1 GOVERNMENT OF ODISHA DEPARTMENT OF WATER RESOURCES DRAINAGE DIVISION, BHADRAK ACTIVITY REPORT OF DRAINAGE DIVISION, BHADRAK FOR THE FINANCIAL YEAR 2016-17 EXECUTIVE ENGINEER, DRAINAGE DIVISION, BHADRAK.

Transcript of ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD...

Page 1: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

1

GOVERNMENT OF ODISHA

DEPARTMENT OF WATER RESOURCES

DRAINAGE DIVISION, BHADRAK

ACTIVITY REPORT

OF

DRAINAGE DIVISION, BHADRAK

FOR THE FINANCIAL YEAR 2016-17

EXECUTIVE ENGINEER,

DRAINAGE DIVISION, BHADRAK.

Page 2: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

2

INDEX

Sl. No Description

Page No

1 Introduction of the Division

3-3

2 Jurisdiction

3-4

3 Staff Position

4-4

4 RIDF

4-5

5 Drainage Improvement Programme

5-5

6 Critical Lump

5-5

7 Check Dam

5-6

8 Status of Doabs

7-7

9 Expenditure statement

8-8

10 Annexure-A

9-11

11 Annexure-B

12-14

12 Annexure-C

15-16

13 Annexure-D

17-19

14 Photographs 20-21

Page 3: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

3

ANNUAL REPORT

OF

DRAINAGE DIVISION, BHADRAK

(For the financial Year 2016-17) Introduction

Drainage Division, Bhadrak was created on dated 01.12.2001 to address the drainage

congestion and waterlogging problems with respect to three Doabs of North Odisha in Bhadrak

district and a part of Balasore and Keonjhar District. Later on, the natural drainage system of

Bhadrak Municipality was entrusted upon this division with a view to improving the disposal of

surface runoff causing aggravated inundation during rains and affecting normal public life.

Jurisdiction The jurisdiction of the division spreads over Doab No-XI (Kansabansa-Mantei), Doab No-XII

(Mantei-Salandi) and Doab No-XIII (Salandi-Baitarani) covering all the seven Blocks of Bhadrak

district, partly two Blocks of Keonjhar district and partly three Blocks of Balasore district. This

Division comprises of four Subdivisions and twelve no of Sections. The jurisdiction of each Sub

division and Sections is placed at Annexure-A.

Drainage under Bhadrak Municipality

In the periphery of Bhadrak Municipality, there are ten natural drains through which the

storm water passes unto river Salandi and other drains at this outskirt. This drainage system was

entrusted upon this division during 2015-16 and two works were taken up to address immediate

congestion of natural drains in the town. A comprehensive approach was taken by the

organization to address the drainage congestion, curb water logging area and effective discharge

of storm water from Bhadrak Municipal area to river Salandi and nearby drains during 2016-17

and accordingly approval was received from 121st

TAC of State Flood Control Board held on dated

22.02.2016 vide L.No-10709/WE Dt 17.3.2016 of Engineer in Chief, Water Resources, Odisha,

Bhubaneswar. The administrative approval was also accorded and communicated vide Lr. No.

11566/WR Dt. 18.05.2016 of Department of Water Resources, Govt. of Odisha for Rs.1249.94

lakh.

Due to some land acquisition problem encountered, the tender was deferred and now, the

survey and investigation is being taken up for re-tendering of the work so that bids in two parts

can be invited during December- 2017and January-2018 under D.I.P.

Page 4: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

4

Natural Drains in Bhadrak Municipality

Sl. No Name of the Drain Length in Mtr.

1) NH5 to Salandi River- 2600

2) Neheru Stadium to Banth Chhak 600

3) Apartibindha, Elekha, Satabhauni to Nalia 3500

4) Dagamunda to NH5 1500

5) Kali Mandir to Rajaghat 1000

6) Dagamunda to Baudpur 2500

7) Sahapur to Motel Chhak to Chhapulia 2000

8) Gabasahi to Collector Residence to railway line 300

9) Chhapulia to Dholi 6710

10) Nazar Nallah 5160

Total- 25870 Mtr.

The main activities of this division are carried out through RIDF, DIP, Critical and other

State Funds. Constructions of Check Dams are also undertaken by this division to stabilise the

ayacut and provide irrigation from in-stream storage to crops during scarce rainfall and Rabi

season.

Staff Position

Sl. No Name of the Post Sanction

Strength

Men in

Position

Remark

1 Executive Engineer 1 1

2 Deputy Executive Engineer 1 2

3 Asst. Executive Engineer 4 3 One no. of AEE (Estimator) is

working on deputation basis

under Chief Engineer,

Drainage.

4 Asst. Engineer 6 5 Vacant-1

5 Junior Engineer 7 6 Vacant-1

1. RIDF Since 2004-05 to till 2015-16, Eleven no of projects were taken up under different tranche

of this scheme which are already completed. During 2016-17, two no of projects are taken up

under RIDF- XIX, status of which are as follows.

Page 5: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

5

PROJECTS UNDER RIDF-XIX (2016-17)

Sl. No Name of the Project Cost (Rs. in lakhs) Status

1 2 3 4

1 Construction of Control Sluice-cum-V.R. Bridge

at RD 1500 mtr. of Parapokhari Drainage Cut

near village Kasia in Basudevpur Block of

Bhadrak District under Kansabansa-Mantei

Doab No.XI.

197.16 Completed.

2 Renovation of Genguti Drainage Channel from

Jahangir to Khadi Mahara from RD 31.75 Km. to

12.60 Km. In Dhamnagar Block of Bhadrak

District under Salandi-Baitarani Doab No.XIII.

594.38 Completed.

2. Drainage Improvement Programme (D.I.P) Funds under this scheme were available from 2014-15. The area retrieved up to 2016-17

under DIP is mentioned below. Twenty five new projects are taken up during 2016-17, status of

which are placed at Annexure-B.

AREA RETRIVED WITH D.I.P.

(Up to 2016-17)

Sl.

No

Year No. of

Projects

taken

Cost of

Projects (in

lakhs)

No. of

Project

completed

No. of

Project

on going

Area retrieved (in

Ha)

Remark

Target Achieved

1 2 3 4 5 6 7 8 9

1 2014-15 52 460.994 52 0 250 250

2 2015-16 31 2958.648 31 0 4285 4285

3 2016-17 25 3478.618 7 18 8980 7240

Total 108 6898.260 90 18 13515 11775

3. Critical Lump The funds under this scheme is utilised to bridge the gap between this schemes D.I.P and

other grants for left over works which are felt direly necessary for public utility. The list of

projects executed during 2016-17are placed at Annexure-C.

4. Check Dam

155 no of Check Dams were completed under this scheme prior to 2016-17 and after their

completion 2117.50 Ha of land were benefited for irrigation. During 2016-17, Forty five no of new

Check Dams are taken up, status of which are placed at Annexure-D.

Page 6: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

6

Sl.

No

Name of the

Block

District Completed up to 2015-16 Completed

During

2016-17

2010-

11

2011-

12

2012-

13

2013-

14

2014-

15

2015-

16

1 2 3 4 5 6 7 8 9 10 1 Basudevpur Bhadrak 7 7 19 2 7 1

2 Bhadrak Bhadrak 7 2 12 1 5 17

3 Bhandaripokhari Bhadrak 6 1 3 4 0

4 Bonth Bhadrak 4 2 0 1 9 10

5 Chandabali Bhadrak 4 0 2 1 2 1

6 Dhamnagar Bhadrak 5 2 1 8

7 Tihidi Bhadrak 2 3 3 1 3

Total nos completed in Bhadrak

District

35 2 12 40 8 28 40

8 Khaira Balasore 1 4 1 2 2

9 Simulia Balasore 5 2 3 1 0

10 Anandapur Keonjhar 0

11 Hatadihi Keonjhar 1 4 3 3 3

Grand

Total

41 2 19 50 9 34 45

Cumulative total - 155 45

Page 7: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

7

STATUS OF DOAB

Name of the Doab Drainage

Area

(Catchment)

(In Ha)

GCA (In

Ha)

CCA (In

Ha)

Area

affected

with

waterlogging

(In Ha)

Area to

be

retrieve

(In Ha)

Farmers to

be

benefitted

Length of Drainage System (In Km)

Primary

Drain

Secondary

Drain

Link

Drain

Total

1 2 3 4 5 6 7 8 9 10 11

Kansabansa-Mantei

Doab No-XI

133070.00 63250.00 56600.00 17300.00 10500.00 145000.00 37.20 144.40 139.55 321.15

Mantei-Salandi

Doab No-XII

161965.00 85000.00 68000.00 14000.00 8500.00 125000.00 61.80 224.15 350.20 636.15

Salandi-Baitarani

Doab No-XIII

110485.00 68000.00 54400.00 950.00 5800.00 150000.00 104.70 166.10 160.60 431.40

Total 405520.00 216250.00 179000.00 40800.00 14800.00 270000.00 203.70 534.65 650.35 1388.70

Page 8: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

8

EXPENDUTURE STATEMENT FOR THE FINANCIAL YEAR 2016-17

Sl.

No.

Name of the Scheme Budgetary allotment with re-allocation

for the year 2016-17 (in lakhs)

Expenditure made up

to 28.02.2017 (in Lakhs)

Expenditure

made during 03/

2017

Cumulative

Expenditure

up to

31.03.2017

1 2 3 4 5 6

1 NABARD (RIDF-XIX) 177.730 144.496 33.234 177.730

2 DRAINAGE IMPROVEMENT

PROGRAMME (STATE PLAN) & State

Plan (Leftout CSP works)

2349.500 1996.485 352.455 2348.940

2749

.201

3 LA 366.510 359.956 6.554 366.510

4 Wages 32.030

16.627 3.284 19.911

5 W/C 9.925 0.065 9.990

6 M & E 2.900 2.233 0.667 2.900

7 T & P 2.800 0.950 0.000 0.950

8 CRITICAL LUMPS 176.000 127.005 48.608 175.613

9 REPAIR & MAINTENANCE (Works) 60.000 41.013 18.987 60.000

10 REPAIR & MAINTENANCE (Non-Res) 2.500 0.354 2.146 2.500

11 CHECK DAM (WHS) 555.000 454.863 100.119 554.982 Total 3724.970 3153.907 566.119 3720.026

Page 9: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

9

Annexure-A

Irrigation Division / Jurisdiction Boundary CEs / CCEs, Division, Sub-Division & Section

Sl.

No

.

Name of

CEs/CCEs

with

District

Name

under

his

control

Name of

Circle

with

District

Name

under

his

control

Name of

Division

with

District

Name

under

his

control

Name of

Sub-

Division

Name of the

Block under

control of Sub

Division

Name of

section Name of GPs / Village under control of section Remarks

Chief Engineer, Drainage, Cuttack

Drainage Circle,

Balasore

Drainage Division, Bhadrak

4 12

1

Jajpur, Bhadrak, Keonjhar (Part) and Balasore

Bhadrak, Balasore (Part) and Keonjhar (Part)

Sub Division-I, Chandbali

Chandabali

&Tihidi

Section-I, Chandabali

Sundarpur, Madhapur, Tentulidihi, Bhuibrutri, Adaastia,

Bhatapada, Chandabali, Panchapada, Motto, Mausuda,

Nalagahira, Aranjia, Orasahi, Bijayanagar, Uttukuda, Baligaon

GPs of Chandabali Block under Bhadrak District.

Section-II,Tihidi

Jaleswarpur, Jashipur, Nuagaon, Totapada, Gopinathpur,

Nalgunda, Ghatapur, Samantarapur, Bansada GPs of Chandabali

Block and Kanpada, Baro, Bilana, Talagopinathpur, Kubera GPs

of Tihidi Block under Bhadrak District.

Section-III, Bhadrak

Sindola, Maharampur, Saya, Bahabalpur (part), Bhatapada,

Kolha, Mukundapur, Mangalpur, Achhaka, Talapada,

Shayamsundarpur, Barsor, Gobindpur, Daulatpur,

Bamanbindha, Sahapur, Jamjodi, Rajnagar GPs of Tihidi Block

under Bhadrak District.

Page 10: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

10

Sub Division-II, Akhuapada

Bonth,

Bhandaripokhari,

Dhamnagar,

Tihidi of Bhadrak

District and

Hatadihi,

Anandapur of

Keonjhar District

Section-I, Akhuapada

Balipokhari, Ranjit, Jhutuna, Nereda, Solampur, Jalamandua,

Malada, Napang GPs of Bhandaripokhari Block, Anandapur

(Dihudi), Khadipada, Dobal, Muftaffapur, Soheda, Korada,

Padhani, Dolanga, Bhagabanpur Gps of Dhamnagar Block under

Bhadrak District.

Section-II, Bhandaripokhari

Naami, Bandalomadhialli, Rajendrapur, Sasan, Tesinga,

Ramachandrapur, Dakhinabad, Bayabanpur, Patudi, Nirgundi,

Bishnupur, Naguana, Sarsoda, Purigaon, Rahania GPs of

Bhandaripokhari Block, Dorada GP of Bhadrak Block, Todagaon,

Kenduapada, Gobindpur, Sendhatira, Nilak, Padhanpada, Bonth

GPs of Bonth Block under Bhadrak District, Gedema, Ayatpur,

Haboleswar, Sadanga, Danar, Salania, Inchaol, Sadanga, Orali,

Samona, Ambo, Panchugochhia, Badarampas, Sulana, Bancho,

Anara, Hatadihi GPs of Hatadihi Block, Kantipal GP of

Anandapur Block under Keonjhar District.

Section-III, Dhamnagar

Dhusuri, Sahaspur, Palasahi, Hasanabad, Arjunpur, Nadigaon,

Ghatasahi, Bayandihi, Dhamnagar, Jayanagar, Radhaballavpur,

Kalyani, Gobindpur, Dahipur, Chudakuti, Asurali, Kothar,

Gadialli, Kashimpur, Fatepur, Katsahi, Khaparpada, Raipur GPs

of Dhamnagar Block, Bodak, Shayamsundarpur,

Talagopabindha GPs of Tihidi Block of Bhadrak District.

Sub Division-III, Bhadrak

Bonth, Bhadrak,

Tihidi of Bhadrak

District and

Hatadihi of

Keonjhar District

Section-I, Bhadrak

Kedarpur, Berhampur, Goramati, Sabaranga, Erada,

Chandigaon, Jagadalpur, Rambhila, Banatia, Bandhagaon,

Amroli, Charampa, Erai, Bania, Porsinga, Korkora, Haripur,

Aranapal GPS of Bhadrak Block, Guamal, Paliiabindha, Talasahi

GPs of Tihidi Block under Bhadrak District.

Section-II, Bhadrak

Andreipalli, Bishnupurbindha, Kalei, Betara, Gelpur, Bentalo,

Khandatada, Gujidarada, Dohisingh, Kaupur, Rahandia,

Baudpur, Olanga, Talanga GPS of Bhadrak Block under Bhadrak

District.

Section-III, Bonth

Rampur, Ramakrushnapur, Ganijanga, Chhayalsingh, Tillo,

Basantia, Ramachandrapur, Adia, Odanga, Kadabaranga,

Badabarchikainya, Anijo, Badamainshigothha, Charigaon,

Gopinathpur, Btpur, Mohantypoda, Purusandho GPs of Bonth

Block under Bhadrak District, Sodha, Jambhira, Pandado,

Dhenka, Sasho, Balibarei, Mithigaon, Sashan, Padhiaripalli,

Akarua, Mareigaon GPs of Keonjhar District.

Page 11: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

11

Sub Division-IV,

Markona

Basudevpur,

Chandabali,

Tihidi of

Bhadrak

District and

Simulia, Khaira,

Soro of

Balasore

District.

Section-I, Markona

Ada, Iswarpur, Sabanga, Anandapur, Bauripada,

Markona, Bangar Khadigadia, Maitapur, Muruna,

Purusottampur, Abjuna, Jamujhadi,

Shayamsundarpur, Pahipuruna, Bati, Bangalpur of

Markona Block and Dungura, Jhinkiria, Manitri,

Badajaypur, Rapeya, Barada, Antara, Saradanga,

Bartana and Badanuagaon GPs of Khaira Block under

Balasore District.

Section-II, Basudevpur

Bari, Kanchapada, Andrei, Kanheibindha, Khirkona,

Chalunigaon GPs of Simulia Block, Tentei of Soro

Block under Balasore District and Padmapur, Sugo,

Ertal, Lunga, Guagadia, Brahamnigaon, Binayakpur,

Arandua, Barandua, Narisinghpur, Arua,

Sudarsanpur, Bachhada, Jaganathpur, Nuagaon,

Eram, Chudamani-01, Padhuan, Adhuan, Kumarpur

GPs of Basudevpur Block under Bhadrak District.

Section-III, Basudevpur

Chudamani-02, Kismat-Krushnapur, Krushnapur,

Binabha-bhabenagar, Bideipur, Gopabandhunagar,

Balimunda, Naikanidihi, Karanjadia, Andola,

Gobindpur, Rajgharpokhari, Balimed, Laxmidaspur,

Jaganthprasad, Biras GPs of Basudevpur Block,

Bhabalpur GP of Thidi Block and Kranpalli,

Panchutikiri, Karanjamala, Kaithokala, Dosinga,

Narisinghpur, Jagula and Bansada GPs of Chnadabali

Block under Bhadrak District.

Page 12: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

12

Annexure-B

DRAINAGE IMPROVEMENT PROGRAMME (D.I.P.) FOR THE FINANCIAL YAER 2016-17 Sl No

Name of work Agreement Date of commence

ment

Date of completion

Present status

(Ongoing/ Complete)

District Block Constituency Doab No

Remarks (Sub-

Division involve)

No Amount (In Lakh)

1 Improvement to D.C Kaudia & its Links ,BauriNalla, Baligaon Mahara, Kaharagohiri to Jadadhari Near Village Panaspada, Nuagaon to Sukleswar, BauriNalla tail end to Kanigodia,Baitarani to Ghusuriganda Thukura mahara, Chadeikhia Nalla (Tentulidiha), Charimania Nalla (Tentulidiha) Thokaramahara (Thokara) Patanali (Bhuinbruti) including Foot Bridge.

28 P1 /16-17

83.966 27.06.2016 26.01.2017 On going Bhadrak Chandabali Chandbali XII Chandabali

2 Improvement of Lunijore (Mantei river to Khatua Sahi sluice) and its Link Drain (Rout Sahi nallah, Anugrahpur to Rampur and Batitangi Nuanala Drainage Channel) in Salandi Mantei Doab No-XII.

36P1/ 16-17

171.790 25.07.2016 24.08.2017 On going Bhadrak Chandabali Chandabali XII Chandabali

3 Renovation of Kansabansa Drainage Channel from RD 54.50 Km to 47.50 Km from village Kanheibanka to Kabirpur in Doab No-XI.

18F2/ 16-17 216.466 21.06.2016 20.05.2017 On going Balasore Simulia/ Soro Simulia/ Soro XI Markona

4 Improvement to Rebo DC (from RD 22.48 Km to 28.80 Km and its link drains and from RD 3.50km to 16.00 km with its link drain, improvement Parvati DC)

17P1/ 16-17

382.817 20.06.2016 19.12.2017 On going Bhadrak/ Keonjhar

Bhadraripokari/ Bonth/ Hatadihi

Bhandaripokari/ Anandapur XII Akhuapda

5 Improvement of Kapali Drainage Channel from Village Kantigodia to Palasa in Chayalsingh and Ganijanga G.P.

01P1/ 16-17

39.770 19.04.2016 18.08.2016 Completed Bhadrak Bonth Bhandaripokhari XII Bhadrak

6 Improvement to Parbati DC with its link drain & const of 3 nos of Foot bridge and 3 nos of Culvert in Gohira DC.

29P1/ 16-17

73.600 27.06.2016 26.03.2017 On going Bhadrak Bhandaripokhari Bhandaripokhari XII Akhuapada

7 Improvement to Khandikapali DC (NH-5 to HLC Range-III) & FB at Gaudasahi & Construction of Slope protection work over rebo DC near village Nirgundi.

30P1/ 16-17

83.726 27.06.2016 26.03.2017 Completed Bhadrak Bhandaripokhari Bhandaripokhari XII Akhuapada

8 Construction of concrete road near village Hatiapada to Kapali drainage channel of Bhadarak Ditrict Doab XIII

15P1/ 16-17

14.030 16.06.2016 15.10.2016 Completed Bhadrak Dhamnagar Dhamnagar XII Akhuapada

Page 13: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

13

9 Improvement to Mantei Drainage Cum Creek along with its R/S Link Drains (Renovation of Kundi nallah, Dhali nai, Dhanatari, Hadigohiri & Siba Nalla its link drain Khandakusi) in Salandi Baitarani Doab No-XIII.

112P1/ 16-17

284.571 23.12.2016 22.01.2018 On going Bhadrak Bhadrak/

Basudevpur Bhadrak/

Basudevpur XIII Bhadrak

10 Improvement to Khandia nallah & Balichatri nallah and its link drains under Salandi-Baitarani Doab No-XIII.

84P1/ 16-17

271.736 05.12.2016 04.01.2018 On going Bhadrak Dhamnagar Dhamnagar XIII Akhuapada

11 Improvement to Link drain Salandi & construction of VRB at Pati sahi and Hansisahi, Rasasagar nalla Const of FB at RG Patana (Jenasahi), Raimani Nalla & Const. of HP culvert, Dankagodia DC & Const of FB , Protection wall to FB at Kaupur and Const of VRB at pattnaik Chhaka link Drain of Salandi (Olanga Daising & Kaupur GP).

64P1/ 16-17

79.413 23.11.2016 22.10.2017 On going Bhadrak Bhadrak Bhadrak XIII Bhadrak

12 Improvement to Kundi nalla at Rasalpur and construction of FB, Harizonsahi Nalla at Saspur and construction HP Culvert, Barakali Nalla to Gopalia canal and construction of FB, Ghodamahara nalla and construction of FB at Jenasahi and culvert at Beherasahi (in Gujidarada, Kedarpur and Bental GP). DC from Mohantypada Haladibani, DC from Andharia to Padhiaripali (Purusanda GP) and VRB at Bodak Mahajib and protection wall at Andharia.

63P1/ 16-17

76.134 23.11.2016 22.10.2017 On going Bhadrak Bhadrak Bhadrak XIII Bhadrak

13 Improvement to Drainage Channel from Charampa ITI to Kadagambhir village, DC from Kadabaranga nalla to Khathagodia and construction of FB, DC from Khandakati sluice gate to Nimagohiri nalla and construction of FB, DC from Khandakati nalla to Sankhari nalla, Renovation of Matia nalla and construction of FB at Haripur (in Chandigaon, Sabaranga).

103P1/ 16-17

173.437 20.12.2016 19.01.2018 On going Bhadrak Bhadrak Bhadrak XIII Bhadrak

14 Improvement to Drainage Channel of Bhatia, Sialia, Batasia, Bhatialanji, Sarughai, Barokali, Dasndikula, Dandiand Ganapati Mahara with 2 nos of Foot bridge.

53P1/ 16-17

82.524 18.11.2016 17.10.2017 On going Bhadrak Dhamnagar Dhamnagar XIII Akhuapada

15 Improvement to Drainage channel of Sibapur, Sata, Patanalla, Baigan Chanda, Rajualibandha, Ekulya, Nidhimahara, Shalogaon, Batapani Drains with 2 nos of Foot bridge.

66P1/ 16-17

80.656 25.11.2016 14.10.2017 On going Bhadrak Dhamnagar Dhamnagar XII Akhuapada

Page 14: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

14

16 Improvement of DC from Bada Haripur to Begunia via Uttukuda and it's link drain, Uttukuda to Mruganayani via Biswali, Singiti Matha to Dian Nalla via Orasahi Red Cross Chamber, Bijayanagara to Kusuma, Improvement to Gaibata nalla, Gohiri nalla, Thakura nalla (Radha Krushna nalla), Guja nalla link drain to Pithia sendha, Banamati Gohiri, Brahmani Pokhari to Banamati Gohiri and construction of VRB on Bijayanagar GP, Orasahi GP, Utukuda GP.

95P1/ 16-17

281.761 17.12.2016 16.01.2018 On going Bhadrak Chandabali Chandbali XII Chandabali

17 Improvement to Drainage Channels, construction of Foot bridges/VRBs, Culverts, Slope protection works and drainage sluices and check dams in Bahabalpur G.P. of Tihidi Block in Kansabansa-Mantei Doab No-XI

69P1/ 16-17

64.615 29.11.2016 24.10.2017 On going Bhadrak Tihidi Basudevpur XI Markona

18 Improvement to Drainage Channels, construction of Foot bridges/VRBs, Culverts, Slope protection works and drainage sluices/check dams in Jagannathprasad and Laxmidaspur GP of Basudevpur Block in Kansabansa-Mantei Doab No-XI

76P1/ 16-17

80.333 29.11.2016 24.10.2017 Completed Bhadrak Basudevpur Basudevpur XI Markona

19 Improvement to Drainage Channels, construction of Foot bridges/VRBs, Culverts, Slope protection works and drainage sluices and check dams in Balimed GP of Basudevpur Block in Kansabansa-Mantei Doab No-XI

83P1/ 16-17

62.970 06.12.2016 05.11.2017 Completed Bhadrak Basudevpur Basudevpur XI Markona

23 Gate works of control sluice cum VRB at RD 1500Mtr over Parapokhari Drainage cut near village Kasia

42F2/ 16-17

55.274 19.09.2016 18.09.2017 Completed Bhadrak Basudevpur Basudevpur XI Markona

24 Improvement to Janadiha Nalla (Balichatri) Drainage Channel and its link drain under Salandi-Baitarani Doab No-XIII

119P1/ 16-17

119.648 24.12.2016 23.01.2018 On going Bhadrak Bhandaripokhari Bhandaripokhari XII Akhuapada

25 Improvement to Drainage Channel of Gajabagicha, Sundarmahara, Ganjanalla, Desibilla, Baulamala, Talabila, Patribindha with with 3 nos of Foot bridge & slope protection at Pandarbatia.

125P1/ 16-17

117.818 26.12.2016 25.01.2018 On going Bhadrak Dhamnagar Dhamnagar XII Akhuapada

Total 2897.055

Page 15: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

15

Annexure-C

CRITICAL LUMPS FOR THE FINANCIAL YAER 2016-17

Sl. No.

Name of the work Estimated Amt/

Sactioned Amt (In lakhs)

Agt. No.

Agt. cost. Dt of Commencement

/ Dt of completion

District Block Constituency Remarks

1 2 3 4 5 6 7 8 9 10

1 Construction of Foot Bridge over Parapokhari Drainage Cut near Tukuna Jena's under Jagannath Prasad G.P., Basudevpur Block of Bhadrak District.

16.03 35P1/ 16-17

13.611 21.07.16/ 20.03.17

Bhadrak Basudevpur Basudevpur Work completed

2 Construction of Box-cell culvert over Dasadiha DC near Sanakandi house of Jayakrushnapur village of Basudevpur Block.

9.69 07P1/ 16-17

8.216 04.06.16/ 03.10.16

Bhadrak Basudevpur Basudevpur -do-

3 Construction of Foot Bridge over Basuli Canal at Dadhibamanpur to Dangamal Road under Jagannath Prasad G.P., Basudevpur Block of Bhadrak District.

10.33 39P1/ 16-17

8.760 06.08.16/ 05.04.17

Bhadrak Basudevpur Basudevpur -do-

4 Improvement to Kanhei Drainage Channel near Aliha Check Dam and its service canal.

10.09 21P1/ 16-17

8.960 22.06.16/ 21.10.16

Balasore Khaira Simulia -do-

5 Construction of Foot Bridges over Kanchudi Drainage Channel near village Kumbharsahi & Swainsahi of Abjona G.P. of Samanathpur village.

31.90 11P1/ 16-17

27.076 10.06.16/ 09.02.17

Balasore Simulia Simulia -do-

6 Construction of FB over Mathasahi nallah near village Chadeipada

6.32 06P1/ 16-17

5.366 04.06.16/ 03.10.16

Bhadrak Chandabali Chandabali -do-

7 Construction of Foot Bridge over DC Khamar nallah near village Uttakada

6.74 33P1/ 16-17

6.723 16.07.16/ 15.11.16

Bhadrak Chandabali Chandabali -do-

8 Construction of Foot Bridge over DC Bada nallah to Badapada near village Talabandha.

8.75 40P1/ 16-17

7.422 09.08.16/ 08.12.16

Bhadrak Chandabali Chandabali -do-

9 Construction of Foot Bridge over DC Naikani Maa nallah near village Naguan Ichhapur.

6.36 09P1/ 16-17

5.398 08.06.16/ 07.10.16

Bhadrak Chandabali Chandabali -do-

10 Construction of Foot Bridge over Kelasahi to Nagarpetta nallah.

10.23 41P1/ 16-17

8.685 10.08.16/ 09.12.16

Bhadrak Tihidi Basudevpur -do-

Page 16: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

16

11 Construction of Foot Bridge over Ankira DC near village Habelswar, Dattasahi.

7.90 37P1/ 16-17

6.702 19.07.16/ 24.11.16

Keonjhar Hatadihi Anandapur Work Completed

12 Construction of Box cell culvert over DC Nami to Rebo near village Sankhula.

8.96 08P1/ 16-17

7.607 04.06.16/ 03.10.16

Bhadrak Bhandaripokhari Bhandaripokhari -do-

13 Construction of Foot Bridge over link drain of Jaw Nai near village Kubergadia.

7.79 10P1/ 16-17

6.601 08.06.16/ 07.10.16

Bhadrak Bhandaripokhari Bhandaripokhari -do-

14 Construction of protection wall near School & Masjid near village Pandarbatia.

14.64 12P1/ 16-17

12.436 10.06.16/ 09.10.16

Bhadrak Dhamanagar Dhamnagar -do-

15 Construction of Foot Bridge over Darkata nallah near village Katika

8.91 16P1/ 16-17

7.559 16.06.16/ 15.10.16

Bhadrak Dhamanagar Dhamnagar -do-

16 Construction of Foot Bridge over link drain to Kundi Nallah at Radhigohiri near Padiharisahi.

9.38 14P1/ 16-17

7.962 16.06.16/ 15.10.16

Bhadrak Tihidi Bhadrak -do-

17 Construction of Foot Bridge over Kapali DC near village Ramachandrapur.

19.94 13P1/ 16-17

16.926 16.06.16/ 15.02.17

Bhadrak Bonth Bhandaripokhari -do-

18 Srengthening of Foot Bridge of Nazar Nallah near village Mirzapur.

3.87 Bhadrak Bhadrak Bhadrak -do-

19 Construction of Box cell culvert near Barapada Medical over DC Dankagadia.

1.97 72F2/ 16-17

1.972 29.11.16/ 28.12.16

Bhadrak Bhadrak Bhadrak -do-

20 Constrction of Boxcell culvert at Sahadagadia near Kadabarang.

4.73 Bhadrak Bonth Bhadrak -do-

21 Construction of Foot Bridge over Kundi nallah near village Sabarang.

9.48 34P1/ 16-17

8.049 19.07.16/ 18.11.16

Bhadrak Bhadrak Bhadrak -do-

22 Construction of Concrete Drain at Kalidaspur of Basudevpur Block of Bhadrak District.

Bhadrak Basudevpur Basudevpur Not executed

23 Construction of Foot Bridge on Panigohiri Maharanala near village Binatara under G.P. Baigam.

8.73 31P1/ 16-17

7.018 16.07.16/ 15.11.16

Bhadrak Chandabali Chandabali Work Completed

24 Construction of Foot Bridge at Chakeisahi Nalla near village Chakeisahi under G.P. Utukuda.

8.30 32P1/ 16-17

5.715 16.07.16/ 15.11.16

Bhadrak Chandabali Chandabali -do-

Total 231.04 188.764

Page 17: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

17

Annexure-D

CHECK DAMS FOR THE FINANCIAL YAER 2016-17 Sl. No.

Name of the work. Cost of the

project (lakhs)

Agt. No. Agt . Amount

(In Lakhs)

District. Block Constituency Date of commencement

Date of completion

Area benefited (in Ha.)

Remarks (Status of

work)

1 Construction of Check Dam at Rajabandha to Mangalpur Nalla (Pandasahi) Baligohira Nalla.

10.326 8.590 03P1/ 16-17

Bhadrak Tihidi Basudevpur 19.04.16 18.08.16 28 Work completed

2 Construction of Check Dam over Kanchudimahara Nalla infront of Malapada School.

7.414 6.240 04P1/ 16-17

Bhadrak Bhadrak Bhadrak 20.04.16 19.08.16 15 -do-

3 Construction of Check Dam over from DC Ricket to Jayakrushnapur near Fakirpur village.

7.459 6.933 05P1/ 16-17

Bhadrak Basudevpur Basudevpur 03.06.16 02.09.16 6 -do-

4 Construction of Check Dam over Jana Nalla near village Bhatasahi.

10.499 9.152 25P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 23.06.16 22.10.16 10 -do-

5 Construction of Check Dam over Bada nalla near village Itapala.

9.421 8.261 19P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 21.06.16 20.10.16 12 -do-

6 Construction of Check Dam over Kuakhia Nalla near Jamuna Dasa Matha, Dhusuri.

10.199 9.013 23P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 23.06.16 22.10.16 15 -do-

7 Construction of Check Dam over Khala Nalla near village Solagaon.

9.348 8.278 24P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 23.06.16 22.10.16 8 -do-

8 Construction of Check Dam over Sahusahi Mahara near village Betaligaon.

10.547 9.179 20P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 21.06.16 20.10.16 20 -do-

9 Construction of Check Dam over Dapanaikani Nalla near village Falapur.

10.283 8.960 22P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 23.06.16 22.10.16 10 -do-

10 Construction of Check Dam over Mgura Nalla Katasahi of Khaparpada G.P.

10.433 9.099 27P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 27.06.16 26.10.16 15 -do-

11 Construction of Check Dam over Kuamuin Nalla (Genguti Mahara) near village Palasahi.

9.556 8.969 124P1/ 16-17

Bhadrak Dhamnagar Dhamnagar 26.12.16 25.03.17 8 -do-

12 Construction of Check Dam over Dhaniabandha nallah near Dhaniabandha of Ratina GP in Khaira Block.

8.097 7.205 78P1/ 16-17

Balasore Khaira Simulia 01.12.16 28.02.17 8 -do-

13 Construction of Check Dam over Dhaniabandha nallah near Palasagadia of Ratina GP in Khaira Block.

8.108 7.214 80P1/ 16-17

Balasore Khaira Simulia 03.12.16 02.03.17 8 -do-

14 Construction of Check Dam over Suna Arangi Nalla near village Sana Aranji under Ganijanga G.P.

7.490 6.338 75P1/ 16-17

Bhadrak Bonth Bhandaripokhari 29.11.16 28.02.17 15 -do-

15 Construction of Check Dam over Koranta Nalla near village Aranji under Ganijanga G.P.

7.422 6.260 82P1/ 16-17

Bhadrak Bonth Bhandaripokhari 06.12.16 05.03.17 15 -do-

Page 18: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

18

16 Construction of Check Dam over link drain of Kapali near village Ramachandrapur Adibasi sahi.

9.884 8.268 65P1/ 16-17

Bhadrak Bonth Bhandaripokhari 23.11.16 22.02.17 20 Work completed

17 Construction of Check Dam over link drain to Kapali near village Sada (Chowdhurisahi).

9.019 7.524 81P1/ 16-17

Keonjhar Hatadihi Anandapur 06.12.16 05.03.17 20 -do-

18 Construction of Check Dam over link drain to Kapali near village Ambagadia.

9.063 7.581 54P1/ 16-17

Keonjhar Hatadihi Anandapur 18.11.16 17.02.17 15 -do-

19 Construction of Check Dam over Banaganthi nallah near village Brundabanpur under Ganijanga G.P.

7.449 6.249 79P1/ 16-17

Bhadrak Bonth Bhandaripokhari 01.12.16 28.02.17 15 -do-

20 Construction of Check Dam over Jhatiapada Nalla under Amroli G.P.

8.371 7.037 58P1/ 16-17

Bhadrak Bhadrak Bhadrak 22.11.16 21.02.17 15 -do-

21 Construction of Check Dam over link drain of Salandi near village Arrei (Chunati).

7.981 6.661 74P1/ 16-17

Bhadrak Bhadrak Bhadrak 29.11.16 28.02.17 14 -do-

22 Construction of Check Dam over Sarala nallah under Dolasahi G.P.

7.995 6.765 59P1/ 16-17

Bhadrak Tihidi Dhamnagar 22.11.16 21.02.17 15 -do-

23 Construction of Check Dam over Nayanjori (near Haripur S/M) under Palibindha G.P.

8.316 8.115 134P1/ 16-17

Bhadrak Tihidi Bhadrak 26.12.16 25.03.18 15 -do-

24 Construction of Check Dam over Jena Bandha Nallah near village Brundabanpur under Ganijanga G.P.

7.422 6.289 85P1/ 16-17

Bhadrak Bonth Bhandaripokhari 09.12.16 08.03.17 15 -do-

25 Construction of Check Dam over link drain to Kapali near village Sada (Jambhira).

9.671 8.069 61P1/ 16-17

Keonjhar Hatadihi Anandapur 23.11.16 22.02.17 15 -do-

26 Construction of Check Dam over Sapua Nallah under Korkora G.P. (Kendriya Vidyalaya)

14.039 11.592 70P1/ 16-17

Bhadrak Bhadrak Bhadrak 26.11.16 28.02.17 20 -do-

27 Construction of Check Dam over link drain of Sarusagar nallah near village Totasahi.

8.350 7.718 60P1/ 16-17

Bhadrak Bonth Bhandaripokhari 23.11.16 22.02.17 10 -do-

28 Construction of Check Dam over link drain of Salandi at Khandagadia near Kuntala village.

8.010 6.724 62P1/ 16-17

Bhadrak Bhadrak Bhadrak 23.11.16 22.02.17 14 -do-

29 Construction of Check Dam over Sunamuhin nalla near Talanga village under Ambroli G.P.

8.593 7.171 55P1/ 16-17

Bhadrak Bhadrak Bhadrak 19.11.16 18.02.17 15 -do-

30 Construction of Check Dam over Bada Nallah under Chandigaon G.P.

7.798 6.601 77P1/ 16-17

Bhadrak Bhadrak Bhadrak 01.12.16 28.02.17 15 -do-

31 Construction of Check Dam over link drain near village Sabaranga under Sabranga G.P.

9.280 7.811 86P1/ 16-17

Bhadrak Bhadrak Bhadrak 09.12.16 08.03.17 15 -do-

32 Construction Check Dam over Kundi nallah at Paliabindha.

9.949 9.821 129P1/ 16-17

Bhadrak Bhadrak Bhadrak 26.12.16 25.03.17 15 -do-

33 Construction of Check Dam over Akala Nallah near village Chunati under Erei G.P.

8.439 7.519 56P1/ 16-17

Bhadrak Bhadrak Bhadrak 19.11.16 18.02.17 15 -do-

Page 19: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

19

34 Construction of Check Dam over Kundi nallah near Mohantypada at Haladibani.

9.709 9.582 138P1/ 16-17

Bhadrak Bonth Bhandaripokhari 26.12.16 25.03.17 16 Work completed

35 Construction of Check Dam over Karandi Gohiri nalla near Panguda village.

9.269 8.661 114P1/ 16-17

Bhadrak Chandabali Chandabali 24.12.16 23.03.17 32 -do-

36 Construction of Check Dam over link drain of Sarusagar nallah near village Binapur.

9.293 7.809 107P1/ 16-17

Bhadrak Bonth Bhandaripokhari 22.12.16 21.03.17 13 -do-

37 Construction of Check Dam over DC from Gharapada to Narayanpur near village Binjha (Roul Plot).

9.405 9.281 126P1/ 16-17

Bhadrak Bonth Bhandaripokhari 26.12.16 25.03.17 5 -do-

38 Construction of Check Dam over Rasasagar nallah near village RG Patna.

15.913 13.379 106P1/ 16-17

Bhadrak Bhadrak Bhadrak 22.12.16 21.03.17 10 -do-

39 Construction of Check Dam over DC from Debatagadia to Gopalpur near village Debatagadia.

10.662 8.916 98P1/ 16-17

Bhadrak Bonth Bhandaripokhari 17.12.16 16.03.17 8 -do-

40 Construction of Check Dam over Charagadia nallah near village Sridharpur.

10.431 8.722 115P1/ 16-17

Bhadrak Bhadrak Bhadrak 24.12.16 23.03.17 6 -do-

41 Construction of Check Dam over Talapadi Jhatia nalla under Ambroli GP.

7.495 5.151 123P1/ 16-17

Bhadrak Bhadrak Bhadrak 26.12.16 25.03.17 4 -do-

42 Construction of Check Dam over Pagoda Bada nalla near village Chandigaon under Chandigaon GP.

7.817 6.644 122P1/ 16-17

Bhadrak Bhadrak Bhadrak 24.12.16 23.03.17 5 -do-

43 Construction of Check Dam over Jalanga Chhapulia Sunamunhi nallah under Ambroli GP.

7.860 6.932 108P1/ 16-17

Bhadrak Bhadrak Bhadrak 22.12.16 21.03.17 5 -do-

44 Construction of Check Dam over Bali nalla near village Baranga under Sabaranga GP.

7.860 6.932 109P1/ 16-17

Bhadrak Bhadrak Bhadrak 23.12.16 22.03.17 4 -do-

45 Construction of Check Dam over Raghunathpur Bada nalla under Sadha GP.

7.860 5.723 111P1/ 16-17

Bhadrak Bhadrak Bhadrak 23.12.16 22.03.17 4 -do-

409.805 354.938 583

Page 20: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

PHOTOGRAPHS:-

GATED WORKS OF CRONTROL SLUICE CUM V.R.BRIDGE AT RD 6500 MTR OF

PARAPOKHARI DRAINAGE CUT NEAR VILLAGE CHANDIMAL

VRB AT RD 73.480 KM NEAR VILLAGE BALISARA OVER KANSABANSA DRAINAGE

20

GATED WORKS OF CRONTROL SLUICE CUM V.R.BRIDGE AT RD 6500 MTR OF

PARAPOKHARI DRAINAGE CUT NEAR VILLAGE CHANDIMAL

73.480 KM NEAR VILLAGE BALISARA OVER KANSABANSA DRAINAGE

CHANNEL.

GATED WORKS OF CRONTROL SLUICE CUM V.R.BRIDGE AT RD 6500 MTR OF

PARAPOKHARI DRAINAGE CUT NEAR VILLAGE CHANDIMAL

73.480 KM NEAR VILLAGE BALISARA OVER KANSABANSA DRAINAGE

Page 21: ACTIVITY REPORT OF DRAINAGE DIVISION, …...1 Construction of Control Sluice-cum-V.R. Bridge at RD 1500 mtr. of Parapokhari Drainage Cut near village Kasia in Basudevpur Block of Bhadrak

CHECK DAM OVER PANIBHANRA CREEK AT PURUSOTTAMPUR VILLAGE.

IMPROVEMENT TO GENGUTI DRAINAGE CHANNEL WITH SLOPE PROTECTION

WORK NEAR VILLAGE MIRGAHATKUL AT RD 25.20KM

21

CHECK DAM OVER PANIBHANRA CREEK AT PURUSOTTAMPUR VILLAGE.

(BASUDEVPUR BLOCK)

IMPROVEMENT TO GENGUTI DRAINAGE CHANNEL WITH SLOPE PROTECTION

WORK NEAR VILLAGE MIRGAHATKUL AT RD 25.20KM

Executive Engineer,

Drainage Division, Bhadrak.

CHECK DAM OVER PANIBHANRA CREEK AT PURUSOTTAMPUR VILLAGE.

IMPROVEMENT TO GENGUTI DRAINAGE CHANNEL WITH SLOPE PROTECTION

WORK NEAR VILLAGE MIRGAHATKUL AT RD 25.20KM.

Executive Engineer,

Division, Bhadrak.