ADAA_Concept Report (low res)

108

Transcript of ADAA_Concept Report (low res)

     

 

INDEX  

A R C H I T E C T U R E

 

S T R U C T U R E

M E C H A N I C A L E L E C T R I C A L P L U M B I N G

S U S T A I N A B I L I T Y

I N T E R I O R D E S I G N

L A N D S C A P E

 

 

A R C H I T E C T U R E   1 

INTRODUCTION

SITE ANALYSYS

LAND USE PLAN

BUILDING HEIGHT

CURRENT SITE IMAGES

ENVIRONMENTAL ANALYSIS

CONCEPT DESIGN

CULTURAL ASPECTS

DESIGN CHALLENGES

DESIGN OPTIONS

BUILDING MASSING / CIRCULATION STUDY

VEHICULAR CIRCULATION

NOISE & DESIGN RESPONSE

DESIGN SKETCHES

BUILDING CODES

AREA

SITE PLAN

FLOOR PLANS

ELEVATIONS

SECTIONS

RENDERINGS

A R C H I T E C T U R E

 

 

A R C H I T E C T U R E   2 

INTRODUCTION The  new  Abu  Dhabi  Accountability  headquarters  will  be  located  on  a  site  that  offers  views  of downtown  to  the  south and  the  surrounding  governmental  and  business  district  in  addition  to  the limited  opportunity  of  the  site,  the  building  restrictions,  regional  environmental  conditions  and response to traditional presents are the primary factors informing the design. 

The  headquarters  building  is  composed  of  two  main  building  masses  the  first  mass  is  oriented perpendicular  to the main road and obtaining the ideal orientation (East‐West) while the other mass is oriented parallel to the first one and forming a big scaled gate  to the project. 

The court yard at the North is derived from the traditional Islamic and gulf type, provides a shaded and protected center to the complex from here the view expands towards the external. 

While maximizing views, the exterior facades are also designed to respond to climatic conditions. The Western,  Southern  and  Eastern  exposures  incorporate  both  horizontal  screens  and  deep  ribbon windows to reduce glare and heat gain. Transoms above the screens have tinted glazing for additional solar protection. The response to the solar condition, together with variation in curtain wall treatment add a  layer of detail and  scale  to  the  compact building mass.   Metal  structures  shade  the  roof and provide a support to the photo voltage panels that will help using the facades. 

 

 

A R C H I T E C T U R E   3 

STE ANALYSIS As per Abu Dhabi plan 2030  

The Abu Dhabi Accountability site  location  is planned  to accommodate national and  institutional use and the maximum height allowed in this area is G+9 (40m) due to Al bateen airport being nearby. 

Al Khaleej Alarabi and Sh. Saeed Al Maktom Roads are the main high ways leading to the area. 

The  site  is  located  in  the middle  of  the  business  district where  some  important  and  governmental buildings are surrounding the site. 

Al the required facilities and services for the project are available around the site. 

 

 

A R C H I T E C T U R E   4 

LAND USE PLAN

 

 

A R C H I T E C T U R E   5 

BUILDING HEIGHT

 

 

A R C H I T E C T U R E   6 

CURRENT SITE IMAGES

Upper photos:  Showing important buildings                                                                                                       around the site                                                                                       Middle left: View to the site                                                                                                      Bottom photo: Panoramatic View from the site 

 

 

A R C H I T E C T U R E   7 

ENVIRONMENTAL ANALYSIS  

 

OPTIMUM BUILDING ORIENTATION 

Using Ecotect Environmental Design Software The Optimum Orientation For The Buildings In Abu Dhabi Has Been Calculated To Be 97.5o From North. 

We have oriented the office mass to a close angle that  is parallel to the plot boundary to achieve the maximum utilization of the land. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   8 

SITE ORIENTATION / WIND STUDY  

Overlaying  the  climatic  data  onto  the  site  shows  the  seasonal  sun  path  as well  as  prevailing wind directions. 

The high sun angles in summer can be efficiently blocked by horizontal shading devices, however lower sun angles at the east/west facades have to be mitigated with deeper shades. 

The  alternating  wind  direction  is  beneficial  in  designing  the  openings  the  favorable  cool  wind  in summer, while blocking it in winter. 

Simulating the movement of prevailing wind around the building’s mass, the court yard and the gate void will be utilizing designing natural  ventilation  strategies,  to  cool  the building during appropriate summer months hence reducing the requirement for mechanical ventilation. 

 

 

A R C H I T E C T U R E   9 

SOLAR SHADING 

According to the studies done on the Building’s mass, Locations receiving the highest solar heat gain where identified and accordingly shading devices where introduced to block solar rays during the peak hours of summer,   

 

 

 

A R C H I T E C T U R E   10 

SUN PATH STUDY 

 

 

A R C H I T E C T U R E   11 

CONCEPT DESIGN Because  of  the  function  of  the  project  as  an  important  authority  one  of  few  that  handles  the monitoring of the accountability of other governmental authority and departments of Abu Dhabi, the transparency, clarity and this transparency was reflected in the overall design of this project  

Using strong straight lines, curtain walls and white cladded walls that reflect the transparency that the function of the authority acts upon. 

Culture 

This  building  is  considered  as  a  new  landmark which  expresses  the  culture  of UAE  in  general;  The concept of this project come to emphasize on the future and to record this moment of change through the relationship between the old and the new, through the relationship between the traditional culture and the new emerging culture through the relationship between the past and the emerging future of Abu Dhabi. 

The  project  is  intended  to  be  integrated  within  the  local  culture  of  UAE.  Studying  the  different elements of the Libyan culture, the project has been inspired by the following elements: 

 

 

A R C H I T E C T U R E   12 

GATE 

As a symbol of traditional architecture, UAE is considered as an organic city at the heart of the desert, which has been developed  through  the  years by  its  residents  reflecting  the unique  gulf  culture  and reacting to the external environment of the place. 

The  traditional Gate  is one of  the  features  that    تميز  the Arabic Culture  in  general  and Gulf  style  in particular. It has been used for the City Gates and palaces and even traditional houses and mosques. 

Gypsum ART 

This form of art, the “GRC” has been known in the Gulf culture since the times of the   االسالمية فتوحال  With its sophisticated details and natural colors, Gypsum pattern is considered as a symbol of the gulf art 

 

 

A R C H I T E C T U R E   13 

CULTURAL ASPECTS After a thorough study of the UAE culture; we chose these four  illustrated patterns to be used  in the building somehow whereas it is either used inside the building, the building gate frame, the large glass box located in the middle of the gate or on the boundary wall around the building. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   14 

Design Challenges: One of the main challenges is the future surrounding buildings witch will negatively affect the present of the building along the main street and in case they are built on the edge of the plot will hide most of the ADAA Headquarters. 

We  have  tried  all  possible  shape  configurations within  the  plot  to  exam  the  vision  impact  on  the building  in the future we found out that To Form an Iconic monumental frame for the building which has a strong present on the area will avoid 0000000 of the building within the site however parts of it are hidden behind the new neighbors. 

SETBACKS 

We have  recommended creating a courtyard  facing  the North versus having equal wider setbacks  in both  sides  allow  having  internal  shaded  area  for  social  gathering  for  the  building  users  as well  as welcoming the important visitor for the Authority. 

And  Further  To  The  Setbacks Defined  By  The  Site  Boundaries.  It Was  Seen  To  Introduce  a  Setback Spacing  Between  The  building  and  the  adjacent  Buildings  At  three  sides.  This  Insures  That  The  l Buildings Receive Sufficient Natural Sunlight, Natural Ventilation And Sky Access. 

Accordingly a Distance of 4 m was allowed as a setback. 

GRID OPTIONS 

To Achieve the Highest Structural and Geometrical Efficiency, a Study has been Done to Optimize the Column Locations, Parking Grids And Aisles. This Insures the Optimum Organization of The Floor Plans Without Impacting On The Flexibility. 

 

 

A R C H I T E C T U R E   15 

Views: 

Studying  The  Site’s Context  Reveals  Recommended Views  Towards  the main Road  to  the west  and towards  the sport city and Sh zayed grand mosque  from  the upper  floors with Less Recommendable Views towards neighbor sides. 

The  courtyard  space  became  a  considerable  internal  view which maximize  the  opportunity  of  good views for most of the office spaces. 

The  two main masses are positioned  in a way not  to obstruct  the view  for each other and open  the view to outside towards the main road. 

The  last floor where the chairman office  located enjoys the best views as two side views towards the main road and to the internal courtyard is obtained.     

Views Through Site

Views towards Site

Views from Site

 

 

A R C H I T E C T U R E   16 

DESIGN OPTIONS

 

 

A R C H I T E C T U R E   17 

BUILDING MASSING / CIRCULATION STUDY

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   18 

VEHICULAR CIRCULATION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   19 

NOISE AND DESIGN RESPONSE  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   20 

DESIGN SKETCHES The initial thought was to create a  statement  that  presents  the governmental Importance.  Examining  different  type  of shapes  that  give  this  effect meanwhile  have  the  best  site utilization,  constructability  and efficient  and  confortable  office spaces.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   21 

BUILDING CODE Occupancy Load: 

As per international Building Code which Abu Dhabi is implementing; 9.3 square meters are dedicated for each person in business use buildings which means that the maximum capacity of the building could reach up to 1236 occupants. 

However as per  the design brief;  the building will accommodate 160 occupants while  in  future with some modifications  in  internal partitions  and  furniture  the  capacity of  the building will  reach  to  its maximum. 

 

Sanitary: 

As  per  International  plumbing  Code  table:  403.1  two  groups  of male  and  female  toilets  should  be provided contains 3 toilets and 2 wash basins for each. 

Handicap toilets for M/F have been provided as per the accessibility chapter  in  international building Code. 

Parking: 

As per (Car Parking Design Standard) issued be Department of transportation of Abu Dhabi a rate of 2.4 cars per 100 square meters of Gross floor area should be provided. 

Having  3 underground  levels  for Car parking we obtained  183  parking  slots with  a  shortage  of  105 parking slots. 

The shortage could be covered be having a forth basement as a solution. 

Other option is to use Automated parking Garage that will provide extra parking and could reduce the basement depth. 

 

 

 

  

 

 

A R C H I T E C T U R E   22 

AREA

Parking Calculation

 

 

A R C H I T E C T U R E   23 

SITE PLAN  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   24 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   25 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   26 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   27 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   28 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   29 

FLOOR PLANS  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   30 

FLOOR PLANS

 

 

A R C H I T E C T U R E   31 

FLOOR PLANS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   32 

FRONT ELEVATION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   33 

LEFT SIDE ELEVATION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   34 

REAR ELEVATION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   35 

RIGHT SIDE ELEVATION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   36 

SECTION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   37 

SECTION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   38 

SECTION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   39 

SECTION  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A R C H I T E C T U R E   40 

RENDERING

 

 

A R C H I T E C T U R E   41 

RENDERING

 

 

A R C H I T E C T U R E   42 

RENDERING

 

 

A R C H I T E C T U R E   43 

RENDERING

 

 

A R C H I T E C T U R E   44 

RENDERING

      1

S T R U C T U R E

S T R U C T U R E

 

1 GENERAL

 

2 MATERIALS 

2.1  Reinforced Concrete 

2.2  Precast – Prestressed Concrete  

3 DURABILITY  

4 DESIGN PHILOSOPHY 

4.1  FOUNDATIONS 

4.2  SUPER STRUCTURE SYSTEM DESCRIPTION 

4.3  ADVANTAGES OF THE PROPOSED SYSTEM 

 

      2

S T R U C T U R E

1 GENERAL  This volume summarizes the construction methodology for the Abu Dhabi Accountability Authority Head Quarters.   The parameters have been established as being  the most appropriate  for  the Project, where  the proposed structural system accommodates the building functions,  its architectural design and the building service requirements. 

 

2 MATERIALS  

The choice of construction material in Abu Dhabi is affected by many factors specific to the region. The following list identifies the most significant of these: 

 • High temperatures, which can exceed 45 Celsius at peak times. • Airborne salt contamination due to the coastal location and high humilities. • Large  temperature  ranges  from  day  and  night  and  seasonally,  these  can  have  significant 

effect on the thermal movements of material such as concrete and hence the requirement for regular spaced movement joints. 

• High evaporation rates due to the high temperatures; this can cause in‐situ concrete to dry quickly causing damaging thermal shrinkage. 

• Availability of local sources of raw materials   

The  above mentioned  factors  are  considered  in  the  selection of  construction material  along  the structural advantages and disadvantages of different options, where in all cases great care must be taken to ensure the structural integrity.    

 2.1 Reinforced Concrete

 Reinforced  concrete  is  the  most  common  indigenous  and  locally  available  structural construction material.  Concrete’s  versatility,  durability  and  economy  have  made  it  the  world’s  most  used construction material.  It  is used  in buildings, high‐rise, dams, homes,  floors and numerous other applications.   Concrete is strong in compression, but weak in tension, thus adding reinforcement increases the strength in tension. In addition, the failure strain of concrete in tension is so low that the reinforcement has to hold the cracked sections together.  

  

  For a  strong, ductile and durable  construction  the  reinforcement  shall have  the  following properties: 

 • High strength • High tensile strain • Good bond to the concrete • Thermal compatibility • Durability in the concrete environment                    

                  

  

Reinforced  concrete  can  encompass many  types of  structures  and  components,  including slabs, walls, beams, columns, foundations, frames and more. Much  of  the  focus  on  reinforcing  concrete  is  placed  on  floor  systems.  Designing  and implementing the most efficient floor system  is key to creating optimal building structures. Small changes in the design of a floor system can have significant impact on material costs, construction schedule, and ultimate strength, operating costs, occupancy levels and end use of a building. 

   

Figure 2.1 Reinforced Concrete Constructions. 

      3

S T R U C T U R E

The advantages of using reinforced concrete are:  

• Local contractors and their tradesmen are experienced in reinforced concrete construction; 

• The reinforced concrete trade is well established in the Emirates; • The building materials used are available locally; • Total flexibility in space planning; • Better resistance to environment attack from salt‐laden water; • Concrete has increased resistance to explosion and/or impact; • Concrete resists very high temperatures from fire for a long time without loss of 

structural integrity; • Concrete inherent mass and strength provides resistance to lateral forces; • Concrete seeks the form – any shape can be achieved; • Concrete has flexibility to accommodate design changes later in the progress; • The  inherent  mass  of  concrete  provides  benefits  in  terms  of  acoustics  and 

vibration criteria of the building. 

 High  yield  deformed  steel  bars  with  a  characteristic  strength  not  less  than  460  MPa proposed to be used.   Reinforcement used for the concrete piles can be epoxy coated and/or special admixtures to the concrete can be used to control corrosion. 

 

 

               

                                           Fig. 2.2 Epoxy Coated Rebar                        Fig. 2.3 High Yield Rebar       

2.2 Precast – Prestressed Concrete

Precast Concrete is a construction product produced by casting concrete in a reusable mold or "form" which is then cured in a controlled environment, transported to the construction site and  lifted  into place.  In  contrast,  standard  concrete  is poured  into  site‐specific  forms and  cured  on  site.  Precast  stone  is  distinguished  from  precast  concrete  by  using  a  fine aggregate  in  the  mixture  so  the  final  product  approaches  the  appearance  of  naturally occurring rock or stone.  By producing precast concrete in a controlled environment (typically referred to as a precast plant),  the  precast  concrete  is  afforded  the  opportunity  to  properly  cure  and  be  closely monitored by plant employees. Utilizing a Precast Concrete  system offers many potential advantages  over  site  casting  of  concrete.  The  production  process  for  Precast  Concrete  is performed on ground level which helps with safety throughout a project. There is a greater control  of  the  quality  of materials  and workmanship  in  a  precast  plant  rather  than  on  a construction site. Financially, the forms used  in a precast plant may be reused hundreds to thousands of times before they have to be replaced which allow cost of formwork per unit to be lower than for site‐cast production.   There  are  many  different  types  of  precast  concrete  forming  systems  for  architectural applications, differing in size, function and cost. Precast architectural panels are also used to clad all or part of a building facade free‐standing walls used for landscaping, soundproofing and security walls and some can be Prestressed concrete structural elements.   Prestressed concrete  is a technique that greatly  increases  loadbearing strength of concrete beams, slabs and walls. The reinforcing steel in the bottom part of the beam, which will be subjected to tensile forces when  in service,  is placed  in tension prior to the concrete being poured around  it. Once  the concrete has hardened,  the tension on  the reinforcing steel  is released, placing a built in compressive force on the concrete. When loads are applied, the reinforcing steel takes on more stress and the compressive force in the concrete is reduced, but does not become a tensile force. Since the concrete  is always under compression,  it  is less subject to cracking and failure. 

 

           

      4

S T R U C T U R E

                         

Figure 2.4 Precast construction   

3 DURABILITY

Concrete  structures  shall  be  designed  to  resist  attack  from  the  following  environmental conditions:  

1. Sulphates and chlorides in the subsoil. 2. Sulphates and chlorides in ground water. 3. Wind‐blown salts including aerosols. 4. The aggressive climate, including marine conditions. 5. Availability of suitable water for mixing and curing concrete. 6. Possible contamination by Sulphates and chlorides in aggregates. 

 

4 DESIGN PHILOSOPHY  

Generally, the design philosophy for the structure is as follows:  

• Gravity loads will be transferred from the floor plates to vertical elements like columns and walls, lateral loads will be transferred through floor diaphragm to the lateral loads resisting 

system of shear walls and / or rigid columns. Scheme  framing diagrams  is shown  in figure 2.5. 

 • Efficient  transfer  of  loads  from  floors  to  foundation will  be  adopted  consistent with  the 

architectural requirements.  

• Maximization of materials and content of local origin will be a priority and will be taken into account in the design decision process relating to the structural media and form. 

 • Incorporation of local construction practices and methods and use of local materials, which 

may give rise to savings, will be considered during the design process.  

• High  strength materials  for  concrete,  reinforcing  steel  and  structural  steel  will  be  used where  possible within  the  constraints  set  by  serviceability  requirements.    This  results  in greater efficiency of construction materials and a lower cost of construction. 

 

  

        

 

 

 

 

 

 

 

                                                          Figure 2.5  Framing and Load Transfer Schematic Diagram. 

 

      5

S T R U C T U R E

4.1 FOUNDATIONS  

Abu Dhabi is situated towards the eastern extremity of the geologically stable Arabian Plate and  is separated from the unstable Iranian Fold Belt to the north by the Arabian Gulf.   It  is believed that a tilting of the entire Arabian Plate occurred during the early Permian period, resulting in uplift in southern Yemen and depression to the north east. Tectonic movement’s peripheral to folding of the Iranian Zagros Range during the Pilo‐Pleistocene epoch probably contributed  to  the  formation  of  both  the  Arabian Gulf  depression  and  the mountainous regions in the north east of the UAE and Oman.  Of particular  interest  geologically and  geotechnically  is  the presence of weakly  cemented calcareous  deposits,  deposits  of  evaporates,  mainly  gypsum  and  potential  cavities/vast features. 

 The foundation design will be based on the subsurface soil investigation interpretive report and  recommendations  of  the  geotechnical  specialist.  Foundation  type  will  be  further discussed during the Schematic Design phase upon soil investigation completion.  A combination of high performance concrete and an external membrane system to achieve the necessary water proofing and durability will be used  for  the  foundation. The use of a high performance concrete  in the foundations and basement external envelope  is essential to the design.  The concrete mix needs to be dense and impermeable, to prevent the ingress of water, chlorides and sulphates  into the concrete matrix to achieve the required  level of durability.    The  concrete  must  also  display  low  shrinkage  and  coefficient  of  expansion characteristics to achieve the joint‐less construction required by the design.  

 4.2 SUPER STRUCTURE SYSTEM DESCRIPTION  

Abu Dhabi Accountability Authority Head Quarter comprises of 7 story plus two basement level  structure  with  span  requirements  of  approx.  maximum  of  9  meters  and  with approximate height clearance of 4 meters. 

Building’s  lateral  stability  is  provided  by  the  conrete  shear  walls.  Slabs  are  acting  as diaphragms in order to transfer horizontal forces to the vertical bracing elements (columns and shear walls). The diaphragm action is obtained by a system capable of transferring the horizontal forces by arching or bending. The system is capable to obtain all forces due to in‐plan action like bending, shear and tension and shall be continuous both in longitudinal and transverse direction.   The utilization of Precast Concrete Hollow Core Slab  framing system  is  introduced  for  this building which has an approximate uniform  spanning of 8.5 meters. 265mm  thick hollow core  slab with  65mm  cast  in  situ  concrete  topping with minimum  reinforcement  area  is 

capable  to  support  the  transfer  loading  forces  as  composite  section  to  the  transversal nipped beams  resting on  the vertical  structural elements “columns and walls”. See  figure 2.6 for Hollow Core Slab photo.   Hollow core slab  is supported on beams, refer to figure 2.7 for the typical detail of hollow core slab resting on beams. Beams are supported by 800x800mm columns that are placed typically  in  a  grid  system.  In  addition  to  the  reinforced  concrete  columns,  300mm  thick reinforced concrete walls are  introduced as  lateral  forces resisting system. Refer  to  figure 2.8 for the Proposed Building Frame and figure 2.9 for the proposed Typical Framing Layout.  

  

 

 

 

 

 

 

 

 

     Figure 2.6   Hollow Core Slab. 

 

 

 

 

 

 

 Figure 2.7 Proposed Typical Detail of Hollow Core Slab.  

      6

S T R U C T U R E

   

                                                                                                                 

                 Figure 2.8 Proposed Building Frame with Shear Wall Cast In‐Situ.       

     

 

  

  

                          

                 Figure 2.9 Proposed Typical Framing Layout.  

      7

S T R U C T U R E

4.3 ADVANTAGES OF THE PROPOSED SYSTEM  The proposed system presented part traditional construction and part Off‐site construction. Advantages of traditional construction are discussed on section 2.1. This section will focused on the Off‐site Construction advantages, as follows:  

• Speed of design (typically 30‐60% quicker design time) • Flexibility of design (ability to “plug & play”) • Concurrent production, whist enabling works are under way • Minimized site disruption, due to far less time on site compared to traditional 

construction methods • Improved quality: controlled conditions not weather dependant • Flexibility,  through future expansion & relocation • Far greater control over MEP, installation and design most of which is pre‐commissioned 

under factory controlled conditions • Construction schedule, reduced construction time by up to 50% • Risk, increased predictability of project outcomes in terms of quality, cost and time • Quality, factory production methodology allows for the improvement of building 

quantity • Procurement, increased ability for collaboration and single‐point of responsibility • Factory Time Efficiency, methods of production reduce construction tast time • Disturbance minimizes, disruptions to adjacent buildings and occupants and increase 

cleanliness of building process • Technology, greater ability to manufacture components with high degree of technical 

complexibility • Site, eliminates various site constraints such as staging, weather, transportation, etc. • Security, factory environment improves conditions for constructioin workers • Sustainability & Waste, improved project sustainability and viability of LEED ESTIMADA 

rating • Relocability, possibility to move structure to new location • Economies of Scale, typical benefits of economy of scale are amplified for large projects 

       

  

For Abu Dhabi Accountability Head Quarters two types of superstructure system can be adapted,   

1. Hollow core slabs with Reinforced Concrete Framing.  This  system  is  a Hybrid  Style  Construction  that  comprises  of  traditional  beams,columns  and shear walls cast in‐situ construction and precast slabs construction. 

  Hollow core slabs are  introduced for the floor system.  Pre‐cast  pre‐stressed  concrete elements with continuous voids to reduce self‐weight  and  achieve  structural  efficiency  are very  popular  and  economic  across  a  wide range of spans and loadings.   The  slabs are part of a  full  frame  system and are capable to provide rigid floor diagphram in precast construction. Figure 2.10 Hollow Core Slab supported on Concrete Beams.  

 The  continuous  slab  voids  can  be  used  as heating or cooling ducts and as raceways for electrical wiring while reducing sound transmission and vibrations between floors.  Hollow Core  floor  planks  are  usually  designed  as  simple,  one‐way‐spanning  slabs.  Floors  are often subject to non‐uniform loads such as line loads, concentrated loads or loads at openings.  

              

Figure 2.10 

      8

S T R U C T U R E

2. Precast slabs, beams, columns and cast in‐situ shear walls.  This system  is a Precast Construction  throughout with cast  in‐situ shear walls only.  It  is best recommended to use reinforced concrete for shear walls to resist lateral forces applied to the building. 

 Precast Construction  is one of the most versatile and sustainable building materials available for  today's  fast‐paced,  environmentally  conscious  construction. Combining  the  strength  and durability of concrete with the flexibility and aesthetics of precast elements, it is considered on the  most  economical  and  attractive  construction  solution  available.  As  discussed,  several advantages using precast or Off‐site construction.  

                                 

 Figure 2.11 Precast Construction. 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   1 

MECHANICAL, ELECTRICAL & PLUMBING

1.0 INTRODUCTION2.0 REGULATIONS, STANDARDS AND REFERENCES 3.0 SCOPE OF WORK 4.0 AIR CONDITIONING AND VENTILATION SYSTEMS 5.0 DOMESTIC WATER SERVICES 6.0 DRAINAGE SERVICES 7.0 FIRE DETECTION AND PROTECTION SERVICES 8.0 ELECTRICAL SYSTEMS 9.0 TELEPHONE AND DATA COMMUNICATION SYSTEM 10.0 CENTRAL ANTENNA TELEVISION AND SATELLITE SYSTEM 11.0 PUBLIC ADDRESS AND MUSIC SYSTEM 12.0 FIRE DETECTION AND ALARM SYSTEM 13.0 SECURITY SYSTEM 14.0 TIME AND ATTENDANCE SYSTEM 15.0 ENERGY SAVING SYSTEMS & SUSTAINABLE MEASUREMENT 16.0 STANDARD AND CODES    

 

 

MECHANICAL, ELECTRICAL & PLUMBING   2 

1.0 INTRODUCTION

1.1 Purpose  

  The purpose of this MEP proposal is to establish key design criteria, methods of servicing, primary distribution routes and locate major items of the electrical and mechanical systems.  

 

2.0 REGULATIONS, STANDARDS AND REFERENCES

2.1 Publications, Standards and References  

  All work shall be carried out  in accordance with the requirements of the  local authorities and the standards and codes included hereinafter. 

 

ARI   American Refrigeration Institute 

ASHRAE   American Society of Heating, Refrigerating and Air Conditioning Engineers Inc.  

ASTM   American Society of Testing Materials 

  SMACNA  Sheet Metal and Air Conditioning Contractors National Association  

  NFPA  National Fire Protection Association 

UL  Under writers Laboratory 

IEE  Institution of Electrical Engineers 

IEC  International Electro‐technical Commission 

IOS  International Organization of Standardization 

ADDC  Abu Dhabi Distribution Company  

ADSSC  Abu Dhabi Sewerage Service Company 

ADCD  Abu Dhabi Civil Defense Authority 

ETISALAT  Local Telecom Authority 

 

CIBSE  Chartered Institution of Building Services Engineers  

 

  BSI       British Standards Institution  

2.2 Materials  

  All materials used on the project shall be brand new and of high quality. 

 

  “New” is defined as newly manufactured, “state of the arts,” tested and proven item of equipment.  Items which have been held in stock for any extended period of time by either the manufacturer or the supplier shall be rejected. 

 

  All materials  used  on  this  project  shall  bear  the  third  party  quality  assurance  stamp  like British Standard kitemark, UL, FM, LPC and/or other quality assurance authority as stated herein. 

 

3.0 SCOPE OF WORK

3.1 Mechanical Services  

  The following services shall be provided for the project: 

 

3.1.1  Air Conditioning 

 

  ‐  Central air‐conditioning and ventilation. 

 

3.1.2  Plumbing & Drainage 

 

  ‐  Cold and hot water services network. 

  ‐  Filtration of cold water services. 

  ‐  Gravity drains connected to the city drainage network. 

 

 

3.1.3  Fire Protection 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   3 

  ‐  Automatic hose reels for use by occupants. 

  ‐  Dry riser and landing valves for use by the fire department. 

- Sprinkler system. - Fire extinguishers 

   

3.1.4  Building Management system 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   4 

4.0 AIR CONDITIONING AND VENTILATION SYSTEMS

4.1 Design Parameters  

  Design  in  general  shall  be  based  on  ASHRAE  62‐2007  recommendations  in  addition  to  the following practical requirements.  

 

4.1.1  Design Conditions 

 

  External  :  46 ºC DB, 29.4 ºC WB 

  (Summer) 

 

  Internal  :  23ºC  DB,  RH  50%  +  5%  (No  specific  humidity  controls  and  resultant  relative humidity will be function of set point temperature). 

 

    :  No winter heating shall be provided. 

 

4.1.2  Ventilation, Occupancy and Heat Dissipation Requirements 

 

Area  Ventilation  Occupancy Heat Dissipation due to Lighting and Power 

Offices   8.5 L/s/person  20 m²/person  40 w/m² 

Meeting room  

3.1 L/s/person  2 m²/person  40 w/m² 

Coffee shop 

4.7 L/s/person  1 m²/person  40 w/m² 

Retail  7.8 L/s/person  6.7 m²/person  70 w/m² 

Circulation/Corridor  

0.3 L/s/m2  ‐‐  20 w/m² 

Area  Ventilation  Occupancy Heat Dissipation due to Lighting and Power 

Storage rooms 

0.12 L/s/m2  ‐‐  10 w/m² 

Reception areas 

3.5  L/s/person  3.3 m²/person  40 w/m² 

Main entry lobbies 

5.5 L/s/person  10 m²/person  40 w/m² 

Prayer rooms 

2.8 L/s/person 0.83 m²/person 

20 w/m² 

Galleries/show rooms  

4.6 L/s/person  2.5 m²/person  70 w/m² 

 

  For other areas refer to ASHRAE Standard 62‐2007.  

  

Extract Air System   

Area  Extract Air 

Public Toilet 

 

25 L/s 

 

 

4.1.3  Noise Levels 

 

  ‐  Offices/Meeting Rooms  NC 35 

  ‐  Corridors & Public Areas  NC 40 

  ‐  Toilets  NC 40 

  ‐  Plant rooms    NC 50      

 

 

MECHANICAL, ELECTRICAL & PLUMBING   5 

 

4.1.4  Air Filtration 

 

  a)  Air filtration shall be based on ASHRAE 52‐76. 

 

  b)  Fresh  Air  handling  units  shall  have  two  banks  of  filters.  Panel  filter  at  25%  ‐  30% efficiency and bag filter at 85% ‐ 90% efficiency.  

 

  c)  Fan coil units shall have 25mm thick cleanable panel filter at 25% efficiency. 

4.2 System Description  

4.2.1      Air Conditioning  

  

Option – 1 

 

Air cooled chillers on the roof of the building to serve FCUs/AHUs through chilled water network. 

 

Although this option is simple and common, the following disadvantages are obvious: 

 

a)  Bulky installation on building roof. 

b)  Standby chiller shall be considered, i.e. dead capacity. 

c)  Major source of noise  

 

Option – 2 

 

Variable Refrigerant Volume System (VRV). The system comprises of modular outdoor unit connected with multi indoor units via refrigerant piping network.  

The system offers a considerable reduction of refrigerant flow as per the cooling load  demand which will lead to a considerable energy reduction.  

 

  All indoor spaces shall be served with ducted indoor units.    

     

    a)  Advantages 

 

1)  Limited/compacted space required on roof for outdoor units installation.  

2)  When  integrated with  control  systems,  the performance  can be optimized  to achieve low energy consumption. 

   

    b)  Disadvantages 

 

1)  System  spare  parts  including  pipe  fittings  and  manifolds  are  limited  to  the equipment supplier. 

  2)  System cost is higher than option‐1.  

  3)  Cooling capacity of the system is limited.  

4)  Fresh  air  handling  unit  shall  be  provided  with  separate  conventional  Direct Expansion  (DX) –  condensing unit due  to  the  limitation of  cooling  capacity  for VRV‐system. 

 

Recommendation: 

 

It is recommended to use Option‐2. 

 

4.2.2   Ventilation   

 

  a)  Central fresh air handling unit shall be provided. Fresh air shall be delivered to all indoor units via insulated duct riser.  

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   6 

 b)   FAHU shall have heat recovery section for energy saving. 

 

  c)  Extract  air  shall  be  taken  from  toilets  and  pantries  and  ducted  to  the  heat  recovery section of FAHU via duct risers. 

 

4.2.3  Heat Recovery System  

 

Thermal wheel shall be provided  in  the FAHUs  in order  to recover energy  from  the extract air and pre‐cool  the  intake air  to  FAHUs,  thus  reducing  the  cooling  load of  FAHU  coil  for energy saving. 

5.0 DOMESTIC WATER SERVICES

5.1 Design Parameters

The design shall be based on the recommendation of the Chartered Institution of Building Services Engineers  and  the  Regulations  of  the  Local  Water  Utilities  Company.    The  following  general guidelines shall be followed: 

a) Water velocity shall be limited to about 2.5m/s. to avoid water flow noise. 

b) The temperature of the stored hot water shall not exceed 65oC. 

c) Dead legs to hot water draw off points shall be kept as short as possible. 

d) Thermal and protective insulation of pipework shall be provided as specified. 

e) Water  storage  tank  shall  be  provided  for  domestic water  consumption  along with  the minimum fire reserve as stipulated by the local Civil Defence Authority. 

f) Over head water storage tank shall be provided for domestic water consumption. 

g) The booster pump shall be sized to supply water to al outlets while maintaining a water pressure in the range of 2.0 to 3.5 bar at the outlets. 

h) Pressure regulation valves shall be provided as necessary to limit the pressure within the maximum permissible limits. 

i) Water meters location shall be accessible to ADDC personnel. 

5.2 System Description  

5.2.1   Cold Water System  

 

  a)  From  the  water  mains,  an  incoming  water  line  shall  be  connected  to  the  main underground concrete (RCC) water storage tank (1.5 daily demand capacity. 

 

  b)   Water  from  underground  water  tank  shall  be  transferred  via  lifting  pumpset  to  the overhead  tanks, which has  to be  located  above  the  floors  served by  these  respective tanks. 

 

  c)   The  overhead  tanks  shall  have  1  daily  demand  as  a  domestic  reserve  for  the  floors served by the respective tank. 

 

d)  Water  supply  to  shall  be  toilets/pantries  through  booster  pump  set  to  maintain minimum 1.5 bar pressure at the draw‐off points. 

 

e)  Water meter shall be provided on the incoming water line to the U/G main water tank. 

 

5.2.2   Hot Water System 

 

  Hot  water  to  the  public  toilets/pantries  shall  be  provided  through  individual  electric  water heater installed within the ceiling void of the wet areas. 

 

 

6.0 DRAINAGE SERVICES  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   7 

6.1 System Design  

  This will be  a  gravity drainage  system designed  in  accordance with  the  recommendation of  the Charted  Institution of Building  Services Engineers  (CIBSE)  to  the  requirements of  the Abu Dhabi Municipality – Town Drainage Department.    

 

6.2 System Description    

  All work shall be installed and tested in accordance with BS5572 Code of Practice for sanitary work and  to  the  satisfaction  of  the  local  Drainage  Department.    The  internal  drainage  system  shall comprise of two stacks (soil and waste) with a separate vent pipe.  All drainage shall be discharged into the city sewer main through a series of gully traps and manholes, as required.   

 

  A separate rain water system shall be installed to collect rainwater from the roof and discharge at agreed locations on to pavement or to discharge into the city storm water main through a series of catch basins and storm water manholes, as required. 

  

   

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   8 

7.0 FIRE DETECTION AND PROTECTION SERVICES 7.1 System Design  

  All systems shall be designed in accordance with the requirements as set out in the relevant British Standards, NFPA and to the requirements of the Local Civil Defence Authority. 

 

  The various systems to be provided for this project are: 

 

a) Automatic fire hose reels. b) Dry riser with landing valves for use by the fire service personnel. c) Automatic sprinkler system. d) Fire extinguishers. 

 

7.2 System Description  

7.2.1  Automatic fire hose reels 

 

This system shall primarily be for use by the occupants and used as a first aid means of fighting a fire whilst awaiting the arrival of the Local Fire Brigade.

 

  The fire hose reel pipework shall be connected to the fire mains through a pressure reducing valve so as to maintain the system under pressure and to automatically release a jet of water when any hose is uncoiled. 

 

  Fire hose reels shall be  located such that these are readily accessible and that these can cover all areas of the building with no part being more than 6 meters from the hose reel nozzle when the hose is uncoiled. 

 

7.2.2  Dry Riser with Landing Valves 

 

  This system shall be provided solely for use by the fire service personnel and shall consist basically of one or more pipes rising vertically up the building with hydrant valve outlets on each floor and at roof level. Landing valves shall be located within the same cabinet to be used for fire hose reels. 

 

7.2.3  Automatic Sprinkler System 

 

  The project  shall be provided with an  automatic  sprinkler  installation,  classified and designed  in accordance to NFPA 13 rules for automatic sprinkler installation.  

 

    The sprinkler system shall be continuously maintained under pressure by fire pumps installed within the  pump  room  and  serving  sprinkler  and  automatic  fire  hose  reels.  The  sprinkler  system  shall consists  of  a  network  of  piping with water  always maintain  the  system  under  pressure.  Fusible sprinkler heads shall be screwed into the piping at interval as recommended by NFPA regulations. 

 

  In the event of a fire, the heat generated shall cause the fusible element  in the adjacent sprinkler head to disintegrate and thus allow water to be discharged onto the fire in the form of a fire spray. 

 

  At the same time as water is discharged onto the fire, water shall also be allowed to flow to a water turbine which in turn shall operate an alarm gong thus giving an audible alarm that the system has operated.   The  system  shall also be  interfaced with  the  fire alarm panel  in order  to actuate  fire alarm bells in a fire situation. 

 

7.2.4  Fire Extinguishers 

 

  Shall be dry powder and/or carbon dioxide as required by the local authorities 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   9 

8.0 ELECTRICAL SYSTEMS 8.1 General          

    The following systems shall be provided for the project: 

 

a) High Voltage System b) Low Voltage Electrical Distribution c) Emergency Power Supply through Standby Generator d) Lighting and Small Power Distribution  System e) Lighting control System f) Central Battery Emergency Lighting System g) Earthing System h) Lightning Protection System i) Security and CCTV System j) Fire Alarm System k) Public Address and Background Music System  l) Voice and Data Systems m) Central Antenna and Satellite System  n) Building management system 

   

8.2 Codes & Standard:  

The electrical  installation shall  in general be designed  to meet  the  following codes, standard and requirement of: 

 

a) NEC           National Electrical Code b) NFPA         National Fire Protection Association  c) UL               Underwriters Laboratories  d) IEEE          Institute of Electrical and Electronic Engineer e) IES              illuminating Engineering society f) IEC            International Electro‐technical Committee   g) TIA             Telecommunications Industry Association h) ADDC          Abu Dhabi Distribution Company i) RSB    Regulation and Supervision Bureau j) ETISALAT    Local Telecom Company k) ADCD            Abu Dhabi Civil Defense           l) BSI                  British Standards Institution m) CIBSE             Charter Institute of Building Services Engineers    

 

 

The installation shall also be designed to protect persons, property and livestock against hazard of electric shock, fire burns and injury from mechanical movement of electrically actuated equipment. 

 

    Integration of mechanical and electrical discipline with the architectural design and adequate space for electro mechanical services shall be provided to improve systems maintainability and reliability and to integrate the same with the surrounding architectural appearance. 

 

    All  electrical  equipment  shall  be  compensated  to  give  the  rated  output  at  35  °C  for  internal installation and at 45 °C for the external installation. 

   

 

8.3 Electrical Load Assessments:  

The preliminary building load estimation shall be based on power density assumptions that apply to the  general  space  programs.  As  the  utilization  of  spaces  and  other  building  systems  are more defined, the load estimation shall be provided accordingly. 

   

8.4 High Voltage System  

HV primary ring feeders shall be derived from the nearest primary substation in coordination with Infrastructure Consultant. 

 

The HV  feeders  shall power  the  ring main unit  (TRM)  rated  to  carry  the  total building  load  and facilitate full redundancy in the event of one source or feeder failure. 

 

The  supply  cables  shall  be  routed  from  primary  substation  to  the  building  via  the  underground concrete encased electrical duct banks. In the buildings, the cables shall be terminated in the TRM which in turns will provide HV feeder for the transformer within the transformer room. From the LV side of  the  transformer  LV  cables  shall be  routed  to  the  LV  room  to  feed  the main  low  voltage switchgears,  from which  further distribution will be provided  to  the entire building via  cables as detailed hereafter: 

 

The substation shall consist of high voltage room, transformer room, Generator room, etc. The LV room will be located within the building at the edge near to the substation to optimize cable runs. The exact arrangement of the sub station  including the transformers and HV panels shall be as agreed with ADDC. 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   10 

 

8.5 Low Voltage System  

The low voltage side of the transformers shall be connected to the low voltage panel located in the LV room. The LV panel shall be constructed to the requirement of BSEN 60439‐1  

 

The low voltage (LV) installation shall consist of 1600A main distribution boards (MDB) in LV rooms located below the substations and motor control centers (MCC) for the chiller plants, sub-main distribution boards (SMDB) and final distribution boards (DB).

 

  Single core armoured cables from LV side of the transformers shall feed the MDB incomer circuit breaker. Outgoing air / moulded case circuit breakers (ACB / MCCB) shall feed SMDBs and MCCs through cables. 

   

  Low voltage system shall consist of the following: 

 

 

 

8.5.1     Main Distribution Boards (MDB) 

 

  The construction of the main distribution boards shall comply with (form 2B, type 2 or Form 4B, type  6)  requirements  of  IEC‐439‐1  based  on  Client’s  recommendation.  The  boards  shall  be constructed to withstand a short circuit current of 50kA for 1 second, which  is considered as a safe short circuit protection level.  Ingress protection shall be to IP 41.   

 

8.5.2     Main Distribution Boards construction details (MDB) 

 

Option: 1 

 

  Form 2b, type 2 assemblies 

 

  Form 2b, type 2 covers overall assemblies which are so enclosed as to provide protection against contact with some internal live parts and components but where there is internal separation of the busbars from functional units. 

 

i. Busbars are separated from functional units.  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   11 

ii. Functional units are not separated from functional units.  

iii. The busbar separation is achieved by metallic or non‐metallic rigid barriers, or partitions.    

iv. Terminals  are  therefore  separated  from  the  busbars  from  functional  units  or  each other’s.  

Option: 2 

 

  Form 4B, type 6 assemblies 

 

  Form 4B, type 6 covers overall assemblies which are so enclosed as to provide protection against contact with internal live parts and components and in which there is internal separation of the busbar  system  from  functional units  and  separation of  all  functional units  from one  another.  Incoming and outgoing terminals are also separated from the busbars and from each other. 

 

i. Busbars are separated from functional units.  

ii. Functional units are separated from each other.  

iii. Terminations to functional units are separated from each other.  

iv. Incoming  and  outgoing  terminals  are  separated  from  each  other  and  from  other terminals. 

 

v. The  busbar  separation  is  by  metallic  or  non‐metallic  rigid  barriers,  or  partitions.  Terminals  are  separated  by  insulated  coverings  and  glanded  in  common  cabling chambers. 

 

The following LV panel forms construction to be advised by the client in terms of cost: 

 

Option  Form  Yes   No 

1  Form 2B Type 2     

2  Form 4B Type 6     

 

 

  From the LV panel cables shall be routed to feed the power to the submain panels located in various electrical rooms of each floor. 

  

8.5.3  Sub Main Distribution Board 

 

  The  construction  of  the  sub‐main  distribution  boards  shall  comply  with  form  2,  type  2 requirements of IEC‐439‐1. The boards shall be constructed to withstand a short circuit current of 30kA. Ingress protection shall be to IP 41. The sub‐main distribution boards shall be located in every floor of the building. 

 

  In general, SMDBs shall be provided to feed final distribution boards isolators in every floor.  

 

8.5.3.1  Form 2, type 2 assemblies 

 

Form 2 covers overall assemblies which are enclosed as to provide protection against contact with any internal live parts or components, and where there is internal separation of the busbars from functional units and their terminations.

 

i. Busbars are separated from functional units and incoming and outgoing terminals.  

ii. Functional units are not separated from other functional units.  

iii. Functional units are not separated from any incoming or outgoing terminals.  

iv. Busbar  separation  is  achieved either by  insulated  covering  (e.g.  sleeving, wrapping or coating) or by metallic or non–metallic rigid barriers or partitions.   

 

  The LV panel and  the sub main distribution shall be arranged such  that maximum  flexibility  is available to respond to any extra power. 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   12 

8.5.4  Final Distribution Boards  

   

From the dedicated SMDB each electrical room armoured cables on heavy duty cable tray shall feed the  final  distribution  boards  (DB)  located within  the  electrical  room  and which  shall  feed  final lighting and power circuits. 

 

The final distribution boards shall be split busbar type and shall be provided with isolator as incomer and miniature circuit breakers (MCBs) as outgoings with common RCD protection for each section of MCBs. The minimum short circuit rating for final DBs and circuit breakers shall be 10 KA. 

 

The LV switchgear and the sub‐main distribution shall be arranged such that maximum flexibility is available to respond to any extra power. 

 

Cables  within  the  building  shall  be  routed  through  cable  trays,  but  all  external  underground installation shall be using concrete encased uPVC ducts and manholes. 

 

All cable shall be sized such that the current carrying capacity at 50 deg. C is equal or higher to the rating  of  the  breaker  protecting  the  cable, method  of  installation  of  the  cable  and  the  spacing between  adjacent  cables  shall  be  taken  into  consideration  in  determining  the  cable  current capacities. 

 

The cables shall also be sized to limit the voltage drop between the main panel boards to the final power consumption point to 4% of the nominal voltage. 

 

8.5.5  Starter Panels 

 

  Local starter panels shall be provided for equipment not controlled from motor control centers. These panels shall be constructed as per form 2, type 2 Standards. 

 

8.5.6  Capacitor Banks 

 

8.5.6.1  Reactive Power Compensation  

 

Electrical networks which include major inductive loads (e.g. motors) shall operate under poor overall lagging power factor conditions. Also, in case these inductive loads are constantly being switched on and off (e.g. HVAC equipment motors), the power factor of the overall system shall change with every switching operation. A poor power factor is a major (and avoidable) cost factor. There are basically three methods which are commonly used to compensate for the inductive power drawn by a load or an electrical installation, and thereby improve its power factor.

  Option‐1: 

 

  Individual Compensation 

 

  In  the case of  individual compensation,  the capacitors are connected directly  to  the  terminals of the  individual  loads and are switched in and out of circuit by the same common switching device. The chillers shall  be provided with its own PFC capacitors to improve the power factor to 0.95. 

 

  Option‐2: 

 

  Group Compensation  

 

  In this case, the power  factor correction equipment provides a  fixed value compensation  for a number  of motors  or  e.g.  fluorescent  lamps which  are  switched  as  a  group  by means  of  a common contactor or circuit – breaker. 

 

  Option‐3: 

 

  Centralized Compensation 

 

  In most cases power factor correction units, which automatically switch power capacitors into or from the load circuit, are used for centralized power factor correction.  They are usually directly associated  with,  and  installed  centrally  at,  a  particular  switchboard,  distribution  board  or incoming supply. 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   13 

 

 

8.5.6.2            Selection of Type of Compensation 

 

  The most  suitable  type  of  compensation  is  arrived  at  based  on  a  number  of  technical  and economical  aspects. Generally,  central  power  factor  correction  units  have  a  higher  price  per installed kVAR.  As a guideline, it has been found that the cost of the two methods is comparable for a diversity  factor  (or  load  factor) as high as 0.7  to 0.8.    If  the diversity  factor  is  lower,  the centralized method of compensation becomes more attractive.   

 

  In general, the system proposed for the project is centralized compensation which also complies with  ADDC  requirements.  The  chillers  shall  have  its  own  PFC  capacitors  as  part  of  the  soft starter. 

 

  Capacitor  banks  shall  be  provided  to  improve  the  system  power  factor  to  greater  than  0.90 lagging  and  shall  be  installed  across  the  MDB.  An  automatic  power  factor  regulator  shall continuously  sense  the  power  factor  condition  across  the  MDB  and  shall  switch  on  or  off capacitors to maintain the overall power factor greater than 0.90 lagging.  

 

  Special  filters shall be provided  for capacitors  to withstand  transient harmonic currents  in  the system. The capacitor panel shall be located adjacent to the MDBs. 

  The capacitor banks shall be constructed to IEC‐831 standard and capacitor bank enclosures shall comply with IEC‐439‐1. 

 

8.5.8              Energy Metering 

 

Energy meters shall be provided as follows: 

 

  Main  meter  as  per  ADDC  requirement  for  LV  Panels  sub  metering  according  to  client requirements.  In  addition  to  the  above,  energy monitoring  units  (EMU)  shall  be  installed  in MDBs  for  remote monitoring of power  consumption,  voltage,  current,  frequency etc. of each panel on the building management system. 

     

8.5.8.1  Dedicated Motor Control Center (MCC) shall be provided at appropriate location near the chiller plant to feed the HVAC system equipment. 

                     

8.6 Emergency Power Supply system  

A  low voltage (415 V, 3 Phase emergency generator and  its dedicated distribution system shall be provided to power primarily the life‐safety equipment and devices. 

The fuel storage tank shall be sized to store enough fuel for 1 days of generator run time. 

 

Limited amount of power shall be available to back up some of non safety equipment in the building that required functioning during the power failure. 

 

The  generator  shall  be  located  in  the  service  block  to  ensure  proper  ventilation  and  near  the substation to reduce cable runs.  

 

A dedicated Emergency Sub Main distribution board shall be provided for the building with a feeder from  the  sub  station  generator  panel  and  shall  be  located  in  the  LV  room  for  feeding  all  the essential services of the building  Further power  distribution from the emergency MSMDB shall be similar  to  the normal power distribution using sub main distribution boards and  final distribution boards to be located at the various electrical rooms and fed by cables on cable tray: The essential services shall also include the following: 

     

    a)  40% of the lighting in the corridors and 25 to 30% of the general public area lighting. 

b)  100% of the fire escape lighting 

c)  Elevator(s) 

d)  Service elevator  

e)  Domestic water pumps 

f)  Sump pumps 

g)  Control, security and main telecom room. 

h)  Smoke extract fans, staircase fans, etc 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   14 

i)  Life and safety equipment such as fire alarm system, public address, CCTV system, security system, BMS, etc... 

j)  UPS 

 

Emergency power generators can be provided 100 % back up subject to client request. 

 

8.7 Un-Interruptible Power Supply (UPS)      

    An  Un‐interruptible  Power  Supply  (UPS)  unit with  battery  backup will  be  provided  in  order  to maintain continuous power supply be provide to the main server and various IDTs. Autonomy time will be 30 minutes.         

8.8 Lighting      

The illumination levels for the various areas of the project shall be generally in accordance with the recommendation of CIBSE code. 

 

i. Illuminance.  

  The design service illuminance for specific areas shall  be as follows: 

 

SN  Space  Illumination (Lux) 

Control  Lamp Type

1. Offices  500  • Presence sensors • Override at space entrance 

T5 Fluorescent  

2. Meeting and conference rooms 

500  • DALI ballasts  • Presence sensors • Dimmer override at space 

entrance 

T5 Fluorescent 

3. Corridors and circulation 

250  • Timer for working hours • Presence sensors for after 

working hours and holidays • Override at reception desk 

Compact Fluorescent 

4. Plant rooms  300  • Conventional switches  T5 Fluorescent 

5. Stairs 150 • Timer for working hours • Presence sensors for after 

working hours and holidays • Override at reception desk 

Compact Fluorescent 

6. Toilets / washrooms 

150 • Presence sensors  Compact Fluorescent 

7. Kitchen / pantry 300 • Presence sensors • Override at space entrance. 

T5 Fluorescent 

8.

 

Multipurpose hall 

300 • Dimmable DALI ballasts • Presence sensors • Handheld touch screen 

controller • Intelligent override switch 

Compact fluorescent + track light provision 

9. Press conference  

300 • Dimmable DALI ballasts • Presence sensors • Handheld touch screen 

controller • Intelligent override switch 

Compact fluorescent + stage lighting provision  

10 External lighting ‐ • Timers and photocells  Metal halide / fluorescent / LED 

 

ii. Illuminance Ratios  

a. The ratio of the minimum illuminance to the average illuminance over the  task area shall  not be less than 0.8. 

b. In an interior with general lighting, the ratio of the average illuminance on the ceiling to the average illuminance on the horizontal working plane shall be within the range 0.3 to 0.9. 

c. In an interior with general lighting, the ratio of the average illuminance of any wall to the average illuminance on the horizontal working plane shall be within the range 0.5 to 0.8. 

d. In an interior with localized or local lighting, the ratio of the illuminance on the task area to the illuminance around the task area shall not be more than 3:1. 

 

iii. The Lighting  layout shall be coordinated with false ceiling  layout and all other services,and the  design service illuminance for specific areas shall  be as follows: 

 

iv. Surface Reflectance  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   15 

  Surface reflectance as detailed below shall  generally be considered: 

 

a. The ceiling cavity reflectance shall   be as high as practicable and generally at  least 0.6.  This shall  usually mean that the reflectance of the paint or other surface finish must be at least 0.8. 

 

b. The  effective  reflectance  of  the  principal walls  shall    be  between  0.3  and  0.7.    This usually means  that  the walls  surface  finish  shall    have  to  have  an  actual  reflectance greater than 0.5.  The reflectance of window wall surfaces shall  be at least 0.6 to reduce contract with the bright scene outdoors during day time. 

 

c. Where  practical,  floor  cavity  reflectance  shall    be within  the  range  0.2  to  0.3.    This usually means that the relevant surfaces shall   have to have a reflectance greater than 0.3. 

 

d. It is desirable for equipment and furnishings in working interiors, and in particular desk tops, to have finishes with a reflectance of not less than 0.2. 

 

v. Colour  

Where accurate colour  judgments are to be made, care shall   be taken to select proper colour rendering group. 

 

vi. Glare  

a. Luminous  ceilings  utilizing  large  diffusing  panels  are  not  recommended  for  lighting interiors.    In  any  case,  the  average  luminance of  such  luminous  ceiling  should not be greater than 500cd/m2. 

 

b. For  indirect  lighting,  the  average  luminance  of  the  ceiling  should  not  be more  than 500cd/m2. 

 

8.7.1    Light Sources 

 

  High efficiency light source shall be utilized wherever possible such as: 

 

a) Fluorescent lamps (T5). b) Compact Fluorescent lamps. c) LED lamps. d) Metal halide 

 

8.7.2  Light Fittings 

 

  The light fittings shall be constructed to BS 4533.  Light fittings shall be specified according to the type  of  protection  against  electric  shock,  the  degree  of  protection  against  ingress  of  dust  or moisture and according  to  the material of  the  supporting  surface  for which  the  light  fitting  is designed. 

 

8.7.2.1 Information which shall be marked on light fittings shall be as follows: a) Mark of origin. b) Rated voltages(s) in volts. c) Rated maximum ambient temperature. d) Symbol of class II or class III light fitting. e) Ingress Protection (IP) number. f) Maker’s model number or type reference. g) Rated wattage of the lamp(s) in watts. h) Symbol for light fittings with built‐in ballast or transformers suitable for direct mounting 

on normally flammable surfaces. i) Information concerning special lamps. j) Terminations to be clearly marked to identify which termination should be connected to 

the  live  side  of  the  supply,  where  necessary  for  safety  or  to  ensure  satisfactory operation.  Earthing terminators shall be clearly indicated. 

k) Symbols  for  the minimum  distance  from  lighted  objects,  for  spotlights  and  the  like, where applicable. 

 

8.7.3  Proposed light fitting for various areas of the project: 

   

 

 

MECHANICAL, ELECTRICAL & PLUMBING   16 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

S. N  Location  Description   Picture  

1.  Cove Light  LED strip cove light, with LED lamps spaces 50mm apart.  Power consumption is around 7W per linear meter, which is less than 25% of the equivalent fluorescent cove power consumption.    

2.  Spot Light  LED spot light made of zinc alloy body, with 3 Nos. LED lamps and 3.6 W power consumption which is 10% of it equivalent halogen spot light power consumption    

 

 

 

3.  Offices   Recessed luminaire equipped with T5 tubular fluorescent lamps with colour rendering 85, 4000 K colour appearance, aluminium louvers with glare control to luminance <1000 cd/m² at >65º C. 

 

4.  Corridors & Circulation  

Recessed, down lighter having wide beam distribution, aluminium reflector, cast aluminium mounting ring with outer frosted floating glass.  

Lamp: 2x18W compact fluorescent               

 

 

5.  Plant Rooms  2x54/2x28 T5 lamp, surface mounted luminaire, having GRP housing, impact resistant prismatic diffuser with stainless steel clips, all to IP65 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   17 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6. 

Façade Lighting  

Powerful LED façade lighting with 3W LED lamps. With colour changing feature. Body made of aluminium alloy, toughened glass to IP 65. 

  

 

 

 

7.  

External  

Lighting (Building Perimeter at ground floor) 

Wall luminaire with optical system allowing light from one lamp to merge in two directions with narrow upward beam and wide down ward beam. 70W metal halide lamp, aluminium alloy body anodized aluminium reflector, IP65. 

 

8.  Roof  Robust luminaire made of die‐cast aluminium and thick walled crystal glass with optical texture, 1x26W compact flourescent lamp, IP55.  

 

9.  Toilet  Recessed luminaire equipped with compact fluorescent lamp with colour rendering 85, 3000 K colour appearance, glass diffuser, IP44. 

 

10.  Server Rooms, Control Rooms 

Recessed luminaire equipped with T5 lamps and glare control to luminance <1000 cd/m² at >65º.  

Colour rendering 85 and colour temperature 4000 K. 

 

11.  Lobbies Entrances 

Decorative recessed circular down lighter with two lamps (T5 Lamps) 

 

 

 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   18 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   19 

 

8.8 Wiring Accessories  

8.8.1  General Purpose Socket Outlet 

 

  General  purpose  13A  switched  socket  outlets  shall  be  provided  throughout  the  proposed development. 

 

 

  All areas  including plant  rooms,  roofs, stores, mechanical equipment  rooms, corridors,  lobbies etc. shall be considered. 

 

The switched socket outlets shall be in accordance with BS 1363 and BS 546 as appropriate. Minimum number of outlets provided in each area shall be as follows:

 

Entrances and Lobbies   :  1 Outlet / 15m2 

Corridors and Circulation Areas   :  1 Outlet / 15m2 

Pantry / Kitchen  : To suit equipment layout  

Receptions     :  One twin 13 ASSO for each work station.  

 

Workstations                              :  One Twin 13A SSO per workstation 

 

8.8.2  Local Switches 

 

  Switches shall be grid  type of  the quick start make, slow break  type specially designed  for AC circuit to BS 3676.  Switches shall be 20A grid type. 

 

8.8.3  Finish of Wiring Accessories 

 

  All  accessories  in wet  and damp  areas  shall    be of  the  splash proof  type  to  IP  55 protection standard. 

 

  All accessories in plant rooms shall  be with metal clad finish. 

 

  All accessories above False Ceiling shall be white plastic finish. 

 

 

  The wiring accessories finishes in the public areas such as main entrance, lift lobbies, etc… shall be either one of the following based on Client’s instruction: 

 

SN  Location 

Wiring accessories finish 

Remarks Slim 

crewless metallic finish 

Slim screwless white 

polycarbonate 

Slim screwless coloured 

polycarbonate 

1. Offices  / workstations 

   

2. Circulation areas    

3. Multipurposehall 

   

4. Press conference  & auditorium 

   

5. Reception    

6. Leasable spaces    

 

8.9 Lighting Control System  

    Programmable  lighting  control  based  on  distributed  intelligence      system  shall  be  provided  for controlling the lighting at the various areas.  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   20 

 

The  system  shall automatically  switch  the  lights on  and off  in pattern as programmed  and with features of changing the timing and type of lights controlled within a group. 

 

All  internal  area  lighting  shall  be  controlled  through  timers  and  presence  sensors.    All  external lighting including those of building facial, landscaping, road/pathway, parking etc shall be controlled through timer and photocells. As detailed in the lighting section 

 

The system shall receive a signal through the fire alarm panel to switch all the lights ON during fire and the lights connected to emergency power supply during power failure 

 

8.10 Emergency Lighting system  

8.10.1    Emergency and Fire Exit Lights 

 

The task of emergency lighting is to provide safety lighting meant to evacuate a building without risk. Emergency lighting systems are generally of two options:

a) Self Contained type, wherein the battery pack is contained in the light fitting itself. b) Central Battery system, wherein the battery pack is centralized for a group of light

fittings and is remotely located. The system proposed for the project is central battery system as it has the following advantages over self contained type light fittings:

 

a) High safety level due to decentralized configuration.

b) Fully automatic periodic testing facility, whereby any faulty light fitting can be immediately detected.

c) Fully automatic monitoring facility.

d) Freely programmable control module.

e) Continuous battery charge monitoring.

f) Very low operating costs.

g) No power loss from ballasts since ballasts are electronic and hence energy saving.

h) Easy maintenance.

i) Periodic function test on all lamps, ballasts etc.

j) Yearly tests.

k) Display of current consumption and status information.

l) Print – out facility.

m) Extended lamp life.

n) Environment friendly maintenance – free lead accumulator battery with a recycling rate of > 96%, over standard pollution prone nickel cadmium battery.

o) Interface with BMS for central control.

The Central Battery Emergency system will be based on DC system as per IEC 598-2-22 standard.

 

Emergency  lights  in the public areas shall be part of the  light fittings used  in that area. Separate slave emergency luminaries shall be used in other areas including offices, shops, plant rooms, sub station, store, etc. 

 

Slave  emergency  luminaires  shall  be  recess  mounted  in  the  offices  and  shops  and  surface mounted in service areas.  

     

  8.10.2    Aircraft Warning Light 

 

    Becon strobe light shall be provided for the project for aircraft warning to satisfy the requirements of the Civil Aviation Authority. 

 

8.11 Main Earthing System  

  The complete electrical installation shall be mechanically and electrically continuous throughout and shall be bonded to the main earth. 

   

  An earth resistance value of 1ohm or less shall be achieved in the main earth pits. 

 

  Earth continuity conductor shall be provided from main panel up to each final circuit termination point. 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   21 

  All conductive but non‐current carrying  installations shall be equipotential bonded to the main earthing system.  The conductive installations shall include the following (as per BS 7430, Clause 20.4): 

   

a) Water pipes. b) Sprinkler and fire fighting pipes. c) HVAC ducting. d) Pipe risers of HVAC systems. e) Exposed metallic parts of the building. f) Lightning conductors.    

8.12 Lightning Protection System  

8.12.1   Effects of Lightning Strike 

8.12.1.1 Electrical Effects As the current is discharged through the resistance of the earth electrode of the lightning

protection system, it produces a resistive voltage drop which may momentarily raise the potential of the protection system to high value relative to true earth. It may also produce around the earth electrode a high potential gradient dangerous to people and animals.

8.12.1.2 Side Flashing The point of strike on the protection system may be raised to a high potential with respect to

adjacent metal. There is therefore a risk of flashover from the protection system to any other metal on or in the structure. If such flashover occurs, part of the lightning current is discharged through internal installations, such as pipes and wiring, and so this flashover constitutes a risk to the occupants and fabric of the structure.

8.12.1.3 Thermal Effects For the purposes of lightning protection, the thermal effect of a lightning discharge is

confined to the temperature rise of the conductor through which the current passes. Although the current is high, its duration is short and the thermal effect on the protection system is usually negligible.

In general, the cross-sectional area of a lightning conductor is chosen primarily to satisfy the

requirements of mechanical strength, which means that it is large enough to keep the rise in temperature to 1°C.

 

8.12.1.4  Mechanical Effects 

 

  Where a high current is discharged along parallel conductors in close proximity or along a single conductor with sharp bends, considerable mechanical forces are produced. 

Similarly, with a side-flash inside the building, the shock wave can result in damage to the

building fabric.  

8.12.1.5  Function of a Lightning Conductor 

 

  A  lightning  conductor  is  incapable of discharging a  thunder  cloud without a  lighting  flash.    Its function is to divert to itself a lightning discharge which might otherwise strike a vulnerable part of the structure to be protected and to convey the current safely to earth.  The range over which a  lightning conductor can attract a  lightning flash  is not constant but  it  is now believed to be a function of the severity of the discharge.   

   

  The range of attraction is therefore a statistical quantity. 

 

  On  the  other  hand,  the  range  of  attraction  is  little  affected  by  the  configuration  of  the conductor, so that vertical and horizontal arrangements are equivalent.   The use of pointed air terminations or vertical finals are therefore not regarded as essential, except where dictated by practical considerations. 

 

8.12.1.6  Need for Protection 

 

  The following situations are to be considered while ascertaining the need for protection: 

 

a) Where large numbers of people congregate. b) Where essential public services are concerned. c) Where the area is one in which lightning is prevalent. d) Where there are very tall or isolated structures. e) Where there are structures of historic or cultural importance. f) Where there are structures containing explosive or flammable contents. 

 

8.12.1.7  Proposed System 

   

 

 

MECHANICAL, ELECTRICAL & PLUMBING   22 

Faraday cage lightning protection system shall be provided to minimize the damage to the complete structure in the event of any lightning strike.

 

8.12.1.7.1  The lightning protection system shall consist of the following principal components: 

 

a) Air terminations. b) Down conductors. c) Joints and bonds. d) Test joints. e) Earth terminations. f) Earth Electrodes.  

The proposed Faraday Cage System for this project shall consist of 25 x 3mm bare copper tape cage on roof  in each span of 10m x 10m span. The down conductors shall be 25x3 mm Tinned copper tape within the structural columns. The tape shall be fixed to the columns by ‘U’ clamps. 

 

9.0 TELEPHONE AND DATA COMMUNICATION SYSTEM  

9.1  Structured Cabling System 

 

    Cat 6A based structured cabling system shall be provided for the Telephone / Data communication network and shall include Main and Intermediate distribution Patch Panels (MDT and IDTs for voice and data), backbone cabling and structured cabling network for voice and data outlets.  

 

    The  system  shall  be  designed  as  per  the  latest  EIA/TIA  standards  and  as  per  local  telephone authority requirements. The topology shall be  in the form of a hierarchical star  in all parts of the cabling infrastructure (horizontal, intra‐building, and inter building). 

 

    Main Distribution Terminal (MDT) of the Network shall be provided  in the computer server room.  Further distribution within the building shall be carried out by dividing each floor of the building into a no. of zones with an area not less than 1000 sq. mtr and by providing a dedicated telecom room for each zone. 

 

    Intermediate Distribution terminal (IDT) shall be provided in the floor telephone rooms and shall be connected to the MDT through cable trays. 

 

    Incoming Telecom cables shall be terminated in Telecom provider room and shall be connected to the router / call manager. 

     

The voice and data horizontal cabling shall be 4 pair unshielded twisted pair Cat 6A and RJ45 outlets shall be provided for both voice and data. 

     

    The network MDT shall be located in the computer server room. 

 

    The  data  backbone  shall  be  12  core multimode  optical  fiber  indoor  cable  to  be  installed  in  a redundant configuration using separate risers.   The cables shall be run from each floor  IDT to the MDT. The cable shall be of type ‘OM3’ to ISO11801. 

 

  19” standard network cabinet with fans and power sockets shall be provided for accommodating all voice and data patch panels, active network equipments, etc in the IDT. 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   23 

  All software and hard ware for the data communication system shall be provided by the client upon handing over the project. 

 

  Voice and data outlets shall be provided at the various areas as per the area of usage and function, in coordination with furniture layout and in accordance with the end user requirements, including but not limited to the following: 

 

a)  Offices/Workstations  

b)   Conference rooms 

c)         Meeting rooms 

d)   Model Hall 

  e)  Reception 

f)  Press Conference & Auditorium 

 

 

  Category 6, four pair UTP cables shall be used  for horizontal cabling. All  indoor cables shall be of Low Smoke Zero Halogen (LSZH) type.  

 

  Twin RJ45 outlet shall be provided for each workstation in coordination with furniture layout. 

9.2 Wireless Data Network (Wi-Fi)    

  Access points  for wireless network  (WLAN)  shall be provided  for wireless  connectivity  inside  the building to allow access to voice and data services for staff away from their desks, and also for the public for mobile internet access using PDA, laptops, mobile phones, etc.  

 

  The system shall be  in compliance with the  IEEE 802.11g standard using 2.4 Ghz radio frequency. This technology, called Wi‐Fi, can provide a data rate throughput upto 54 Mbps. 

 

  Wi‐Fi  access  points  shall  be  installed  at  various  areas  in  coordination  with  architectural  and structural layouts and to obtain maximum coverage of the areas.  These Wi‐Fi hotspot can be open 

or  secured. Secured hotspot use an encryption  system  called WEP(Wired Equivalent Privacy)  for transmitting data, and only the user having a WEP key can be connect to the wireless network. 

 

                   All Wi‐Fi hotspots shall be connected to the structured cabling network all the required provisions shall be provided for the same. Actual equipment shall be supplied by the client based on the latest technology product available in the market at the time of installation, which shall be based on the current IEE802.11 standard (Wi‐Fi) or the latest IEE802.16 standard (WiMax).  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   24 

 

  Telephone & Data Communication System Architecture 

10.0 CENTRAL ANTENNA TELEVISION AND SATELLITE SYSTEM  

                    Satellite /television /radio distribution system shall be provided capable of receiving and distributing all present transmissions.   The system shall use high gain amplifier multi switches and modulators with automatic gain control for each channel.   The system will utilize IF to watch all the channels covered by the satellites on the roof after installing there own receivers.  

             

  MATV  socket  outlets  shall  be  provided  at  the  various  areas  including  but  not  limited  to  the following: 

 

a) Model hall b) Press conference & auditorium c) Conference rooms d) Reception/entrance lobby e) Waiting areas f) Coffee shop  

Antennas and dishes shall be located on roof, and the head end station shall be located in the roof electrical room.  

Distribution  from  the head end  station at  roof  to  the various areas  shall be using coaxial cables, splitters, and multi‐switches. Multi‐switch boxes shall be located in each floor electrical rooms.  

Only free to air channels shall be provided. 

 

11.0 PUBLIC ADDRESS AND MUSIC SYSTEM  

    Public address and background music system shall be provided  in the building to cover the public areas and corridors.  The speakers shall be installed in the corridors, lobbies, waiting, and all other public areas.  

 

    The system shall be designed in accordance with BS 6259: 1982. 

 

    The system shall consist of recessed ceiling speakers, Microprocessor based audio matrix switcher, amplifiers,  music/signal  sources  from  double  cassette  deck,  tuner,  Multi  Disc  CD  player,  and microphone desks, and a master control console located in the reception at ground floor. 

 

    Recessed ceiling speakers shall be provided at the various areas and speakers shall be selected to provide as uniform coverage of an area as practicable. Local volume control with override relay shall be provided at meeting rooms, etc  

    The system design shall allow for making site broadcast from the master control and it shall also be possible to individually select each or all sub systems for site broadcasting purpose.   

     

    The system shall be interlocked with the fire alarm system in order to mute the ceiling speakers in the public areas and for broadcast of emergency evacuation messages. 

 

    Paging microphones shall be provided at the information desk/reception. 

12.0 FIRE DETECTION AND ALARM SYSTEM      

Fire detection and alarm system shall be provided for the buildings in accordance to NFPA72, and to the local civil defence authority requirements. 

 

System shall be of analog addressable type and fire fighters telephone system. System  shall consist of  addressable    smoke  sensors,  heat  sensors, manual  call  points,  evacuation  sounders,  strobes, sounders with strobe, etc distributed throughout the buildings to provide complete fire detection and alarm  coverage. Main  fire alarm  control panel  shall be provided  in  the entrance  lobby, and repeater panel shall be provided in the control/BMS room.  

Smoke detection within the false ceiling areas shall be using smoke detectors in the return air ducts of  air  handling  units. Magnetic  door  holders  shall  be  provided  to  separate  fire  compartments. Strobes or speakers with strobe shall be provided  in all areas as required  in compliance with  the relevant codes and standards. 

System shall be  interfaced to HVAC system to achieve the required monitoring and control of the HVAC during alarm and fire situations in accordance with the client approved cause and effect logic.  

 

System shall also be interconnected with the following: 

 

a) Elevator control b) Central battery emergency lighting system 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   25 

c) Intelligent lighting control system  

                     It shall be possible to monitor the system through BMS. 

   

  System operation shall be as follows: 

 

  Actuation of a manual station,  thermal detector, smoke detector  in  the respective  fire zone shall initiate the following: 

           

  a)   Actuation of evacuation alarm on the fire zone.   

           b)  Automatically shut‐off all fresh air supply fans, all air handling units and fan coil units in the respective  fire zone within the public area.   Restarting of  these units should be manually controlled depending on the fire situation and under fireman's advise. 

  c)  Elevator shall return to the ground floor and keep the doors open.  

   d)  The system shall  include an automatic evacuation cancel control switch, acknowledgment push button and indicator lamp at the control panel.  If the operator does not acknowledge an  alarm  within  the  stipulated  time  period,  a  second  stage  evacuation  alarm  shall  be automatically initiated throughout the building. 

  e)  Actuation of a general alarm switch in a manual station or of the total evacuation switch in the control panel shall initiate a second stage general alarm tone throughout the building. 

 

  The  fire alarm system shall be connected  through modem and  telephone  line  to  the nearest  fire station.  

                     

 

 

                               (Fire Alarm System Architecture) 

 

13.0 SECURITY SYSTEM    

  System shall consist of security access control with card reader and CCTV system. 

 

13.1  Access Control System  

 

  Areas with restricted access shall be provided with door access units linked to the electric door lock.   Door contacts shall be provided for those rooms to detect any forced entry.  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   26 

 

  System shall be complete with door access proximity smart card readers, door locks, door contacts, exit switches, door controllers and main controller with PC and system software. 

   

  Proximity card readers shall be provided wherever specially required.  

   

  The door controller shall also be microprocessor based similar to the main controller, with on‐board time and date generation and battery and shall be responsible for all access control decision and alarm monitoring detection in the system. It does not require a command from the Main controller or central computer to deny or grant any access. 

   

  Door contacts shall be provided for all plant rooms and stores.  

 

  The system shall be linked to the CCTV system such as in case of any forced entry a signal shall be initiated from the system to the CCTV system such as to orient the camera to the door subject to the forced entry and to record the event.  

13.2 CCTV System  

    Closed  circuit  TV  system  shall  be  provided  to  allow  complete monitoring  of  all    unsupervised entrances, entrance lobby/reception, cashier and similar locations, corridors, all other public areas, external, etc.  System shall be complete with dome type fixed and with pan, tilt and zoom (PTZ) type cameras of the smallest size available, Matrix switcher, Digital Video Multiplexer Recorders (DVMR), Color monitors, movement sensors, etc. 

     

    The cameras  for  the CCTV  system shall be with auto  Iris  lens.   Recording of Camera provided  to monitor the unsupervised entrances and the stores shall be based on motion sensing. . System shall have video motion sensing facility and/or movement sensors at various locations in order to achieve the same. 

     

    System shall have, based on its storage/compression technology, enough storage capacity to record all cameras for a minimum period of 30 days. 

 

    Location of the monitors and central controller shall be in the control or security room and to client approval 

 

    System shall be linked with security door access system. 

    System shall be integrated with BMS system. 

 

 

(CCTV System Architecture) 

14.0 TIME AND ATTENDANCE SYSTEM

Computerized time and attendance system will be provided at the time office/ staff entrance for staff  time and attendance  recording. Combined  finger print and  card  readers  scanners will be used for the system.  

15.0 ENERGY SAVING SYSTEMS & SUSTAINABLE MEASUREMENT

15.1 Introduction The systems listed hereunder will be utilized in our project in order to achieve maximum possible energy saving. 

 

 

MECHANICAL, ELECTRICAL & PLUMBING   27 

 

1. Heat recovery units  2. Water supply pumps with VFD 3. Glass thermal properties and external walls construction details 4. Building management system 5. Thermal control and zoning  6. Power factor correction 7. Lighting control system 8. Energy saving lamps 9. Electronic ballasts   

15.3 Heat Recovery Units The central extract system risers from toilets and general areas shall be discharging cold/hot air with different temperature related to every season.  

 

Heat  recovery  sections  comprising  thermal wheel  shall  be  added  to  the  FAHUs  to  exchange cooling/heating  from  the  extract  air  duct  risers,  which  leads  to  increasing/reducing  the temperature on the heating/cooling coil of FAHU. 

 

A  significant  amount  of  cooling/heating  can  be  retrieved  by  this  unit,  thereby  reducing  the cooling/heating load on chillers /boilers and electrical power consumptions accordingly. 

15.4 Water Supply Pumps with VFD Main booster water pumps will be equipped with negotiable speed drives and shall be employed to supply water to the entire facility.  

 

These pumps will supply varying amount of water proportional to the demand dictated by the project. Therefore at a time of low demand these pumps shall not work on full capacity and thus reduce electrical consumption. 

  

15.5 Glass thermal properties and external walls construction details We recommend the use of high performance double glazing for all floors and thermal insulated external walls for the entire building. This will help in reducing the cooling/heating load as well as in reduction of noise transmission. 

15.6 Building Management System (BMS) Introducing  BMS  for  the  building  will  result  in  significant  energy  saving  by  switching  off  all unnecessary loads 

15.7 Thermal Control and Zoning The design will allow individual users to control air supply rates, air temperatures and humidity (for  some  specific  areas) which will  allow  a  reduction  in  load  requirement  during  partial/no‐occupancy hours.  

15.8 Power Factor Correction  

 Utilization of power factor correction system will result in a huge reduction of the reactive power as described hereunder: 

 

 Total connected load   =  (X) KW 

S = Apparent Power   =  (X) KW 

P = Active Power  =  S cos Ø 

Q = Reactive Power  =  S sin Ø  

 

COS Ø1    =  Uncorrected power factor = 0.8 

COS Ø2    =  Corrected power factor = 0.93 

 

Estimated reactive power saving = 7.5 % 

15.9 Lighting Control System  

 The most intelligent lighting control system will be utilized and will be based on occupancy sensors, timers and photo cells. By utilizing this system all unnecessary luminaires will be switched off and accordingly a saving of 20% in energy consumption for lighting will be achieved. 

15.10 Energy Saving Lamps  

Utilizing  T5  lamps  instead  of  T8  lamps  will  result  in  higher  illumination  with  less  energy consumption.  The  calculated  energy  saving  for utilizing  T5  lamps  is  equal  to 20% of  the  total fluorescent lamps energy. 

15.11 Electronic Ballasts  

 

 

MECHANICAL, ELECTRICAL & PLUMBING   28 

All luminaires in air conditioned areas will be provided with electronic ballasts to reduce energy consumption of lamps and increase its life time.  

 

16.0 STANDARD AND CODES  

All work and materials used shall be in strict compliance with the applicable sections of the codes and standards, design guides issued by the following agencies: 

 

ARI  :   American Refrigeration Institute 

 

ASHRAE  :    American Society of Heating, Refrigerating & Air Conditioning Engineers Inc. 

   

ASTM         :   American Society of Testing Materials 

              

SMACNA   :    Sheet Metal and Air Conditioning Contractors National Association. 

 

CIBSE        :   Chartered Institution of Building Services Engineers. 

 

NFPA         :   National Fire Protection Association. 

 

UL  :    Under writers Laboratory. 

 

BS      :    British Standards Institution 

     

IEE  :   Institution of Electrical Engineers. 

 

IEC  :   International Electro ‐ technical     Commission. 

 

ISO          :    International Organization of Standardization. 

 

ADDC        :    Abu Dhabi Distribution Company. 

 

ADCD  :    Civil Defence Authority of Abu Dhabi. 

 

ETISALAT   :  Telecom Company  

 

  :    The Institute of Plumbing, UK 

 

‐   End of Report   ‐ 

 

 

 

 

I N T E R I O R   D E S I G N   1 

I N T E R I O R D E S I G N

 INTRODUCTION MOOD IMAGES 

 

 

I N T E R I O R   D E S I G N   2 

INTRODUCTION

A‐Introduction:  

As  the building  is  intended  for a public and private usage  it’s design shall be a synthesis of a  functional modern office space and an experimental space that is regarded as  a modern museum,  that  includes all features enabling that  space  to adjust  to any  temporary exhibition or event, and preserve  its  functionality,   character and  spatial impact on its visitors. 

In order to achieve this, our design would be based on the several criteria: 

B‐Design Criteria: 

i) Functionality: 

A  primary  goal  is  provide  appropriate  adjacencies  and  connections  for  required  spaces  according  to  the information provided by MUSANADA, to date.  

The uniqueness of the building is in how the various public and private uses interact and function within the same volume  and the intended mixture and interaction between the public and the official spaces, the challenge would be how to render a workspace composed of several departments working together, and at the same time receiving Clients, potential clients and visitors. 

ii) Image and Corporate Identity:  

The MUSANADA brand requires visibility and recognition considered  integral with this building. Some maybe introduced to Yas Island for the first time or there for business. 

iii) Flexibility and Multi usage: 

As the main functionality of the exhibition space is achieved, it shall also be adaptable / flexible and shall include features and components that will allow it to change, reconfigure and even reshape. 

iv) Incorporation of technology: 

The importance of the building having the necessary technology is being addressed part of the initial planning.  The architecture shall be provide the correct background for this and also be ready to accept the future technologies.  

v) Choice of Materials: 

The choice of the correct materials and finishes shall contribute to the general impact and success of the building. The choice of materials within the budget  is a goal to be achieved while still meeting expectations for durability, appeal, and sustainability.  

vi) Spatial Experience: 

Is the outcome that will happen after achieving the right blend between all the above criteria.  

Our goal will be achieved when the visitors have an exceptional experience that will remain as the correct image in their memory. And the employees will have a modern, functional and comfortable working space. 

Figure A ‐ Incorporation of technology 

 

 

I N T E R I O R   D E S I G N   3 

 

 

 

 

 

 

 

 

 

 

 

                                                                       

Figure B. Choice of Materials 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure C. Spatial Experience 

 

 

I N T E R I O R   D E S I G N   4 

C‐Concept: the modular screen  

Inspired from a traditional element in the Arabic architecture (the Machrabiyah), we find that the incorporation of a screen concept, in a studied modular way will help us to achieve the following: 

• Reconfiguration of the model hall and public space character. 

• Separation with in the office spaces other than generic partitioned cubicles. 

• Separation between the public and office spaces. 

• Display event  information 

• Exhibition background 

• Audio visual projection 

• Filtering of natural light 

 

 

Figure D. Traditional Macharabiyah 

 

 

 

 

 

                                                            

 

 

 

 

 

 

Figure E.  Modular Sliding Screen 

 

 

 

 

 

 

 

 

 

 

 

        

                                                                   

 

 

 

 

I N T E R I O R   D E S I G N   5 

 

 

                 

Figure I.    Guest Meeting Spaces (divided with screens rather than walls) 

 

 

 

 

 

                          

 

 

 

 

 

  

Figure F. Exhibition Space (Gridded Screen System for exhibition)   

 

 

 

 

 

 

 

 

 

 

 

 

Figure G. Exhibition Space (separation from office area, filtering natural light)  

 

 

 

 

 

 

 

 

 

 

 

 

 Figure H.  Office Space (separation: Stations and enclosed offices, ceiling‐wall treatment) 

  

 

 

I N T E R I O R   D E S I G N   6 

MOOD IMAGES         

        VIP Office / Meeting Room                                   Reception & Lobby 

                  

VIP Office / Meeting Room              Cafeteria    

  

                                      

Auditorium / Model Space      

 

 

I N T E R I O R   D E S I G N   7 

MOOD IMAGES                   

Display Area                     

                Glass Partition and Workstations  

                     

Display Area                       

 

 

I N T E R I O R   D E S I G N   8 

MOOD IMAGES                     

Display Area                          

Glass Partition and Workstations 

                       

Display Area                    

Reception & Lobby 

 

 

S U S T A I N A B I L I T Y   1 

S U S T A I N A B I L I T Y

 

 

 

 

S U S T A I N A B I L I T Y   2 

INTRODUCTION A‐Introduction:  

Environmental impact of Buildings 

According  to  the UAE Minister of Public Work  the baseline benchmark  referring  at  energy: 300kWh  /sqm  annually  and water: 500 liter per person per day. The U.S. Department of Energy data book – October 2009, commercial building in the United  States  indirectly  contribute  18%,  or  6  billion  metric  tons,  of  the  nation’s  dioxide  (Co2)  emission  through  the consumption of energy, and consume 35.8% of all electricity generated in the United State. More than 50% of this electricity is derived from carbon –intense energy sources, such as coal and petroleum. Built a green building is not only mandatory by law  but  is  an  opportunity  to  positively  impact  the  environment  and meet  the  requirement  of  the  RFP.  The Owner  is receptive  to  implementing measures  that will positively  impact  them  and will  appreciate  that  you have  educated  them about green options  

Commitment to sustainability 

The process of integrating Estidama principal into property management is not always a linear journey. There are multiple entry point, and most owners and operators will have already start on many of the task outlined propose in this proposal. Regarding of where one begins, there are several consistent element to achieve success, beginning with making a commitment. 

Changing the manner in which commercial property is operated does not need to be complex, but it has to start with commitment from stakeholders. Building Managers and owners must be committed to adopting sustainable practices and incorporating sustainability into their decision making. Many measures and policy changes can help transform a building’s operation, but without a commitment, these actions will not necessarily deliver the intended results. Greening a new building does not always demand a significant capital investment, but it does require the desire to find solution and willingness to measure efforts. 

Greening Process. 

There are five areas in which building can be greened:  

‐ Energy‐saving ‐ Potable water reduction and water conserving initiatives  ‐ Health ‐ Safety ‐ Indoor and outdoor environmental quality 

 In order successfully pursue Estidama Pearl Rating System PBRS certification, proper preparation and visioning is critical before commencing. Without buy‐in from of the involved parties, the creation of committed team, and proper financial planning, projects run the risk of falling short on their certification goals.     Estidama Vision Abu Dhabi's Plan 2030 establishes a clear vision for sustainability as the foundation of any new development occurring in the Emirate and capital city of Abu Dhabi. This commitment is a reflection of the values and ideals of our nation. The tenets 

of sustainable living in the Middle East are the guiding force behind Estidama. More than just a sustainability program, Estidama is the symbol of an inspired vision for governance and community development. The ESTIDAMA certification system is a flexible framework that allows project teams to decide which sustainable strategies to pursue based on the specifics of a particular project. ESTIDAMA requires all projects to meet certain prerequisites, and project teams choose which optional credits to pursue for additional points toward certification.  

Method Statement for the Estidama Services RW Armstrong Sustainability Team will collect  the data and develop strategy  for sustainable, green building  technologies and energy efficiency for ADAA headquarters. To provide the best sustainability intent in the cost effective way to achieve tree pearl required from the client. RW Armstrong as Sustainability Team will refer as guideline on the ESTIDAMA Building Perl Rating System (PBRD ver. 1) developed by Abu Dhabi Urban Planning Council (UPC).  

After the data collection RW Armstrong Sustainability Team will consolidate the “Estidama strategy” and necessary report necessaries for the UPC preliminary design review for the New Headquarter for Abu Dhabi Accountability Authority (ADAA) Project.  

The final result of the consolidation we will a  list of achievable credit/recommendation to achieve the main target of the project.  

The Consultant will must follow the ESTIDAMA Review Process of Abu Dhabi UPC and the framework. The Design team will be assisted in all the stage of the project to comply with: credit intent, credit requirement, and calculation methodology and should use all the reference included in the Rating System Sheet during the design stage. RW Armstrong Sustainability Team will provide the required document that will show the effective compliance with the credit requirement split in the 7 project stage.  

Stage 1 – Concept design Stage 2 Schematic Design Stage 3 – Design Development Stage 4 – Tender/Construction Document Stage 5 – Tender services Stage 6 – Construction Supervision Stage 7 – Project Close out  RW  Armstrong  Sustainability  Team  will  assist  the  design  team  in  all  the  project  stage,  in  coordination  and  the implementation of an  Integrated Design Process. The  integrated project delivery will be maintain with    interact keck‐off meeting, a program workshop and other workshop spitted in all the project stage. Regular weekly and bi‐weekly meeting 

 

 

 

S U S T A I N A B I L I T Y   3 

RW  Armstrong  Sustainability  Team  will  assist  the  Design  Team  to  develop  a  holistic  concerted  concept  in  order  to considerably  improve  the energy efficiency,  sustainability and  living quality of  the building. RW Armstrong Sustainability Team will develop  in  the Estidama Concept Report,  the best strategy  in order  to provide a cooling building strategy. The Sustainability Team will support the Landscape architect to create an  interconnected network of open spaces, differing  in size,  character  and  purpose  to  support  a  variety  of  human  activities  and  natural  systems,  in  order  to  increase  the permeability  of  the  building  and  create  and  improve  the  active  urban  environments  of  the  area with  less  urban  heat reduction. All the consideration will demonstrate and commented with the utilization of tools  (Autodesk Ecotect Analysis and SunPath), and develop inside of the Sustainability Concept Report:  

‐ Commented Bio‐Climatic Analysis:  ‐ Climatic Analysis (latitude, climatic data, solar radiation, local specific condition of prevalent winds) ‐ Natural input (orientation and morphology) ‐ Dynamic shadows Analysis ‐ Orientation and shadow analysis ‐ Outdoor Thermal Comfort Strategy ‐ Thermal analysis Study ‐ Passive housing strategy and calculation ‐ Cool Building passive strategy ‐ PBRS Energy calculation  ‐ PBRS Water Calculation ‐ PBRS Waste Calculation ‐ Selection of plant strategy for landscape or xeriscaping 

RW Armstrong Sustainability Team will assist the MEP Team to develop and optimize and integrate a comprehensive water strategy during  the  early  stage of design with  the  goal of minimizing  the overall water  consumption  and  establishing  a project water balance. The Sustainability Team will also recommend the MEP Design Team to reduce the potable water use in exterior water features by minimizing evaporative  loss and through the use of recycled water for achieve the target of 20% base on  the  ESTIDAMA PBRS water Calculator  ver. 1.2. Will  also help  the MEP Design  Team  to  recued  the energy consumption and carbon emission associated with  lighting and reduce peak electricity demand and  increase efficiency  in order to achieve the target of 45% of reduction base on ASHRAE 90.1.2007  

Estidama Strategy for ADAA This ESTIDAMA approach to  integrate the various design elements,  in order to reach a Sustainable Green Building Design included in the Client’s vision for the Abu Dhabi Accountability Authority (ADAA) Project 

The client vision related to the sustainability is to achieve Estidama 3 pearl according to the PBRS that mean achieve all mandatory credits plus 85 credit point   The main design considering the following criteria: 

‐ Reduce impact on the environment by proper selection of construction materials ‐ Design energy efficient building ‐ Create and maintain a healthy and natural environment ‐ Provide the residents‐users controls on their comfort ‐ Enhance natural lighting (day lighting) ‐ Waste Management and recycling. ‐ Integration to surrounding urban networks  The building will be designed in a way to operate and serve to achieve luxury level of 5 star hotel the expected not ordinary comfort in compare to in similar projects, while minimizing energy and resources usage. Various systems and components 

are  to  be  coordinated  to  provide  the maximum  energy  usage  efficiency  under  the  buildings’  operating  and  budgetary constraints alongside with provision of thermal comfort and enhanced and monitored indoor air quality. 

In  addition,  the  sustainable  design  will  also  cover  the  construction  and  the  operating  phases  of  the  Project.  In  the Construction phase, controlling construction waste and emissions, using environmental  friendly and renewable materials, and minimizing  construction  and  equipping  induced  environmental  effects. During  the Operational phase,  the  aim  is  to mitigate the Project’s impacts on its surroundings, by reducing both its energy usage and waste production. 

ESTIDAMA‐based Sustainable Design Basic Concepts For the purpose of the Abu Dhabi Accountability Authority (ADAA) Project, a set of basic design concepts are defined earlier in this phase. They constitute the Sustainability Basis of Design of the ADAA project, addressing architectural and structural aspects, as well as the HVAC and electrical utilities and services. 

These basic design concepts fall under seven major categories: 

• IDP ‐ Integration Development Process • NS ‐ Natural System • LBo ‐ Livable Building: Outdoor • LBi ‐ Livable Building: Indoors • PW ‐ Precious Water • RE ‐Resourceful Energy  • SM‐ Stewarding Materials 

 It is worth defining in this ESTIDAMA Proposal report these basic design concepts as follows: 

IDP – Integration Development Process An  essential  part  of  the  strategy  for  achieving  Estidama  is  to  fundamentally  change  the  way  we  approach  design, construction. The  Integration Development process calls  for cross‐disciplinary  teamwork and builds upon sound  thinking, delivery quality and environmental management through the life of the project. This approach requires an integrated design approach from very early on in the design a clear vision and sustainability targets and implementation strategy. 

The strategy to achieve the requirement past by: 

 

 

 

 

S U S T A I N A B I L I T Y   4 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Develop  and maintain  an  Life Cycle Cost  (LCC)  analysis  from  the  concept design by  a qualified professional,  to evaluate and compare various design option throughout the design stage in option appraisals 

2. Develop  an Guest Worker Accommodation Plan with  the  contractor  to promote  fair  labor practices  in building construction 

3. Develop with the contractor the Construction Environmental Management Plan (CEMP)  

NS – Natural System Fundamental of the Abu Dhabi Plan 2030  is the need to foster careful, sensitive growth that will conserve, preserve, and restore the region’s critical natural environments and habitats. Plan 2030 concept is to create a green gradient that design an adequate level of conservation, prevention and restoration and propone an open space framework, a system of formal and informal spaces to implementing leading to healthier ecosystem, habitat and ultimately communities. 

The intent of this credit section is intended to encourage natural resource management and sustainable land use trough: 

 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Enhance the ecological value of the site by planting native or adoptive species  

 

 LBo – Livable Building: Outdoors In order to be considered truly sustainable, new development must go beyond the environment to address the other three pillars  of  Estidama:  Social,  Cultural  and  Economic.  This  requires  consideration  of  issues  such  as  increased mobility  and access to community facilities and connectivity and comfort of the public realm to encourage increased pedestrian activity. Our ultimate goal  is to create a cohesive, contemporary and sustainable urban fabric  for this new city and prosper as an attractive, livable place that preserves the emirate’s unique culture and environment. 

 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Increase outdoor thermal comfort during transition months and reduce thermal discomfort during summer months in public spaces and walkways  

2. Encourage active lifestyle by providing building occupants and users with recreational public open space 3. Encourage the reduction of night time light pollution and its associated impact on human and ecological health. 

LBi – Livable Building: Indoors Further research suggests that Green Building with improved indoor environmental quality can reduce the number of work days lost to sick leave by approximately three day per person per annum. Similarly, an increase of almost 5% in productivity has  been  attributed  to  healthier  indoor  environments.  In  order  to  creating  a  ‘livable  indoors’  the  new  development buildings  that  address  the  challenges  of  improving  occupant  health  and  wellbeing  whilst  fostering  economic  growth anticipate from productivity gains, staff redemption and reduced absenteeism. 

 

 

 

 

 

S U S T A I N A B I L I T Y   5 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Increase outdoor thermal comfort during transition months and reduce thermal discomfort during summer months in public spaces and walkways  

2. Encourage active lifestyle by providing building occupants and users with recreational public open space 3. Encourage the reduction of night time light pollution and its associated impact on human and ecological health. 4. Promote  the  provision  of  building  system  that  support  the wellbeing  and  comfort  of  occupants  by  providing 

sufficient outside air ventilation 5. Low emission material to encourage the desirability of their space in relation to improved occupant  6. Implement Hybrid‐construction method off‐site  construction practice  that promotes a high degree of  indoor air 

quality (IAQ) for construction workers and building occupants. 7. Provide adequate air quality within enclosed car parks. 8. Provide individual comfort control for the wellbeing productivity and thermal comfort of occupants. 9. Promote indoor visual comfort through the interior natural daylight and use of high frequency lighting solution 10. Provide building occupants with a visual connection to the outdoors 11. Provide  acoustic  conditions  that  area  commensurate  with  the  sensitivity  and  the  privacy  requirement  of  the 

propose use. 

PW – Precious Water Water  conservation  is  a  priority  for  Estidama,  because  Abu  Dhabi  has  a  limited  annual  rainfall,  hot  climate,  and  the significant  embodied  in potable water due  to desalination. One of  the most  important  challenges  for  the  Emirate  is  to balance water supply and demand as efficiently as possible given that the per capita consumption of fresh water is among the highest in the world and new water supplies are expensive 

 

The Precious Water section of the PBRS  includes the building calculator that should be used throughout the entire design process.  This  will  help  the  designer  team  to  assess  inputs  and  flows  of  water  to  and  from  the  project  with  holistic perspective, and assist in identifying how and where reductions in the use of potable water may be made.  

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Improve of the reduction of 20%  for the  interior potable water consumption through the use of efficient  fixture and appliances, and the use of recycled water. 

2. Minimize landscape water demand through effective plant selection, irrigation strategies and promoting the use of recycled water 

3. Reduce potable water use for exterior landscape excluding the any water feature from the project 4. Minimize peak  storm water discharge and protect  the  storm water drainage  system and  receiving water bodies 

from pollutant loading during and after storm events. 

5. Minimize the storm water discharge and protect the storm water drainage system and receiving water bodies from pollutant loading during and after storm event. 

RE – Resourceful Energy  Through  the Pearl Rating  System, Estidama  seeks  to  target energy  conservation  through  technological  transitions  in  the building sector. Techniques to conserve energy at the building design and construction stage can have significant impacts on reducing  overall  energy  consumption  during  operation.  The  resourceful  Energy  section  requires  energy  calculation  and assessment  process  to  be  undertaken.  This  assessment will  facilitate  careful  consideration  of  energy  issues  during  the design of building, resulting in better informed decision making. 

 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

1. Determine  the most effective  solution  to  reducing a building’s  cooling demand by  incorporating passive design strategy as a priority awarded based on reduction in the annual external heat gain of the propose building compare with the baseline 

2. Minimize the energy consumed by common building appliances 3. Promote project that specify and install energy efficient vertical movement and transportation system 

SM – Stewarding Materials In  a  sustainable development,  the materials  chosen,  and  the process by which  associated waste  is disposed,  should be viewed as a complete cycle, not two disconnected processes. Transportation of waste use  large amount of fossil fuel and decaying landfill trash generates methane, a major greenhouse gas. The stewarding material section of the PBRS encourage the design team to consider this entire continuum – or ‘whole‐of‐life’ cycle when selecting and specifying material, with an overall  objective  to  improve  the  social  and  environmental  outcomes  associated  with  their  manufacture,  transport, installation and disposal. 

 

 

S U S T A I N A B I L I T Y   6 

 

The forecast Estidama achievable credit related to this Pearls Building Rating System section will include: 

 

1. Promote  selection of material  that do not have  long  term negative  impact on human health or pollute natural systems 

2. Lengthen the useful life of building through design that is easily adaptable for other program uses. 3. Facilitate the future deconstruction and reuse of building and their structure and envelope components 4. Minimize waste associated with replacement of flooring system through the use of modular system 5. Encourage the use of timber sourced from legal and sustainable sources 

Process 

 

Team Structure Criteria: 

‐ Included Building Operator  ‐ Include LCC consultant ‐ Include Contractor or Construction Manager ‐ Environmental Engineer ‐ Include Landscape consultant ‐ Include Acoustic Engineer 

‐ Include Sustainability Team  Building Design Criteria: 

1. Utilize a Unitized System instead Stick System for the façade 2. Primary and Secondary Pedestrian walkway 85% Shadow calculated at 1:00 pm clock time on equinox (20 March or 

20 September) and summer solstice (21 June) 3. Surface car Parking 55%  shadow calculated at 1:00 pm clock  time on equinox  (20 March or 20 September) and 

summer solstice (21 June) 4. Include Landscape Area for recreation 5. Smoking Area: Establish 25 smoke free zone around the entrance 

Provide no smoking signage in the building and in the basement 6. All internal construction material meet formaldehyde VOC content class E1 level 7. Hybrid‐Construction Method: Our proposal is to construct these buildings using a Hybrid style construction 

comprising part traditional in‐situ construction and part modular construction off‐site. HYBRID construction looks at constructing the core utilizing traditional construction methods such as reinforced concrete cast in‐situ. The principal behind the modular method of construction is that the individual modules will be able to support the axial load from the modules stacked on top. The horizontal restraint, required to stabilize the structure will come from the modules being tied into the inner core of the buildings. 

8. Glade Control Devices Automated controlled internal glade control devices for all the windows 9. Natural daylight shall be guarantee of 250 lux on the working plan (762 mm from FFL) for a 75% of the occupied 

area calculated based on a CIE standard clear sky at 10am, 12pm, and 2pm on the equinox and summer solstice excluding contribution from any artificial light 

10. View  75%  of  all  occupied  area  have  a  direct  line  of  sight  to  the  outside  through  vision  glazing  Vision Glazing includes  those windows within  the vision area of 762 mm  to 2286 mm height  from FFL and excludes any  frame area. Seated Head Height is 1.1 m from FFL.  

11. Noise Pollution All internal ambient noise level not exceed 50 dB (A) Leq in the area to be occupied 12. Energy efficient appliances All installed appliances shall be and that tenant guideline outlines the benefit of energy 

efficient appliances will be produced 13. Staircase visible. Develop a vertical distribution system  that will make easily accessible stairs  to at  least  the  first 

three floors, and that the stairs are either visible from the main entrance or visible from the main building lift. The stairs shall be open or visible at least one side 

14. Energy Efficient Lift – included regenerative drive system and LED lighting and LCD display features 15. Energy Efficient escalator – Offer an automated stop/start function linked to occupancy sensor to enable standby 

mode when is no passenger demand and LED strip lighting  

Structural Design Criteria 1. Hybrid‐Construction Method: Our proposal is to construct these buildings using a Hybrid style construction 

comprising part traditional in‐situ construction and part modular construction off‐site. HYBRID construction looks at constructing the core utilizing traditional construction methods such as reinforced concrete cast in‐situ. The principal behind the modular method of construction is that the individual modules will be able to support the axial load from the modules stacked on top. The horizontal restraint, required to stabilize the structure will come from the modules being tied into the inner core of the buildings. 

 Infrastructural Design Criteria: 

1. Develop a storm water management plan:  

 

 

S U S T A I N A B I L I T Y   7 

Storm water calculation shall be demonstrate that the post‐development peak runoff rate and quantity from the 2 year 24 hour design storm does not exceed the pre development peak run‐off rate and quantity through structural method or a combination of both structural and nonstructural methods. The propose management system is capable of collecting and treating a minimum of 90% of storm water and that the treatment process in capable of achieving the following minimum standard for quality control: 80% removal of Total  Suspended  Solids  (TSS),  Min.  95%  removal  of  litter  (gross  pollutants,  >1mm,  min.  90%  removal  of hydrocarbons, use of petrol interceptors or suitable permeable paving for car parks for more than 4. 

 Landscape Design Criteria: 

2. Plants  selection:  70%  of  the  plants  specified  for  planting  on  the  site  to  comprise  native  and  adoptive  drought and/or saline tolerant species including a minimum of 10 different of species. 

3. Irrigation.  incorporated  into  the  landscape  design  a  Water  efficient  irrigation  system  and  operational  and maintenance plan with an average of irrigation demand < 4 liter / m2 / day 

4. Outdoor Thermal Comfort:   Public Open Space 70% of shadow Primary and Secondary Pedestrian walkway 85% Shadow Cycle Tracks 65% shadow Surface Car Parking 55% 

5. Include Landscape Area for recreation 6. Light Pollution: All not  safety  and  security  external  lighting,  including display,  advertising  and  specially  lighting, 

must be automatically switched off between 23:00 hrs. And 7:00 hrs. 7. Smoking Area: Establish 25m smoke free zone around the entrance 

Provide dedicate external smoking areas away from public or high use pedestrian  8. No water feature included in the project 9. Hard Landscape: Paving – Porosity of the paving for all the external hard landscape that will prioritize infiltration, 

sustainable urban drainage system  

 MEP Design Criteria: 

1. Electrical: Interior Lighting:  The project it’s classified under IECC 2009 Zones as LZ3 for this reason should follow the following requirement:  

 Lighting Zone  Max. initial Illuminance at 

site boundary LUX Max Initial Illuminance at specified Distance beyond Site Boundary LUX 

Max  % Uplight 

LZ3  2.2  <1 at 4.5 meters  5% 

The angle of maximum candela from each interior luminaire, as positioned in the building, must not exit throng the windows. Alternatively, all non‐ emergency  interior  lighting must be controlled  to automatically  turn off outside the normal hours of occupancy. Manual override must be enabled  to allow  for any out‐for‐hour use. Reference standard IESNA RP‐33‐99 and IES RP‐8 No incandescent lamps may be installed in the internal environment and for all permanently installed fluorescent lighting installations must incorporate high frequency electronic ballasts. Occupancy sensor in all rooms intended for individual occupancy, conferencing or meeting rooms, open plan office space and hallways or corridor Install Daylight sensor to light fitting that receive sufficient daylight illuminance Automated glade control devices must be connected to the building management system 

Natural daylight shall be guarantee of 250 lux on the working plan (762 mm from FFL) for a 75% of the occupied area calculated based on a CIE standard clear sky at 10am, 12pm, and 2pm on the equinox and summer solstice excluding contribution from any artificial light Energy  Efficient Appliances  all  installed  appliances  shall be  energy  efficient by  energy  star program,  EU  energy Efficiency label scheme Accessible stairs Achieve min.  light  level of 150  lux measured at the walking surfaces and the artificial  light used within the stair must be supplied with color corrected lamps with provide a minimum CRI of 80  

Mechanical Ventilation and HVAC: Thermal Comfort ‐ Design for separate zones and control for maximum of 35m2 of opens space on the perimeter of the building and maximum 70 m2 of open space plan in the internal areas of the building ‐ Each thermal zone must have thermostat that allow control over air speed or temperature as a minimum ‐ Single office, or office with two occupants, must have one thermostatic controller must be provided that allows control over air speed or temperature as a minimum. ‐ Multi‐occupant space (meeting room, conference hall) must at least have one thermostatic controller.  

Ventilation:  ‐ Increase the air ventilation of 15% above the outdoor air ventilation as per standard ASHRAE 62.1.2007  ‐ Provide occupant sensor linked to HVAC system that automatically modulate temperature and air flow rate based on occupancy down to a minimum design setback in all multi‐occupant space ‐ Install Permanent Carbon Dioxide (CO2) monitoring and alert system to ensure the adequate provision of outside air  at  all  times. At minimum,  one  CO2  sensor must  installed  at  each  return  point.  The  CO2  level must  not  be allowed to exceed 1000ppm ‐  Car Park ventilation: The design meets or exceed requirement for pollutant concentration in car park of: Air Pollutant Averaging Time  Maximum concentrationCarbon Monoxide (CO) 15 min.  100 mg/m3Nitrogen Dioxide (NO2) 1 hour  200 µg/m3Particular Matter PM10 24 hours  50 µg/m3

 ‐ Install air quality sensor ‐ Outdoor air intakes and outlets ‐ Air quality alert system ‐ BMS point schedules 

2. Plumbing  ‐ Legionella Management Plan and Implementation ‐ Water fixture baseline Flow rates Not Residential Fixtures Flow Rate  Kitchen Taps 6 l/min @ 417.7 KPa Bathroom wash basin taps 1.9 l/min @ 417.7 KPa Toilet Dual Flush 6/4 l/min or l/use Urinals 0.5 l/flushing cycle Absolution Spray 6 l/min 

‐ Water Meter  Provide water Meter  for:  External  hose  bibs,  Irrigation  Systems,  Bathroom  /  Toilet  Facilities, Kitchen/Catering Facility. 

 

 

S U S T A I N A B I L I T Y   8 

All  the meters must have data  logging  capability and be  connected  to a  central monitoring  system  so  that information on the exterior and interior water consumption can be recorded. 

‐Leak Detection: The leak detection system that covers all main water distribution pipes within the project must be installed and should be capable of: sounding an alarm when a  leak  is detected,  identifying varying  leakage rates, and being programmed to fit the project water consumption requirement  ‐ Dedicate network for supply recycled water. The project will  include a dedicate network for WC flush tank and urinal. All pipes containing  recycled water must be color coded  in order  to easily distinguish  them  from potable water pipes  

ID Design Criteria: 2. Lighting: the angle of maximum candela from each interior luminaire, as positioned in the building, must not exit 

throng the windows. 3. Adhesives and sealants Min of 95% (by weight) of all adhesives and sealants must not exceed the VOC limit for the 

following product type as per ‘VOC limit in South Coast Air Quality Management District Rule 1168’: ‐ Indoor carpet Adhesive ‐ Carpet Pad Adhesive ‐ Wood Flooring Adhesive ‐ Rubber Flooring Adhesive ‐ Sub‐floor Adhesive ‐ Ceramic Tile Adhesive ‐ Cove base Adhesive ‐ Plasterboard and wall panel Adhesive ‐ Multipurpose construction Adhesive ‐ Structural glazing Adhesive ‐ Architectural sealants 

4. Paint & Coatings Min.95% of the  interior surface area cover by paint and coating meet or are  less than the max VOC  content  as  per  ‘Annex  II,  Phase  II,  Table  A  of  the  European  Directive  2004/42/CE:2004  for  the  following product category: 

‐ Interior matt walls and ceiling (gloss <25 @60°) ‐ Interior matt walls and ceiling (gloss >25 @60°) ‐ Interior trim and cladding paint for wood and metal ‐ Interior trim varnishes and wood stains, including opaque wood stains ‐ Interior minimal build wood stains ‐ Primers ‐ Binding Primers ‐ One‐Pak performance coating ‐ Two‐pack reactive performance coating for specific and use such as floors ‐ Multi Colored coatings ‐ Decorative effect coating 

5. Carpet 100% for all surface area covered by: Carpet following requirements of: ‐  Carpet and Rug Institute Green Label ‐ Green Label Plus Program ‐ Green guard Indoor Air Quality 

 6. Hard flooring 100% for all surface area covered by hard flooring following requirements of 

‐ FloorScore Certification ‐ Greenguard Indoor Air Quality 

7. Wood  Flooring  100%  of  the wood  flooring  product  do  not  exceed  class  E1  for  formaldehyde  content  and  not exceed 6 parts per million (ppm) for Pentachlorophenol (PCP) ref. BS EN 14342:2005 

8. Ceiling System All the suspended ceiling system comply with the category E1 (no asbestos) requirement of the BS EN 13964:2004 

9. All furniture All internal construction and furniture meet formaldehyde VOC content class E1 level 10. Noise Pollution All internal ambient noise level not exceed 50 dB (A) Leq in the area to be occupied 11. Water fixture baseline Flow rates 

Not Residential Fixtures Flow Rate  Kitchen Taps 6 l/min @ 417.7 KPa Bathroom wash basin taps 1.9 l/min @ 417.7 KPa Toilet Dual Flush 6/4 l/min or l/use Urinals 0.5 l/flushing cycle Absolution Spray 6 l/min 

12.   

Contractor Selection Criteria:  

• Contractor shall be ISO 14001 or EHSMS certified. • Contractor shall be able to manage Hybrid style construction comprising part traditional in‐situ construction and 

part modular construction off‐site.  Contractor duties:  

1. The contractor must employ an independent commissioning contractor to commissioning the installed system and commence the development of a Building Log Book (BLB) as per CIBSE TM31 or similar guide (ref. PBRS‐IDP‐R3) 

2. Audit  checklist  associated  with  the  legionella  Management  Plan  Process  including  but  not  limited  to  plant installation and commissioning, testing training and competency and record keeping. (ref.LBi‐R3) 

3. Develop a Construction and Demolition West Management Plan (CDWMP) and implement monthly monitoring to achieve minimum  recycling  salvage  rate  of  30%  of  construction  and  demolition waste  (by weight  or  volume) (ref.SM‐R2) 

4. The contractor will also carry out a full envelope air tightness test to achieve the required air leakage rate. (ref. RE‐R1) 

5. Constrictor shall be develop a construction Indoor Air Quality (IAQ) Management Plan  

 Codes and Guidelines The following codes and guidelines are applied to the project in order to meet the requirements of various Estidama credits: 

Integrated Development Process Credit: 

•  Estidama Website: www.upc.gov.ae •  Abu Dhabi Urban Planning Council Website, www.upc.gov.ae •  AIA ‐ Integrated Project Delivery: A Guide 2007 ver.1 •  CIBSE TM31 CIBSE Building log book tool kit Natural System Credit 

•  Abu  Dhabi  Urban  Planning  Council  (for  Development  Review  and  Design  Process,  and  Coastal  Development Guidelines), www.upc.gov.ae 

 

 

S U S T A I N A B I L I T Y   9 

•  Environment  Agency  Abu  Dhabi  (for  Environmental  Impact  Assessment  (EIA)  and  Preliminary  Environmental Review (PER) guidelines), www.ead.ae 

•  Union for Conservation of Nature, IUCN, www.iucn.org •  Wild Flowering Plants of the UAE, Environmental Research and Wildlife Development Agency, 2002 •  Birds of Abu Dhabi – Checklist, Environmental Research and Wildlife Development Agency, July 2001 •  Interpretation Manual  of Major  Terrestrial Natural  and  Semi‐natural  habitat  types  of Abu Dhabi  Emirate, Gary 

Brown and Benno Boer, Environmental Research and Wildlife Development Agency, September 2004 •  Red  List  of  Terrestrial  Mammalian  Species  of  the  Abu  Dhabi  Emirate,  Environmental  Research  and  Wildlife 

Development Agency, May 2005 •  The  terrestrial mammals,  reptiles  and  amphibians  of  the  UAE  –  Species  list  and  status  report,  Environmental 

Research and Wildlife Development Agency, January 2005 •  Terrestrial Environment of Abu Dhabi Emirate, Environment Agency Abu Dhabi, 2008, www.ead.ae •  Handbook for Phase 1 Habitat Survey – a technique for environmental audit, JNCC, 2007, www.jncc.gov.uk •  Vascular Plants of Abu Dhabi Emirate, Gary Brown and Sabitha Sakkir, August 2004  

Livable Building Credit •  Plan 2030 relevant to the site •  Development Codes relevant to the site •  Area Plans relevant to the site •  Plan 2030 (Abu Dhabi, Al Ain, Western Region or Eastern Region) www.upc.gov.ae •  "Abu Dhabi Urban Planning Council, Development Review Process •  www.upc.gov.ae/en/DevelopmentReview/DevelopmentReviewProcess.aspx" •  Abu Dhabi Urban Planning Council, Coastal Development Guidelines www.upc.gov.ae •  ASTM E1980 ‐ 01 Standard Practice for Calculating Solar Reflectance  Index of Horizontal and Low‐Sloped Opaque 

Surfaces •  ASTM E1918‐06, Standard Test Method for Measuring Solar Reflectance of Horizontal and Low‐Sloped Surfaces in 

the Field •  ASTM C1549‐09, Standard Test Method for Determination of Solar Reflectance near Ambient Temperature Using a 

Portable Solar Reflectometer •  ASTM  E  408‐71(2008),  Standard  Test Methods  for  Total Normal  Emittance  of  Surfaces Using  Inspection‐Meter 

Techniques •  ASTM C1371‐04a,  Standard  Test Method  for Determination of  Emittance of Materials near Room  Temperature 

Using Portable Emissometers •  Abu Dhabi Urban Street Design Manual •  Community facilities requirements, Urban Planning Council •  ASHRAE 62.1.2007 “Ventilation for Acceptable Indoor Air Quality”, www.ashrae.org •  "‘Legionnaire’s  Disease‐  The  Control  of  Legionella  Bacteria  in Water  Systems’,  Approved  Code  of  Practice  and 

Guidance (L8), 3rd Edition 2000, UK Health and Safety •  Executive, www.hse.gov.uk" •  "Control of Legionella bacteria in water systems: Audit Checklists, 2003, UK Health and •  Safety Executive, www.hse.gov.uk" •  SMACNA, IAQ Guidelines for Occupied Buildings under Construction  

Precious Water Credit •  Pearl Rating System Building Water Calculator  

Resourceful Energy Credit 

•  "ASHRAE/ASHRAE/IESNA 90.1 – 2007: Energy Standard for Buildings Except Low‐Rise •  Residential Buildings" •  GIL 65: Metering Energy Use in New Non‐Domestic Buildings •  CIBSE TM39 2009: Building Energy Metering •  IECC 2009 – International Energy Conservation Code  

Stewarding Material Credit 

•  "Cabinet Resolution No. 39 of 2006 Concerning Prohibiting Import, Production and •  Utilization of Asbestos Boards" •  ASTM E 2356‐04 ‐ Comprehensive Building Asbestos Surveys •  Centre of Waste Management, Abu Dhabi: www.cwm.ae •  Centre of Waste Management, Abu Dhabi: www.cwm.ae  

General Green Building Code and Good Practice 

•  Local Erosion and Sedimentation Control Standards •  Local Definition of Wetlands, Prime Agricultural Land, Brownfield Sites •  National and Regional Endangered Species Lists •  Local Guideline on Management for Source of Non‐Pollution in Coastal Waters •  American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide •  ASTM E1903‐97 Phase II Environmental Site Assessment •  ASTM E1980‐01 Standard Practice for Calculating Solar Reflectance Index •  ASTM E408‐71 Standard Test Method for Total Normal Emittance •  ASTM E903‐96 Solar Absorptance, Reflectance and Transmittance •  ASTM E1918‐97 Solar Reflectance of Horizontal Surfaces •  ASTM C1371‐04 Determination of Emittance of Materials near Room Temperature •  ASTM C1549‐04 Determination of Solar Reflectance near Ambient Temperature •  ASHRAE/IESNA 90.1‐2004 Energy Standard for Buildings except Low Rise Residential – Exterior Lighting Section9 •  IESNA RP‐33 •  The Energy Policy Act of 1992 •  EPA Clean Air Cat, Title VI, Rule 608 Procedure Governing Refrigerant Management and Reporting •  EPA List of Substitutes for Ozone‐depleting Substances •  International Performance Measurement and Verification Protocol (IPMVP) Volume III •  ISO 14021‐1999 Environmental Labels and Declarations •  Forest Stewardship Council (FSC) Principles and Criteria •  ANSIASTM E779‐03 Standard Test Method for Determining Air Leakage Rate  •  South Coast Air Quality Management District Rule No. 1168 regarding VOC  limits  for adhesives and sealants and 

Rule No. 1113 regarding Architectural Paint •  Green  Seal  Standard  GS‐36  regarding  VOC  Limits  for  Commercial  adhesives,  GS‐11  regarding  VOC  Limits  for 

Commercial Paints, GS‐03 regarding VOC Limits for anti‐corrosive and anti‐rust paints and coatings •  Carpet and Rug Institute Green Label Testing Program regarding VOC emission limits for carpets and carpet cushion •  ASHRAE 55‐2007 Thermal Environmental Conditions for Human Occupancy  

 

Pearl Building Rating System

Project Name New Headquarter for Abu Dhabi Accountability Authority (ADAA)

Project ID N/A

Building Use Office

Pearl Rating Stage Design

Pearl QP Name Antonio Ceci

Pearl QP Number N/A

Date

Credit Points Summary

Yes Maybe No Yes Maybe No

IDPIDP-R1 Integrated Development Strategy Required Integrated Design Process / stakeholder / Project Management

IDP-R2 Tenant Fit-Out Design & Construction Guide Required Not in the design stage

IDP-R3 Basic Commissioning Required Commissioning

IDP-1 Life Cycle Costing 4 4 Mona have experience

IDP-2 Guest Worker Accommodation 2 2 we have already document

IDP-3 Construction Environmental Management 2 2Construction Environmental Management Plan / Certified Contractor’s ISO

14001 or Abu Dhabi EHSMS certification

IDP-4 Building Envelope Verification 1 1 Curtain wall / Unitized Panel

IDP-5 Re-Commissioning 2 2

IDP-6 Sustainability Communication 2 2 Occupant Handbook / Occupant Feedback / Building Automation System BMS

TOTAL 13 13 0 0 0 0 0

NSNS-R1 Natural Systems Assessment Required Abu Dhabi Natural System Report

NS-R2 Natural Systems Protection Required Nothing to be protected

NS-R3 Natural Systems Design & Management Strategy Required Landscape strategy

NS-1 Reuse of Land 2 2 Impossible

NS-2 Remediation of Contaminated Land 2 2 Impossible

NS-3 Ecological Enhancement 2 2 10 different type of plant for saline environment

NS-4 Habitat Creation & Restoration 6 6

TOTAL 12 2 6 4 0 0 0

LBoLBo-R1 Plan 2030 Required Compliance with Plan 2030

LBo-R2 Urban Systems Assessment Required UPC Report

LBo-R3 Outdoor Thermal Comfort Strategy Required 40% Parking / 75% primary walkway

LBo-1 Improved Outdoor Thermal Comfort 2 2 55% Parking / 85% Primaey walkay - SRI 29

LBo-2 Pearl Rated Communities 1 1

LBo-3 Accessible Community Facilities 1 1 350 m facility to be check

LBo-4 Active Urban Environments 1 1 Landscape for recreation

Report a Template Bug : [email protected]

Yes

Yes

Yes

Yes

Yes

Yes

Project Details

ConstructionDesignCredit Title

Credit Points Available

Credit Reference

Yes

Yes

Comments

Integrated Development Process

Natural Systems

Livable Buildings : Outdoors

Yes

Pearl Building Rating System

Project Name New Headquarter for Abu Dhabi Accountability Authority (ADAA)

Project ID N/A

Building Use Office

Pearl Rating Stage Design

Pearl QP Name Antonio Ceci

Pearl QP Number N/A

Date

Credit Points Summary

Yes Maybe No Yes Maybe No

Report a Template Bug : [email protected]

Project Details

ConstructionDesignCredit Title

Credit Points Available

Credit Reference Comments

LBo-5 Private Outdoor Space n/a

LBo-6 Public Transport 3 3 bus stop or metro in 350 m

LBo-7 Bicycle Facilities 2 1 Shade park for bicycle long term 1 space for 500 mq 1space for shart

LBo-8 Preferred Car Parking Spaces 1 1 6% of parkign for electric car

LBo-9 Travel Plan 1 1

LBo-10 Light Pollution Reduction 1 1 light pollution

13 5 6 1 0 0 0

LBiLBi-R1 Healthy Ventilation Delivery Required

LBi-R2 Smoking Control Required

LBi-R3 Legionella Prevention Required

LBi-1 Ventilation Quality 3 3 (CO2) monitoring + 15 % more ventilation

LBi-2.1 Materials Emissions : Adhesives & Sealants 1 1 95% of all adhesives & sealants meet criteria

LBi-2.2 Materials Emissions : Paints & Coatings 1 1 95% of all surface areas meet criteria

LBi-2.3 Materials Emissions: Carpet & Hard Flooring 1 1 100% of all carpets, carpet cushion, hard flooring and associated

LBi-2.4 Materials Emissions : Ceiling Systems 1 1 no asbestos and formaldehyde

LBi-2.5 Materials Emissions : Formaldehyde Reduction 2 2 No formaldehyde class E1 levels material

LBi-3 Construction Indoor Air Quality Management 2 2 Hybrid Construction

LBi-4 Car Park Air Quality Management 1 1Carbon Monoxide (CO) 15 minutes 100 mg / m3

Nitrogen Dioxide (NO2) 1 hour 200 ��g/m3Particular Matter PM10 24 hours 50 ��g/m3

LBi-5.1 Thermal Comfort & Controls: Thermal Zoning 1 thermostatic controller for multipurpose room and max 35 mq thermal zone

LBi-5.2 Thermal Comfort & Controls: Occupant Control 2 2 1 control per space

LBi-5.3 Thermal Comfort & Controls: Thermal Comfort Modeling 2 2

LBi-6 High Frequency Lighting 1 1 No incandescent lamps -> LED

LBi-7 Daylight & Glare 2 2Home Automation BMS Demonstrate a minimum daylight illuminance of 250 Lux on

the working plane (762mm from finished floor level)

LBi-8 Views 1 1 75% od occupancy have wxternal view

LBi-9 Indoor Noise Pollution 1 1 internal ambient noise levels do not exceed 50 dB(A) Leq

LBi-10 Safe & Secure Environment 1 1 Safety & Security Risk Assessment / etc

23 19 3 0 0 0 0

Yes

Yes

Yes

SUB-TOTAL

SUB-TOTAL

Livable Buildings : Indoors

Pearl Building Rating System

Project Name New Headquarter for Abu Dhabi Accountability Authority (ADAA)

Project ID N/A

Building Use Office

Pearl Rating Stage Design

Pearl QP Name Antonio Ceci

Pearl QP Number N/A

Date

Credit Points Summary

Yes Maybe No Yes Maybe No

Report a Template Bug : [email protected]

Project Details

ConstructionDesignCredit Title

Credit Points Available

Credit Reference Comments

PWPW-R1 Minimum Interior Water Use Reduction Required

PW-R2 Exterior Water Monitoring Required

PW-1 Improved Interior Water Use Reduction 15 5

PW-2.1 Exterior Water Use Reduction: Landscaping 8 4 4 Plant with irrigation < 4 liters/m2/day + water meter connect to the BMS

PW-2.2 Exterior Water Use Reduction: Heat Rejection 8 8

PW-2.3 Exterior Water Use Reduction: Water Features 4 4 No waterfeatures

PW-3 Water Monitoring & Leak Detection 4 4 water monitor for each bathroom and leak detection system

PW-4 Stormwater Management 4 2 2 Stormwater management system

TOTAL 43 19 14 0 0 0 0

RERE-R1 Minimum Energy Performance Required 12% reduction

RE-R2 Energy Monitoring & Reporting Required Monitoring system BMS home authomathion

RE-R3 Ozone Impacts of Refrigerants & Fire Suppression Systems Required

RE-1 Improved Energy Performance 15 12 45%

RE-2 Cool Building Strategies 6 6 Passive design

RE-3 Energy Efficient Appliances 3 3

Demonstrate that all developer purchased and/or leasedinstalled appliances shall be energy efficient, and that tenantguidelines outlining the benefits of energy efficient appliances

will be produced.

RE-4 Vertical Transportation 3 3Accessible stairs for the first 3 floors / energy efficient lift / escalator energy

efficiency

RE-5 Peak Load Reduction 4 4

RE-6 Renewable Energy 9 9

RE-7 Global Warming Impacts of Refrigerants & Fire Suppression Systems 4 4

TOTAL 44 18 14 9 0 0 0

SM

SM-R1 Hazardous Materials Elimination Required

SM-R2 Basic Construction Waste Management Required

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Stewarding Materials

Precious Water

Resourceful Energy

Pearl Building Rating System

Project Name New Headquarter for Abu Dhabi Accountability Authority (ADAA)

Project ID N/A

Building Use Office

Pearl Rating Stage Design

Pearl QP Name Antonio Ceci

Pearl QP Number N/A

Date

Credit Points Summary

Yes Maybe No Yes Maybe No

Report a Template Bug : [email protected]

Project Details

ConstructionDesignCredit Title

Credit Points Available

Credit Reference Comments

SM-R3 Basic Operational Waste Management Required

SM-1 Non-Polluting Materials 3 3 Zero ODP, Low GWP Insulation

SM-2 Design for Materials Reduction 1 1 Building Integrated Photovoltaics (BIPV) / Green Roof or green wall

SM-3 Design for Flexibility & Adaptability 1 1 Floor H = 3.6 meters; / All Unitized Panel / duct flexibility

SM-4 Design for Disassembly 1 1 hybrid construction

SM-5 Modular Flooring Systems1 1

95% (by surface area) of finished floor areas use modularflooring products.

SM-6 Design for Durability 1 1

SM-7 Building Reuse 2 2

SM-8 Material Reuse 1 1

SM-9 Regional Materials 2 2 500 km 20% of the total cost

SM-10 Recycled Materials 6 6

SM-11 Rapidly Renewable Materials 1

SM-12 Reused or Certified Timber 2 2 70% (by cost) of the specified timber

SM-13 Improved Construction Waste Management 2 2 Hybrid Construction

SM-14 Improved Operational Waste Management 2 2 Hybrid Construction

SM-15 Organic Waste Management 2

TOTAL 28 13 6 6 0 0 0

IPIP-1 Innovative Cultural & Regional Practices 1

IP-2 Innovating Practice 2

TOTAL 3 0 0 0 0 0 0

Yes

Innovating Practice

 

 

L A N D S C A P E   1 

L A N D S C A P E

 

 

 

 

L A N D S C A P E   2 

LANDSCAPE PLAN

 

 

L A N D S C A P E   3 

LANDSCAPE MOOD

 

 

L A N D S C A P E   4 

PLANTING PALLETE

 

 

L A N D S C A P E   5 

HARDSCAPE MATERIAL