MDOT ACTT WORKSHOP
UTILITIES/ RAILROADCOORDINATION
Final Presentation
![Page 3: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/3.jpg)
Utilities/Railroad CoordinationTeam MembersMarion Leaphart, Utility Director, Coleman-Snow
Consultants, (Retired Utilities Manager, SC DOT) Veena Jasuja, MDOT, Detroit TSCNick Lefke, MDOT, Lansing, Real EstateBill Stonebrook, MDOT, Lansing, DesignSteve Rapp, MDOT, Lansing, DesignFacilitator:Anu Taneja, MDOT, Lansing, Contract ServicesNotes:Lynn Venturino, MDOT, Lansing, Design Support
![Page 4: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/4.jpg)
Utilities
![Page 5: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/5.jpg)
Designate a full time MDOT utilities coordinator
• Oversee all aspects of utility coordination, communication, and cooperation during design and construction
• Act as “go to” person for MDOT, utilities, and vendors
![Page 6: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/6.jpg)
Utilize Subsurface Utility Engineering (SUE)
• Have SUE provider available during design and construction
• Update current SUE data
• Utilize SUE deliverables effectively with stakeholders
• Expedites conflict resolution
![Page 7: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/7.jpg)
Identify and resolve municipal utility issues
• Early and often involvement of municipal utilities
• Early identification of potential “show stoppers”
• Identify all relocation and proposed new work
• Coordination with stakeholders
![Page 8: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/8.jpg)
Identify and resolve private/public utility issues• Early and often involvement of
private/public utilities• Early identification of potential
“show stoppers” • Identify all relocation and
proposed new work• Identify reimbursable relocations• Advanced utility relocations• Coordination with stakeholders
![Page 9: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/9.jpg)
Participate in preliminary engineering costs for private/public utilities
• Provides incentive to private/public utilities to cooperate in a timely manner
• Increases cooperation during design phase
![Page 10: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/10.jpg)
Railroads
![Page 11: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/11.jpg)
Form Steering Committee of officials from MDOT
and Railroads (RR)
• Authority to make high level decisions
• Expedite RR decision making (i.e. trackage rights, union work rules, etc.)
![Page 12: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/12.jpg)
Form a Design Engineering Committee
• Early and often involvement of railroads
• Early identification of design constraints
• Early identification of potential “show stoppers”
![Page 13: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/13.jpg)
Provide adequate time for RR coordination in the
MDOT process
• Two year minimum coordination time
• Coordination time begins from submittal of preliminary plans from MDOT to RR
![Page 14: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/14.jpg)
Contract with qualified vendor to perform RR
coordination • Vendor must be
knowledgeable in RR operations
• Effective in obtaining RR approvals
• Involve MDOT RR experts in vendor selection process
![Page 15: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/15.jpg)
Coordinate at-grade crossings with service roads
Diagnostic Team Review (DTR) meeting should take place well in advance of construction, if required
![Page 16: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/16.jpg)
Maintenance of RR traffic
• Early and often involvement of RR
• Construct temporary runaround “shoo-fly” tracks
• Part width bridge construction• Roll-in/lift-in superstructure • Build new permanent bridges
parallel to existing RR• Trackage rights agreements
between RR during construction
![Page 17: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/17.jpg)
Possible elimination of two RR structures over I-75
• RR approval required
![Page 18: ACTT WORKSHOP](https://reader035.fdocuments.in/reader035/viewer/2022062217/5681474a550346895db489ef/html5/thumbnails/18.jpg)
Questions