Ad Hoc Procedure

download Ad Hoc Procedure

of 13

Transcript of Ad Hoc Procedure

  • 8/2/2019 Ad Hoc Procedure

    1/13

    Impact assessment tool Ad hoc method

    By:

    Sangeeta Mukherjee

    11EN21F

    M.Tech 1st year, 2nd semester

  • 8/2/2019 Ad Hoc Procedure

    2/13

    EIA is defined as

    the systematic identification and evaluation of thepotential impacts of proposed projects, plans,programs, or legislative actions relative to thephysical-chemical, biological, cultural and socio-economic components of the total environment.

    Changing needs of EIA:

    Predictive method

    Environmental risk assessment

    Economic analysis & expert system

  • 8/2/2019 Ad Hoc Procedure

    3/13

    INTERFACE Examples of analytical tool Examples of planningprocesses

    A Traditional EIA National ConservationStrategies

    Sectoral Natural ResourceStrategies

    B Social Cost Benefit Analysis Traditional Development Plans

    C Some Human Ecology &

    Anthropology Studies

    UNESCO Man and theBiosphere

    Programme

    D Sustainability Analysis

    (modifiedEIA)

    National Sustainable

    DevelopmentPlans/Strategies

  • 8/2/2019 Ad Hoc Procedure

    4/13

    EIA methodologies:

    Ad hoc procedure

    Overlay techniquesChecklistMatrices simple, complex

    Network

  • 8/2/2019 Ad Hoc Procedure

    5/13

    Ad hoc procedures involve assembling a team ofspecialists to identify impacts in their areas of

    expertise , with minimal guidance beyond therequirements of the NEPA (NationalEnvironmental Protection Act)

    What is Ad hoc procedure?

  • 8/2/2019 Ad Hoc Procedure

    6/13

    Ad hoc procedures come into playwhen -

    Time constraints&Lack of information

    Require that the EIA must rely on expert opinion

  • 8/2/2019 Ad Hoc Procedure

    7/13

    Ad hoc methods are not really methods as they do not

    structure the problem

    It is more amenable to systematic analysis

    A good example is a team of experts assembled for a

    short time to conduct an EIA

    Each experts conclusions are based on a unique

    combination of experience, training and intuition

    These conclusions are assembled into a report

    Sometimes this is the only required and possible

    approach

    Salient features

  • 8/2/2019 Ad Hoc Procedure

    8/13

    Aim of the ad hocWorking Group -

    The aim of the ad hocWorking Group is two-fold.Based on an analysis of the existing requirements it

    should be considered whether there is need for:

    New regulations; and/or

    A guide for the practical application of the existingregulations, in order ensure clear procedures and aharmonized implementation in the region.

  • 8/2/2019 Ad Hoc Procedure

    9/13

    Possible considerations by the adhocWorking Group -

    Thead hoc

    Working Group might want to Look into the existing regulations applicable to EIAprocedures

    Assess examples of practice in implementing the EIA

    procedure and see whether any gaps exist

    Discuss how to overcome possible gaps

  • 8/2/2019 Ad Hoc Procedure

    10/13

    Possible questions to consider -

    When to carry out an EIA

    The time schedule

    The different stages of an EIA procedure

    The final decision

    The role of the experts in the process

  • 8/2/2019 Ad Hoc Procedure

    11/13

    Alternatives

    Items A B C

    Number of reservoirs on river system 4 1 0

    Combined surface area, ha 8500 300 -Total reservoir shoreline, km 190 65 -

    New irrigation areas, ha 40000 12000 -

    Reduced open space because of project and associated

    population increases, ha 10000 2000 -

    Inundated archaeological sites, nos. 11 3 -Reduced soil erosion, relative magnitude 4x 1x Nil

    Enhanced fisheries, relative magnitude 4x 1x Nil

    Provision of flood control measures Yes Yes No

    New potential malarial areas, relative magnitude 4x 1x Nil

    Additional employment potential, number of persons 1000 200 -

    Results of using the ad hocmethod to comparealternative reservoir arrangements :

  • 8/2/2019 Ad Hoc Procedure

    12/13

    This method is very easy to use but does have a fewdrawbacks :

    It may not encompass all the relevant impacts

    The criteria used to evaluate impacts are not comparable;thus the relative weights of various impacts cannot be

    compared

    It is inherently inefficient as it requires sizeable effort toidentify and assemble an appropriate panel of experts for eachassessment

    It provides minimal guidance for impact analysis whilesuggesting broad areas of possible impacts

    The process of assessment can never be replicated making it

    difficult to review and critique the conclusions in the EIA

  • 8/2/2019 Ad Hoc Procedure

    13/13