Actualtests.pmi-001 Questions Answers With Explanation October.2011

196
For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/ Project Management Professional Exam PMI-001 Number : PMI-001 Passing Score : 900 Time Limit : 120 min File Version : 15.3

description

PMP Test exam simulations questions, Project Management Professional Exam PMI-001

Transcript of Actualtests.pmi-001 Questions Answers With Explanation October.2011

Page 1: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Project Management Professional Exam PMI-001

Number: PMI-001Passing Score: 900Time Limit: 120 minFile Version: 15.3

Page 2: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Exam A

QUESTION 1Which of the following does NOT assess the value a project brings to an organization?

A. Benefit cost analysis

B. Net present value

C. Value analysis

D. Needs assessment

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 2Your management has decided that all orders will be treated as "projects" and that project managers will beused to update orders daily, to resolve issues, and to ensure that the customer formally accepts the productwithin 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. Theproject manager will not be required to perform planning or provide documentation other than daily status. Howwould you define this situation?

A. Because each individual order is a "temporary endeavor," each order is a project.

B. This is program management since there are multiple projects involved.

C. This is a recurring process.

D. Orders incurring revenue over $100,000 would be considered projects and would involve projectmanagement.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 3A project manager in a predominantly hierarchical organization has been assigned a major project withaggressive timelines. The BEST approach for developing an initial project charter in this environment is to:

A. Create a project charter using brainstorming sessions with potential team members and stakeholders.

B. Create and present a draft project charter to potential team members and stakeholders to solicit their input.

C. Create a project charter jointly with management for distribution to potential team members andstakeholders.

D. Create a project charter with the functional managers and present it to the sponsor for signature.

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 3: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 4All of the following are correct statements about a project manager EXCEPT:

A. He or she is assigned after the project charter is created.

B. He or she may initiate changes to the project.

C. He or she manages changes and factors that create change.

D. He or she is held accountable for project success or failure.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 5A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the projectmanager should ask for help from:

A. The sponsor.

B. Other project managers.

C. The project management office.

D. The team.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 6While preparing your risk responses, you realize that you have not planned for unknown risk events. You needto make adjustments to the project to compensate for unknown risk events. These adjustments are based onyour past project experience when unknown risk events occurred and knocked the project off track. Whatshould you do?

A. Include a management reserve in the budget to try to compensate for the unknown risks, and notifymanagement to expect unknown risks to occur.

B. Document the unknown risk items and calculate the expected monetary value based on probability andimpact that may result from the occurrence.

C. Determine the unknown risk events and the associated cost, then add the cost to the project budget asreserves.

D. With the stakeholders, determine a percentage of the known risk budget to allocate to a managementreserve budget.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 7You are about to begin negotiations with people from another country. Which of the following should provide

Page 4: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

guidance on what business practices are allowed and not allowed?

A. The company code of conduct

B. The project charter

C. The scope management plan

D. The negotiation plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 8An employee approaches you and asks to tell you something in confidence. He advises you that he has beenperforming illegal activities within the company for the last year. He is feeling guilty about it and is telling you inorder to receive advice as to what he should do. What should you do?

A. Ask for full details.

B. Confirm that the activity is really illegal.

C. Inform your manager of the illegal activity.

D. Tell the employee to inform his boss.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 9What is one of the KEY objectives during contract negotiations?

A. Obtain a fair and reasonable price.

B. Negotiate a price under the seller's estimate.

C. Ensure that all project risks are thoroughly delineated.

D. Ensure that an effective communications management plan is established.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 10You are a new project manager who has never managed a project before. You have been asked to plan a newproject. It would be BEST in this situation to rely on _______ during planning to improve your chance ofsuccess.

A. Your intuition and training

B. Stakeholder analysis

C. Historical information

Page 5: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Configuration management

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 11If a project manager is concerned with gathering, integrating, and disseminating the outputs of all projectmanagement processes, she should concentrate on creating a better:

A. WBS.

B. Communications management plan.

C. Project management information system.

D. Project scope management plan.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 12The Java development of a project is outsourced to India. The project schedule is starting to slip.What is the LEAST likely cause of the slippage?

A. Lack of competent programmers

B. Cultural influences

C. Internationalization

D. Communication

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 13A project manager has made a change to the project. What should she do NEXT?

A. Assign resources.

B. Revise the project management plan and/or project documents.

C. Evaluate impact.

D. Request change control board involvement.

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 6: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 14A work authorization system can be used to:

A. Manage who does each activity.

B. Manage when and in what sequence work is done.

C. Manage when each activity is done.

D. Manage who does each activity and when it is done.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 15A project team member tells you that she went to her project manager with a good idea for a useful change tothe project. Instead of giving her approval to make the change, the project manager asked her to write a reportdescribing the benefits of the change. What is the MOST appropriate advice for the situation?

A. The project manager is being unreasonable and should do that kind of work herself.

B. Remind the project manager that the benefit cost analysis for the project was done during project planning.

C. A project manager must be able to weigh the benefits of the change versus the costs and compare them toother possible changes. The team member should do what was asked.

D. The team member should do what was asked because this sort of information must be given to the projectsponsor to make the change.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 16A project manager has finished the project. He knows that the project scope has been completed and is withincost and time objectives set by management. Management, however, says that the project is a failure, becausethe original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was33 weeks, the project is a success because:

A. It only had six weeks of changes.

B. It was completed within the baseline.

C. There were so few changes.

D. There was good communication control.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 17

Page 7: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Your company has just presented its new five-year strategic plan. You have received a new product requestfrom a customer that is in line with the previous five-year strategic plan, but it does not meet the objectives ofthe new plan. The product description seems to have a valid business driver and to be a straightforwarddevelopment effort. As project manager, what is the BEST course of action?

A. Do a benefit cost analysis of the project and submit it for management approval.

B. Submit the new product request to the PMO for review and approval before proceeding.

C. Inform the customer of the change in corporate direction and ask him/her to take another look at the project.

D. Request a project charter from management and begin a WBS.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 18The performing organization is trying to decide whether to split the contracts department and assignprocurement responsibilities to departments directly responsible for the projects. A procurement professionalmight not want this split to occur because they would lose ___________ in a decentralized contractingenvironment.

A. Standardized company project management practices

B. Loyalty to the project

C. Experience

D. Access to others with similar expertise

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 19Linear programming is an example of what type of project selection criteria?

A. Constrained optimization

B. Comparative approach

C. Benefit measurement

D. Impact analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 20A project manager has just been assigned to a new project and has been given the approved project charter.The FIRST thing the project manager must do is:

Page 8: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Create a project scope statement.

B. Confirm that all the stakeholders have had input to the scope.

C. Analyze project risk.

D. Begin work on a project management plan.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 21A person is writing a document identifying the business need for a project and is including a description of theproduct created by the project. She includes a list of stakeholders and pre assigned resources. What is the roleof this person on the project?

A. The project manager for the project or a company functional manager

B. A member of the project management team working at the direction of the project manager

C. The sponsor or the project manager

D. A manager or executive in the organization who is higher in the corporate hierarchy than the projectmanager

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 22Generally, when is the BEST time to create a procurement management plan?

A. After the contract is signed

B. Preceding the Conduct Procurement process

C. During project initiating

D. When updating the procurement management plan

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 23All the following are needed to create the WBS EXCEPT:

A. Organizational process assets.

B. Quality measurements.

C. Requirements documentation.

D. Project scope statement.

Page 9: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 24Which of the following is a KEY output of the Verify Scope process?

A. A more complete scope management plan

B. Customer acceptance of project deliverables

C. Improved schedule estimates

D. An improved project management information system

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 25A project manager discovers that two team members discussed what was needed to complete a work packageon the project and made many changes to the project scope. The work package is now completed and theteam members are planning to go on to the next work package. In looking at what was done, the projectmanager determines that the work does NOT meet the requirements of the project. What is the BEST courseof action for the project manager?

A. Add another work package, formatted with the correct scope, to the project.

B. Refuse the submittal of the work package.

C. Have the team begin the work package again and include the incident in their performance reviews.

D. Ask the team member's manager to assign different people to the work package.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 26You are the project manager on an information technology project on which you and the sponsor have alreadyapproved the scope. An information specialist on your team, after having lunch with a low ranking customerrepresentative working with him on a software project, learns that a simple alteration in the display would be agreat addition to the project. The information specialist installs the change with no negative effect on the projectschedule and at no additional cost. What action should be taken?

A. The information specialist should be recognized for exceeding customer expectations without affectingproject cost or schedule.

B. The project manager should add an activity to the project management plan with no associated time.

C. The information specialist should be told that his behavior was unacceptable, as it may have negativelyaffected the overall project.

D. The project manager should create a change control form and have the customer approve the change sincethe change has already been made.

Page 10: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 27Which of the following is NOT included in a schedule change control system?

A. Approval levels necessary for authorizing changes

B. Tracking systems

C. Paperwork necessary for making changes

D. Limitations on the scope of changes

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 28Which of the following is generally the MOST CORRECT use of a project network diagram?

A. Showing the project schedule

B. Documenting activity interdependencies

C. Defining project resources

D. Defining the project costs

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 29In an activity-on-node diagram, the nodes represent:

A. Work packages.

B. Activities.

C. Dependencies.

D. Discretionaries.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 30

Page 11: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed beforeActivity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed beforeActivity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C iscompleted. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and Gmust be completed for the project to be completed. Which activities have float available?

A. Activity A has two weeks float, activity F has one week.

B. Activity F has one week float.

C. There is no float available in the project.

D. Activity A has eight weeks float.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 31An activity-on-node (AON) network diagram shows the following activities on two critical paths; Start, D, E, J, L,End and Start, D, E, G, I, L, End. Each activity is at least three days in duration, except for activity L, which isone day in duration. If you are directed to reduce the project by one day, which activities are MOST likely tochange?

A. Activity L

B. Activity E or activity J

C. Activity G or activity I

D. Activity D or activity E

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 32A project manager has increased project costs by US $100,000, but completed the project four weeks earlierthan planned. What activity is BEST described here?

A. Resource leveling

B. Schedule compression

C. Critical chain

D. Adjusting leads and lags

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 33The project manager has performed schedule network analysis, compressed the schedule, and completed a

Page 12: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Monte Carlo analysis. What time management activity should be done NEXT?

A. Update resource requirements

B. Recommend corrective actions

C. Estimate Activity Durations

D. Create a milestone list

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 34If project time and cost are not as important as the number of resources used each month, which of thefollowing is the BEST thing to do?

A. Perform a Monte Carlo analysis.

B. Fast track the project.

C. Perform resource leveling.

D. Analyze the life cycle costs.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 35A team member from research and development tells you that her work is too creative to provide you with afixed single estimate for the activity. You both decide to use the average labor hours per installation from pastprojects to predict the future. This is an example of which of the following?

A. Parametric estimating

B. Three-point estimating

C. Analogous estimating

D. Monte Carlo analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 36In attempting to complete the project faster, the project manager looks at the cost associated with crashingeach activity. The BEST approach to crashing would also include looking at the:

A. Risk impact of crashing each activity.

B. Customer's opinion of which activities to crash.

C. Boss's opinion of which activities to crash and in which order.

Page 13: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Project life cycle phase in which the activity is due to occur.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 37Based on the chart, while completing the project, a team member tells you that the team forgot somethingduring planning. Activity F needs the results of activity E before it can begin. Taking this new dependency intoaccount, what would be the effect on the project?

A. It would increase the critical path.

B. Communication would be more complex.

C. There would be no effect.

D. It would delay activity F.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 38Using the chart, what is the lowest cost of crashing this project to save four weeks?

A. $18,000

B. $6,000

C. $7,000

D. $9,000

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 39Based on the network diagram in the chart, the resource working on activity G is replaced with anotherresource with 50 percent of the productivity of the previous resource. How long will this project take?

A. 44

B. 51

C. 52

D. 36

Answer: CSection: (none)

Explanation/Reference:

Page 14: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 40Instead of celebrating the end of the project, the stakeholders are breathing a sigh of relief. None of them wereconfident the project would meet the end date. Which of the following is NOT one of the reasons this projecthad difficulty?

A. Lack of a payback period

B. Lack of milestones

C. Lack of a communications management plan

D. Lack of a staffing management plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 41A project manager for a small construction company has a project that was budgeted for US $130,000 over asix-week period. According to her schedule, the project should have cost US $60,000 to date. However, it hascost US $90,000 to date. The project is also behind schedule, because the original estimates were notaccurate. Who has the PRIMARY responsibility to solve this problem?

A. Project manager

B. Senior management

C. Project sponsor

D. Manager of the project management office

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 42While reviewing project performance, the project manager determines that the schedule variance is -500. Whatis the BEST thing to do?

A. Let the sponsor know.

B. Determine the cost variance.

C. Look for activities that can be done in parallel.

D. Move resources from the project to one that is not failing.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 43

Page 15: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know howlong the project will take if only nine resources each month are committed to your project. What is this activitycalled?

A. Crashing

B. Floating

C. Leveling

D. Fast tracking

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 44A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews.The project is 40 percent complete and has used 60 percent of the available calendar time. What is the FIRSTthing you should do?

A. Rebaseline the schedule to reflect the new date.

B. Analyze the critical path activities for potential to fast track or crash the schedule.

C. Document the lack of progress and associated issues to management.

D. Identify activities that required more time than planned.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 45To accommodate a new project in your department, you need to move resources from one project to another.Because your department is currently working at capacity, moving resources will inevitably delay the projectfrom which you move the resources. It would cause the LEAST negative impact if you move resources fromwhich of the following projects?

A. Project A with a benefit cost ratio of 0.8, no project charter, and four resources

B. Project B with a net present value of $60,000, 12 resources, and variable costs between US $1,000 and$2,000 per month

C. Project C with an opportunity cost of US $300,000, no project control plan, and an internal rate of return of12 percent

D. Project D with indirect costs of US $20,000 and 13 resources

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 46Who has the cost risk in a fixed price (FP) contract?

Page 16: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. The team

B. The buyer

C. The seller

D. Management

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 47The project management office is worried about the quality of the company's various projects. They want toknow which projects are having problems and which ones are doing well. If the PMO receives the followinginformation, which project should they be the MOST concerned about?

A. Project A with a benefit cost ratio of 2.3

B. Project B with a benefit cost ratio of 1.3

C. Project C with a benefit cost ratio of negative 2.3

D. Project D with a benefit cost ratio of negative 1.3

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 48Earned value measurement is an example of:

A. Performance reporting.

B. Planning control.

C. Ishikawa diagrams.

D. Integrating the project components into a whole.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 49A project manager and team from a firm that designs railroad equipment are tasked to design a machine toload stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilledrock per day. In which of the following does the project manager document quality control, quality assurance,and quality improvements for this project?

A. Quality management plan

B. Quality policy

C. Control charts

Page 17: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Project management plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 50All of the following are inputs to the quality process EXCEPT:

A. Organizational process assets.

B. Checklists.

C. Quality policy.

D. The project scope statement.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 51A quality management plan is created during which of the following?

A. Project Executing

B. Plan Quality

C. Perform Quality Assurance

D. Perform Quality Control

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 52Which of the following is an example of a tool used in Plan Quality?

A. Fishbone diagram

B. Quality audit

C. Cause and effect diagram

D. Benchmarking

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 18: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 53You are in the middle of a major new facility construction project. The structural steel is in place and the heatingconduits are going into place when a senior manager informs you that he is worried that the project will notmeet the quality standards. What should you do in this situation?

A. Assure senior management that during the Plan Quality process it was determined that the project wouldmeet the quality standards.

B. Analogously estimate future results.

C. Form a quality assurance team.

D. Check the results from the last quality management plan.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 54Management wants to be sure that the project is following defined quality standards. Which of the followingshould they look at?

A. Risk management plan

B. WBS

C. Statement of work

D. Quality audit

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 55All of the following are tools of Perform Quality Control EXCEPT:

A. Cost of quality.

B. Inspection.

C. Control charts.

D. Flowcharting.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 56Which of the following helps a project manager determine possible causes of problems on a project?

A. The 50/50 rule

B. A fishbone diagram

Page 19: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. A control chart

D. A Pareto chart

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 57If two events cannot both occur in a single trial, they are:

A. False events.

B. Mutually exclusive.

C. Statistically independent.

D. Just-in-time.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 58The customer's expectations for quality are shown on a control chart as the:

A. Mean.

B. Specification limits.

C. Rule of seven.

D. Upper and lower control limits.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 59Co-location can help with:

A. Bringing customers together.

B. Building the team.

C. Decreasing project rental costs.

D. Decreasing project time.

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 20: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 60A project involves arranging for the closing of the company office where the team works and relocatingeveryone to a new city. The BEST thing the project manager can do is:

A. Spend time carefully creating the work breakdown structure.

B. Have a strong quality control plan.

C. Decrease the fringe benefits.

D. Carefully consider the reward system for the project.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 61A team member is not performing well on the project because she is inexperienced in system developmentwork. There is no one else available who is better qualified to do the work. What is the BEST solution for theproject manager?

A. Consult with the functional manager to determine project completion incentives for the team member.

B. Obtain a new resource more skilled in development work.

C. Arrange for the team member to get training.

D. Allocate some of the project schedule reserve.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 62The management theory that all people can direct their own efforts is:

A. Theory Y.

B. Herzberg's theory.

C. Maslow's hierarchy.

D. Theory X.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 63A project team member has been having a big disagreement with another team member for over two monthswhen the other team members become involved. The issues are complex, but you have specific experience inthe area and know what needs to be done. The BEST choice would beto:

Page 21: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Make the decision yourself.

B. Strive for fair resolution of the issue.

C. Ask the other team members to stay out of the issue.

D. Bring the team together and work out the issue to a win-win solution.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 64While creating the agenda for a status meeting with the team, a project manager receives input from one teammember that an item should be added. Another team member says the team is not ready to resolve the itemduring the meeting. After much discussion, the project manager decides to put the item on the agenda as aninitial discussion item only. Which conflict resolution technique is the project manager using?

A. Compromise

B. Smoothing

C. Forcing

D. Withdrawal

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 65As the project manager, you are preparing your methods for quality management. You are looking for a methodthat can demonstrate the relationship between events and their resulting effects. You want to use a method todepict the events that cause a negative effect on quality. Which of the following is the BEST choice foraccomplishing your objective?

A. Histogram

B. Pareto chart

C. Ishikawa diagram

D. Control chart

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 66Formal written correspondence with the customer is required when:

A. Defects are detected.

B. The customer requests additional work not covered under contract.

Page 22: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. The project has a schedule slippage that includes changes to the critical path.

D. The project has cost overruns.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 67Extensive use of ___ communication is MOST likely to aid in solving complex problems.

A. Verbal

B. Written

C. Formal

D. Nonverbal

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 68Which of the following techniques incorporates a form of risk assessment?

A. Arrow diagramming method

B. Network diagramming

C. Critical path method

D. Three-point estimating

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 69A project manager is creating a risk response plan. However, every time a risk response is suggested, anotherrisk is identified that is caused by the response. Which of the following is the BEST thing for the projectmanager to do?

A. Document the new risks and continue the Plan Risk Responses process.

B. Make sure the project work is better understood.

C. Spend more time making sure the risk responses are clearly defined.

D. Get more people involved in the Identify Risks process since risks have been missed.

Answer: ASection: (none)

Explanation/Reference:

Page 23: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 70If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months,what is the probability that this risk event will occur during the fourth month of the project?

A. Less than 1 percent

B. 20 percent

C. 60 percent

D. 80 percent

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 71What is the purpose of a decision tree?

A. It demonstrates the path of events in a project.

B. It calculates the probability of an outcome.

C. It determines what events may take place.

D. It takes into account future events for today's choices.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 72Executing the risk response plan in order to react to risk events throughout the project is called:

A. Contingency planning.

B. Monitoring and control.

C. Mitigation.

D. Life cycle costing.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 73What is the difference between management reserves and contingency reserves?

A. Contingency reserves address known knowns, whereas management reserves address known unknowns.

B. Contingency and management reserves both address known unknowns and could be considered the same.

Page 24: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. Contingency reserves address known unknowns, whereas management reserves address unknownunknowns.

D. Contingency reserves are managed by senior management, whereas management reserves are managedby the project manager.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 74A project manager is asked to select a contract type for a new software development project that has complete,detailed requirements. Which is the BEST contract to choose?

A. Cost reimbursable (CR)

B. Fixed price (FP)

C. Time and material (T&M)

D. Cost plus fixed fee (CPFF)

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 75The project manager and project sponsor are discussing the project costs and whether it is better to have theirown company do part of the project or hire another company to do the work. If they asked for your opinion, youmight say it would be better to do the work yourself if:

A. There is a lot of proprietary data.

B. You have the expertise, but you do not have the available manpower.

C. You do not need control over the work.

D. Your company resources are limited.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 76While project work is being done, conflicts can arise between the procurement officer and the project managerbecause the procurement officer:

A. Is the only one who can change the contract.

B. Works for a different department.

C. Needs to obtain the project manager's approval to make project changes.

D. Has a different approach to creating a contract.

Page 25: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 77You are negotiating with a seller. Time is of the essence but you have a limited budget, and the seller knowsthis. What is your BEST negotiating strategy under these circumstances?

A. Focus the negotiation on seller's profit margin in order to decrease the project cost.

B. Negotiate to get the work done even sooner than necessary in order to add a reserve.

C. Negotiate identified risks.

D. Arrange to reschedule the negotiation until you can acquire information of which the seller is not aware.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 78You receive 25 new computers from the seller, but were expecting only 20. In looking at the contract, you seethat it says "seller to provide twenty (25) computers." What should you do FIRST?

A. Issue a change order through the contract manager.

B. Return the five extra computers.

C. Make payment for the 25 computers.

D. Call the seller and ask for clarification.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 79A project manager you are mentoring comes to you for help because he is about to face his first procurementaudit. You might explain that he should NOT worry about such an audit because it:

A. Identifies successes and failures that warrant transfer to other procurements.

B. Makes sure the contract is being followed.

C. Makes sure costs are in line with the project.

D. Makes sure the seller is following the contract.

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 26: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 80All of the following are typical concerns of matrixed team members EXCEPT:

A. Wondering who will handle their evaluations.

B. Serving multiple bosses.

C. Developing commitment.

D. Computing fringe benefits when working on multiple projects.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 81The seller tells you that your activities have resulted in an increase in their costs. You should:

A. Recommend a change to the project costs.

B. Have a meeting with management to find out what to do.

C. Ask the seller for supporting information.

D. Deny any wrongdoing.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 82Which of the following is CORRECT?

A. The critical path helps prove how long the project will take.

B. There can be only one critical path.

C. The network diagram will change every time the end date changes.

D. A project can never have negative float.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 83Which of the following is CORRECT about quality improvements?

A. They are a tool of Perform Quality Assurance and an output of Verify Scope.

B. They require the preparation of change requests or the recommendation of corrective actions.

C. They occur only through experience of the project manager, team, and sponsor.

D. They are a product of cooperation between the customer and the project manager.

Page 27: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 84A problem occurs on an activity with free float and the project manager has extended its duration.What is MOST likely to be affected?

A. Project duration

B. Resource schedules

C. Project scope management plan

D. The latest start for the successor activity

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 85Which of the following is NOT a reason to measure variances from the baseline?

A. To catch deviations early

B. To allow early corrective action

C. To determine if there are any wild fluctuations

D. To create a project control system

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 86A team member notifies the project manager that the activities comprising a work package are no longerappropriate. It would be BEST for the project manager to be in what part of the project management process?

A. Corrective action

B. Integrated change control

C. Monitoring and controlling

D. Project closing

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 28: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 87During project executing, a project team member informs the project manager that a work package has not metthe quality metric, and that she believes it is not possible to meet it. The project manager meets with all partiesconcerned to analyze the situation. Which part of the quality management process is the project managerinvolved in?

A. Perform Quality Assurance

B. Project Control

C. Perform Quality Control

D. Plan Quality

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 88The project manager notices that project activities being completed by one department are all taking slightlylonger than planned. To date, none of the activities/work packages have been on the critical path, nor have theyaffected the critical chain planning that has occurred. The project manager is bothered by the problem, sincefour of the next five critical path activities are being completed by this department. After making three calls, theproject manager is finally able to converse with the department manager to determine what is going on. Theconversation is slow, because both speak different native languages and they are trying to converse in French,a shared language. To make communication easier, the project manager frequently asks the departmentmanager to repeat back what has been said. The department manager communicates that his staff is followinga company policy that requires two levels of testing. During the conversation, the department manager alsomakes a comment that leads the project manager to believe that the policy may include excessive work. This isthe fourth time the project manager has heard such a comment. What is the BEST thing to do?

A. Create a better communications management plan that requires only one language to be the universallanguage on the project and have translators readily available on a moment's notice.

B. Contact someone else in the department who speaks the project manager's native language better toconfirm the department manager's opinion.

C. Find out if the upcoming activities should be re estimated.

D. Work on increasing the effectiveness of the performing organization by recommending continuousimprovement of the policy in question.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 89The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Eachmonth the sponsor requires the project manager to submit CPI calculations and an analysis of the cost tocomplete. The project manager explains to the sponsor that extra profits should NOT be a worry on this projectbecause:

A. The team is making sure the seller does not cut scope.

B. All costs invoiced are being audited.

Page 29: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. There can only be a maximum 10 percent increase if there is an unexpected cost overrun.

D. The fee is only received by the seller when the project is completed.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 90Which of the following is the LEAST effective way to influence the factors that create changes to the costbaseline?

A. Review the project scope with the functional manager responsible for the greatest number of requestedchanges.

B. Explain to those requesting changes the negative impact of change to the project.

C. Eliminate the scope causing the most changes.

D. Notify all stakeholders that no more changes will be allowed.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 91If a project manager is using observation and conversation to help control the project, she must be involved inwhich process?

A. Develop Project Team

B. Distribute Information

C. Manage Stakeholder Expectations

D. Manage Project Team

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 92Which of the following would be the MOST appropriate thing to do during the planning process group?

A. Update corporate processes and procedures based on lessons learned.

B. Evaluate the effectiveness of risk responses.

C. Recommend changes and defect repair.

D. Work with the customer to determine acceptance criteria.

Answer: DSection: (none)

Page 30: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 93Which of the following would be the MOST appropriate thing to do during the monitoring and controlling processgroup?

A. Implement recognition and reward systems.

B. Obtain sign-off of the product of the project.

C. Issue performance reports.

D. Keep everyone focused on completing the project to the charter.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 94The widget production project is well underway. The requirements are clear that each widget must weighbetween 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgetsinspected, 47 percent fell within the acceptable weight range. This is an exampleof:

A. Control limits.

B. Quality assurance.

C. Control charting.

D. Corrective action.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 95In which of the following contract types does the buyer have the most cost risk?

A. Cost plus percentage of costs (CPPC)

B. Cost plus fixed fee (CPFF)

C. Cost plus award fee (CPAF)

D. Cost plus incentive fee (CPIF)

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 96

Page 31: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

What is the difference between expected monetary value and net present value?

A. Expected value is the estimated value of the work actually accomplished and net present value is the valueof the work to be done.

B. Expected value is the value it takes to recover your investment and net present value is the value of money.

C. Expected value is the probability times impact of an opportunity and net present value is the benefits lesscosts over many time periods.

D. Expected value is the estimated value of risk response plans and net present value helps determine thevalue of investments.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 97A company attorney, newly hired by the company, walks into the project manager's office and tells her that he isready to work with her on the procurement process. The project manager has little experience withprocurement, so she is excited to have the assistance. With which of the following would it be BEST for theproject manager to ask the attorney for help?

A. Claims administration, audit results, and updating organizational process assets

B. Contract change control system, payments, and change requests

C. Recommended corrective actions, performance reporting, and records management system

D. Procurement documentation, project management plan updates, and procurement management planupdates

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 98A project manager discovers an urgent need for outsourced resources on the project. He knows he has themoney to cover the cost of these resources. He goes to the procurement manager and explains the situation,insisting a contract be drawn up today so he can obtain resources and circumvent the standard procedure. Isthis the correct process to follow?

A. Yes, of course. For urgent needs, it is not necessary to follow the organization?s procedure regardingprocurement.

B. Yes. Urgent needs from projects should always be dealt with immediately, as directed by the projectmanager.

C. No. The procurement manager has a process to follow when creating contracts that helps protect thecompany and its projects.

D. No. The procurement manager should be checking in with the project manager to see if he is in need of acontract, rather than making the project manager come and ask for one.

Answer: CSection: (none)

Explanation/Reference:

Page 32: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 99Which of the following is the BEST thing to do at a bidder conference?

A. Answer sellers' questions

B. Meet the sellers' teams

C. Make sure the sellers have all the procurement documents

D. Make sure the sellers ask all their questions

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 100To-complete performance index (TCPI) is represented by which of the following?

A. BAC - EV/BAC - AC

B. A measure of the value of work completed compared to the actual cost or progress

C. A measure of progress achieved compared to progress planned

D. AC + (BAC - EV)

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 101The inputs of the Performance Reporting process include all of the following except for which one?

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

Answer: ASection: (none)

Explanation/Reference:Explanation:Performance reviews are not an input of the Performance Reporting process. The remaining inputs of thisprocess are quality control measurements, project management plan, approved change requests, anddeliverables.

QUESTION 102You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competingwith another retail store for the option of opening two new stores in a foreign country. You know, but have notyet informed your company, that you are going to go to work for the competitor, which happens to be bidding for

Page 33: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

this same opportunity. What is the most appropriate response?

A. You decide to participate in the initial meetings with the foreign business partners because any informationyou gain now will help you when you make the move to the new company.

B. You inform the foreign business partners that you're going to be working with a new company and that youknow the deal they'll receive from the competing company is better than the one this company is proposing.

C. You decline to participate in the initial meetings with the foreign business partners because of a conflict ofinterest.

D. You've not yet received an official offer from the competing company for your new job opportunity, so youchoose to participate in the initial meetings with the foreign business partners.

Answer: CSection: (none)

Explanation/Reference:Explanation:The most appropriate response is to decline to participate because of a conflict of interest.

QUESTION 103"Pass Any Exam. Any Time." - www.actualtests.com 40PMI PMI-001 ExamThe most effective team motivator is:

A. understanding the importance of the project

B. the satisfaction of meeting a challenge

C. All of the other alternatives apply.

D. the visibility of the team's contribution

E. the individual's professional challenge

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 104Complete final contract performance reporting and verify product is done in

_______ .

A. Conduct Procurements

B. Close Procurements

C. Plan Procurements

D. Administer Procurements

Answer: BSection: (none)

Explanation/Reference:Explanation:Complete final contract performance reporting and verify product is done in Close Procurements.

Page 34: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 105Continually measuring and monitoring the actual cost versus the budget is done to _____.

A. None of the other alternatives apply.

B. analyze the reasons for variances

C. establish the variances

D. identify the problems

E. All of the other alternatives apply.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 106You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who liedabout his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition.Which of the following could happen if you don't correct this?

A. The project costs could increase, there might be rework, and schedule delays might result.

B. The project management plan's process for verification and acceptance of the deliverables needs to beupdated as a result of the poor scope definition.

C. The poor scope definition will adversely affect the creation of the work breakdown structure, and costs willincrease.

D. The stakeholders will require overtime from the project team to keep the project on schedule.

Answer: ASection: (none)

Explanation/Reference:Explanation:Option A might seem like a correct answer, but option D is more correct. There isn't enough information todetermine whether stakeholders will require overtime. We do know that poor scope definition might lead to costincreases, rework, schedule delays, and poor morale.

QUESTION 107You are a project manager working in a foreign country. You observe that some of your project team membersare having a difficult time adjusting to the new culture. You provided them with training on cultural differencesand the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of thefollowing statements is true?

A. This condition is known as culture shock.

B. This is the result of jet lag and travel fatigue.

C. This is the result of working with teams of people from two different countries.

D. This condition is known as globalculturalism.

Answer: ASection: (none)

Page 35: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:When people work in unfamiliar environments, culture shock can occur. Training and researching informationabout the country you'll be working in can help counteract this.

QUESTION 108Which of the following is not true for a Responsibility Assignment Matrix (RAM):

A. Defines what project member is responsible for each activity

B. Defines responsibilities for each WBS component

C. Defines all people associated with each activity

D. Text description of roles, responsibilities, authorities

Answer: DSection: (none)

Explanation/Reference:Explanation:The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart.

QUESTION 109The erection of foundation formwork before the placement of foundation concrete would be an example of a_____ dependency.

A. Soft logic

B. Subcontracted

C. Mandatory

D. Discretionary

E. External

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 110You are the project manager of a project .You have just completed the Collect

Requirements and Define Scope. What should you do next?

A. Control Scope

B. Create WBS

C. Value analysis

D. Verify Scope

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 36: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Create the WBS is the process that follows Collect Requirements and Define Scope.

QUESTION 111Which of the following is not true for a Responsibility Assignment Matrix (RAM):

A. Defines what project member is responsible for each activity

B. Defines all people associated with each activity

C. Defines responsibilities for each WBS component

D. All of the other alternatives apply

Answer: DSection: (none)

Explanation/Reference:Explanation:The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart.

QUESTION 112Giving a part of project work to a contractor is an example of:

A. risk assumption

B. risk assignment

C. risk delegation

D. risk deflection

E. risk mitigation

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 113Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely

6 days, what is the PERT weighted average?

A. 6.1

B. 6.3

C. 6

D. 4

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 114Management reserves are normally defined as a % of the total budget. As a project progresses, the project

Page 37: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

manager wants the $ value of management reserve to _____, whereas the customer wants the managementreserve to _____.

A. Increase, increase.

B. Increase, decrease.

C. Remain the same, return to customer.

D. Decrease, increase.

E. Decrease, decrease.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 115The project manager has, as a prime responsibility, to assure proper integration of activities. In whichorganizational form does the project manager probably have the easiest time in integrating work?

A. Matrix

B. Pure project

C. Coordinator

D. Classical

E. Expediter

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 116Formal written correspondence is mandated in which of the following situations:

A. Client requests additional work not covered under contract

B. None of the other alternatives apply

C. Both 1) Client requests additional work not covered under contract, and 2) Project manager calls a meeting.

D. Project manager calls a meeting

E. Product undergoes casual in-house testing

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 117Smoothing out resource requirements from period to period is called resource _____.

A. None of the other alternatives apply.

Page 38: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Leveling.

C. Quantification

D. Partitioning

E. Allocation.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 118You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedyfilms for the big screen. Your latest project has just been completed and accepted. You've been given your nextproject, which starts right away. Which of the following statements is true?

A. This project ended due to integration because it was completed and accepted.

B. This project ended due to extinction because it was completed and accepted.

C. This project ended due to integration because it was completed and accepted and the project managermoved on to a new project.

D. This project ended due to addition because it was completed and accepted and archived into the company'scatalog of available films.

Answer: BSection: (none)

Explanation/Reference:Explanation:Extinction is the best type of project end because it means the project was completed successfully andaccepted by the sponsor or customer.

QUESTION 119Which is a valid response to negative risks?

A. mitigation

B. Enhance

C. Exploit

D. Share

Answer: ASection: (none)

Explanation/Reference:Explanation:Risk mitigation is a response to negative risks and not positive risks. Positive risks may be responded by -"Exploit", "Enhance", "Share", "Accept".

QUESTION 120Project leadership requires that the project manager pay attention simultaneously to the:

A. Time, cost and performance deliverables

Page 39: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Tasks to be performed and needs of the team

C. Quantity and quality of the work to be performed

D. All of the other alternatives apply

E. Efficiency and effectiveness of the team

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 121A quality control manager decides to increase his daily sample size from three to six. The size of the controlband will:

A. not determinable from given data

B. None of the other alternatives apply.

C. decrease

D. remain unchanged

E. increase

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 122What is one of the most important skills a project manager can have?

A. Negotiation skills

B. Communication skills

C. Influencing skills

D. Problem-solving skills

Answer: BSection: (none)

Explanation/Reference:Explanation:Negotiation, influencing, and problem-solving skills are all important for a project manager to possess.However, good communication skills are the most important skills a project manager can have.

QUESTION 123The critical path in a schedule network is the path that:

A. Takes the longest time to complete

B. Allows some flexibility in scheduling a start time.

C. Is not affected by schedule slippage

Page 40: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Must be done before any other tasks

E. All of the other alternatives apply.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 124In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid inputinto the employee's performance review?

A. All of the other alternatives apply

B. Employees spend only a short amount of time assigned to the project

C. Not working directly with the assigned functional employees

D. Not being knowledgeable enough to evaluate employees on technical judgment

E. Both 1) Not working directly with the assigned functional employees, and 2) Employees spend only a shortamount of time assigned to the project.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 125You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competingwith another retail store for the option of opening two new stores in a foreign country.You have been invited to dinner with the prospective foreign business partners and their spouses upon yourarrival. You know that all of the following statements are generally true except for which one?

A. You should respect the cultural differences you'll encounter when working with your prospective foreignbusiness partners.

B. You should build an atmosphere of mutual trust and cooperation.

C. You should spend time building relationships with your prospective foreign business partners before gettingdown to business.

D. You should explain your company's rules, standards, and operating policies at your first meeting with theprospective foreign business partners.

Answer: DSection: (none)

Explanation/Reference:Explanation:Your first meeting with foreign partners should be spent getting to know them on a personal basis. Manycultures like to spend time building relationships first and then talking business. Since you've been invited todinner upon your arrival and the dinner includes the spouses of your prospective partners, chances are theywant to spend some time getting to know you personally first. The discussion of the company's rules,standards, and operating policies should occur at the second or third meeting.

QUESTION 126

Page 41: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Reserve Analysis a technique not used in:

A. Estimate Costs

B. Estimating Activity Duration

C. Control Costs

D. Determine Budget

Answer: CSection: (none)

Explanation/Reference:Explanation:Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in manyschedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.

QUESTION 127A Project with a total funding of $70,000 finished with a BAC value of $60,000.

What term can best describe the difference of $10,000?

A. Management Contingency Reserve

B. Cost Variance

C. Schedule Variance

D. Management Overhead

Answer: ASection: (none)

Explanation/Reference:Explanation:The difference between the Cost Baseline and Funding requirement at Project completion is ManagementContingency Reserve. BAC represents the revised Cost baseline for the project. So Management ContingencyReserve is true.

QUESTION 128The positive value of conflict is underestimated. Properly managed, conflict is a valuable tool, particularly when

A. A diversion is needed

B. Conflict may cause a loss of status or position power

C. Conflictive situations are in their early stages and emotional involvement is low

D. Conflictive situations are in their late stages and emotional involvement is high

E.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 129You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis.

Page 42: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

When you've completed this process, you'll produce all of the following as part of the risk register update outputexcept which one?

A. Probability of achieving time and cost estimates

B. Watch list of low-priority risks

C. Priority list of risks

D. Risks grouped by categories

Answer: ASection: (none)

Explanation/Reference:Explanation:Probability of achieving time and cost estimates is an update that is produced from the Quantitative RiskAnalysis process.

QUESTION 130A clear definition of the user's needs serves as the direct basis for the:

A. Selection of personnel.

B. Termination decision.

C. Work breakdown structure.

D. Functional requirements.

E. Project cost estimate.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 131A summary WBS is usually developed in the

A. close-out phase

B. All of the other alternatives apply phases

C. implementation phase

D. planning phase

E. Conceptual phase

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 132Many companies self insure against some risk. Problems which can arise from self-insurance include:

A. confusion of business risks with insurable risks.

Page 43: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Both 1) failure to reserve funds to handle worst case scenarios (low probability events) resulting in severefinancial damage to the company, and 2) confusion of business risks with insurable risks.

C. stiff competition from insurance companies

D. All of the other alternatives apply.

E. failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financialdamage to the company

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 133You are a contract project manager working with the State of Bliss. Your latest project involves rewriting theDepartment of Revenue's income tax system. As project manager, you have taken all the appropriate actionsregarding confidentiality of data. One of the key stakeholders is a huge movie buff, and she has the power topromote you into a better position at the conclusion of this project. She's reviewing some report data that justhappens to include confidential information regarding one of her favorite movie superstars. What is the mostappropriate response?

A. Do nothing, because she has the proper level of access rights to the data and this information showed upunintentionally.

B. Request that she immediately return the information, citing conflict of interest and violation of confidentialcompany data.

C. Request that she immediately return the information until you can confirm that she has the proper level ofaccess rights to the data.

D. Report her to the management team.

Answer: ASection: (none)

Explanation/Reference:Explanation:As project manager, it's your responsibility to make sure the people you will be sharing data with have theproper permissions to see the data; this question indicated that you did that. In this case, D is not correctbecause it implies that you did not verify ahead of time that the stake-holder had the proper level of approvals touse the data.

QUESTION 134Resource reallocation from non critical to critical activities is an example of which

Project Scheduling technique:

A. Critical Path Method

B. Schedule Compression

C. Resource Leveling

D. What if Analysis

Answer: CSection: (none)

Explanation/Reference:

Page 44: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:Resource Leveling: Allocate scare resources to critical path activities first.

QUESTION 135Which of the following statements is in agreement with McGregor's concepts concerning Theory X and TheoryY managers?

A. All of the other alternatives apply

B. Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegateresponsibility

C. Both 1) Theory X managers view subordinates as being lazy, irresponsible, and resistant to change, and 2)Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

D. Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

E. Theory X managers view subordinates as being lazy, irresponsible, and resistant to change

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 136Management by objectives assumes that the team

A. Both 1) is receptive to an unstructured environment, and 2) possesses a self-fulfillment philosophy

B. possesses a self-fulfillment philosophy

C. All of the other alternatives apply

D. is receptive to an unstructured environment.

E. does not require close supervision

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 137An activity that consumes no time or resources and shows only that a dependency exists between two activitiesis called:

A. A milestone

B. A dummy activity

C. Both 1) A milestone and 2) A dummy activity

D. A hammock

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 45: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 138A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A. Parametric

B. Bottom up.

C. Budget

D. Top down."Pass Any Exam. Any Time." - www.actualtests.com 55PMI PMI-001 Exam

E. Definitive.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 139What is the standard deviation for the estimates in the above problem?

A. 2

B. 0.5

C. 1.5

D. 0.6

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 140Which of the following is most closely associated with pure risk:

A. profit and loss

B. personnel turnover

C. market fluctuations

D. insurance

E. Both 1) profit and loss and 2) market fluctuations.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 141Your company, Kick That Ball Sports, has appointed you project manager for its new Cricket product lineintroduction. This is a national effort, and all the retail stores across the country need to have the new productson the shelves before the media advertising blitz begins. The product line involves three new products, two of

Page 46: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

which will be introduced together and a third one that will follow within two years. Product number three will beelaborated in more detail closer to the product's release date, while the first two products will be elaborated ingreat detail now. The scope management plan has just been completed. Which of the following is true?(Choose the best response.)

A. The WBS template from a previous project, a tool and technique of the Create WBS process, was used tocreate the WBS for this project. The WBS encompasses the major deliverables for the project.

B. Only the deliverables associated with the work of the project should be listed on the WBS.Since product number three isn't being released until a later date it should not yet be included on the WBS.

C. The WBS encompasses the full scope of work for the project and the technique in the question is calledrolling wave planning.

D. The WBS should be created next, and it encompasses the full scope of work for the project.Only the work of the project is listed on the WBS.

Answer: CSection: (none)

Explanation/Reference:Explanation:There isn't enough information in the question to know whether "The WBS template from a previous project, atool and technique of the Create WBS process, was used to create the WBS for this project. The WBSencompasses the major deliverables for the project." is correct, although it could be. "The WBS should becreated next, and it encompasses the full scope of work for the project. Only the work of the project is listed onthe WBS." is not correct because the next process after the scope management plan is created is the ScopeDefinition process. The WBS details the entire scope of the project and includes all deliverables. It is an outputof the Create WBS process and the technique of elaborating some deliverables at a later date is called rollingwave planning.

QUESTION 142The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A. type I error

B. producer's risk

C. consumer's risk

D. buyer's risk

E. consumer's risk and type I error

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 143Parametric cost estimating involves

A. using a statistical model to estimate costs

B. calculating the individual estimates of work packages

C. defining the perimeters of the life-cycle

D. using the WBS to do bottom up estimates

E. Both 1) using the WBS to do bottom up estimate, and 2) calculating the individual estimates of workpackages

Page 47: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 144You are a project manager for Picture Shades, Inc. It manufactures window shades that have replicas ofRenaissance-era paintings on the inside for hotel chains. Picture Shades is taking its product to the homemarket, and you're managing the new project. It will offer its products at retail stores as well as on its website.You're developing the project schedule for this under-taking and have determined the critical path. Which of thefollowing statements is true?

A. You calculated the early and late start dates, the early and late finish dates, and float times for all activities.

B. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

C. You calculated the activity dependency and the optimistic and pessimistic activity duration estimates.

D. You calculated the most likely start date and most likely finish dates, float time, and weighted averageestimates.

Answer: ASection: (none)

Explanation/Reference:Explanation:The CPM calculates a single early and late start date and a single early and late finish date for each activity.Once these dates are known, float time is calculated for each activity to determine the critical path. The otheranswers contain elements of PERT calculations.

QUESTION 145Your project team has identified several potential risks on your current project that could have a significantimpact if they occurred. The team examined the impact of the risks by keeping all the uncertain elements attheir baseline values. What type of diagram will the team use to display this information?

A. Process flowchart

B. Tornado diagram

C. Influence diagram

D. Fishbone diagram

Answer: BSection: (none)

Explanation/Reference:Explanation:The question describes sensitivity analysis, which is a tool and technique of the Quantitative Risk Analysisprocess. Tornado diagrams are often used to display sensitivity analysis data.

QUESTION 146Response Planning is the responsibility of the functional areas and considers

A. deflection.

B. contingency planning.

Page 48: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. unforeseen occurrences.

D. All of the other alternatives apply.

E. mitigation.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 147Your project sponsor has requested a cost estimate for the project on which you're working. This project issimilar in scope to a project you worked on last year. She would like to get the cost estimates as soon aspossible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decideto use ___________________.

A. parametric modeling techniques

B. analogous estimating techniques

C. bottom-up estimating techniques

D. computerized modeling techniques

Answer: BSection: (none)

Explanation/Reference:Explanation:Analogous-or top-down-estimating techniques are a form of expert judgment. Since this project is similar toanother recent project, you can use the cost estimates from the previous project to help you quickly determineestimates for the current project.

QUESTION 148For communication to occur, there must be:

A. All of the other alternatives apply

B. a communication process

C. Two or more people involved

D. the transmittal of information

E. The transmittal of information and a communication process

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 149Your company has asked you to be the project manager for the product introduction of its new DeskTop Rockmedia system. You recently published the project scope statement. Which of the following is not contained inthe project scope statement?

A. Requested changes

Page 49: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Project configuration management requirements

C. Constraints

D. Project specifications

Answer: ASection: (none)

Explanation/Reference:Explanation:Requested changes are an output of the Scope Definition process. They are not part of the project scopestatement.

QUESTION 150You are working on a project that is similar in scope to a project performed last year by your company. Youmight consider which of the following?

A. Using the previous project's alternatives identification as a template

B. Reusing the previous project's product description when writing the scope statement

C. Using the previous project's WBS as a template

D. Reusing the previous project's cost-benefit analysis as justification for this project

Answer: CSection: (none)

Explanation/Reference:Explanation:WBSs from previous projects can be used as templates on projects that are producing similar products,services, or results. Some companies write WBS templates to be used for projects of similar scope.

QUESTION 151What are the performance measurements for the Schedule Control process?

A. SV (EV - PV) and SPI (EV ÷ PV)

B. SV (PV - EV) and SPI (PV ÷ EV)

C. SV (EV - BAC) and SPI (EV ÷ BAC)

D. SV (EV - AC) and SPI (EV ÷ AC)

Answer: ASection: (none)

Explanation/Reference:Explanation:Schedule variance is (EV - PV) and schedule performance index is (EV ÷ PV).

QUESTION 152The work that must be done in order to deliver a product with the specified features and functionsis:

A. Project verification

B. Project scope

C. Project control

Page 50: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Product scope

Answer: BSection: (none)

Explanation/Reference:Explanation:Project Scope: The work that must be done in order to deliver a product with the specified features andfunctions.

QUESTION 153The project manager is assigned in the?

A. Management Plan

B. SOW

C. Charter (contract)

D. Project Plan

Answer: CSection: (none)

Explanation/Reference:Explanation:Project Manager should be assigned in the early phase of the project otherwise project may get delay.

QUESTION 154Parametric Estimating is done as a part of which process:

A. Estimate Activity Durations

B. Sequence Activities

C. Develop Schedule

D. Estimate Activity Resources

Answer: ASection: (none)

Explanation/Reference:Explanation:Tools and Techniques for Estimate Activity Durations are: Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.

QUESTION 155Make payment to seller is done in _______ .

A. Plan Procurements

B. Conduct Procurements

C. Administer Procurements

D. Close Procurements

Answer: CSection: (none)

Page 51: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:Make payment to seller is done in Administer Procurements.

QUESTION 156You have accumulated project information throughout the project and need to distribute some importantinformation you just received. Which of the following is not an information distribution method?

A. Electronic mail

B. Videoconferencing

C. Voicemail

D. Electronic databases

Answer: DSection: (none)

Explanation/Reference:Explanation:Electronic databases are a type of information gathering and retrieval system, not a distribution method.

QUESTION 157The following reports are normally developed during the project closure phase?

A. None of the other alternatives apply

B. Communications Management Plan and Lessons Learned

C. Records Archive, Closure Report, & Specifications Document

D. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

E. Communications Management Plan and Closure report

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 158Which one of the following is not an acquisition method?

A. negotiation

B. invitation

C. purchase

D. advertising

E. all are acquisition methods

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 52: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 159Communication in both project and non-project-driven organizations should occur in directions.

A. four

B. one

C. two

D. three

E. five

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 160In which of the following is the cost of risk hidden by the contractor?

A. Fixed Price Plus Incentive

B. Firm Fixed Price Contract and Fixed Price Plus Incentive

C. Firm Fixed Price Contract

D. Cost Plus Percentage of Cost

E. Cost Plus Fixed Price

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 161Objectives can be described as all of the following except for which one? Choose the least correct answer.

A. The monetary units used to express the cost criteria for the project

B. The functionality and specific conditions that must be met in order to satisfy the project, contract, standard,or specification

C. The quantifiable results used to measure project success that should include schedule, cost, and qualitycriteria

D. The purpose for undertaking the project

Answer: BSection: (none)

Explanation/Reference:Explanation:According to the PMBOK Guide, functionality and specific conditions that must be met in order to satisfy theproject, contract, standard, or specification describe the criteria for requirements, not objectives.

QUESTION 162All of the following statements are true regarding the RBS except for which one?

Page 53: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. The RBS is similar to the WBS in that the lowest levels of both are easily assigned to a responsible party orowner.

B. The RBS is contained in the risk management plan.

C. The lowest level of the RBS can be used as a checklist, which is a tool and technique of the RiskIdentification process.

D. It describes risk categories, which are a systematic way to identify risks and provide a foundation forunderstanding for everyone involved on the project.

Answer: ASection: (none)

Explanation/Reference:Explanation:The RBS describes risk categories, and the lowest level can be used as a checklist to help identify risks. Riskowners are not assigned from the RBS; they're assigned during the Risk Response Planning process.

QUESTION 163You are the project manager for Lucky Stars nightclubs. They specialize in live country and western bandperformances. Your newest project is in the Planning process group. You've published the scope statementand scope management plan. The document that describes who will receive copies of this information as wellas future project information, how it should be distributed, and who will prepare it is which of the following?

A. Scope management plan

B. Project charter

C. Communications management plan

D. Information distribution plan

Answer: CSection: (none)

Explanation/Reference:Explanation:The communications management plan documents what information will be distributed, how it will bedistributed, to whom, by whom, and the timing of the distribution.

QUESTION 164With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

A. 25.0

B. 22.5

C. 27.5

D. 30.0

Answer: DSection: (none)

Explanation/Reference:Explanation:mean = (20+30+40)/3= 30

QUESTION 165

Page 54: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Sally is a project manager working on a project that will require a specially engineered machine. Only threemanufacturers can make the machine to the specifications Sally needs. The price of this machine is particularlycritical to this project. The budget is limited, and there's no chance of securing additional funds if the bids for themachine come in higher than budgeted. She's developing the evaluation criteria for the bidders' responses andknows all of the following are true except for which one?

A. Sally will review the project management plan, including the risk register, as inputs to this process.

B. Sally will base the evaluation criteria on price alone since the budget is a constraint.

C. Sally will update the contract statement of work with any new information.

D. Sally will use standard contract forms provided by her procurement department to write the contract for thismachine.

Answer: BSection: (none)

Explanation/Reference:Explanation:Evaluation criteria can be based on price alone when there are many vendors who can readily supply the goodor services. The question states that only three vendors make the machine, which means evaluation criteriashould be based on more than price.

QUESTION 166Failure costs are also known as which of the following?

A. Internal costs

B. Prevention costs

C. Cost of keeping defects out of the hands of customers

D. Cost of poor quality

Answer: DSection: (none)

Explanation/Reference:Explanation:Failure costs are associated with the cost of quality and are also known as cost of poor quality.

QUESTION 167During the opening rounds of contract negotiation, the other party uses a fait accompli tactic. Which of thefollowing statements is true about fait accompli tactics?

A. One party claims the issue under discussion was documented and accepted as part of Scope Verification.

B. One party claims the issue under discussion has already been decided and can't be changed.

C. One party claims to accept the offer of the other party, provided a contract change request is submitteddescribing the offer in detail.

D. One party agrees to accept the offer of the other party but secretly knows they will bring the issue back up ata later time.

Answer: BSection: (none)

Explanation/Reference:Explanation:Fait accompli is a tactic used during contract negotiations where one party convinces the other that the

Page 55: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

particular issue is no longer relevant or cannot be changed. Option B is not correct because Scope Verificationdoes not generally occur during contract negotiations since the work of the project has not yet been performed.

QUESTION 168The most rapid Estimate Costs technique is:

A. Analogous estimating

B. Template estimating

C. Computerized estimating

D. Square foot estimating

Answer: CSection: (none)

Explanation/Reference:Explanation:Computerized estimating rapid Estimate Costs technique

QUESTION 169Management styles associated with production environments, such as assembly lines commonly include:

A. assumption that workers lack ambition and dislike responsibility

B. All of the other alternatives apply.

C. a directing style of leadership.

D. a lack of confidence in their workers

E. a Theory X style of leadership

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 170The person in the organization that authorizes the commencement of a project is the______________?

A. Project Admin

B. Sponsor

C. Project Manager

D. Senior Manager

Answer: BSection: (none)

Explanation/Reference:Explanation:The project manager executes the project but does not authorize the project. Sponsor authorize the project.

QUESTION 171Constraints do not include:

Page 56: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Expected staff assignments

B. Collective bargaining

C. Organizational structure of the performing organization

D. Impacts of weather

Answer: DSection: (none)

Explanation/Reference:Explanation:Impacts of weather

QUESTION 172Job continuity would be an example of _____ in Maslow's hierarchy of needs.

A. Self-actualization

B. Physiological

C. Safety

D. Belonging

E. Esteem

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 173The estimated cost to complete (ETC) is _____.

A. BCWP/ACWP

B. the forecasted and final cost - cost to date

C. None of the other alternatives apply.

D. Total estimate - ACWP

E. (ACWP-BCWP)/BCWP * 100

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 174Formal written communication is mandated for which of the following?

A. Both 1) scope changes not part of the original project, and 2) taking exception to a specification.

B. scope changes not part of the original project

C. procurement of raw materials

D. All of the other alternatives apply.

Page 57: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

E. taking exception to a specification

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 175Risk mitigation includes all but which of the following:

A. performing contingent planning

B. Obtaining insurance against loss

C. Developing system (policies, procedures, responsibilities)

D. identification of project risks.

E. developing planning alternatives

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 176Lessons learned are most often based upon project historical records. Lessons learned can be used to:

A. See how others have solved problems

B. "Predict trends, highlight problems and identify alternatives"

C. See what mistakes others have made

D. All of the other alternatives apply

Answer: DSection: (none)

Explanation/Reference:Explanation:All of the other alternatives apply

QUESTION 177In which type of organization(s) is the project manager's role most likely part-time?

A. Functional

B. Weak Matrix

C. Balanced Matrix

D. Both 1) Functional and 2) Weak Matrix

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 58: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 178A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consumetime or resources.

A. Event.

B. Activity

C. Correlation

D. Event constrained within planned effort.

E. Constant

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 179Trend Analysis is best described as:

A. Examining project performance over time

B. Calculating Earned Value

C. Calculating Cost Variance

D. Analyzing performance of similar projects over time

Answer: ASection: (none)

Explanation/Reference:Explanation:Trend Analysis is Examining project performance time by time

QUESTION 180Overlapping activities on a project, such as design and construction, is referred to as:

A. Process improvement.

B. Synchronous manufacturing

C. Fast tracking

D. Parallel management.

E. Risk conversion.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 181All the techniques described below can be used to keep a meeting focused except:

Page 59: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Rephrase unclear ideas presented by group members

B. Encourage pursuit of interesting new ideas

C. Summarize discussion periodically

D. Recall agenda items/purpose of meeting

E. All are acceptable techniques

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 182Resource leveling _____.

A. Attempts to reduce resource requirements within a constraint on project duration

B. Smoothes out resource requirements by rescheduling activities within their float time.

C. Allocates resources to activities to find shortest schedule within fixed resource limits.

D. Smooths out resource requirements by substituting activities with unassigned resources.

E. 1) Smoothes out resource requirements by rescheduling activities within their float time, or 2) Attempts toreduce resource requirements within a constraint on project duration

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 183The highest degrees of project risk and uncertainty are associated with the following phase of the project:

A. Both 1) conceptual, and 2)post project evaluation

B. cut-over

C. conceptual

D. execution

E. post project evaluation

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 184You are a project manager for an engineering company. Your company won the bid to add ramp- meteringlights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portionof the project to another company. The subcontractor's work involves digging the holes and setting the lamppoles in concrete. The subcontractor's performance is not meeting the contract requirements. Which of thefollowing is not a valid option?

Page 60: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. You document the poor performance in written form and send the correspondence to the subcontractor.

B. You terminate the contract for poor performance and submit a change request through ContractAdministration.

C. You agree to meet with the subcontractor to see whether a satisfactory solution can be reached.

D. You submit a change request through Contract Administration demanding that the subcontractor complywith the terms of the contract.

Answer: DSection: (none)

Explanation/Reference:Explanation:The contract change control system describes the processes you'll use to make changes to the contract, not asa means of communication. The changes might include contract term changes, date changes, and terminationof a contract.

QUESTION 185Job descriptions are examples of ______communications.

A. horizontal

B. downward

C. diagonal

D. upward

E. None of the other alternatives apply

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 186You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungentbreath. Which of the following communication barriers describe these distractions?

A. None of the other alternatives apply

B. Selective Perception

C. Sensory Limitations

D. Varying Alertness of Perception

E. Sign Detection

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 187Group brainstorming encourages all of the following except:

A. Analysis of alternatives

Page 61: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Decision making

C. Team building

D. Convergent thinking

E. Uninhibited verbalization

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 188In crashing a task, you would focus on:

A. Accelerate performance by minimizing cost.

B. As many tasks as possible and accelerate performance by minimizing cost.

C. Non critical tasks.

D. Accelerating performance of tasks on critical path.

E. As many tasks as possible.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 189You have been assigned to a project in which the objectives are to expand three miles of the north-to-southhighway through your city by two lanes in each direction. You are in charge of the demolition phase of thisproject, and you report to the project manager in charge of this project. You have been hired on contract andwill be released at the completion of the demolition phase. What type of organizational structure does thisrepresent?

A. Balanced matrix organization

B. Functional organization

C. Projectized organization

D. Weak matrix organization

Answer: CSection: (none)

Explanation/Reference:Explanation:Projectized organizations are focused on the project itself. One issue with this type of structure is determiningwhat to do with project team members when they are not actively involved on the project. One alternative is torelease them when they are no longer needed.

QUESTION 190You are a project manager of ABC organization. You are estimating the project in initiation phase.What level of accuracy you can expect?

Page 62: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. -75 percent to +75 percent

B. -25 percent to +25 percent

C. -50 percent to +50 percent

D. -50 percent to +100 percent

Answer: DSection: (none)

Explanation/Reference:Explanation:In the project initiation phase estimation is rough therefore it can fluctuate -50 percent to +100 percent.

QUESTION 191Root Cause Analysis related to ________.

A. Process Analysis

B. Performance Measurements

C. All of the other alternatives apply

D. Quality Audits

Answer: ASection: (none)

Explanation/Reference:Explanation:Root Cause Analysis relates to Process Analysis.

QUESTION 192Range estimating in determining cost risk probabilities requires _____ .

A. an amount of financial exposure.

B. risks and opportunities ranked in order of bottom line importance

C. All of the other alternatives apply.

D. contingency requirements for expected level of confidence

E. probability of cost overrun occurrences

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 193When working in a matrix environment, all of the following are true regarding the Manage Project Teamprocess except for which one?

A. Communication methods and issue logs are used to create performance appraisals, provide feedback, andtrack issues.

B. Managing project teams in a matrix environment is often a critical success factor for the project.

C. Loyalty issues might arise when managing projects in a matrix environment.

Page 63: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. It's the project manager's responsibility to make certain this dual reporting relationship is managedeffectively.

Answer: ASection: (none)

Explanation/Reference:Explanation:Communication methods are not a tool and technique of the Manage Project Team process.

QUESTION 194Who are the audience of project charter?

A. The senior Project Manager

B. The project team

C. stakeholders

D. The project manager

Answer: CSection: (none)

Explanation/Reference:Explanation:The project sponsor creates and issues the project charter and the audience are the stakeholders.

QUESTION 195Communication always makes use of.

A. words

B. All of the other alternatives apply.

C. language

D. gestures

E. symbols

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 196The major difference between PERT and CPM networks is:

A. PERT is measured in days whereas CPM uses weeks or months.

B. PERT addresses only time whereas CPM also includes cost and resource availability.

C. PERT requires three time estimates whereas CPM requires one time estimate.

D. PERT is used for construction projects whereas CPM is used for R & D.

E. PERT requires computer solutions whereas CPM is a manual technique.

Answer: CSection: (none)

Page 64: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 197Risk event probability is defined as:

A. the total number of possible events divided into the expectations or frequency of the risk event

B. the fraction of the total project tasks which may be affected by the risk event

C. the number of times the risk event may occur

D. Both 1) the total number of possible events divided into the expectations or frequency of the risk event and2) the number of times the risk event may occur.

E. the total number of possible events divided into the consequences of the risk event.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 198You've been assigned as a project manager on a research and development project for a new dentalprocedure. You're working in the Scope Planning process. What is the purpose of the project scopemanagement plan?

A. The project scope management plan describes and documents a scope baseline to help make futureproject decisions.

B. The project scope management plan decomposes project deliverables into smaller units of work.

C. The project scope management plan describes how project scope will be developed and how changes willbe managed.

D. The project scope management plan describes how cost and time estimates will be developed for projectscope changes.

Answer: CSection: (none)

Explanation/Reference:Explanation:The scope management plan outlines how project scope will be managed and how changes will beincorporated into the project.

QUESTION 199What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

A. Idle resources

B. Negative float

C. Lots of free float

D. Positive float

Answer: ASection: (none)

Page 65: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 200The ability to achieve cost savings is inversely proportional to _____.

A. empowerment to the P.M.

B. productivity

C. the estimated costs to complete

D. the earned value achieved to date

E. None of the other alternatives apply.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 201The strong matrix versus a weak matrix.

A. strong matrix is more difficult to manage.

B. the balance of power has shifted away from the PM.

C. All of the other alternatives apply.

D. functional managers no longer has control over the technical processes.

E. team members are more likely to be assigned to the project office in a strong matrix

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 202According to Herzberg, which of the following is a motivational factor?

A. Working conditions

B. Achievement

C. Vacation time

D. Pay

E. Hygiene needs

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 203

Page 66: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

The scope of a project can be expected to change if:

A. The project manager must provide cost estimates without having a design concept

B. All of the other alternatives apply are possible based upon the situation

C. The project manager is assigned after the project is defined, and the cost and schedule are approved

D. A clear objective is not provided

E. Oversimplification (underestimating) of the nature of the work occurs

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 204Work authorization forms are needed in order to:

A. Authorize line organizations to charge against the project

B. Develop a structured methodology for release of funds

C. Establish an audit trail

D. All of the other alternatives apply

E. 1) Authorize line organizations to charge against the project and 2)Develop a structured methodology forrelease of funds

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 205Cost management includes processes that are required to maintain financial control of projects. Theseprocesses may include:

A. economic evaluation

B. cost estimating and cost forecasting

C. cost estimating

D. cost forecasting

E. All of the other alternatives apply.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 206Communication plays a major role in:

A. Organizing

Page 67: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Controlling

C. All of the other alternatives apply

D. Directing

E. Planning

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 207A Project with a total funding of $70,000 finished with a BAC value of $60,000.

What term can best describe the difference of $10,000?

A. Management Overhead

B. Management Contingency Reserve

C. Cost Variance

D. Schedule Variance

Answer: BSection: (none)

Explanation/Reference:Explanation:The difference between the Cost Baseline and Funding requirement at Project completion is ManagementContingency Reserve. BAC represents the revised Cost baseline for the project. So Management ContingencyReserve is true.

QUESTION 208You are a project manager for an agricultural supply company. You have just completed and obtained sign-offon the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed youthat a deliverable is missing from the project scope statement. This deliverable is a critical success factor.Which of the following actions should you take?

A. Modify the scope statement to reflect the new deliverable.

B. Modify the scope statement after an approved change request has been received from the stakeholder.

C. Inform the stakeholder that work not stated in the scope statement is excluded from the project.

D. Inform the stakeholder that this deliverable must be included in phase two of this project since sign-off hasalready been obtained.

Answer: BSection: (none)

Explanation/Reference:Explanation:The project scope statement will change throughout the project as change requests are received and approved.Project managers must be certain to discover all deliverables before publishing the project scope statement toprevent situations like the one described in this question.

QUESTION 209

Page 68: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Control chart theory is based on the differentiation of the causes of variations in quality. Variations may beproduced by assignable causes. All of the following are examples of assignable causes except:

A. None of the other alternatives apply (all are examples)

B. differences among materials.

C. differences among machines.

D. differences among workers.

E. differences in each of these factors over time.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 210The basic elements of communication include:

A. Reading, writing and listening

B. Communicator, encoding, message, medium, decoding, receiver, and feedback

C. All of the other alternatives apply

D. Clarity of speech and good listening habits

E. Listening, talking and sign language.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 211Life seems to be going very well for your close friend, a fellow PMP. She has taken a trip to France, bought anew car, and stocked her wine cellar with a half dozen expensive bottles of wine, all within the last six months.After a few cocktails one evening, she tells you her secret. The vendor she's working with on the $4 billionproject she's managing has given her all of these items as gifts. Which of the following should you do? (Choosethe best answer.)

A. You tell your friend these gifts probably aren't appropriate and leave it at that.

B. Your friend doesn't see a problem with accepting these gifts at all. You know this is a conflict of interestsituation and should be reported as a PMP Code of Professional Conduct violation.

C. You and your friend have a long conversation about the gifts, and she decides to return them (with theexception of the trip) and not accept any more gifts in the future.

D. You're happy for your friend and say nothing.

Answer: BSection: (none)

Explanation/Reference:Explanation:This is a conflict of interest situation, and you should report it as a violation of the PMP Code of ProfessionalConduct.

Page 69: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 212All of the following are tools and techniques of the Contract Administration process except for which one?

A. Contract change control system, buyer-conducted performance review, and inspections and audits

B. Records management system and information technology

C. Contract performance information gathering and contract reporting systems

D. Performance reporting, payment system, and claims administration

Answer: CSection: (none)

Explanation/Reference:Explanation:The tools and techniques of the Contract Administration process are contract change control system, buyer-conducted performance review, inspections and audits, performance reporting, payment system, claimsadministration, records management system, and information technology.

QUESTION 213Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance areelements of the:

A. Contracts and administration costing system.

B. Fringe benefits packages.

C. None of the other alternatives apply.

D. Capital budgeting process.

E. Overhead rates.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 214You are the project manger for Xylophone Phonics. This company produces children's software programs thatteach basic reading and math skills. You are ready to assign project roles, responsibilities, and reportingrelationships. Which project Planning process are you working on?

A. Human Resource Acquisition

B. Acquire Staff

C. Human Resource Planning

D. Resource Planning

Answer: CSection: (none)

Explanation/Reference:Explanation:The Human Resource Planning process identifies project resources, documents roles and responsibilities ofproject team members, and documents reporting relationships.

Page 70: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 215The process of Manage Stakeholder Expectations is part of which process?

A. Executing

B. Monitoring and Control

C. Planning

D. QA

Answer: ASection: (none)

Explanation/Reference:Explanation:Manage Stakeholder Expectations is part of Monitoring and Control process.

QUESTION 216Collect Requirements is:

A. Developing a plan from major stakeholders

B. Developing a written scope statement as the basis for future project decisions

C. Planning project milestones

D. Formalizing acceptance of the project scope

Answer: BSection: (none)

Explanation/Reference:Explanation:Collect Requirements: Process of progressively elaborating and documenting the project work that producesthe product of the project

QUESTION 217Which is not one of the triple constraint of a project?

A. Cost

B. Time

C. Resources

D. Scope

Answer: CSection: (none)

Explanation/Reference:Explanation:Projects triple constraints are 1) Scope, 2)Time and 3)Cost

QUESTION 218What is one of the advantages of a functional organization?

Page 71: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. All employees report to two or more managers, but project team members show loyalty to functionalmanagers.

B. All employees report to one manager and have a clear chain of command.

C. Teams are co-located.

D. The organization is focused on projects and project work.

Answer: BSection: (none)

Explanation/Reference:Explanation:Advantages for employees in a functional organization are that they have only one supervisor and a clear chainof command exists.

QUESTION 219The Japanese Quality Control (QC) Circle movement motivated its participants in many ways. Which of thefollowing represents the most important motivation for the QC circle participants?

A. strengthening of relationships between co-workers

B. recognition among co-workers

C. self-improvement

D. improving the performance of the company

E. financial incentives

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 220The methods and techniques for determining the economic costs, the environmental impact, the economicreturns, and the probability for success are called:

A. Bills of materials.

B. Pert charts.

C. Managerial reserves.

D. None of the other alternatives apply

E. Feasibility studies.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 221Which of the following statements is true regarding schedule variances?

A. Schedule variances never impact the schedule.

Page 72: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Schedule variances sometimes impact the schedule.

C. Schedule variances impact scope, which impacts the schedule.

D. Schedule variances always impact the schedule.

Answer: BSection: (none)

Explanation/Reference:Explanation:Schedule variances will sometimes-but not always-impact the schedule. Changes to non-critical path tasks willnot likely impact the schedule, but changes to critical path tasks will always impact the schedule.

QUESTION 222Which is not an example of formal communication?

A. Contract

B. email

C. Project status report

D. Status meeting

Answer: BSection: (none)

Explanation/Reference:Explanation:Communication via email is not considered a formal communication.

QUESTION 223You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525. What is VAC?

A. 25

B. 30

C. 20

D. 70

Answer: ASection: (none)

Explanation/Reference:Explanation:VAC is calculated this way: VAC = BAC - EAC. Therefore, 525 - 500 = 25.

QUESTION 224In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ projectcosts.

A. Increase, increase

B. Decrease, decrease.

C. Increase, decrease.

D. Increase, increase or decrease.

Page 73: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

E. Decrease, increase.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 225Bar charts are most appropriate for:

A. Showing slack time.

B. Comparing actual to planned performance to each activity.

C. All of the other alternatives apply.

D. Showing critical path dependencies.

E. Showing which activities can be rearranged in parallel.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 226All of the following may hinder a person's ability to transmit/receive a message except:

A. Preoccupation

B. Assuming

C. Unfamiliarity with topic

D. Noise

E. Withholding information

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 227The Communications Management Plan should contain the following:

A. Selection of appropriate media to meet specific needs

B. Communications policy

C. All of the other alternatives apply

D. Communications media

E. Reporting channels

Answer: CSection: (none)

Page 74: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 228A project manager believes that the best way to manage is to form a good, harmonious working relationshipwith the team, and high performance will follow. The project manager could be defined as a _____ manager.

A. 1,9

B. 9,1

C. 1,1

D. 9,9

E. 5,5

Answer: ASection: (none)

Explanation/Reference:Explanation: Section: (none)Explanation/Reference:Four types of project leader that are considered best suited to different project circumstances are, imaginativeExplorer (9,9), assertive Driver (9,1), catalyst Coordinator (5,5) and Professional Administrator (1,9) are placedin four quadrants of Focus (X) and Approach (Y) axis of General Personality Characteristics Grid. These valuesof (9,9), (9,1), (1,9) and (5,5) are Blake-Mouton Grid descriptions. (Refer to http://www.maxwideman.com/papers/profiles/general.htm) (1,9) represents Administrator who believes in forming a good, harmoniousworking relationship with the team. Administrator recognizes the need for stability, typically in order to optimizeproductivity through maximizing repetition to the extent possible on a project and to get the work finished.Often, requisite information must be assembled and carefully analyzed, with thought given to the trade-offs andhow conflicts and problems can be resolved and disposed of in advance. Work must be carefully scheduledand procedurized if potential gains are to be realized and "all the pieces are to be carefully put in place".So,Answer A (1,9) the Administrator manager.

QUESTION 229Which involves estimating the cost of individual work items:

A. Analogous estimating

B. Bottom up estimating

C. Computerized

D. Square foot

Answer: BSection: (none)

Explanation/Reference:Explanation:Bottom-up estimating: Estimating the cost of individual work items and then rolling up the costs to arrive at aproject total , more accurate

QUESTION 230You are a project manager for the Swirling Seas Cruises food division. You're considering two different projectsregarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, withexpected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months. Which projectshould you recommend?

Page 75: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. ProjectFish'n for Chips, because the costs on Project Picnic are unknown.

B. Project Picnic, because ProjectFish'n for Chips' payback period is two months longer than Project Picnic's.

C. Project Picnic, because ProjectFish'n for Chips' payback period is four months longer than Project Picnic's.

D. ProjectFish'n for Chips, because its payback period is two months shorter than Project Picnic's.

Answer: BSection: (none)

Explanation/Reference:Explanation:The payback period for Project Fish'n for Chips is eight months. This project will receive $300,000 every threemonths, or $100,000 per month. The $800,000 will be paid back in eight months.

QUESTION 231A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost inprocurement, shipping/freight, storage and loss.

A. Procurement.

B. All of the other alternatives apply.

C. Inventory control.

D. Materials management.

E. Inventory control and Procurement.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 232Mathematical models using linear programming, dynamic, or algorithm models are considered:

A. form of expert judgment

B. project closing method

C. Project selection criteria

D. Project selection methods

Answer: DSection: (none)

Explanation/Reference:Explanation:< li >Mathematical models are one of the methods described in the project selection methods tool andtechnique.< li >These types of models are in use only in certain types of projects and are not going to be used for simplerprojects.

QUESTION 233The purpose of configuration management is to:

A. control change during the production only

Page 76: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. control change throughout the project

C. inform the project manager of changes

D. generate engineering change proposals

E. insure drawings are updated

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 234The project charter is developed by:

A. the customer

B. senior management and the project manager

C. senior management

D. None of the other alternatives apply.

E. the project manager

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 235Lessons learned are most often based upon project historical records. Lessons learned can be used to:

A. See what mistakes others have made

B. All of the other alternatives apply

C. See how others have solved problems

D. Predict trends, highlight problems and identify alternatives

E. Both 1) See what mistakes others have made, and 2) See how others have solved problems

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 236You are a contract project manager for a wholesale flower distribution company. Your project is to develop awebsite for the company that allows retailers to place their flower orders online. You will also provide a separatelink for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower'ssite. This project involves coordinating the parent company, growers, and distributors. You are preparing aperformance review and have the following measurements at hand: PV = 300, AC = 200, and EV = 250. Whatis the CPI of this project?

A. 0.83

Page 77: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. 0.80

C. 1.25

D. 1.5

Answer: CSection: (none)

Explanation/Reference:Explanation:CPI is calculated as follows: EV ÷ AC. In this case, 250 ÷ 200 = 1.25.

QUESTION 237A work breakdown structure is most useful for:

A. determining potential delays

B. developing a cost estimate

C. scheduling the start of tasks

D. identifying individual tasks for a project

E. A and C

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 238You are the project manager for a top-secret software project for an agency of the United States government.Your mission-should you choose to accept it-is to complete the project using internal resources. The reason isthat finding contractors with top-secret clearances takes quite a bit of time, and waiting for clearances wouldjeopardize the implementation date. Your programmers are 80 percent of the way through the programmingand testing work when your agency appoints a new executive director. Slowly but surely your programmers aretaken off this project and reassigned to the executive director's hot new project. Which of the following type ofproject ending is this?

A. Extinction

B. Starvation

C. Addition

D. Integration

Answer: DSection: (none)

Explanation/Reference:Explanation:Integration occurs when resources, equipment, or property are reassigned or redeployed back to theorganization or to another project.

QUESTION 239Define Activities is typically performed by which of the following:

Page 78: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Project Manager who created the WBS

B. Management

C. Project Team Members responsible for the work package

D. Project Stakeholder

Answer: CSection: (none)

Explanation/Reference:Explanation:Define Activities is typically performed by Project Team Members. identify the activities that need to be done tocomplete the project.

QUESTION 240Which of the following is closest to Juran's definition of Quality:

A. conformance to requirements.

B. fitness for use.

C. customer focus.

D. continuous improvement.

E. All of the other alternatives apply.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 241Which of the following MUST NOT performed in project initiation process?

A. identify the requirements.

B. identify business need.

C. create project scope statement.

D. create project charter.

Answer: CSection: (none)

Explanation/Reference:Explanation:project scope statement created during project planning phase.

QUESTION 242You are a project manager for a software manufacturing firm. The project you've just finished created a newsoftware product that is expected to become a number-one seller. All prerelease of software is handled throughthe marketing department. A friend of yours is a certified software instructor. They have asked you for a copy ofthe software prior to the beta release so they can get familiar with it. What is the most appropriate response?

A. Since your friend is certified to teach your company's brand of software, provide them with a copy of thesoftware.

Page 79: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Decline the request since you stand to gain from this transaction by receiving free training.

C. Ask them to sign a nondisclosure agreement before releasing a copy of the software.

D. Decline the request because the software is the intellectual property of the company.

Answer: DSection: (none)

Explanation/Reference:Explanation:The most appropriate response is to deny the request. Software is considered intellectual property and shouldnot be used for personal gain or given to others without prior consent from the organization. This questionstates that the release of the beta software is handled through the marketing department, so you should notgive your friend a copy of the software outside of this process.

QUESTION 243Resource leveling will often affect the project by making it:

A. Shorter.

B. More responsive to customer needs.

C. Longer and more responsive to customer needs.

D. Shorter and more responsive to customer needs

E. Longer

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 244Going from Level 2 to Level 4 in the work breakdown structure will result in

A. None of the other alternatives apply

B. A greater likelihood that something will fall through the cracks

C. Less estimating accuracy

D. Lower status reporting costs

E. Better control of the project

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 245The role of the _____ can be invaluable in problem solving.

A. dominator

B. devils advocate

C. recognition seeker or dominator

Page 80: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. topic jumper

E. recognition seeker

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 246Which of the following must not performed in the project initiation process?

A. Evaluate historical information

B. List down business need

C. List down stakeholders

D. Create scope statement

Answer: DSection: (none)

Explanation/Reference:Explanation:Scope statement generally created in planning phase.All others are done in initiation phase.

QUESTION 247You have assembled your thoughts into a message. As you pass this information to a second party, you aregiving this person your:

A. Input and Data

B. Feedback

C. Data

D. Output

E. Input

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 248The quality management plan documents how the project team will implement the quality policy. It mustaddress all of the following except which one?

A. Continuous process improvement

B. Quality assurance

C. Quality control

D. Quality checklists

Answer: D

Page 81: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:Quality checklists are an output of the Quality Planning process.

QUESTION 249Which quality management tool would be used to determine potential causes of a production problem?

A. run chart.

B. scatter diagram.

C. histogram.

D. control chart.

E. Ishikawa diagram.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 250A project may be defined as _____

A. an integrated approach to managing projects

B. a coordinated undertaking of interrelated activities.

C. a group of activities directed by a project manger over a life cycle

D. All of the other alternatives apply.

E. an undertaking with a defined starting point and defined objectives

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 251You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of anorganization's operating system on 236 servers. You performed this project under contract. You are in theClosing process and know that product verification is for what purpose?

A. To verify that all the work was completed correctly and satisfactorily

B. To evaluate project goals and ensure that the product of the project meets the requirements

C. To verify the goals of the project and ensure that the product of the project is complete

D. To evaluate all the work of the project and compare the results to project scope

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 82: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Product verification is performed by the buyer and examines all the work of the project and verifies that thework was completed correctly and satisfactorily.

QUESTION 252Which of the following is not a cost of non-conformance?

A. maintenance and calibration

B. warranty repairs

C. All of the other alternatives apply.

D. scrap

E. rework

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 253In which of the following types of contracts is it most important for the contractor to maintain control of cost,schedule and scope changes.

A. cost plus incentive fee

B. Cost plus incentive fee and firm fixed price

C. firm fixed price

D. cost plus fixed fee

E. unit price

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 254You are working with XYZ organization. Your senior manager imposed new delivery date which is earlier thanmentioned project deliverables date in scope statement. To whom you are most accountable?

A. customer

B. team member

C. sponsor

D. senior manager

Answer: ASection: (none)

Explanation/Reference:Explanation:The project manager must accountable to customer first.

Page 83: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 255The LEAST effective form of communication for complex situations is:

A. formal

B. verbal - face to face and formal

C. informal

D. written

E. verbal - face to face

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 256If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95percent confidence rating which of the following?

A. The activity will take from 464 to 536 days.

B. The activity will take from 494 to 506 days.

C. The activity will take from 476 to 524 days.

D. The activity will take from 488 to 512 days.

Answer: CSection: (none)

Explanation/Reference:Explanation:There is a 95 percent probability that the work will finish within plus or minus two standard deviations. Theexpected value is 500, and the standard deviation times 2 is 24, so the activity will take from 476 to 524 days.

QUESTION 257You are working on a project that was proceeding well until a manufacturing glitch occurred that requirescorrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketingpeople are absolutely crazy about its potential. The corrective action is canceled, and you continue to producethe product with the newly discovered enhancement. As the project manager, you know that a change hasoccurred to the project scope. Which of the following statements is true?

A. Performance measurement baselines might be affected by scope changes.

B. Project scope change uses workarounds to correct unexpected problems with scope change.

C. Project scope change uses inspection to determine whether change has occurred.

D. Project scope changes do not require CCB approval.

Answer: ASection: (none)

Explanation/Reference:Explanation:A project scope change affects the performance measurement baselines, which might include schedulebaselines and cost baselines.

Page 84: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 258You are managing an internal project where a vice president from the user group is acting as the sponsor. Youhave just been informed by your team that the critical path has slipped by three weeks. You should:

A. See the sponsor after you have evaluated alternatives, recommendations, and performed an impactanalysis

B. Inform your senior management of the problem and tell them that you will get back to them after youassessed the situation

C. Look for someone to blame before you see the sponsor

D. Do nothing until the slippage occurs

E. Immediately inform the sponsor and ask for advice

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 259Parametric estimates are based on variables such as:

A. Project objectives and manpower allocations.

B. Physical characteristics and historical data.

C. Precise measurements and multiple inputs.

D. The WBS and similar projects.

E. Detailed planning and cost restraints.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 260All of the following are true regarding Communications Planning except for which one?

A. Communications requirements analysis, communications technology, and PMIS are tools and techniques ofthis process.

B. It's the only output of the Communications Planning process.

C. It's tightly linked with enterprise environmental factors and organizational influences, and lessons learnedand historical information are two inputs that should get a lot of attention during this process.

D. It should be completed as early in the project phases as possible.

Answer: ASection: (none)

Explanation/Reference:Explanation:Communications requirements analysis and communications technology are the tools and techniques of theCommunications Planning process.

Page 85: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 261The Delphi Method is well-suited for:

A. Decision-making

B. All of the other alternatives apply

C. Decision-making and Forecasting

D. Forecasting

E. Overhead rate estimating

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 262A non-critical path activity is completed in half the time. Then,

A. All of the other alternatives apply.

B. The slack in the path containing this activity will increase.

C. The total cost for this activity has decreased.

D. The critical path is also reduced.

E. Manpower from this activity can be assigned to other activities.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 263Advantages of the functional (hierarchical) form of organization include _____ and creation of technicalcompetence.

A.

B. Single voice to customers

C. High information processing capability

D. Ease of horizontal coordination

E. Clearly defined authority

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 264During your project meeting, a problem was discussed, and a resolution to the problem was reached. Duringthe meeting, the participants started wondering why they thought the problem was such a big issue. Sometimeafter the meeting, you received an email from one of the meeting participants saying they've changed their mind

Page 86: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

about the solution reached in the meeting and need to resurface the problem. The solution reached during theinitial project meeting is a result of which of the following conflict resolution techniques?

A. Forcing

B. Confrontation

C. Storming

D. Smoothing

Answer: DSection: (none)

Explanation/Reference:Explanation:The smoothing technique does not usually result in a permanent solution. The problem is downplayed to makeit seem less important than it is, which makes the problem tend to resurface later.

QUESTION 265Which of the following would most likely increase the accuracy of estimating the project cost?

A. Using historical data.

B. Pricing out the work at lower levels in the work breakdown structure.

C. Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people whohave worked on similar projects."Pass Any Exam. Any Time." - www.actualtests.com 108 PMI PMI-001 Exam

D. Talking to people who have worked on similar projects.

E. 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who haveworked on similar projects, and 3) Using historical data.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 266You are a project manager of Software Product Company. After hired a person you got to know that many ofthis person's ideas were developed by the competing company. Are you going to implement the same ideas?

A. Accept the new ideas.

B. Ask to sign NDA.

C. Ignore the ideas because it may be violation of code of conduct.

D. Tell the person that he should not mention that the ideas came from another company.

Answer: ASection: (none)

Explanation/Reference:Explanation:Unless the employee signed the NDA with his or her previous organization, there is no obligation for him or hernot to share knowledge that was gained while working for the competitor.

Page 87: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 267Risk Event Status is defined as _____ .

A. Both 1) the severity of the consequences, and 2)how likely the event is to occur with risk.

B. (Cost + Benefit + Business Risk) / Insurable Risk.

C. how likely the event is to occur with risk.

D. Risk Probability x Amount At Stake.

E. the severity of the consequences.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 268Which statement is TRUE about Present Value(PV)?

A. The difference in benefit received between a chosen project and a project that was not chosen

B. The interest rate that makes the net present value of all cash flow equal zero

C. The value today of future cash flow

D. The present value of cash inflow less the present value of cash outflow

Answer: CSection: (none)

Explanation/Reference:Explanation:Present Value(PV): The value today of future cash flow. The higher the PV, the better.

QUESTION 269All of the following are tools and techniques of the Performance Reporting process except which one?

A. Performance measurements

B. Information presentation tools

C. Time reporting systems

D. Cost reporting systems

Answer: ASection: (none)

Explanation/Reference:Explanation:The tools and techniques of the Performance Reporting process are information presentation tools,performance information gathering and compilation, status review meetings, time reporting systems, and costreporting systems.

QUESTION 270Most project (and non-project) managers prefer _____ communications.

A. Lateral

Page 88: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Oral

C. Downward

D. Written

E. Upward

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 271Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?

A. Empowerment

B. Self-actualization

C. Belonging

D. Esteem

E. Safety

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 272A project manager believes that modifying the scope of the project may provide added value for the customer.The project manager should:

A. Change the project's objectives

B. Call a meeting of the configuration control board

C. Postpone the modification until a separate enhancement project is funded after this project is completedaccording to the original baseline

D. Change the scope baseline

E. Prepare a variance report

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 273What are the Scope Definition process tools and techniques?

A. Product analysis, alternatives identification, expert judgment, and stakeholder analysis

B. Alternatives identification, stakeholder analysis, and expert judgment

C. Product analysis, cost benefit analysis, alternatives identification, and expert judgment

D. Cost benefit analysis, templates, and expert judgment

Page 89: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:The tools and techniques of the Scope Definition process include product analysis, alternatives identification,expert judgment, and stakeholder analysis.

QUESTION 274All of the following statements about acceptance sampling are true except:

A. Acceptance sampling plans do not directly control the quality of a series of lots; they instead specify the riskof accepting lots of given quality.

B. Acceptance sampling plans are never effective at rejecting nonconforming units as 100 percent inspection,even when the inspection process is very tedious.

C. Acceptance sampling plans are not very effective for inspecting small lots of custom-made products.

D. Acceptance sampling plans are beneficial when the cost of inspection is high and the resulting loss ofpassing nonconforming units is not great.

E. Acceptance sampling plans are necessary when destructive inspections are required.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 275Who is responsible for issuing the project charter?

A. The project sponsor

B. The senior Project Manager

C. The project team

D. The project manager

Answer: ASection: (none)

Explanation/Reference:Explanation:The project sponsor creates and issues the project charter.

QUESTION 276The use of quality circles:

A. provides a quick fix for most quality problems.

B. is particularly effective in overcoming labor/management conflicts.

C. 1) Has proven ineffective in bothJapan and the U.S. and 2) is particularly effective in overcoming labor/management conflicts.

D. has proven ineffective in bothJapan and the U.S.

E. allows workers the opportunity to generate solutions for chronic quality problems.

Page 90: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 277You are a project manager working on gathering requirements and establishing estimates for the project.Which process group are you in?

A. Monitoring and Controlling

B. Initiating

C. Executing

D. Planning

Answer: DSection: (none)

Explanation/Reference:Explanation:The Planning process is where requirements are fleshed out, stakeholders are identified, and estimates onproject costs and time are made.

QUESTION 278You have been assigned to a project that will allow job seekers to fill out applications and submit them via thecompany website. You report to the VP of human resources. You are also responsible for screeningapplications for the information technology division and setting up interviews. The project coordinator has askedfor the latest version of your changes to the online application page for his review. Which organizationalstructure do you work in?

A. Functional organization

B. Balanced matrix organization

C. Weak matrix organization

D. Projectized organization

Answer: CSection: (none)

Explanation/Reference:Explanation:Functional managers who have lots of authority and power working with project coordinators who have minimalauthority and power characterizes a weak matrix organization. Project managers in weak matrix organizationsare sometimes called project coordinators, project leaders, or project expeditors.

QUESTION 279Planning activities such that predetermined resource availability pools are not exceeded is called:

A. Manpower planning.

B. Manpower leveling.

C. Resource leveling.

D. Manpower contingency planning.

Page 91: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

E. Resource limited planning.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 280As project manager, you wish to impose a standard method by which subordinates calculate project costs.Which level of communication should be required for this effort?

A. All of the other alternatives apply.

B. Face-to-face

C. Written

D. Non-verbal

E. Telephone

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 281A line manager who is asked to wear two hats and function as a project manager at the same time is likely toexercise:

A. All of the other alternatives apply]

B. Influence

C. Power

D. Authority and Power

E. Authority

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 282By which process may an unsuccessful supplier seek remedy for unjust awards?

A. None of the other alternatives apply.

B. Contract dispute

C. Bid protest

D. Coffective action

E. Stop work order

Answer: C

Page 92: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:

QUESTION 283The project charter:

A. Establishes that organizational structure with the project.

B. Expresses upper management commitment to the project.

C. Provides that authority by which the project will be run.

D. Specifies overall objectives and timeframe of the project.

E. All of the other alternatives apply.

Answer: ESection: (none)

Explanation/Reference:Explanation:

QUESTION 284If you are the project manager for a new project. You have collected the necessary input information anddelivered the project charter to the stakeholders. What should you do next?

A. Develop the preliminary project scope statement.

B. Get the project charter signed.

C. Start to create project plan

D. Start the initial project planning process.

Answer: BSection: (none)

Explanation/Reference:Explanation:After delivered the project charter to the stakeholders, First thing you have to do get the project charter signed..Project charter is the only authorized document to start project.

QUESTION 285You are a project manager working on a software development project. You've developed the risk managementplan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, andyou implement the response for that risk. Then, another risk occurs as a result of the response youimplemented. What type of risk is this called?

A. Residual risk

B. Mitigated risk

C. Secondary risk

D. Trigger risk

Answer: CSection: (none)

Page 93: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:Secondary risks occur as a result of the implementation of a response to another risk.

QUESTION 286A project manager is assigned to a project which phase of the project?

A. Closing

B. Initiation

C. Estimation

D. Planning

Answer: BSection: (none)

Explanation/Reference:Explanation:In the Initiation phase, the sponsor releases resources to get the project done, and the project manager ischosen.

QUESTION 287Which describes how cost variances will be managed?

A. Cost management plan

B. Cost baseline

C. Cost estimate

D. Chart of accounts

Answer: ASection: (none)

Explanation/Reference:Explanation:Cost management plan describes how cost variances will be managed.

QUESTION 288History has shown that project managers can be trained in a combination of ways. Which method is usuallypreferred by most companies?

A. None of the other alternatives apply

B. Formal education and special course (degreed programs)

C. Experiential learning, on-the-job

D. Professional activities, seminars

E. Individual readings

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 94: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 289Who is responsible for decide project management process for a particular project?

A. Sponsor

B. Project Manager

C. Stakeholders

D. Senior management

Answer: BSection: (none)

Explanation/Reference:Explanation:Project Manager is responsible for decide project management process for a particular project.

QUESTION 290The most common form of written project communication is

A. Bulletin boards

B. All of the other alternatives apply

C. Publications

D. Letters and memos

E. Reports

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 291Which performance measurement tells you what the projected total cost of the project will be at completion?

A. ETC

B. CPI

C. EAC

D. SPI

Answer: CSection: (none)

Explanation/Reference:Explanation:Estimate at completion (EAC) estimates the total cost of the project at completion based on the performance ofthe project to date.

QUESTION 292Your project team consists of 12 people in the same building you're located in, 4 people from the West Coastoffice, 2 people from the Kansas City office, and 6 people from the London office. Your office works differenthours than all the other offices. Additionally, not all of the resources in your building are available at the same

Page 95: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

times during the day. Three of the 12 team members work swing shift hours. You use tools like webconferencing and email to distribute information to the team. Which of the following is true?

A. This question describes resource availability from the Develop Project Team process and informationdistribution methods from the Information Distribution process.

B. This question describes the staffing management plan from the Acquire Project Team process andcommunication skills from the Information Distribution process.

C. This question describes project staff assignments from the Develop Project Team process andcommunication skills from the Information Distribution process.

D. This question describes virtual teams from the Acquire Project Team process and information distributionmethods from the Information Distribution process.

Answer: DSection: (none)

Explanation/Reference:Explanation:Virtual teams are teams that don't necessarily work in the same location or have the same hours but all sharethe goals of the project and have a role on the project. The web conferencing and email references describethe information distribution methods tool and technique of the Information Distribution process.

QUESTION 293You are a project manager for a documentary film company. In light of a recent regional tragedy, the companypresident wants to get a new documentary on the rescue efforts of the heroic rescue teams to air as soon aspossible. She's looking to you to make this documentary the best that has ever been produced in the history ofthis company. She guarantees you free rein to use whatever resources you need to get this project donequickly. However, the best photographer in the company is currently working on another assignment. Which ofthe following is true?

A. The primary constraint is time because the president wants the film done quickly. She told you to get it to airas soon as possible.

B. The primary constraint is quality because the president wants this to be the best film ever produced by thiscompany. She's given you free rein to use whatever resources needed to get the job done.

C. The schedule is the primary constraint. Even though the president has given you free rein on resource use,you assume she didn't mean those actively assigned to projects. The photographer won't be finished foranother three weeks on his current assignment, so schedule adjustments will have to be made.

D. Resources are the primary constraint. Even though the president has given you free rein on resource use,you assume she didn't mean those actively assigned to projects.

Answer: BSection: (none)

Explanation/Reference:Explanation:The primary constraint is quality. If you made the assumption as stated in "Resources are the primaryconstraint. Even though the president has given you free rein on resource use, you assume she didn't meanthose actively assigned to projects.", you assumed incorrectly. Clarify these assumptions with your stakeholdersand project sponsors. This applies to "The schedule is the primary constraint. Even though the president hasgiven you free rein on resource use, you assume she didn't mean those actively assigned to projects. Thephotographer won't be finished for another three weeks on his current assignment, so schedule adjustmentswill have to be made." as well.

QUESTION 294Which may be employed to shorten a schedule without changing the scope of the task?

Page 96: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Alter to task priorities.

B. Releasing resources earlier from tasks which were scheduled with a late start.

C. Fast tracking or Crashing

D. Fast tracking.

E. Crashing

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 295Surveys have shown that the primary skill needed to be a project manager is communication skill. The typicalproject manager spends approximately ______percent of his or her time communicating.

A. 40-50

B. 50-60

C. 90-95

D. 75-90

E. 60-75

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 296A computer tape which contains historical project information is called ____ tape.

A. Database

B. Archive.

C. Lessons learned.

D. Baseline.

E. Life cycle summary.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 297Power games, withholding information, and hidden agendas are examples of-.

A. mixed messages

B. indirect communication

C. noise

Page 97: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. communication barriers

E. All of the other alternatives apply

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 298Your team is split between two buildings on either side of town. As a result, the team isn't very cohesivebecause the members don't know each other very well. The team is still in the storming stage because of theseparation issues. Which of the following should you consider?

A. Training

B. Co-location

C. Corrective action

D. Conflict resolution

Answer: BSection: (none)

Explanation/Reference:Explanation:Co-location would bring your team members together in the same location and allow them to function moreefficiently as a team. At a minimum, team members meeting in a common room, such as a war room, for allteam meetings would bring the team closer together.

QUESTION 299Risk event is the description of what may happen to the _____ of the project.

A. Budget

B. harm

C. Schedule

D. Manager

Answer: BSection: (none)

Explanation/Reference:Explanation:Risk event is the description of what may happen to the harm of the project.

QUESTION 300Which of the following is NOT part of stakeholder's management?

A. Identify stakeholder's need

B. make sure all the stakeholders are in project plan

C. Identify stakeholders

D. make sure all the stakeholders are in communication plan

Page 98: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:Stakeholders are NOT in project plan.

Topic 2, Volume B

QUESTION 301On what is project baseline development established?

A. Approved product requirements

B. Estimated project cost and schedule

C. Actual project cost and schedule

D. Revised project cost and schedule

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 302Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangiblecomponents of each deliverable are all part of which of the following?

A. Work breakdown structure

B. Organizational breakdown structure

C. Resource breakdown structure

D. Bill of materials

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 303What is the definition of project plan execution?

A. Integrating all planned activities.

B. Performing the activities included in the plan.

C. Developing and maintaining the plan.

D. Execution of deliverables.

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 99: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 304What is a tool to improve team performance?

A. Staffing plan

B. External feedback

C. Performance reports

D. Co-Location

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 305Which type of analysis is used to develop the communications management plan?

A. Product

B. Cost benefit

C. Stakeholder

D. Research

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 306Information distribution involves making needed information available to project stakeholders in a timelymanner. What is an output from information distribution?

A. Earned value analysis

B. Trend analysis

C. Project records

D. Performance reviews

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 307Which type of analysis is used to examine project results through time to determine if performance is improvingor deteriorating?

A. Control chart

B. Earned value

Page 100: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. Variance

D. Trend

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 308You are assigned to implement the project control plan. What should you do to ensure the plan is effective andcurrent?

A. Perform periodic project performance reviews.

B. Identify quality project standards.

C. Follow ISO 9000 quality standards

D. Complete the quality control checklist.

Answer: ASection: (none)

Explanation/Reference:Explanation: The document control plan is an outline or guide on how physical or virtual documents will bemanaged throughout the life of the project. It provides a road map for tracking documents and for adding,archiving, and removing new documentation from the process.

QUESTION 309Which of the following is an example of a risk symptom?

A. Failure to meet intermediate milestones

B. Force of nature, such as a flood

C. Risk threshold target

D. Crashing front loading or fast tracking

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 310During what process is the quality policy determined?

A. Initiating

B. Executing

C. Planning

D. Controlling

Answer: CSection: (none)

Page 101: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 311What is one of the MAJOR outputs of activity sequencing?

A. Responsibility assignment matrix

B. Work breakdown structure update

C. Project network diagram

D. Mandatory dependencies list

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 312Scope verification is PRIMARILY concerned with which of the following?

A. Acceptance of the work deliverables.

B. Accuracy of the work deliverables.

C. Approval of the scope statement.

D. Accuracy of the work breakdown structure.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 313Which of the following is an example of contract administration?

A. Negotiating the contract

B. Authorizing contractor work

C. Developing the statement of work

D. Establishing evaluation criteria

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 314Who MUST know when a risk event occurs so that a response can be implemented?

A. Customers

B. Project sponsors

Page 102: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. Project management team

D. Insurance claims department

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 315A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, theactual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

A. -$700

B. -$200

C. +$200

D. +$500

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 316How is quality control performed?

A. By identifying quality standards that are relevant to the project and determining how to satisfy them.

B. By monitoring specific project results in compliance with relevant quality standards and determiningcorrective actions as needed.

C. By ensuring that the entire project team has been adequately trained in quality assurance processes.

D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformanceto quality standards.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 317As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total projectcost. You should calculate the forecast using which of the following methods?

A. BAC

B. EAC

C. ETC

D. WBS

Page 103: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 318How is scheduled variance calculated using the earned value technique?

A. EV less AC

B. AC less PV

C. EV less PV

D. AC less EV

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 319The project management processes presented in the PMBOK Guide should:

A. Always be applied uniformly

B. Be selected as appropriate by the sponsor

C. Be selected as appropriate by the project team

D. Be applied based on ISO guidelines.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 320Who is responsible for determining which processes from the Process Groups will be employed and who will beperforming them?

Page 104: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Project sponsor and project manager

B. Project sponsor and functional manager

C. Project manager and project team

D. Project team and functional manager

Answer: CSection: (none)

Explanation/Reference:Explanation: The project management processes are presented as discrete elements with well- definedinterfaces. However, in practice they overlap and interact in ways that are not completely detailed here. Mostexperienced project management practitioners recognize there is more than one way to manage a project. Thespecifics for a project are defined as objectives that must be accomplished based on complexity, risk, size, timeframe, project team's experience, access to resources, amount of historical information, the organization'sproject management maturity, and industry and application area. The required Process Groups and theirconstituent processes are guides to apply appropriate project management knowledge and skills during theproject. In addition, the application of the project management processes to a project is iterative and manyprocesses are repeated and revised during the project. The project manager and the project team areresponsible for determining what processes from the Process Groups will be employed, by whom, and thedegree of rigor that will be applied to the execution of those processes to achieve the desired project objective.

QUESTION 321Which of the following processes is necessary to ensure that the project employs all processes needed to meetits requirements?

A. Perform Quality Control

B. Quality Policy

C. Perform Quality Assurance

D. Quality Planning

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 322Which process occurs within the Monitoring and Controlling Process Group?

A. Cost Control

B. Quality Planning

C. Quantitative Risk Analysis

D. Cost Budgeting

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 323The Define Scope process is in which of the following process groups?

Page 105: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Initiating

B. Planning

C. Monitoring & Controlling

D. Executing

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 324Which activity is an input to the select sellers process?

A. Organizational process assets

B. Resource availability

C. Change control process

D. Team performance assessment

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 325What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A. Pareto

B. Ishikawa

C. Shewart-Deming

D. Delphi

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 326Which of the following methods is a project selection technique?

A. Flowcharting

B. Earned value

C. Cost-benefit analysis

D. Pareto analysis

Answer: CSection: (none)

Page 106: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation: Selection MethodsThere are various project selection methods practiced by the modern businessorganizations. These methods have different features and characteristics. Therefore, each selection method isbest for different organizations. Although there are many differences between these project selection methods,usually the underlying concepts and principles are the same.Following is an illustration of two of such methods (Benefit Measurement and Constrained Optimizationmethods).

As the value of one project would need to be compared against the other projects, you could use the benefitmeasurement methods. This could include various techniques, of which the following are the most common.

· You and your team could come up with certain criteria that you want your ideal project objectives to meet. Youcould then give each project scores based on how they rate in each of these criteria, and then choose theproject with the highest score.· When it comes to the Discounted Cash flow method, the future value of a project is ascertained byconsidering the present value and the interest earned on the money. The higher the present value of theproject, the better it would be for your organization. · The rate of return received from the money is what isknown as the IRR. Here again, you need to be looking for a high rate of return from the project.

The mathematical approach is commonly used for larger projects. The constrained optimization methodsrequire several calculations in order to decide on whether or not a project should be rejected.

Cost-benefit analysis is used by several organizations to assist them to make their selections. Going by thismethod, you would have to consider all the positive aspects of the project, which is the benefits, and thendeduct the negative aspects (or the costs) from the benefits. Based on the results you receive for differentprojects, you could choose which option would be the most viable and financially rewarding.

These benefits and costs need to be carefully considered and quantified in order to arrive at a properconclusion. Questions that you may want to consider asking are in the selection process are:

1. Would this decision help me to increase organizational value in the long run?2. How long will the equipment last for?3. Would I be able to cut down on costs as I go along?

In addition to these methods, you could also consider Choosing based on opportunity cost - When choosingany project, you would need to keep in mind the profits that you would make if you do decide to go ahead withthe project.Profit optimization is therefore the ultimate goal. You need to consider the difference between the profits of the

Page 107: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

project you are primarily interested in, and the next best alternative.

QUESTION 327While implementing an approved change, a critical defect was introduced. Removing the defect will delay theproduct delivery. What is the MOST appropriate approach to managing this situation?

A. Utilize the change control process.

B. Crash the schedule to fix the defect.

C. Leave the defect in and work around it.

D. Fast-track the remaining development.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 328Which tool is used to develop technical details within the project management plan?

A. Expert Judgment

B. Project Management Methodology

C. Project Management Information

D. Project Selection Methods

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 329Which of the following are outputs of the Monitor and Control Project Work process?

A. Requested changes, forecasts, recommended corrective actions

B. Forecasts, resources plan, bottom up estimating

C. Recommended corrective actions, cost baseline, forecasts

D. Requested changes, recommended corrective actions, project constraints

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 330Which tool or technique measures performance of the project as it moves from project initiation through projectclosure?

A. Resource leveling

Page 108: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Parametric measuring

C. Pareto chart

D. Earned value

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 331An input required to develop a preliminary project scope statement is:

A. Organizational Structure

B. Organizational Process Assets

C. Organizational Matrix

D. Organizational Breakdown Structures

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 332The product scope description is used to:

A. Gain stakeholders' support for the project.

B. Document the characteristics of the product.

C. Describe the project in great detail.

D. Formally authorize the project.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 333What are the identified risks for doing excessive decomposition in a WBS?

A. Insufficient project funding and disqualification of sellers

B. Insufficient project funding and ineffective use of resources

C. Disqualification of sellers and non-productive management efforts

D. Non-productive management effort and inefficient use of resources

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 109: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 334Which of the following techniques is used during Control Scope?

A. Cost-Benefit Analysis

B. Variance Analysis

C. Reserve Analysis

D. Stakeholder Analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 335Which is the document that presents a hierarchical project organization?

A. WBS

B. CPI

C. OBS

D. BOM

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 336Which of the following inputs is required for the WBS creation?

A. Project Quality Plan

B. Project Schedule Network

C. Project Management Software

D. Project Scope Management Plan

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 337Which of the following are inputs to Activity Definition?

A. Project Scope Statement and Work Breakdown Structure

B. Activity list and Arrow Diagram

C. Change Requests Lists and Organizational Process Assets

Page 110: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Project Management Plan and Resource Availability

Answer: ASection: (none)

Explanation/Reference:Explanation:Activity definition refers to the process of parsing a project into a number of individual tasks which must becompleted before the deliverables can be considered completed. Activity definitions rely on a number of specificinput processes. These include enterprise environmental factors, organizational process assets, the projectscope statement, the work breakdown structure, the WBS dictionary, the project management plan (whichconsists of the project scope management plan and the schedule management plan). Through use of theseinputs, the activities that will need to ultimately be completed in order to compete all of the project objectivescan be readily defined, and the activity definition can be further accomplished through the utilization of anumber of tools and techniques including decomposition, templates, rolling wave planning, expert judgment,and planning components. The four ultimate outputs of the activity definition process are the activity list, theresulting activity attributes, all requested changes, and any milestones. This term is defined in the 3rd edition ofthe PMBOK but not in the 4th.

QUESTION 338Activity resource requirements and resource breakdown structure are outputs from what Project TimeManagement process?

A. Schedule Control

B. Activity Definition

C. Schedule Development

D. Activity Resource Estimating

Answer: DSection: (none)

Explanation/Reference:Explanation:Activity Resource Estimate Assumptions and Breakdown StructuresIn the Estimate Activity Resources process,the key output is activity resource requirements. These requirements describe the types and quantities ofresources needed for each project activity.Once you know what resources you need, you can begin to estimatethe time each activity will take to complete. In this way, the activity resource requirements list generated by theEstimate Activity Resources process become inputs for the Estimate Activity Durations process. Activityresource requirements listThe activity resource requirements list identifies, for tracking purposes, the activity'scode in the work breakdown structure, as well as its name. Vital to generating the project schedule, it details theresources that you've estimated you need to complete the activity, and addresses.

Resource description - The Resource description column lists each type of resource that is required for theactivity. This includes human resources, materials, and facilities. Number required - The Number requiredcolumn identifies the quantity required of each resource. This value can be specified in any measurement unit,such as hours, days, or physical number of units required.Resource assumptions - Resource assumptions are important factors to consider when devising the projectschedule. Any relevant assumptions about the resource can be included, for example resource availability,skills, or quality.Resource availability - The Resource availability column specifies when each resource can be used. This is vitalinformation for putting together the project schedule. Resource dependencies - The Resource dependenciescolumn identifies factors that may affect the availability of resources. It's important to identify dependencieswhen devising the project schedule because any change in an activity that has a dependency can affect theproject timeline.The final row of the activity resource requirements list identifies the total resources needed forthe activity. The resource totals are important in project scheduling as a base from which to calculate theduration of the activity.

Page 111: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Resource Assumptions - It's important to record resource assumptions, as they can help during different stagesof a project. Select each project stage to find out how resource assumptions can help.Monitoring - Recorded assumptions can affect performance monitoring. For example, if a particular task seemsto be taking too long, looking at the assumptions can help you identify the problem.Controlling - Recorded assumptions can also help you control performance. Having used the assumptions toidentify a problem, you can now make performance adjustments so that the project can run more efficiently.Closing - Recorded assumptions can provide insights during post-project assessments at the closing stage. Forexample, if you had made incorrect assumptions about staff capabilities, looking at the assumptions helps youunderstand what went wrong. This can then be recorded in the lessons learned file for the project.Failure torecord assumptions can also have an impact during the Monitor and Control Project Work process.Resource breakdown structuresAlong with the activity resource requirements list, there's one more main outputof the Estimate Activity Resources process - the resource breakdown structure.The resource breakdownstructure provides a hierarchical diagram of the resources required for a project. This structure is visuallysimple, showing resource information at a glance breaks resources into categories and resource types helpsyou to organize a project schedule and report on resource utilization information.Although they look similar, a resource breakdown structure is not the same as a work breakdown structure.A work breakdown structure, or WBS, decomposes a project into manageable units of work. Elements in aWBS include project phases, tasks, sub-tasks, and work packages. These represent all the activities in aproject.Project document updatesThe Estimate Activity Resources process concludes with project document updates -the final output of the process. Initially, various project documents are used as inputs for the process. Now thatresource estimation is complete, new information may have come to light. For this reason, you may need toupdate documents so they reflect the latest project information.In the process of estimating resource requirements and creating the resource breakdown structure, it's oftennecessary to add or delete schedule activities that appear in the activity list.The activity changes have asubsequent effect on activity attributes and resource calendars. Because project activities have changed, youneed to document those changes by updating the descriptions of activities and the availability of relevantresources. The first output of the Estimate Activity Resources process is an activity resource requirements list.It's important to record any assumptions you've made about resources in this list, for use in monitoring andcontrolling project work, and in post-project assessments. A second output of the process is the resourcebreakdown structure. This is a hierarchical diagram that shows the resources required for the project in avisually simple way. It groups resources by category, and can be used for organizing and reporting onresources. The final output of the process is updates to relevant project documents, such as the activity list,activity attributes, and resource calendars.

QUESTION 339Project scope statement and resource calendars are inputs to what Project Time Management process?

A. Activity Sequencing

B. Activity Resource Estimating

C. Schedule Development

D. Schedule Control

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 340Which of the following tools or techniques is used for Estimate Activity Duration?

A. Critical path

B. Rolling Wave

Page 112: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. PDM

D. Parametric

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 341Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

A. Analogous Estimating

B. Expert Judgment

C. Optimistic Estimates

D. Reserve Analysis

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 342Which of the following schedule network analysis techniques is applied when a critical path method calculationhas been completed and resources availability is critical?

A. Applying calendars

B. Resource Leveling

C. Resource Planning

D. Resource Conflict Management

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 343Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or anyperformance status to stakeholders?

A. Performance organizations

B. Schedule baselines

C. Performance measurements

D. Change requests

Answer: CSection: (none)

Explanation/Reference:

Page 113: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 344Which technique is utilized in the Schedule Control process?

A. Performance Measure

B. Baseline Schedule

C. Schedule Comparison

D. Variance Analysis

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 345Cost baseline is an output of which of the following processes?

A. Cost Control

B. Cost Budgeting

C. Cost Estimating

D. Cost Planning

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 346Analogous Cost Estimating relies on which of the following techniques?

A. Expert Judgment

B. Project Management Software

C. Vendor Bid Analysis

D. Reserve Analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 347The project budget is set at $150,000. The project duration is planned to be one year. At the completion ofWeek 16 of the project, the following information is collected:

Actual cost = $50,000

Plan cost = $45,000

Page 114: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Earned value = $40,000

What is the cost performance index?

A. 0.80

B. 0.89

C. 1.13

D. 1.25

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 348The PV is $1000, EV is $2000 and AC is $1500. What is CPI?

A. 1.33

B. 2.00

C. 0.75

D. 0.5

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 349At the end of the project, what will be the value of SV?

A. Positive

B. Zero

C. Negative

D. Greater than one

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 350Which is one of the determining factors used to calculate CPI?

A. EV

B. SPI

C. PV

Page 115: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. ETC

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 351Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?

A. -$8,000

B. -$2,000

C. $2,000

D. $8,000

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 352What does a CPI value greater than 1.0 indicate?

A. Cost right at the estimated value

B. Cost under the estimated value

C. Cost right at the actual value

D. Cost over the estimated value

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 353Which type of tool would be used for the quality planning activity?

A. Schedule Analysis

B. Checklist Analysis

C. Assumption Analysis

D. Cost-Benefit Analysis

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 116: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 354Another name for an Ishikawa diagram is:

A. Cause and effect diagram

B. Control Chart

C. Flowchart

D. Histogram

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 355Which type of control tool identifies whether or not a process has a predictable performance?

A. Cause and effect diagram

B. Control Charts

C. Pareto Chart

D. Histogram

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 356Which quality control technique illustrates the 80/20 Principle?

A. Ishikawa diagram

B. Control Chart

C. Run Chart

D. Pareto Chart

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 357Which of the following is an input to Develop Human Resource Plan?

A. Team performance assessment

B. Roles and responsibilities

C. Staffing management plan

D. Enterprise environmental factors

Page 117: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 358Which of the following is an input to the Qualitative Risk Analysis process?

A. Risk register

B. Risk data quality assessment

C. Risk categorization

D. Risk urgency

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 359Which technique is commonly used for the Quantitative Risk Analysis activity?

A. Brainstorming

B. Strategies for Opportunities

C. Decision Tree Analysis

D. Risk Data Quality Assessment

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 360Which of the following strategies is used to deal with risks that may have a negative impact on projectobjectives?

A. Exploit

B. Share

C. Enhance

D. Transfer

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 361

Page 118: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Which of the following is a strategy to deal with positive risks or opportunities?

A. Mitigate

B. Transfer

C. Exploit

D. Avoid

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 362A weighting system is a tool for which area of procurement?

A. Plan contracting

B. Request seller responses

C. Select sellers

D. Plan purchase and acquisition

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 363Project contracts generally fall into which of the following three broad categories?

A. Fixed-price, cost reimbursable, time and materials

B. Make-or-buy, margin analysis, fixed-price

C. Time and materials, fixed-price, margin analysis

D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 364Which of the following choices is a contract closure tool or technique?

A. Contract plan

B. Procurement plan

C. Closure process

D. Procurement audits

Answer: D

Page 119: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:

QUESTION 365Which of the following is a project constraint?

A. Twenty-five percent staff turnover is expected.

B. The technology to be used is cutting-edge.

C. Project leadership may change due to volatile political environment.

D. The product is needed in 250 days.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 366A Project Management Office (PMO) manages a number of aspects, including what?

A. Project scope, schedule, cost, and quality of the products of the work packages

B. Central coordinator of communication management across projects, and for the delivery of specific projectobjectives, organization opportunity assessment

C. Assigns project resources to best meet project objectives

D. Overall risk, overall opportunity and interdependencies among projects

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 367Which of the following correctly explains the term "progressive elaboration"?

A. Changing project specifications continuously

B. Elaborate tracking of the project progress

C. Elaborate tracking of the project specifications with a change control system

D. Project specifications becoming more explicit and detailed as the project progresses

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 368What is the function of a Project Management Office (PMO)?

Page 120: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tiedto the parent organizations' or the client's overall business objectives.

B. To coordinate and manage the procurement of projects relevant to the parent organization's businessobjectives and to administer the project charters accordingly.

C. To administer performance reviews for the project manager and the project team members and to handleany personnel and payroll issues.

D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of thework packages.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 369A project manager is responsible for managing which of the following at the project level?

A. Methodology

B. Standards

C. Constraints

D. Interdependencies

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 370Company A is launching a new communications satellite system. Resource B was assigned combined projectsof design, construction, integration, and launch of the satellite.

Resource B's role is that of a:

A. Project manager

B. Portfolio manager

C. Work breakdown manager

D. Program manager

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 371Which of the following defines a characteristic of a project?

A. Repetitive

Page 121: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Unique

C. No outcome

D. Permanent

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 372Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:

A. process groups.

B. phase gates.

C. knowledge areas.

D. project phases.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 373Which of the following is the definition of a project?

A. Temporary endeavor undertaken to create a temporary business process or product

B. Temporary endeavor undertaken to create a unique product, service, or result

C. Permanent endeavor that produces repetitive outputs

D. Temporary endeavor that produces repetitive outputs

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 374The Project Management Body of Knowledge (PMBOK Guide) should be considered as a:

A. guide to project management processes, tools and techniques.

B. methodology for managing projects.

C. guide for project, portfolio and program management.

D. standard for project, portfolio and program management.

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 122: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 375Which of the following is a Process Group?

A. Scoping

B. Budgeting

C. Closing

D. Quality

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 376In which type of organizational structure are staff members grouped by specialty?

A. Functional

B. Projectized

C. Matrix

D. Balanced

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 377Which of the following statements best describes the influence of stakeholders and the cost of changes asproject time advances?

A. The influence of the stakeholders increases, the cost of changes increases.

B. The influence of the stakeholders decreases, the cost of changes increases.

C. The influence of the stakeholders increases, the cost of changes decreases.

D. The influence of the stakeholders decreases, the cost of changes decreases.

Answer: BSection: (none)

Explanation/Reference:Explanation: Explanations: Stakeholders and changes versus time in the Project Life Cycle There are lots ofcommon features regarding project life cycles:· Most stages of the project follow one after the other and in many cases could be described in technical way.· Expenditures and personnel engaged in the task are quite cheap at the beginning of the project, rise in themiddle phase and fall significantly in the final stage. The Picture below shows exactly the described model.

Page 123: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

· At the beginning of the project - in initial stage the risk of failure and not to meet your goals is very high. Whenthis crucial period is over the project comes into an intermediate phase where the situation is more stable andpredictable.· Stakeholders have a big influence for the project's product in many technical aspects, costs etc. at thebeginning of its life cycle. However their impact become lower within duration of the project and cost of changesand other corrections - which are low in initial phase rise considerably as the project continues. The Picturebelow demonstrates clearly this situation.

In our opinion lots of project life cycles have many similar characteristics but few of them are the same. Forexample some projects can consist of five stages, others with ten or more? Depend on complexity and durationof the project. One institution's hardware testing can have one individual testing stage whereas anotherorganization can have more phases for this task like: general and detailed testing, error correction, compatibilitywith different computers etc. Separate life cycles can also cover these subprojects for instance: one team ofengineers can analysis and look for any defects of the product and the other team can simultaneously checkcompatibility with other devices.

Page 124: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

In conclusion we recommend you to deal with every project separately and especially at big and complexenterprises treat every phase as subproject with an individual life cycle.

QUESTION 378Projects can be divided into phases to provide better management control. Collectively, what are these phasesknown as?

A. Complete project phase

B. Project life

C. The project life cycle

D. Project cycle

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 379In an organization with a projectized organizational structure, who controls the project budget?

A. Functional manager

B. Project manager

C. Program manager

D. Project management office

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 380At which point of the project is the uncertainty the highest and the risk of failing the greatest

A. Final phase of the project

B. Start of the project

C. End of the project

D. Midpoint of the project

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 381When do stakeholders have the greatest influence?

A. At the start of the project

Page 125: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. At the end of the project

C. During execution

D. Stakeholders have constant influence

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 382Which of the following provides a comprehensive and consistent method of controlling the project and ensuringits success?

A. Stakeholder management

B. Monitoring and controlling

C. Project governance

D. Project management methodology

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 383Company A is delivering a product in three parts. The contract allows for the parts to be delivered either oneafter the other or at the same time.

Which type of project phasing will allow for the most flexibility in delivering the full product when productrequirements are subject to rapid change?

A. Sequencing the delivery phases one after the other

B. Overlapping the delivery phases

C. Delivering the products iteratively

D. Delivering all of the product at the same time

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 384In which type of organization does a project manager have a moderate-to-high resource availability?

A. Functional

B. Weak

C. Balanced

D. Strong

Page 126: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 385Which stakeholder is responsible for managing related projects in a coordinated way?

A. Sponsor

B. Portfolio manager

C. Program manager

D. Project manager

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 386In which of the following organizational structures does the project manager have full authority on a project?

A. Functional

B. Strong matrix

C. Balanced matrix

D. Projectized

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 387What are three basic types of project phase-to-phase relationships?

A. Sequential, Overlapping, Non-overlapping

B. Sequential, Iterative, Overlapping

C. Sequential, Non-overlapping, Iterative

D. Iterative, Overlapping, Non-overlapping

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 388Which is a true statement regarding project governance?

Page 127: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Project governance approach must be described in the project management plan.

B. Project governance is independent of the organization or program sponsoring it.

C. Once a project has begun, it is not necessary to formally initiate each project phase.

D. Review of project performance and key deliverables is not required for each project phase.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 389A project manager has limited authority in which type of organizational structure?

A. Weak matrix

B. Functional

C. Balanced matrix

D. Projectized

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 390Which of the following is an input to direct and manage project execution?

A. Requested changes

B. Approved preventive action

C. Work performance information

D. Implemented defect repair

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 391Who selects the appropriate processes for a project?

A. Project stakeholders

B. Project sponsor and project stakeholder

C. Project manager and project team

D. Project manager and project sponsor

Answer: CSection: (none)

Page 128: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 392A project becomes officially authorized when which of the following occurs?

A. Project manager is appointed

B. Stakeholders approve the project

C. Project charter is approved

D. Project sponsor approves the project

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 393How is the process of collecting requirements defined?

A. Defining and documenting project sponsors' needs to meet the project objectives

B. Defining and documenting stakeholders' needs to meet the project objectives

C. Defining and documenting the project teams' needs to meet the project objectives

D. Defining and documenting the project needs to meet the project objectives

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 394Monitor and control project work is a process of which of the following knowledge areas?

A. Project risk management

B. Project scope management

C. Project time management

D. Project integration management

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 395Which process group can be performed outside the project's scope of control?

A. Planning

Page 129: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Monitoring and Control

C. Closing

D. Initiating

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 396The procurement document is an input to which of the following processes?

A. Develop Project Management Plan

B. Develop Schedule

C. Identify Stakeholders

D. Determine Budget

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 397Which of the following is involved in the initiation process group?

A. Develop Project Management Plan

B. Identify Stakeholders

C. Plan Communications

D. Collect Requirements

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 398Which of the following is defined by a project's life cycle and varies by application area?

A. Product

B. Product-oriented processes

C. Project management process groups

D. Project-oriented processes

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 130: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 399How many knowledge areas are there according to PMBOK Guide?

A. 5

B. 8

C. 9

D. 12

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 400Which of the following must be taken into account for every process, even if they are not explicitly listed asinputs in the process specifications?

A. Organizational processes and procedures and enterprise environmental factors

B. Organizational processes and procedures and corporate knowledge base

C. Organizational process assets and enterprise environmental factors

D. Corporate knowledge base and enterprise environmental factors

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 401Perform quality assurance belongs to which of the following process groups?

A. Planning

B. Executing

C. Monitoring and Control

D. Closing

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 402A project team is in which of the following processes when they finalize all activities across all of themanagement process groups to formally complete the project?

A. Closing

B. Executing

Page 131: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. Monitoring and Controlling

D. Planning

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 403Which process group defines the course of action required to attain the objectives that the project wasundertaken to achieve?

A. Initiating

B. Executing

C. Planning

D. Monitoring and Controlling

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 404How many process groups are there according to the PMBOK Guide?

A. 5

B. 9

C. 10

D. 12

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 405The Monitoring and Controlling process group contains which of the following processes?

A. Plan Quality

B. Perform Quality Assurance

C. Perform Quality Control

D. Identify Stakeholders

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 132: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 406Which process group establishes the total scope of a project?

A. Initiating

B. Planning

C. Monitoring and Controlling

D. Executing

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 407Who must accept the end product for a project to be considered closed?

A. Project team

B. Project manager

C. Project management office

D. Customer or sponsor

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 408Manage Project Team belongs to which knowledge area?

A. Project Integration Management

B. Project Time Management

C. Project Procurement Management

D. Project Human Resource Management

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 409Where are product requirements and characteristics documented?

A. Product scope description

B. Project charter

C. Preliminary project scope statement

Page 133: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Communications management plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 410What are the formal and informal policies, procedures, and guidelines that could impact how the project'sscope is managed?

A. Organizational process assets

B. Enterprise environmental factors

C. Project management processes

D. Project scope management plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 411Which of the following is an input to the Direct and Manage Project Execution Process?

A. Approved corrective actions

B. Approved contract documentation

C. Work performance information

D. Rejected change requests

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 412Which of the following consists of the detailed project scope statement and its associated WBS and WBSdictionary?

A. Scope plan

B. Product scope

C. Scope management plan

D. Scope baseline

Answer: DSection: (none)

Explanation/Reference:Explanation:

Page 134: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 413What scope definition technique is used to generate different approaches to execute and perform the work ofthe project?

A. Build vs. buy

B. Expert judgment

C. Alternatives identification

D. Product analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 414The scope management plan is a subsidiary of which project document?

A. Schedule management plan

B. Project management plan

C. Quality management plan

D. Resource management plan

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 415What type of project structure is a hierarchically organized depiction of the resources by type?

A. Organizational Breakdown Structure (OBS)

B. Resource Breakdown Structure (RBS)

C. Work Breakdown Structure (WBS)

D. Project Breakdown Structure (PBS)

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 416What causes replanning of the project scope?

A. Requested changes

B. Project scope statement changes

C. Variance analysis

Page 135: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Approved change requests

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 417Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A. WBS directory

B. Activity list

C. WBS

D. Project schedule

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 418What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the projectobjectives and create the required deliverables?

A. Organizational Breakdown Structure (OBS)

B. Work Performance Information

C. Work Package

D. Work Breakdown Structure (WBS)

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 419What component of the project scope definition defines project exclusions?

A. Project boundaries

B. Project constraints

C. Project assumptions

D. Project objectives

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 136: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 420What tool and technique is used to determine whether work and deliverables meet requirements and productacceptance criteria?

A. Decomposition

B. Benchmarking

C. Inspection

D. Checklist analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 421Which of the following is an output of Define Scope?

A. Project document updates

B. Project management plan

C. Scope baseline

D. Product analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 422What is an output of Control Scope?

A. Accepted deliverables

B. Work performance measurements

C. Requirements documentation

D. Work performance information

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 423The decomposition technique is used to do which of the following?

A. Subdivide the estimated costs of individual activities

B. Subdivide project deliverables and project work into smaller, more manageable components

C. Relate the work packages to the performing organizational units

Page 137: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Shorten the project schedule duration and the amount of resources needed

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 424A project manager needs the project team to make a group decision. Which of the following is a method thatcan be used to reach a group decision?

A. Expert judgment

B. Majority

C. SWOT analysis

D. Brainstorming

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 425Decomposition is a tool and technique used in which of the following?

A. Define Scope and Define Activities

B. Collect Requirements and Estimate Activity Resources

C. Create WBS and Define Activities

D. Create WBS and Estimate Activity Duration

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 426Which of the following is a tool or technique of the Collect Requirements process?

A. Group decision making techniques

B. Project management information system

C. Alternative identification

D. Communication requirement analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 138: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 427Which of the following is an input to Collect Requirements?

A. Stakeholder register

B. Requirements documentation

C. Prototypes

D. Organizational process assets

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 428The use of group creativity techniques as a tool and technique is done in which of the following processes?

A. Plan Quality

B. Collect Requirements

C. Define Scope

D. Perform Quality Control

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 429Which is an input to the Collect Requirements process?

A. Requirement documentation

B. Organizational process assets

C. Requirements management plan

D. Stakeholder register

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 430Which of the following can be used to track the requirements throughout the project life cycle?

A. Requirements traceability matrix

B. Scope management plan

C. Project charter

D. Work breakdown structure

Page 139: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 431Which of the following is an example of a group creativity technique?

A. Delphi technique

B. Unanimity

C. Observation

D. Presentation technique

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 432Which process includes facilitated workshops as a tool and technique?

A. Collect Requirements

B. Plan Communications

C. Develop Project Team

D. Report Performance

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 433Which of the following is a tool or technique used to verify scope?

A. Product analysis

B. Ishikawa diagram

C. Inspection

D. Requirements traceability matrix

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 434

Page 140: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Inspection is a tool and technique for which of the following processes?

A. Create WBS

B. Define Scope

C. Control Scope

D. Verify Scope

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 435What is the lowest level in the WBS at which the cost and activity durations for the work can be reliablyestimated and managed?

A. Work product

B. Work package

C. Project deliverable

D. Scope baseline

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 436Many organizations categorize requirements into which of the following two categories?

A. Project and Product

B. Staffing and Budget

C. Stakeholder and Customer

D. Business and Technical

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 437Plurality is a type of which of the following?

A. Group creativity techniques

B. Group decision making techniques

C. Facilitated workshops

D. Prototypes

Page 141: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 438Which of the following events would result in a baseline update?

A. Your project is behind schedule and you want your baseline to reflect estimated actual completion.

B. Your customer has approved a change request broadening the project scope and increasing the budget.

C. One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.

D. One of your key project team resources has left your team and no replacement is available.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 439Which schedule compression technique has phases or activities done in parallel that would normally have beendone sequentially?

A. Crashing

B. Fast tracking

C. Leads and lags adjustment

D. Parallel task development

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 440Which schedule development technique modifies the project schedule to account for limited resources?

A. Human resource planning

B. Fast tracking

C. Critical chain method

D. Rolling wave planning

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 441

Page 142: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Which schedule development tool and technique produces a theoretical early start date and late start date?

A. Critical path method

B. Variance analysis

C. Schedule compression

D. Schedule comparison bar charts

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 442What is the minimum a project schedule must include?

A. Variance analysis

B. A planned start date and a planned finish date for each schedule activity

C. A critical path diagram

D. Critical chain analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 443What cost control technique is used to compare actual project performance to planned or expectedperformance?

A. Cost aggregation

B. Trend analysis

C. Forecasting

D. Variance analysis

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 444Using the following data, what is the Schedule Performance Index (SPI)?

EV = $500

PV= $750

AC= $1000

BAC= $1200

Page 143: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. 0.67

B. 1.50

C. 0.75

D. 0.50

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 445Which enterprise environmental factors are considered during cost estimating?

A. Marketplace conditions and commercial databases

B. Marketplace conditions and company structure

C. Commercial databases and company structure

D. Existing human resources and market place conditions

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 446Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A. Cost baseline

B. Cost forecasting

C. Cost variance

D. Cost budgeting

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 447What is the schedule performance index (SPI) using the following data?

BAC = $100,000

PV = $50,000

AC = $80,000

EV = $40,000

Page 144: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. 1.00

B. 0.40

C. 0.50

D. 0.80

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 448The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 forthe project. What is the actual status of this project?

A. Behind schedule and over budget

B. Behind schedule and under budget

C. Ahead of schedule and under budget

D. Ahead of schedule and over budget

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 449EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate tocomplete) the remaining work. Which of the following is a valid formula for calculating EAC?

A. EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]

B. EAC = BAC - AC

C. EAC = 1 - CPI

D. EAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 450Which of the following equations is used to calculate schedule variance?

A. EV/PV

B. PV/EV

C. EV-PV

D. PV-EV

Answer: C

Page 145: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:

QUESTION 451Which tool and technique uses a statistical relationship between historical data and other variables to calculateestimates?

A. Analogous estimating

B. Three-point estimates

C. Parametric estimating

D. Bottom-up estimating

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 452Which of the following equations is used to calculate cost variance?

A. EV-AC

B. AC-EV

C. AC+EV

D. AC/EV

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 453Given the following values, what is the calculated expected activity cost (CE) when using PERT?

CO = $7,000

CM = $10,500

CP = $11,000

A. $ 4,750

B. $ 9,500

C. $10,000

D. $11,500

Answer: CSection: (none)

Page 146: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 454What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115,and a worst case scenario of $165?

A. $115

B. $138

C. $140

D. $165

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 455What does a SPI value greater than 1.0 indicate?

A. More work was completed than planned

B. Less work was completed than planned

C. Cost overrun for completed work has occurred

D. Cost underrun for completed work has occurred

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 456Total funding requirements and periodic funding requirements are derived from:

A. funding limit reconciliation

B. scope baseline

C. activity cost estimates.

D. cost baseline.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 457What is the status of the project whose data is shown in the following S-curve?

A. Under budget and ahead of schedule

Page 147: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Over budget and behind schedule

C. Over budget and ahead of schedule

D. Under budget and behind schedule

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 458If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would bethe cost performance index (CPI)?

A. 0.66

B. 0.8

C. 1.25

D. 1.5

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 459Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of whatprocess?

A. Perform Quality Control

B. Perform Quality Assurance

C. Quality Planning

D. Performance Reporting

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 460Which tool and technique identifies inefficient and ineffective policies, processes and procedures?

A. Scope audits

B. Scope reviews

C. Quality audits

D. Control chart

Answer: CSection: (none)

Page 148: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 461What quality control tool graphically represents how various elements of a system interrelate?

A. Control chart

B. Flowchart

C. Run chart

D. Pareto chart

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 462Which tool and technique of quality planning involves comparing actual or planned practices to those of otherprojects to generate ideas for improvement and provide a basis by which to measure performance?

A. Histogram

B. Quality audits

C. Benchmarking

D. Performance measurement analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 463In which domain of project management would a Pareto chart provide useful information?

A. Scope Management

B. Time Management

C. Communications Management

D. Quality Management

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 464What is the primary benefit of meeting quality requirements?

A. Quality metrics

Page 149: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Less rework

C. Quality control measurements

D. Benchmarking

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 465What is the name of the statistical method that helps identify which factors may influence specific variables of aproduct or process under development or in production?

A. Failure modes and effects analysis

B. Design of experiments

C. Quality checklist

D. Risk analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 466What is the term assigned to products or services having the same functional use but different technicalcharacteristics?

A. Scope

B. Quality

C. Specification

D. Grade

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 467Which of the following provides a basis for assessing project performance?

A. Profitability and impact matrix

B. Expert judgment

C. Benchmarking

D. Risk categorization

Answer: CSection: (none)

Page 150: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 468Regardless of style, what information is shown in a process flowchart?

A. Actions, decision points, and process drivers

B. Activities, decision points, and the order of processing

C. Activities, process drivers, and the order of processing

D. Actions, decision points, and activities

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 469Which quality assurance tool and technique confirms the implementation of approved change requests,corrective actions, defect repairs, and preventive actions?

A. Quality checklists

B. Quality metrics

C. Quality audits

D. Process analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 470Which tool or technique uses the 80/20 principle?

A. Pareto chart

B. Cause and effect diagrams

C. Control charts

D. Flowcharting

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 471What is a cost of nonconformance?

A. Rework

Page 151: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

B. Inspections

C. Training

D. Testing

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 472What is included in a control chart?

A. Baseline

B. Planned value

C. Upper specification limit

D. Expenditure

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 473What tool and technique includes all costs incurred over the life of a product by investment in preventingnonconformance to requirements?

A. Cost of quality

B. Measure of design

C. Statistical control

D. Systematic analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 474In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entireprocess, the goal is 10 and the standard deviation is 1.

For this data set, it is correct to say that the process:

A. is under control.

B. is out of control.

C. has an increasing trend.

D. has a decreasing trend.

Answer: B

Page 152: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:

QUESTION 475In which tool and technique is it possible to find a correlation between dependent and independent variables?

A. Fishbone diagram

B. Control chart

C. Run chart

D. Scatter diagram

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 476A project manager arranges for project specific training for the new team members. Under which category doesthis cost fall?

A. Appraisal

B. Internal failure

C. External failure

D. Prevention

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 477Which of the following describes the purpose of the quality control process?

A. To identify quality requirements of the project

B. To identify ineffective processes and eliminate them

C. To assess performance and recommend necessary changes

D. To ensure quality standards are used

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 478What is an objective of the Developing Project Team Process?

Page 153: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Feelings of trust and improved cohesiveness

B. Ground rules for interaction

C. Enhanced resource availability

D. Functional managers become more involved.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 479Which tools or techniques will the project manager use for developing the project team?

A. Negotiation

B. Roles and responsibilities

C. Recognition and rewards

D. Prizing and promoting

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 480When managing a project team, what helps to reduce the amount of conflict?

A. Clear role definition

B. Negotiation

C. Risk response planning

D. Team member replacement

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 481Conflict should be best addressed in which manner?

A. Early, in private, using a direct, collaborative approach

B. Early, in public, using an indirect, collaborative approach

C. Early, in private, using an indirect, cooperative approach

D. As late as possible, in public, using a direct, confrontational approach

Answer: ASection: (none)

Page 154: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 482What is the name of a graphic display of project team members and their reporting relationships?

A. Role dependencies chart

B. Reporting flow diagram

C. Project organization chart

D. Project team structure diagram

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 483Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsiblefor managing this dual reporting relationship factor?

A. Functional manager

B. Project manager

C. Functional manager supported by the project manager

D. Project management office

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 484What provides information regarding the ways people, teams, and organizational units behave?

A. Organizational chart

B. Organizational theory

C. Organizational structure

D. Organizational behavior

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 485In which of the following team development stages does the team meet and learn about the project and theirformal roles and responsibilities?

Page 155: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Forming

B. Storming

C. Norming

D. Performing

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 486Which of the following is a technique for resolving conflict?

A. Collaborating

B. Issue log

C. Leadership

D. Motivation

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 487Which of the following is a conflict resolving technique that emphasizes areas of agreement rather than areasof difference?

A. Withdrawing/Avoiding

B. Forcing

C. Collaborating

D. Smoothing/Accommodating

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 488In which of the team development stages are the teams interdependent and work through issues smoothly andeffectively?

A. Norming

B. Forming

C. Storming

D. Performing

Page 156: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 489The resource calendars document is an output of which process?

A. Estimate Activity Resources

B. Acquire Project Team

C. Develop Schedule

D. Develop Project Team

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 490In which of the following team development stages does the team begin to work together, develop trust, andadjust to the work habits and behavior?

A. Norming

B. Forming

C. Storming

D. Performing

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 491Project team members begin to address the project work and technical decisions. The project team is in whichof the following stages of team development?

A. Storming

B. Forming

C. Norming

D. Performing

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 157: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 492Placing many or all of the most active project team members in the same physical location to enhance theirability to perform as a team is called which of the following?

A. Team training

B. Co-location

C. Team location

D. Organization training

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 493Emphasizing areas of agreement rather than areas of difference is part which of the following conflictmanagement techniques?

A. Smoothing

B. Compromising

C. Avoiding

D. Forcing

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 494Which knowledge area is concerned with the processes required to ensure timely and appropriate generation,collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project Integration Management

B. Project Communications Management

C. Project Information Management System (PIMS)

D. Project Scope Management

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 495Which of the following involves making information available to project stakeholders in a timely manner?

A. Contract management

B. Performance reporting

C. Project status reports

Page 158: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Information distribution

Answer: DSection: (none)

Explanation/Reference:Explanation: The project management term or phrase that is used for the purposes of representing the projectmanagement process that focuses on taking the facts and happenings in regards to a particular project anddisseminating this information to all of the relevant parties, with a particular focus on providing information tothose who have a financial stake in the ultimate outcomes of the project. These methods of informationdissemination can come in means including regularly scheduled conferences and or meetings, regularlyscheduled conference calls in which some or all members of the project team participate, informal writtencommunications such as periodic updates via email and of other short form, less formal means ofcommunications, as well as formal reports that may or may not have been requisite to the completion of theproject. Information distribution is essential to assuring that the financial stakeholders are fully aware of theprogress throughout as it helps to assure no surprises arise at the time that deliverables are expected to befinal.This term is defined in the 3rd edition of the PMBOK but not in the 4th.

QUESTION 496Forecasts, requested changes, recommended corrective actions, and organizational process asset updates areall outputs of which process?

A. Risk response planning

B. Risk monitoring and control

C. Performance reporting

D. Manage stakeholders

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 497Which of the following is contained within the communications management plan?

A. An organizational chart

B. Glossary of common terminology

C. Organizational process assets

D. Enterprise environmental factors

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 498Which knowledge area employs the processes required to ensure timely and appropriate generation, collection,distribution, storage, retrieval, and ultimate disposition of project information?

Page 159: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Project Risk Management

B. Project Integration Management

C. Project Communications Management

D. Project Quality Management

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 499Approved change requests, approved corrective actions, and updates to organizational process assets are alloutputs of which project management process?

A. Risk response planning

B. Manage stakeholders

C. Scope definition

D. Performance reporting

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 500What is a technique used in the performance reporting process?

A. Expert judgment

B. Project management methodology

C. Stakeholder analysis

D. Status review meetings

Answer: DSection: (none)

Explanation/Reference:Explanation: Performance Reporting is the process for "collecting and distributing performance information" like"status reporting, progress measurement, and forecasting" (comp. PMBOK3, p. 221): On the base of thecollected performance information concerning scope, schedule, cost and quality this process generates thereports which are distributed to the stakeholders (comp. PMBOK3, p. 231). Basicly one can determine fourtypes of reports:

· Forcast reports for describing future trends· Progess reports for describing trends from past to presence · Status reports for describing actual status· Variance reports for describing differences between the planned baseline and the real data

QUESTION 501What is the number of stakeholders, if the project has 28 potential communication channels?

Page 160: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. 7

B. 8

C. 14

D. 16

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 502What information does the stakeholder register contain?

A. Communication model

B. Identification information

C. Communication method

D. Identification plan

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 503Stakeholder analysis identifies what information and relates it to the purpose of the project?

A. Requirements, influence, and functional department

B. Interest, requirements, and functional role

C. Requirements, expectations, and influence

D. Interest, expectations, and influence

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 504Which of the following is a tool and technique to the Manage Stakeholder Expectations process?

A. Issue log

B. Change register

C. Stakeholder register

D. Interpersonal skills

Answer: DSection: (none)

Page 161: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 505When using the Delphi technique for gathering information, what forecasting method is being used?

A. Time series method

B. Casual method

C. Econometric method

D. Judgmental method

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 506Which of the following is one of the key components of the basic communications model?

A. Push

B. Decode

C. Pull

D. Duration

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 507Which of the following is a tool or technique for distribute information?

A. Project management plan

B. Report performance

C. Communications requirements analysis

D. Communication methods

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 508A project manager convenes a meeting to determine why the time to produce one product according tospecifications has increased from one day to three days over the past month. Which tool or technique is used inthis case?

Page 162: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Expert judgment

B. Quality assurance

C. Quality control

D. Variance analysis

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 509There are seven members on the project team not counting the project manager and the sponsor.How many communication channels are there?

A. 21

B. 28

C. 36

D. 42

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 510ABC project is at risk for failing to achieve a major project objective due to unresolved stakeholder issues.Team member morale is low.

Who is primarily responsible for the project being at risk?

A. Team members who have low morale

B. Sponsor who is not actively supporting the project

C. Project manager who is responsible for managing stakeholder expectations

D. Stakeholders who have unrealistic expectations

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 511When communicating with large audiences, which communication method works most effectively?

A. Push

B. Interactive

C. Parallel

D. Pull

Page 163: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 512What are assigned risk ratings based upon?

A. Root cause analysis

B. Assessed probability and impact

C. Expert judgment

D. Risk Identification

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 513Which of the following processes includes prioritizing risks for subsequent further analysis or action byassessing and combining their probability of occurrence and impact?

A. Qualitative risk analysis

B. Quantitative risk analysis

C. Risk management planning

D. Risk response planning

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 514Which of the following documents allows the project manager to assess risks that may require near termaction?

A. Probability and impact matrix

B. Contingency analysis report

C. Risk urgency assessment

D. Rolling wave plan

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 164: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 515Which of the following is an example of a technique used in quantitative risk analysis?

A. Sensitivity analysis

B. Probability and impact matrix

C. Risk data quality assessment

D. Risk categorization

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 516When does risk monitoring and control occur?

A. At project initiation

B. During work performance analysis

C. Throughout the life of the project

D. At project milestones

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 517A risk may be graded into different priorities by which process?

A. Risk monitoring and controlling

B. Risk response planning

C. Qualitative risk analysis

D. Quantitative risk analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 518Quality and credibility of the qualitative risk analysis process requires that different levels of the risk'sprobabilities and impacts be defined is the definition of what?

A. Risk breakdown structure (RBS)

B. Risk probability and impact

C. Qualitative risk analysis

Page 165: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Risk response planning

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 519What is one of the objectives of project risk management?

A. Decrease the probability and impact of event on project objectives.

B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C. Increase the probability and impact of positive events.

D. Removal of project risk.

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 520Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A. Mitigate

B. Transfer

C. Share

D. Avoid

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 521Taking out insurance in relation to risk management is called what?

A. Transference

B. Avoidance

C. Exploring

D. Mitigation

Answer: ASection: (none)

Explanation/Reference:Explanation:

Page 166: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 522What risk technique is used to quantify the probability and impact of risks on project objectives?

A. Expert judgment

B. Risk registry

C. Risk response planning

D. Interviewing

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 523What defines the portion of work included in a contract for items being purchased or acquired?

A. Procurement management plan

B. Evaluation criteria

C. Work Breakdown Structure (WBS)

D. Contract Statement of Work (SOW)

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 524Which of the following is an example of the simplest fixed-price contract?

A. Purchase requisition

B. Purchase order

C. Verbal agreement

D. Request for quote

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 525Which of the following lists contain processes that are included within Project Procurement Management?

A. Plan purchases and acquisitions, plan contracting, request seller responses, select sellers

B. Plan purchases and acquisitions, request seller responses, select sellers, schedule control

C. Plan purchases and acquisitions, acquire project team, request seller responses, select sellers

D. Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Page 167: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 526Which type of analysis is used as a general management technique within the Plan Procurements Process?

A. Risk assessment analysis

B. Make or buy analysis

C. Contract value analysis

D. Cost impact analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 527A purchase order for a specified item to be delivered by a specified date for a specified price is the simplestform of what type of contract?

A. Cost-reimbursable

B. Time and material

C. Fixed price or lump-sum

D. Cost-plus-fixed-fee

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 528What is the tool and technique used to request seller responses?

A. Procurement documents

B. Expert judgment

C. Bidder conferences

D. Contract types

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 529

Page 168: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A contract change control system defines which of the following?

A. Process by which the procurement is being satisfied

B. Process by which the procurement can be modified

C. Process by which the procurement can be obtained

D. Process by which the procurement can be disposed

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 530In what type of contract is the seller reimbursed for all allowable costs for performing the contract work andreceives a predetermined fee based upon achieving certain performance objectives as set forth in the contract?

A. Cost-plus-fixed-fee

B. Cost-plus-incentive-fee

C. Firm-fixed-price

D. Fixed-price-incentive-fee

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 531Who decides buyer and seller roles in a teaming agreement?

A. Executive management

B. Project members

C. Project manager

D. Contract administrator

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 532In which of the following contract types is a price ceiling set and any additional costs above the price ceilingbecomes the responsibility of the performing organization?

A. Firm-Fixed-Price Contracts (FFP)

B. Fixed-Price-Incentive-Fee Contracts (FPIF)

C. Cost-Reimbursable Contracts

D. Time and Materials Contracts (T&M)

Page 169: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 533The degree of risk shared between the buyer and seller is determined by the:

A. contract type.

B. sponsors.

C. project manager.

D. stakeholders.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 534Company A bought a well-defined project deliverable from Company B. Company A will pay a fixed total priceplus a percentage premium for the schedule target achieved.

For which type of contract have they subscribed?

A. Fixed-price-incentive-fee contracts (FPIF)

B. Firm-fixed-price-contracts (FFP)

C. Fixed price with Economic Price Adjustment Contracts (FP-EPA)

D. Time and material contracts (T&M)

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 535Negotiated Settlements are an example of a technique used in which Project Procurement ManagementProcess?

A. Plan Procurements

B. Conduct Procurements

C. Administer Procurements

D. Close Procurements

Answer: DSection: (none)

Explanation/Reference:

Page 170: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 536Which project management process ensures the seller's performance meets procurement requirements andthat the buyer performs according to the terms of the legal contract?

A. Plan Procurements

B. Perform Quality Assurance

C. Administer Procurements

D. Conduct Procurements

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 537Which contract type is typically used whenever the seller's performance period spans a considerable period ofyears?

A. Fixed-Price-Incentive-Fee contracts (FPIF)

B. Fixed Price with Economic Price Adjustment contracts (FP-EPA)

C. Cost-Plus-Fixed-Fee contracts (CPFF)

D. Time and Material contracts (T&M)

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 538The project management information system is used as tools and techniques in which of the followingprocesses?

A. Develop Project Charter

B. Develop Project Management Plan

C. Direct and Manage Project Execution

D. Monitor and Control Project Work

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 539Final product transition is an output of which process?

Page 171: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Direct and Manage Project Execution

B. Close Project or Phase

C. Perform Integrated Change Control

D. Monitor and Control Project Work

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 540Which of the following provides a standardized, effective, and efficient way to centrally manage approvedchanges and baselines within a project?

A. Project management information system

B. Configuration management system

C. Change control board

D. Project management plan

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 541The approval of which of the following indicates formal initiation of the project?

A. Procurement management plan

B. Project management plan

C. Project scope document

D. Project charter

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 542Which one of the following is true regarding the change control board?

A. Describes how changes are managed.

B. Approves or rejects change requests.

C. Needs updated project management plans to approve or reject a change.

D. Describes how changes are documented.

Answer: BSection: (none)

Page 172: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 543Which document is a narrative description of products or services to be delivered by the project?

A. Project charter

B. Contract

C. Business case

D. Project statement of work

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 544Reviewing, tracking, and regulating the process to meet performance objectives defined in the projectmanagement plan are part of which process?

A. Monitor and Control Project Work

B. Direct and Manage Project Execution

C. Monitor and Control Risk

D. Perform Integrated Change Control

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 545Which document contains initial requirements that satisfy stakeholders' needs and expectations?

A. Project charter

B. Project management plan

C. Project statement of work

D. Project scope statement

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 546The decision to approve or reject a particular change request is made in which of the following processes?

Page 173: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Perform Integrated Change Control

B. Monitor and Control Project Work

C. Develop Project Management Plan

D. Direct and Manage Project Execution

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 547Who authorizes a project?

A. Sponsor

B. Project manager

C. Project team

D. Buyer

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 548Providing forecasts to update current cost and schedule information is a part of which process?

A. Perform Integrated Change Control

B. Direct and Manage Project Execution

C. Monitor and Control Risks

D. Monitor and Control Project Work

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 549A business case is an input to which of the following processes?

A. Collect Requirements

B. Define Scope

C. Develop Project Charter

D. Develop Project Management Plan

Answer: CSection: (none)

Page 174: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 550What should be covered in an implementation when the change is approved?

A. Functional requirement

B. Status report

C. Customer need

D. Defect repair

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 551The Project Integration Management knowledge area includes which of the following set of processes?

A. Develop Project Charter, Direct and Manage Project Execution, Perform Integrated Change Control

B. Define Project Scope, Create WBS, Close Project or Phase

C. Develop Project Charter, Develop Human Resource Plan, Estimate Costs

D. Identify Stakeholders, Plan Communications, Develop Project Management Plan

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 552What document should be reviewed by a project manager before finalizing the project closure?

A. Customer acceptance

B. Statement of work

C. Product report

D. User manual

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 553Which of the following is a tool and technique for activity duration estimating?

A. Parametric estimating

B. Monte Carlo analysis

Page 175: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. Top-down estimating

D. Bottom-up estimating

Answer: ASection: (none)

Explanation/Reference:Explanation: Explanations:An estimating technique that uses a statistical relationship between historical data and other variables (forexample, square footage in construction, lines of code in software development) to calculate an estimate foractivity parameters, such as scope, cost, budget, and duration. This technique can produce higher levels ofaccuracy depending upon the sophistication and the underlying data built into the model. An example for thecost parameter is multiplying the planned quantity of work to be performed by the historical cost per unit toobtain the estimated cost.

QUESTION 554Which process involves identifying and documenting the logical relationships among schedule activities?

A. Schedule development

B. Activity sequencing

C. Create WBS

D. Applying leads and lags

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 555What type of planning is used where the work to be accomplished in the near term is planned in detail, whilework in the future is planned at a higher level?

A. Finish-to-start planning

B. Rolling wave planning

C. Short term planning

D. Dependency determination

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 556When would resource leveling be applied to a schedule model?

A. Before constraints have been identified

B. Before it has been analyzed by the critical path method

C. After it has been analyzed by the critical path method

D. After critical activities have been removed from the critical path

Page 176: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 557Which is the duration of the project?

A. 63

B. 65

C. 66

D. 70

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 558Which tool and technique is used to sequence activities?

A. Decomposition

B. Project management software

C. Applying lead and lags

D. Expert judgment

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 559What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight,and complexity from a previous, similar project as the basis for estimating the same parameter or measure fora future project?

A. Bottom-up estimating

B. Analogous estimating

C. Parametric estimating

D. Three-point estimates

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 177: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 560Which schedule format usually shows both the project network logic and the project's critical path scheduleactivities with activity date information?

A. Schedule table

B. Schedule network diagram

C. Bar chart

D. Milestone chart

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 561Which is the total float for the activity G?

A. 0

B. 3

C. 5

D. 10

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 562Which of these are logical dependencies in a precedence diagram method?

A. End-to-end

B. Finish-to-end

C. Start-to-end

D. Start-to-start

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 563In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, theoptimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in whichthe activity will be completed?

A. 90 days

B. 100 days

Page 178: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. 110 days

D. 660 days

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 564Which of the following techniques uses historical information to estimate the activity duration?

A. Three-point estimating

B. Organizational process asset

C. Analogous estimating

D. Reserve analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 565What is a specific advantage of analogous estimating in comparison with other cost estimate techniques?

A. Uses contingency reserves

B. Less costly and time consuming

C. Can be applied to segments of work

D. More accurate

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 566Which of the following is an output of the Estimate Activity Resources process?

A. Alternative analysis

B. Bottom-up estimating

C. Resource breakdown structure

D. Enterprise environmental factors

Answer: CSection: (none)

Explanation/Reference:Explanation:

Page 179: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 567In the precedence diagramming method, which of the following is a logical relationship for the activities?

A. Finish-to-start

B. Applying leads and lags

C. Activity-on-node

D. Dependency determination

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 568During the initial stages of the project, what do activity attributes include?

A. Activity name, dependencies, assumptions

B. Activity ID, WBS ID, activity name

C. Activity ID, assumptions, constraints

D. Activity name, WBS ID, activity description

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 569Which of the following is one of the tools and techniques for the Define Activities process?

A. Rolling wave planning

B. Dependency determination

C. Schedule network template

D. Applying leads and lags

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 570Which of the following is a tool and technique to develop the schedule?

A. What-if scenario analysis

B. Benchmarking

C. Variance analysis

D. SWOT analysis

Page 180: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 571Rolling wave planning is used as a tool and a technique in which of the following processes?

A. Estimate Activity Durations

B. Define Activities

C. Develop Schedule

D. Sequence Activities

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 572Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AONor another technique to derive the answer using F-S relationships.

What is the critical path duration for the given schedule network?

A. 22

B. 23

C. 24

D. 25

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 573Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AONor another technique to derive the answer using F-S relationships.

What is the total float on path BEG?

A. 0

B. 1

C. 2

D. 3

Answer: CSection: (none)

Page 181: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 574If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?

A. $0.2

B. $5

C. $44

D. $66

Answer: DSection: (none)

Explanation/Reference:Explanation:

"Pass Any Exam. Any Time." - www.actualtests.com 220 PMI PMI-001 Exam

QUESTION 575What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is0.75?

A. Under budget and behind schedule

B. Over budget and ahead of schedule

C. Under budget and ahead of schedule

D. Over budget and behind schedule

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 576Which of the following will be required to perform simulation for schedule risk analysis?

A. Activity list and activity attributes

B. Schedule network diagram and duration estimates

C. Schedule data and activity resource requirements

D. Milestone list and resource breakdown structure

Answer: BSection: (none)

Explanation/Reference:

QUESTION 577

Page 182: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

The risk register contains which of the following?

A. Identified risks and potential responses

B. Identified risks and updates to scope baseline

C. Risk management plan

D. Risk related contract decisions

Answer: ASection: (none)

Explanation/Reference:Explanation: A Risk Register is a Risk Management tool commonly used in Project Management andorganizational risk assessments. It acts as a central repository for all risks identified by the project ororganization and, for each risk, includes information such as risk probability, impact, counter-measures, riskowner and so on. It can sometimes be referred to as a Risk Log

QUESTION 578Which of the following is an input to identify risk?

A. Organizational process assets

B. Scope management plan

C. Communication management plan

D. Expert judgment

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 579Which analysis helps to determine the risks that have the most potential for impacting the project?

A. Expected monetary value analysis

B. Sensitivity analysis

C. Modeling and simulation

D. Expert judgment

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 580Which of the following risk management processes uses brainstorming as a technique?

A. Identify Risks

B. Monitor and Control Risks

C. Plan Risk Management

Page 183: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Plan Risk Responses

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 581Reserve analysis is a tool and technique used in which of the following processes?

A. Monitor and Control Risks

B. Qualitative Risk Analysis

C. Quantitative Risk Analysis

D. Plan Risk Responses

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 582What is risk tolerance?

A. Ability to manage risks

B. Willingness to accept varying degrees of risks

C. Ability to mitigate risks

D. Willingness to develop a risk management plan

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 583Expected Monetary Value (EMV) analysis is commonly used in:

A. probability distribution.

B. decision tree diagram.

C. sensitivity analysis.

D. modeling and simulation.

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 184: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 584Which of the following is a strategy for positive risks?

A. Avoid

B. Transfer

C. Accept

D. Mitigate

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 585An Ishikawa or fishbone diagram is used for which of the following?

A. Identifying causes of risks

B. Identifying frequency of occurrence of risks

C. Developing a resource plan

D. Developing schedule

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 586Which analysis uses beta and triangular distributions as a tool and technique?

A. Quantitative risk analysis

B. Qualitative risk analysis

C. Perform quality assurance

D. Perform quality control

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 587What should a project manager do with low-priority risks?

A. Ignore low-priority risks

B. Monitor periodically with other low-priority risks

C. Create a mitigation plan for the low-priority risks

D. Increase the contingency reserve

Page 185: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 588Which of the following is a technique for Identify Risks?

A. Risk categorization

B. SWOT analysis

C. Risk register categorization

D. Risk probability and impact assessment

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 589The project manager decides to conduct a meeting with the team and management after a new risk has beenidentified. After the meeting, the decision is to allow the risk to occur.

This is an example of which type of risk response strategy?

A. Mitigate

B. Accept

C. Avoid

D. Transfer

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 590The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizesthat the implementation of the risk response would generate another risk. This new risk is which of the followingtypes of risk?

A. Secondary

B. Primary

C. Residual

D. Tertiary

Answer: ASection: (none)

Explanation/Reference:

Page 186: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation:

QUESTION 591What is the first step in preparing the risk register?

A. Qualitative risk analysis

B. Quantitative risk analysis

C. Risk response planning

D. Risk identification

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 592What is Project Portfolio Management?

A. Management of a project by dividing the project into more manageable sub-projects.

B. Management of a project by utilizing a portfolio of general management skills, such as planning, organizing,staffing, executing and controlling.

C. Management of all projects undertaken by a company.

D. Management of a collection of projects that are grouped together to facilitate effective management andmeet strategic business objectives.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 593When is a project finished?

A. After verbal acceptance of the customer or sponsor

B. After lessons learned have been documented in contract closure

C. When the project objectives have been met

D. After resources have been released

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 594Define Activities and Estimate Activity Resources are processes in which project management knowledgearea?

Page 187: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. Time management

B. Cost management

C. Scope management

D. Human resources management

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 595What characteristic do project and operational work share in common?

A. Performed by systems

B. Constrained by limited resources

C. Repetitiveness

D. Uniqueness

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 596What are the components of the "triple constraint"?

A. Scope, time, requirements

B. Resources, time, cost

C. Scope, management, cost

D. Scope, time, cost

Answer: DSection: (none)

Explanation/Reference:Explanation: The Project Management Triangle (called also Triple Constraint) is a model of the constraints ofproject management. It is often used to illustrate that project management success is measured by the projectteam's ability to manage the project, so that the expected results are produced while managing time and cost.Like any human undertaking, projects need to be performed and delivered under certain constraints.Traditionally, these constraints have been listed as "scope," "time," and "cost". These are also referred to as the"Project Management Triangle," (also known as the "Iron Triangle") where each side represents a constraint.One side of the triangle cannot be changed without affecting the others. A further refinement of the constraintsseparates product "quality" or "performance" from scope, and turns quality into a fourth constraint.

QUESTION 597Which statement is true about the project management body of knowledge?

A. Recognized by every project manager

B. Constantly evolving

Page 188: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

C. The sum of all knowledge related to project management

D. A sum of knowledge that should be applied on every project

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 598What do composite organizations involve?

A. Functional and project managers

B. Functional managers only

C. Project managers only

D. Technical managers and project managers

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 599Which of the following is TRUE about most project life cycles?

A. Staffing level is highest at the start.

B. The stakeholders' influence is highest at the start.

C. The level of uncertainty is lowest at the start.

D. The cost of changes is highest at the start.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 600What happens to a stakeholder's project influence over time?

A. Increases

B. Decreases

C. Stays the same.

D. Has no bearing.

Answer: BSection: (none)

Explanation/Reference:Explanation:

Page 189: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

QUESTION 601To which process is work performance information an input?

A. Contract administration

B. Direction and management of project execution

C. Create WBS

D. Qualitative risk analysis

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 602Which of the following is an output of the Information Distribution Process?

A. Project calendar

B. Communication management plan

C. Requested changes

D. Communication requirement plan

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 603Which process documents the business needs of a project and the new product, service or other result that isintended to satisfy those requirements?

A. Develop project management plan

B. Develop project charter

C. Develop preliminary project scope statement

D. Scope planning

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 604Which process group typically consumes the bulk of a project's budget?

A. Monitoring & Controlling

B. Executing

C. Planning

Page 190: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

D. Initiating

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 605What process determines which risks might affect the project?

A. Qualitative risk analysis

B. Identify Risks

C. Plan Risk Management

D. Quantitative risk analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 606Verification of project deliverables occurs during which process?

A. Develop preliminary project scope statement.

B. Close Project or Phase.

C. Develop project charter.

D. Create WBS.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 607Information collected on the status of project activities being performed to accomplish the project work is knownas what?

A. Project management information system

B. Work performance information

C. Work breakdown structure

D. Variance analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:Work Performance Information

Page 191: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Part of the executed project management plan includes the routine collection of work performance information.The information gathered is important, and is useful as input data for quality control measures and programs. Itis also useful when audits, quality reviews, and process analyses are conducted. This is especially true of workperformance information collected which includes technical performance measures, project deliverables status,required corrective actions, and performance reports. Pertinent work performance Information is essential tothe project management plan and includes, but is not limited to:

· Status information on schedule progress.· Whether deliverables have been completed, or not.· Start and finish status of schedule activities.· Quality standards expectation results.· Authorized costs vs. costs incurred to date.· Estimated completion time for scheduled activities in progress. · Percentage of physical completion of in-progress schedule activities. · Experience based knowledge acquired, documented, and posted to knowledgebase.· Details of resource utilization.

Gathering and analysis of work performance information is essential to the project management plan andshould be considered a priority. Work performance information contributes to the efficient use of resources,identifies potential trouble spots and problems, and serves as an effective project management tool. This termis defined in the 3rd and the 4th edition of the PMBOK.

QUESTION 608Which is a tool used in monitoring and controlling project work?

A. Work performance information

B. Project management information system (PMIS)

C. Activity duration estimates

D. Scheduled network analysis

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 609Which is an input to the Scope Verification Process?

A. Performance report

B. Work breakdown structure

C. Requested changes

D. Project scope statement

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 610When are deliverables accepted or not accepted?

Page 192: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. When the project is initiated.

B. As an output of the scope verification process.

C. When the project is closing.

D. In the contract closure process.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 611During which process would you obtain stakeholders' formal acceptance of the completed project scope?

A. Quality control

B. Scope verification

C. Scope control

D. Close project

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 612The initial development of a Project Scope Management plan uses which technique?

A. Alternatives identification

B. Scope decomposition

C. Expert judgment

D. Product analysis

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 613What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A. Risk register

B. Risk breakdown structure (RBS)

C. Risk management plan

D. Risk category

Answer: BSection: (none)

Page 193: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 614Which is a tool or technique used in scope definition?

A. Templates, forms and standards

B. Change requests

C. Stakeholder analysis

D. Project assumptions

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 615What is the total float of the critical path?

A. Can be any number

B. Zero or positive

C. Zero or negative

D. Depends on the calendar

Answer: CSection: (none)

Explanation/Reference:Explanation:

QUESTION 616Which of the following is the correct network diagram for the table?

A. Begin - A - C - D - E - End - B - D

B. Begin - A - B - C - D - E - End

C. Begin - A - B - D - E - End A - C - D

D. Begin - A - C - D - E - End - B - C

Answer: ASection: (none)

Page 194: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Explanation/Reference:Explanation:

QUESTION 617Which of the following is a schedule network analysis technique that takes limited resources into account?

A. Network reserve analysis

B. Critical chain method

C. Lead and lag adjustment

D. Critical path method

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 618Fast tracking is a schedule compression technique used to shorten the project schedule without changingproject scope. Which of the following can result from fast tracking?

A. The risk of achieving the shortened project time is increased.

B. The critical path will have positive total float.

C. Contingency reserves are released for redeployment by the project manager.

D. Duration buffers are added to maintain a focus on planned activity durations.

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 619Which estimating technique uses the actual costs of previous similar projects as a basis for estimating thecosts of the current project?

A. Analogous

B. Parametric

C. Bottom-up

D. Top-down

Answer: ASection: (none)

Explanation/Reference:Explanation:

QUESTION 620Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days.What should be your concern?

Page 195: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

A. There is a cost under run.

B. There is a cost overrun.

C. May not meet deadline.

D. The project is 20 days behind schedule.

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 621Which illustrates the connection between work that needs to be done and its project team members?

A. Work breakdown structure

B. Network diagrams

C. Staffing management plan

D. Responsibility matrix

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 622When can pre-assignment of project team members occur?

A. When the project uses capital expenditures.

B. When the required staff can be acquired from outside sources.

C. When the project would be ignored due to travel expenses.

D. When the project is the result of specific people being promised as part of a competitive proposal.

Answer: DSection: (none)

Explanation/Reference:Explanation:

QUESTION 623Which process uses occurrence probability and impact on project objectives to assess the priority of identifiedrisks?

A. Risk identification

B. Qualitative risk analysis

C. Risk management planning

D. Quantitative risk analysis

Answer: B

Page 196: Actualtests.pmi-001 Questions Answers With Explanation October.2011

For more latest dumps & quality exam material, visit my folder => http://www.filemaze.ws/users/sepstica/

Section: (none)

Explanation/Reference:Explanation:

QUESTION 624In which process might you use risk reassessment as a tool and technique?

A. Qualitative risk analysis

B. Risk monitoring and control

C. Monitor and control project work

D. Risk response planning

Answer: BSection: (none)

Explanation/Reference:Explanation:

QUESTION 625A contract management plan is a subsidiary of what other type of plan?

A. Resource plan

B. Project management plan

C. Cost control plan

D. Expected monetary value plan

Answer: BSection: (none)