying devices.

E. Apply identification devices to surfaces that require finish after completing finish work.

F. Attach signs and plastic labels that are not self-adhesive type with mechanical fasteners appropriate to the location and substrate.

G. Attach plastic raceway and cable labels that are not self-adhesive type with clear vinyl tape, with adhesive appropriate to the location and substrate.

H. Cable Ties: For attaching tags. Use general-purpose type, except as listed below:

1. Outdoors: UV-stabilized nylon.2. In Spaces Handling Environmental Air: Plenum rated.

I. Painted Identification: Comply with requirements in painting Sections for surface preparation and paint application.

J. Aluminum Wraparound Marker Labels and Metal Tags: Secure tight to surface of conductor or cable at a location with high visibility and accessibility.

K. System Identification Color-Coding Bands for Raceways and Cables: Each color-coding band shall completely encircle cable or conduit. Place adjacent bands of two-color markings in contact, side by side. Locate bands at changes in direction, at penetrations of walls and floors, at 40-foot maximum intervals in straight runs, and at 25-foot maximum intervals in congested areas.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 5

L. During backfilling of trenches, install continuous underground-line warning tape directly above cable or raceway at 6 to 8 inches below finished grade. Use multiple tapes where width of multiple lines installed in a common trench or concrete envelope exceeds 16 inches overall.

3.3 IDENTIFICATION SCHEDULE

A. Accessible Raceways, 600 V or Less, for Service, Feeder, and Branch Circuits.: Identify with self-adhesive vinyl tape applied in bands. Install labels at 30-foot maximum intervals.

B. Accessible Raceways and Cables within Buildings: Identify the covers of each junction and pull box of the following systems with self-adhesive vinyl labels containing the wiring system legend and system voltage. System legends shall be as follows:

1. "POWER."

C. Power-Circuit Conductor Identification, 600 V or Less: For conductors in vaults, pull and junction boxes, manholes, and handholes, use color-coding conductor tape to identify the phase.

1. Color-Coding for Phase and Voltage-Level Identification, 600 V or Less: Use colors listed below for ungrounded service, feeder, and branch circuit conductors.

a. Color shall be factory applied or field applied for sizes larger than No. 8 AWG if authorities having jurisdiction permit.

b. Colors for 208/120-V Circuits:

1) Phase A: Black.2) Phase B: Red.3) Phase C: Blue.

c. Field-Applied, Color-Coding Conductor Tape: Apply in half-lapped turns for a minimum distance of 6 inches from terminal points and in boxes where splices or taps are made. Apply last two turns of tape with no tension to prevent possible unwinding. Locate bands to avoid obscuring factory cable markings.

D. Control-Circuit Conductor Identification: For conductors and cables in pull and junction boxes, manholes, and handholes, use tags with the conductor or cable designation, origin, and destination.

E. Control-Circuit Conductor Termination Identification: For identification at terminations, provide labels with the conductor designation.

F. Conductors To Be Extended in the Future: Attach tags to conductors and list source.

G. Auxiliary Electrical Systems Conductor Identification: Identify field-installed alarm, control, and signal connections.

1. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, and pull points. Identify by system and circuit designation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 6

2. Use system of marker-tape designations that is uniform and consistent with system used by manufacturer for factory-installed connections.

3. Coordinate identification with Project Drawings, manufacturer's wiring diagrams, and operation and maintenance manual.

4. Label and paint the covers of the systems junction boxes as follows. Provide Kwal Howell colors as listed, or approved equal:

a. Fire Alarm Red Alert AC118R

H. Locations of Underground Lines: Identify with underground-line warning tape for power, lighting, communication, and control wiring and optical-fiber cable.

1. Install underground-line warning tape for direct-buried cables and cables in raceways.

I. Warning Labels for Indoor Cabinets, Boxes, and Enclosures for Power and Lighting,

1. Apply to exterior of door, cover, or other access.2. For equipment with multiple power or control sources, apply to door or cover of

equipment, including, but not limited to, the following:

a. Power-transfer switches.b. Controls with external control power connections.

J. Arc Flash Warning Labeling: Self-adhesive thermal transfer vinyl labels.

1. Comply with NFPA 70E and ANSI Z535.4.2. Comply with Section 260574 "Overcurrent Protective Device Arc-Flash Study"

requirements for arc-flash warning labels.

K. Operating Instruction Signs: Install instruction signs to facilitate proper operation and maintenance of electrical systems and items to which they connect. Install instruction signs with approved legend where instructions are needed for system or equipment operation.

L. Equipment Identification Labels: On each unit of equipment, install unique designation label that is consistent with wiring diagrams, schedules, and operation and maintenance manual. Apply labels to disconnect switches and protection equipment, central or master units, control panels, control stations, terminal cabinets, and racks of each system. Systems include power, lighting, control, communication, signal, monitoring, and alarm unless equipment is provided with its own identification.

1. Labeling Instructions:

a. Elevated Components: Increase sizes of labels and letters to those appropriate for viewing from the floor.

b. Fasten labels with appropriate mechanical fasteners that do not change the NEMA or NRTL rating of the enclosure.

c. Mark each device box and junction box with a permanent ink marker, indicating the circuit to which the device is connected: Example: LP1-12. Mark circuit number on exterior side of junction boxes located in accessible locations, and inside junction boxes in non-accessible locations.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 7

2. Equipment to be labeled with engraved, laminated acrylic or melamine plastic label, punched, or drilled for mechanical fasteners. Unless otherwise indicated, provide a single line of text with 1/2-inch high letters on 1-1/2-inch high label; where two lines of text are required, use labels 2 inches high:

a. Panelboards.b. Enclosures and electrical cabinets.c. Access doors and panels for concealed electrical items.d. Switchgear.e. Switchboards, including branch breakers or fusible switches.f. Variable-speed controllers.

S. Install Arc-flash hazard labels on the following equipment:

1. Service entrance equipment.2. Power distribution switchboards or panelboards.3. Branch panelboards.

END OF SECTION 26 0553

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 0553 - 8

BLANK PAGE

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 1

SECTION 26 2416 - PANELBOARDS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Lighting and appliance branch-circuit panelboards.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of panelboard.

1. Include materials, switching and overcurrent protective devices, accessories, and components indicated.

2. Include dimensions and manufacturers' technical data on features, performance, electrical characteristics, ratings, and finishes.

B. Shop Drawings: For each panelboard and related equipment.

1. Include dimensioned plans, elevations, sections, and details.2. Show tabulations of installed devices with nameplates, conductor termination sizes,

equipment features, and ratings.3. Detail enclosure types including mounting and anchorage, environmental protection,

knockouts, corner treatments, covers and doors, gaskets, hinges, and locks.4. Detail bus configuration, current, and voltage ratings.5. Short-circuit current rating of panelboards and overcurrent protective devices.6. Detail features, characteristics, ratings, and factory settings of individual overcurrent

protective devices and auxiliary components.7. Include wiring diagrams for power, signal, and control wiring.8. Key interlock scheme drawing and sequence of operations.9. Include time-current coordination curves for each type and rating of overcurrent

protective device included in panelboards.

1.4 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For panelboards and components to include in emergency, operation, and maintenance manuals. In addition to items specified in Section 01 "Operation and Maintenance Data," include the following:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 2

1. Manufacturer's written instructions for testing and adjusting overcurrent protective devices.

2. Time-current curves, including selectable ranges for each type of overcurrent protective device that allows adjustments.

1.5 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Keys: Two spares for each type of panelboard cabinet lock.2. Fuses for Fused Switches: Equal to 10 percent of quantity installed for each size and type,

but no fewer than three of each size and type.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: ISO 9001 or 9002 certified.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Remove loose packing and flammable materials from inside panelboards; install temporary electric heating (250 W per panelboard) to prevent condensation.

B. Handle and prepare panelboards for installation according to NECA 407 and NEMA PB 1.

1.8 FIELD CONDITIONS

A. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary electric service according to requirements indicated:

1. Notify Owner no fewer than seven days in advance of proposed interruption of electric service.

2. Do not proceed with interruption of electric service without Owner's written permission.3. Comply with NFPA 70E.

1.9 WARRANTY

A. Manufacturer's Warranty: Manufacturer agrees to repair or replace panelboards that fail in materials or workmanship within specified warranty period.

1. Panelboard Warranty Period: 24 months from date of Substantial Completion.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 3

PART 2 - PRODUCTS

2.1 PANELBOARDS REQUIREMENTS

A. Fabricate and test panelboards according to IEEE 344 to withstand seismic forces defined in Section 26 0548 "Seismic Controls for Electrical Systems."

B. Product Selection for Restricted Space: Drawings indicate maximum dimensions for panelboards including clearances between panelboards and adjacent surfaces and other items. Comply with indicated maximum dimensions.

C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

D. Comply with NEMA PB 1.

E. Comply with NFPA 70.

F. Enclosures: Flush and surface mounted, dead-front cabinets as indicated on the drawings.

1. Rated for environmental conditions at installed location.

a. Indoor Dry and Clean Locations: NEMA 250, Type 1.

2. Height: 84 inches maximum.3. Front: Secured to box with concealed trim clamps. For surface-mounted fronts, match

box dimensions; for flush-mounted fronts, overlap box. Trims shall cover all live parts and shall have no exposed hardware.

4. Hinged Front Cover: Entire front trim hinged to box and with standard door within hinged trim cover. Trims shall cover all live parts and shall have no exposed hardware.

5. Finishes:

a. Panels, back boxes, and Trim: Steel, or galvanized steel, factory finished immediately after cleaning and pretreating with manufacturer's standard two-coat, baked-on finish consisting of prime coat and thermosetting topcoat.

G. Incoming Mains:

1. Location: Convertible between top and bottom.2. Main Breaker: Main lug interiors up to 400 amperes shall be field convertible to main

breaker.

H. Phase, Neutral, and Ground Buses:

1. Material: Tin-plated aluminum, 98 percent conductivity.

a. Plating shall run entire length of bus.b. Bus shall be fully rated the entire length.

2. Interiors shall be factory assembled into a unit. Replacing switching and protective devices shall not disturb adjacent units or require removing the main bus connectors.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 4

3. Equipment Ground Bus: Adequate for feeder and branch-circuit equipment grounding conductors; bonded to box.

4. Full-Sized Neutral: Equipped with full-capacity bonding strap for service entrance applications. Mount electrically isolated from enclosure. Do not mount neutral bus in gutter.

I. Conductor Connectors: Suitable for use with conductor material and sizes.

1. Material: Tin-plated aluminum, 98 percent conductivity.2. Terminations shall allow use of 75 deg C rated conductors without derating.3. Size: Lugs suitable for indicated conductor sizes, with additional gutter space, if required,

for larger conductors.4. Main and Neutral Lugs: Mechanical type, with a lug on the neutral bar for each pole in

the panelboard.5. Ground Lugs and Bus-Configured Terminators: Mechanical type, with a lug on the bar

for each pole in the panelboard.6. Subfeed (Double) Lugs: Mechanical type suitable for use with conductor material. Locate

at same end of bus as incoming lugs or main device.

J. Future Devices: Panelboards shall have mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices.

K. Panelboard Short-Circuit Current Rating: Fully rated to interrupt symmetrical short-circuit current available at terminals. Assembly listed by an NRTL for 100 percent interrupting capacity.

1. Panelboards and overcurrent protective devices rated 240 V or less shall have short-circuit ratings as shown on Drawings, but not less than 10,000 A rms symmetrical.

2. Panelboards and overcurrent protective devices rated above 240 V and less than 600 V shall have short-circuit ratings as shown on Drawings, but not less than 14,000 A rms symmetrical.

2.2 POWER PANELBOARDS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company; GE Energy Management - Electrical Distribution.3. Siemens Energy.4. Square D; by Schneider Electric.

B. Panelboards: NEMA PB 1, distribution type.

C. Doors: Secured with vault-type latch with tumbler lock; keyed alike.

1. For doors more than 36 inches high, provide two latches, keyed alike.

D. Branch Overcurrent Protective Devices for Circuit-Breaker Frame Bolt-on circuit breakers..

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 5

2.3 DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company; GE Energy Management - Electrical Distribution.3. Siemens Energy.4. Square D; by Schneider Electric.

B. Fused Switch: NEMA KS 1, Type HD; clips to accommodate specified fuses; lockable handle.

1. Fused Switch Features and Accessories:

a. Standard ampere ratings and number of poles.b. Mechanical cover interlock with a manual interlock override, to prevent the

opening of the cover when the switch is in the on position. The interlock shall prevent the switch from being turned on with the cover open. The operating handle shall have lock-off means with provisions for three padlocks.

c. Auxiliary Contacts: Two normally open and normally closed contact(s) that operate with switch handle operation.

2.4 IDENTIFICATION

A. Panelboard Label: Manufacturer's name and trademark, voltage, amperage, number of phases, and number of poles shall be located on the interior of the panelboard door.

B. Breaker Labels: Faceplate shall list current rating, UL and IEC certification standards, and AIC rating.

C. Circuit Directory: Directory card inside panelboard door, mounted in metal frame with transparent protective cover.

1. Circuit directory shall identify specific purpose with detail sufficient to distinguish it from all other circuits.

D. Circuit Directory: Computer-generated circuit directory mounted inside panelboard door with transparent plastic protective cover.

1. Circuit directory shall identify specific purpose with detail sufficient to distinguish it from all other circuits.

2.5 ACCESSORY COMPONENTS AND FEATURES

A. Accessory Set: Include tools and miscellaneous items required for overcurrent protective device test, inspection, maintenance, and operation.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 6

B. Portable Test Set: For testing functions of solid-state trip devices without removing from panelboard. Include relay and meter test plugs suitable for testing panelboard meters and switchboard class relays.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify actual conditions with field measurements prior to ordering panelboards to verify that equipment fits in allocated space in, and comply with, minimum required clearances specified in NFPA 70.

B. Receive, inspect, handle, and store panelboards according to NECA 407 and NEMA PB 1.1.

C. Examine panelboards before installation. Reject panelboards that are damaged, rusted, or have been subjected to water saturation.

D. Examine elements and surfaces to receive panelboards for compliance with installation tolerances and other conditions affecting performance of the Work.

E. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. Coordinate layout and installation of panelboards and components with other construction that penetrates walls or is supported by them, including electrical and other types of equipment, raceways, piping, encumbrances to workspace clearance requirements, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels.

B. Comply with NECA 1.

C. Install panelboards and accessories according to NECA 407 and NEMA PB 1.1.

D. Equipment Mounting:

1. Attach panelboard to the vertical finished or structural surface behind the panelboard.2. Comply with requirements for seismic control devices specified in Section 26 0548

"Seismic Controls for Electrical Systems."

E. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from panelboards.

F. Comply with mounting and anchoring requirements specified in Section 26 0548 "Seismic Controls for Electrical Systems."

G. Mount top of trim 90 inches above finished floor unless otherwise indicated.

H. Mount panelboard cabinet plumb and rigid without distortion of box.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 7

I. Mount recessed panelboards with fronts uniformly flush with wall finish and mating with back box.

J. Mounting panelboards with space behind is recommended for damp, wet, or dirty locations. The steel slotted supports in the following paragraph provide an even mounting surface and the recommended space behind to prevent moisture or dirt collection.

K. Mount surface-mounted panelboards to steel slotted supports a minimum of 5/8 inch in depth. Orient steel slotted supports vertically.

L. Install overcurrent protective devices and controllers not already factory installed.

1. Set field-adjustable, circuit-breaker trip ranges.2. Tighten bolted connections and circuit breaker connections using calibrated torque

wrench or torque screwdriver per manufacturer's written instructions.

M. Make grounding connections and bond neutral for services and separately derived systems to ground. Make connections to grounding electrodes, separate grounds for isolated ground bars, and connections to separate ground bars.

N. Install filler plates in unused spaces.

O. Stub six 1-inch empty conduits from panelboard into accessible ceiling space or space designated to be ceiling space in the future. Stub four 1-inch empty conduits into raised floor space or below slab not on grade.

P. Arrange conductors in gutters into groups and bundle and wrap with wire ties.

Q. Mount spare fuse cabinet in accessible location.

3.3 IDENTIFICATION

A. Identify field-installed conductors, interconnecting wiring, and components; install warning signs complying with requirements in Section 26 0553 "Identification for Electrical Systems."

B. Create a directory to indicate installed circuit loads; incorporate Owner's final room designations. Obtain approval before installing. Handwritten directories are not acceptable. Install directory inside panelboard door.

C. Panelboard Nameplates: Label each panelboard with a nameplate complying with requirements for identification specified in Section 26 0553 "Identification for Electrical Systems."

D. Device Nameplates: Label each branch circuit device in power panelboards with a nameplate complying with requirements for identification specified in Section 26 0553 "Identification for Electrical Systems."

E. Install warning signs complying with requirements in Section 26 0553 "Identification for Electrical Systems" identifying source of remote circuit.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

PANELBOARDS 26 2416 - 8

3.4 FIELD QUALITY CONTROL

A. Acceptance Testing Preparation:

1. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit.

2. Test continuity of each circuit.

B. Tests and Inspections:

1. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest.

C. Panelboards will be considered defective if they do not pass tests and inspections.

D. Prepare test and inspection reports, including a certified report that identifies panelboards included and that describes scanning results, with comparisons of the two scans. Include notation of deficiencies detected, remedial action taken, and observations after remedial action.

3.5 ADJUSTING

A. Adjust moving parts and operable components to function smoothly, and lubricate as recommended by manufacturer.

B. Set field-adjustable circuit-breaker trip ranges as indicated.

C. Circuit changes made during load balancing may negate color-coding of phases and circuits. If load balancing proves undesirable or is to be performed by others, delete "Load Balancing" Paragraph below.

D. Load Balancing: After Substantial Completion, but not more than 60 days after Final Acceptance, measure load balancing and make circuit changes. Prior to making circuit changes to achieve load balancing, inform Architect of effect on phase color coding.

1. Measure loads during period of normal facility operations.2. Perform circuit changes to achieve load balancing outside normal facility operation

schedule or at times directed by the Architect. Avoid disrupting services such as fax machines and on-line data processing, computing, transmitting, and receiving equipment.

3. After changing circuits to achieve load balancing, recheck loads during normal facility operations. Record load readings before and after changing circuits to achieve load balancing.

4. Tolerance: Maximum difference between phase loads, within a panelboard, shall not exceed 20 percent.

END OF SECTION 26 2416

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 1

SECTION 26 2726 - WIRING DEVICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Receptacles, receptacles with integral GFCI, and associated device plates.2. Weather-resistant receptacles.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton (Arrow Hart).2. Hubbell Incorporated; Wiring Device-Kellems.3. Leviton Manufacturing Co., Inc.4. Pass & Seymour/Legrand (Pass & Seymour).

B. Source Limitations: Obtain each type of wiring device and associated wall plate from single source from single manufacturer.

2.2 GENERAL WIRING-DEVICE REQUIREMENTS

A. Wiring Devices, Components, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

C. Devices that are manufactured for use with modular plug-in connectors may be substituted under the following conditions:

1. Connectors shall comply with UL 2459 and shall be made with stranding building wire.2. Devices shall comply with the requirements in this Section.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 2

2.3 STRAIGHT-BLADE RECEPTACLES

A. Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 Configuration 5-20R, UL 498, and FS W-C-596.

2.4 GFCI RECEPTACLES

A. General Description:

1. Straight blade, non-feed-through type.2. Comply with NEMA WD 1, NEMA WD 6, UL 498, UL 943 Class A, and FS W-C-596.3. Include indicator light that shows when the GFCI has malfunctioned and no longer

provides proper GFCI protection.

B. Duplex GFCI Convenience Receptacles, 125 V, 20 A.

C. Tamper-Resistant GFCI Convenience Receptacles, 125 V, 20 A.

D. Weather-Resistant GFCI Convenience Receptacles, 125 V, 20 A.

2.5 WALL PLATES

A. Single and combination types shall match corresponding wiring devices.

B. Wet-Location, Weatherproof Cover Plates: NEMA 250, complying with Type 3R, weather-resistant, die-cast aluminum with lockable cover.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with NECA 1, including mounting heights listed in that standard, unless otherwise indicated.

B. Coordination with Other Trades:

1. Protect installed devices and their boxes. Do not place wall finish materials over device boxes and do not cut holes for boxes with routers that are guided by riding against outside of boxes.

2. Keep outlet boxes free of plaster, drywall joint compound, mortar, cement, concrete, dust, paint, and other material that may contaminate the raceway system, conductors, and cables.

3. Install device boxes in brick or block walls so that the cover plate does not cross a joint unless the joint is troweled flush with the face of the wall.

4. Install wiring devices after all wall preparation, including painting, is complete.

C. Conductors:

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 3

1. Do not strip insulation from conductors until right before they are spliced or terminated on devices.

2. Strip insulation evenly around the conductor using tools designed for the purpose. Avoid scoring or nicking of solid wire or cutting strands from stranded wire.

3. The length of free conductors at outlets for devices shall meet provisions of NFPA 70, Article 300, without pigtails.

4. Existing Conductors:

a. Cut back and pigtail, or replace all damaged conductors.b. Straighten conductors that remain and remove corrosion and foreign matter.c. Pigtailing existing conductors is permitted, provided the outlet box is large enough.

D. Device Installation:

1. Replace devices that have been in temporary use during construction and that were installed before building finishing operations were complete.

2. Keep each wiring device in its package or otherwise protected until it is time to connect conductors.

3. Do not remove surface protection, such as plastic film and smudge covers, until the last possible moment.

4. Connect devices to branch circuits using pigtails that are not less than 6 inches in length.

5. When there is a choice, use side wiring with binding-head screw terminals. Wrap solid conductor tightly clockwise, two-thirds to three-fourths of the way around terminal screw.

6. Use a torque screwdriver when a torque is recommended or required by manufacturer.7. When conductors larger than No. 12 AWG are installed on 15- or 20-A circuits, splice

No. 12 AWG pigtails for device connections.8. Tighten unused terminal screws on the device.9. When mounting into metal boxes, remove the fiber or plastic washers used to hold

device-mounting screws in yokes, allowing metal-to-metal contact.

3.2 IDENTIFICATION

A. Comply with Section 26 0553 "Identification for Electrical Systems."

B. Identify each receptacle with panelboard identification and circuit number. Use hot, stamped, or engraved machine printing with black -filled lettering on face of plate, and durable wire markers or tags inside outlet boxes.

3.3 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Test Instruments: Use instruments that comply with UL 1436.2. Test Instrument for Convenience Receptacles: Digital wiring analyzer with digital

readout or illuminated digital-display indicators of measurement.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

WIRING DEVICES 26 2726 - 4

B. Tests for Convenience Receptacles:

1. Line Voltage: Acceptable range is 105 to 132 V.2. Percent Voltage Drop under 15-A Load: A value of 6 percent or higher is unacceptable.3. Ground Impedance: Values of up to 2 ohms are acceptable.4. GFCI Trip: Test for tripping values specified in UL 1436 and UL 943.5. Using the test plug, verify that the device and its outlet box are securely mounted.6. Tests shall be diagnostic, indicating damaged conductors, high resistance at the circuit

breaker, poor connections, inadequate fault current path, defective devices, or similar problems. Correct circuit conditions, remove malfunctioning units and replace with new ones, and retest as specified above.

C. Wiring device will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

END OF SECTION 26 2726

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 1

SECTION 26 2913 - MOTOR STARTERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes the following enclosed controllers rated 600 V and less:

1. Full-voltage manual.2. Full-voltage magnetic.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of enclosed controller. Include manufacturer's technical data on features, performance, electrical characteristics, ratings, and enclosure types and finishes.

B. Shop Drawings: For each enclosed controller. Include dimensioned plans, elevations, sections, details, and required clearances and service spaces around controller enclosures.

1. Show tabulations of the following:

a. Each installed unit's type and details.b. Factory-installed devices.c. Nameplate legends.d. Short-circuit current rating of integrated unit.e. Listed and labeled for integrated short-circuit current (withstand) rating of OCPDs

in combination controllers by an NRTL acceptable to authorities having jurisdiction.

f. Features, characteristics, ratings, and factory settings of individual OCPDs in combination controllers.

2. Wiring Diagrams: For power, signal, and control wiring.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control reports.

B. Load-Current and Overload-Relay Heater List: Compile after motors have been installed, and arrange to demonstrate that selection of heaters suits actual motor nameplate full-load currents.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 2

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For enclosed controllers to include in, operation, and maintenance manuals.

1. Routine maintenance requirements for enclosed controllers and installed components.2. Manufacturer's written instructions for testing, adjusting, and reprogramming reduced-

voltage solid-state controllers.

1.6 MATERIALS MAINTENANCE SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Fuses for Fused Switches: Equal to 10 percent of quantity installed for each size and type, but no fewer than three of each size and type.

1.7 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Comply with NFPA 70.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Store enclosed controllers indoors in clean, dry space with uniform temperature to prevent condensation. Protect enclosed controllers from exposure to dirt, fumes, water, corrosive substances, and physical damage.

1.9 PROJECT CONDITIONS

A. Environmental Limitations: Rate equipment for continuous operation under the following conditions unless otherwise indicated:

1. Ambient Temperature: Not less than minus 22 deg Fand not exceeding 104 deg F2. Altitude: Not exceeding 6600 feet.

1.10 COORDINATION

A. Coordinate layout and installation of enclosed controllers with other construction including conduit, piping, equipment, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels.

B. Coordinate installation of roof curbs, equipment supports, and roof penetrations.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 3

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Eaton.2. General Electric Company.3. Siemens Power Transmission & Distribution, Inc.4. Square D; by Schneider Electric.

B. Source Limitations: Obtain each enclosed controller type from single source from single manufacturer.

2.2 FULL-VOLTAGE CONTROLLERS

A. General Requirements for Full-Voltage Controllers: Comply with NEMA ICS 2, general purpose, Class A.

1. Configuration: Full Voltage Non reversing2. Red pilot light.

B. Fractional Horsepower Manual Starters: "Quick-make, quick-break" toggle or push-button action; marked to show whether unit is off, on, or tripped.

1. Overload Relays: Inverse-time-current characteristics; NEMA ICS 2, Class 10 tripping characteristics; heaters matched to nameplate full-load current of actual protected motor; external reset push button melting alloy type

2. Surface mounting.3. Green pilot light.

C. Integral Horsepower Manual Starters: "Quick-make, quick-break" toggle marked to show whether unit is off, on, or tripped.

1. Configuration: Non reversing 2. Overload Relays: Inverse-time-current characteristics; NEMA ICS 2, Class 10tripping

characteristics; heaters and sensors in each phase, matched to nameplate full-load current of actual protected motor and having appropriate adjustment for duty cycle; external reset push button melting alloy type

3. Surface mounting.4. Green pilot light.5. [N.O.] [N.C.] auxiliary contact.

D. Magnetic Starters: Full voltage, across the line, electrically held.

1. Configuration: Non reversing.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 4

2. Power Contacts: Totally enclosed, double-break, silver-cadmium oxide; assembled to allow inspection and replacement without disturbing line or load wiring.

3. Control Circuits: 120 V ac; obtained from integral CPT, with primary and secondary fuses with CPT of sufficient capacity to operate integral devices and remotely located pilot, indicating, and control devices.

4. Solid-State Overload Relay:

a. Switch or dial selectable for motor running overload protection.b. Sensors in each phase.c. Class 20 tripping characteristic selected to protect motor against voltage and

current unbalance and single phasing.

5. Provide (2) spare normally open (N.O.) and (2) spare normally closed (N.C.) contacts6. External overload reset push button.

E. Combination Magnetic Controller: Factory-assembled combination of magnetic controller, OCPD, and disconnecting means.

1. Fusible Disconnecting Means:

a. NEMA KS 1, heavy-duty, horsepower-rated, fusible switch with clips or bolt pads to accommodate Class R fuses.

b. Lockable Handle: Accepts three padlocks and interlocks with cover in closed position.

2. Auxiliary Contacts: (2) N.O./(2) N.C., arranged to activate before switch blades open.

2.3 ENCLOSURES

A. Enclosed Controllers: NEMA ICS 6, to comply with environmental conditions at installed location.

1. Dry and Clean Indoor Locations: Type 12. Outdoor Locations: Type 3R3. Other Wet or Damp Indoor Locations: Type 44. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Noncorrosive Liquids:

Type 12.

2.4 ACCESSORIES

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and surfaces to receive enclosed controllers, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 5

3.2 INSTALLATION

A. Wall-Mounted Controllers: Install enclosed controllers on walls with tops at uniform height unless otherwise indicated, and by bolting units to wall or mounting on lightweight structural-steel channels bolted to wall. For controllers not at walls, provide freestanding racks complying with Section 260529 "Hangers and Supports for Electrical Systems."

B. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from enclosures and components.

C. Install fuses in each fusible-switch enclosed controller.

D. Install fuses in control circuits if not factory installed. Install heaters in thermal overload relays. Select heaters based on actual nameplate full-load amperes after motors have been installed.

E. Install, connect, and fuse thermal-protector monitoring relays furnished with motor-driven equipment.

F. Comply with NECA 1.

3.3 IDENTIFICATION

A. Identify enclosed controllers, components, and control wiring. Comply with requirements for identification specified in Section 260553 "Identification for Electrical Systems."

1. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs.

2. Label each enclosure with engraved nameplate.3. Label each enclosure-mounted control and pilot device.

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Acceptance Testing Preparation:1. Test continuity of each circuit.

C. Tests and Inspections:

1. Inspect controllers, wiring, components, connections, and equipment installation2. Test insulation resistance for each enclosed-controller element, component, connecting

motor supply, feeder, and control circuits.3. Test continuity of each circuit.4. Verify that voltages at controller locations are within plus or minus 10 percent of motor

nameplate rated voltages. If outside this range for any motor, notify Architect Test each motor for proper phase rotation.

5. Perform each electrical test and visual and mechanical inspection stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.

AIR CONDITIONING VBFA #17471FAIRFIELD JUNIOR HIGH SCHOOL

MOTOR STARTERS 26 2913 - 6

6. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest.

D. Enclosed controllers will be considered defective if they do not pass tests and inspections.

3.5 ADJUSTING

A. Set field-adjustable switches, auxiliary relays, time-delay relays, timers, and overload-relay pickup and trip ranges.

B. Adjust overload-relay heaters or settings if power factor correction capacitors are connected to the load side of the overload relays.

END OF SECTION 26 2913