Activity Sampling.ppt 1
-
Upload
navam-nanthan -
Category
Documents
-
view
218 -
download
0
Transcript of Activity Sampling.ppt 1
-
8/3/2019 Activity Sampling.ppt 1
1/16
Activity Sampling
IntroductionConstruction work involves the employment of different kind of
people for different situations.
To record the level of productivity in these conditions is not easily
achieved, because conditions are rarely are conditions stableenough for clear process to take place.
The reason is, in construction industry output of a worker may vary
over a wide margin, because of
bad weather condition,
machine breakdowns,
poor communication, etc.
The time between observation and report is usually too long to
pick up in efficient sections of work quickly enough for corrective
action to be taken.
-
8/3/2019 Activity Sampling.ppt 1
2/16
Activity Sampling
Introduction
The technique call activity sampling is a
method which provides the project
manager with a fairly sensitive
management tool to do a similar job to
time study methods without many of its
disadvantages when applied toconstruction work.
-
8/3/2019 Activity Sampling.ppt 1
3/16
Activity Sampling
Introduction - Example First occasion Eight men taking near excavation (road
side)
Second occasion The place was deserted
Third occasion Four men watching, one man priming
a pump, one man holding a pneumatic hammer
Fourth occasion Four men near excavation
Fifth occasion
Six men watching, one man working
Sixth occasion Seven men watching one man at work
Final disappointment for some time but excavation
was finally filled done
-
8/3/2019 Activity Sampling.ppt 1
4/16
-
8/3/2019 Activity Sampling.ppt 1
5/16
Activity Sampling
Field Count
Obviously if the rating causes concern,
further investigation may be warranted
-
8/3/2019 Activity Sampling.ppt 1
6/16
Activity Sampling
Field Count
Obviously if the rating causes concern,
further investigation may be warranted
-
8/3/2019 Activity Sampling.ppt 1
7/16
Activity Sampling
Field Count The total number of men observed should be between
7580% of the total employed workforce.
Clearly the field count technique can only provide a
guide since the number of observa-tions is so few.
The following example illustrates the use of statistics in
turning the method into something more meaningful.
-
8/3/2019 Activity Sampling.ppt 1
8/16
Activity Sampling
Field Count Example
A field count indicates that about 40% of the available
work time on a section of construction work is spent on
unproductive work. How many observations arerequired to be sure that the proportion is within 2%
accuracy? Given that 95% confidence is required.
If the field count is repeated on many occasions and the
proportion of unproductive workers plotted graphically,it is quite likely that the data will fit a normal distribution
as illustrated in Fig. 2.3. Such data can then be
interpreted statistically in the following way.
-
8/3/2019 Activity Sampling.ppt 1
9/16
Activity Sampling
Field Count Example
-
8/3/2019 Activity Sampling.ppt 1
10/16
Activity Sampling
Field Count Example
By substituting for in equations (1) and (2)
0.02 = 2 x [P (1-P)/n]
n = 4 x 0.4 (1 0.4)
0.022
n = 2400 observations
Therefore by taking 2400 observations the proportion of
underproductive work is determined to within 2%
accuracy.
-
8/3/2019 Activity Sampling.ppt 1
11/16
Activity Sampling
Activity Sampling Procedure1. First, carry out a preliminary survey to get a feeling for
the problem. The information collected will help in
deciding on the size of the section of work to be studied
and the number of workers involved.2. Identify the workers by name, and list the operations
and tasks to be studied. Sometimes this need only be
Working or Not working, but for a much fuller
investigation greater detail will be required, such asFixing formwork, Cleaning shutter panels, Receiving
instructions etc.
3. Prepare a suitable observation sheet (Fig. 2.4) for
recording the information.
-
8/3/2019 Activity Sampling.ppt 1
12/16
Activity Sampling
Activity Sampling Procedure4. Consult the supervisor of the work and ensure that
everyone is fully informed. Failure to do so may cause
unrest, which can quickly escalate and feed smoldering
grievances.5. The number of observations required is normally quite
large; therefore, a planned timetable of observation
times should now be assembled. In mass production
work these times are normally chosen ran-domly sincethe work patterns tend to be regular. However, in
construc-tion work, activities by their very nature take a
random time to complete and thus the observations can
be taken at regular intervals. Even so, caution is
required with some types of building work, e.g.
-
8/3/2019 Activity Sampling.ppt 1
13/16
Activity Sampling
Activity Sampling Procedure6. Choose a suitable position for taking the observations.
7. Record each activity that is in operation at the instant it
is observed, together with the worker involved.
8. From the percentages of the activities observed select
the activity or activities which show a disproportionate
amount of time being spent on them. Corrective action
can then be considered.
-
8/3/2019 Activity Sampling.ppt 1
14/16
Activity Sampling
Activity Sampling Procedure
-
8/3/2019 Activity Sampling.ppt 1
15/16
Activity Sampling
Output Rates The Activity Sampling technique can, if carefully
applied, is used to determine production output data for
use in estimating and planning the duration of activities.
When recording the number of observations for eachoperation, the performance level of the operative, or
machine etc. is assessed at each observation on the
standard rating scale described in the previous chapter
under TimeS
tudy and the mean rating for the operationtogether with time spent as a proportion of the whole
activity are calculated. If the total elapsed time of the
activity is also recorded, then the basic times of the
individual operations in the task can be calculated.
-
8/3/2019 Activity Sampling.ppt 1
16/16
Activity Sampling - Assignment
Perform a activity sampling for siteoperation such as brickwork,
formwork fixing or reinforcement.
Write a short report based on yourobservations.