Activity Networks Example 3matematik

download Activity Networks Example 3matematik

of 24

Transcript of Activity Networks Example 3matematik

  • 7/28/2019 Activity Networks Example 3matematik

    1/24

    Activity networks Example 3

    Task Duration (days) Immediate

    predecessors

    A 2 -

    B 4 -

    C 5 A, B

    D 3 B

    E 6 C

    F 3 C

    G 8 D

    H 2 D, F

    The table below shows the tasks involved in a project,

    with their durations and immediate predecessors.

    Draw an activity network and use it to find the critical

    activities and the minimum duration of the project.

  • 7/28/2019 Activity Networks Example 3matematik

    2/24

    Activity networks Example 3

    Begin with a start node,

    labelled 1.

    Activities A and B have no

    preceding activities, so can

    both begin at the start node.

    A(2)

    B(4)

    1

  • 7/28/2019 Activity Networks Example 3matematik

    3/24

    Activity networks Example 3

    Activity C depends on both A

    and B, but activity D

    depends on B only.

    We can deal with this by

    adding a dummy activity.

    A(2)

    B(4)

    1

    3

    2

  • 7/28/2019 Activity Networks Example 3matematik

    4/24

    Activity networks Example 3

    Now add activity C, which

    depends on both A and B ...

    and activity D, which

    depends on B only.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

  • 7/28/2019 Activity Networks Example 3matematik

    5/24

    Activity networks Example 3

    Activities E and F depend on

    C only

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    and activity G depends on

    D only.

    4

    5

    E(6)

    F(3)

    G(8)

  • 7/28/2019 Activity Networks Example 3matematik

    6/24

    Activity networks Example 3

    Activity H depends on

    activities D and F.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    To deal with this, we need a

    dummy activity from event 5.

    4E(6)

    F(3)

    G(8)

    5

    Now activity H can be added.

    6

    H(2)

  • 7/28/2019 Activity Networks Example 3matematik

    7/24

    Activity networks Example 3

    A finish node is now needed.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4E(6)

    F(3)

    G(8)5

    6

    H(2)

    E(6)

    G(8)

    7

  • 7/28/2019 Activity Networks Example 3matematik

    8/24

    Activity networks Example 3

    The next step is to find the

    early event times (EETs).

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    7

  • 7/28/2019 Activity Networks Example 3matematik

    9/24

    Activity networks Example 3

    Event 1 occurs at time zero.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

  • 7/28/2019 Activity Networks Example 3matematik

    10/24

    Activity networks Example 3

    Event 2 cannot occur until B

    has finished, so the earliest

    time for event 2 is 4.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

  • 7/28/2019 Activity Networks Example 3matematik

    11/24

    Activity networks Example 3

    Event 3 cannot occur until

    both A and B have finished,

    so the earliest time for event

    3 is 4.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4

  • 7/28/2019 Activity Networks Example 3matematik

    12/24

    Activity networks Example 3

    Event 4 cannot occur until C

    has finished, so the earliest

    time for event 4 is 4 + 5 = 9.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

  • 7/28/2019 Activity Networks Example 3matematik

    13/24

    Activity networks Example 3

    Event 5 cannot occur until D

    has finished, so the earliest

    time for event 5 is 4 + 3 = 7.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

  • 7/28/2019 Activity Networks Example 3matematik

    14/24

    Activity networks Example 3

    Event 6 cannot occur until both D and F

    have finished. The earliest time that D can

    finish is 7, and the earliest time that F can

    finish is 9 + 3 = 12, so the earliest time for

    event 6 is 12.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

  • 7/28/2019 Activity Networks Example 3matematik

    15/24

    Activity networks Example 3

    Event 7 cannot occur until E, G and H have all finished.

    The earliest time that E can finish is 9 + 6 = 15, the

    earliest time that G can finish is 7 + 8 = 15, and the

    earliest time that H can finish is 12 + 2 = 14, so the

    earliest time for event 7 is 15.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15

  • 7/28/2019 Activity Networks Example 3matematik

    16/24

    Activity networks Example 3

    The next step is to find the late event

    times (LETs), working backwards

    through the network.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15

  • 7/28/2019 Activity Networks Example 3matematik

    17/24

    Activity networks Example 3

    The latest time that event 7 can occur

    without delaying the project is 15.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

  • 7/28/2019 Activity Networks Example 3matematik

    18/24

    Activity networks Example 3

    The latest time that activity H can start

    is 13, so the latest time for event 6 is

    13.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

  • 7/28/2019 Activity Networks Example 3matematik

    19/24

    Activity networks Example 3

    Activity G and a dummy activity both lead out of

    event 5. The latest time that activity G can start is

    7, and the latest time that the dummy activity can

    start is 13, so the latest time for event 5 is 7.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

    7

  • 7/28/2019 Activity Networks Example 3matematik

    20/24

    Activity networks Example 3

    Activities E and F both lead out of event 4. The

    latest time that activity E can start is 9, and the

    latest time that activity F can start is 9, so the

    latest time for event 4 is 9.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

    7

    9

  • 7/28/2019 Activity Networks Example 3matematik

    21/24

    Activity networks Example 3

    The latest time that activity C

    can start is 4, so the latest time

    for event 3 is 4.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

    7

    94

  • 7/28/2019 Activity Networks Example 3matematik

    22/24

    Activity networks Example 3

    Activity D and a dummy activity both lead out of

    event 2. The latest time that activity D can start

    is 6, and the latest time that the dummy activity

    can start is 4, so the latest time for event 2 is 4.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

    7

    94

    4

  • 7/28/2019 Activity Networks Example 3matematik

    23/24

    Activity networks Example 3

    Finally, the latest time for event 1 is zero.

    A(2)

    B(4)

    1

    3

    2

    C(5)

    D(3)

    4

    F(3)

    5

    6

    H(2)

    E(6)

    G(8)

    70

    4

    4 9

    7

    12

    15 15

    13

    7

    94

    4

    0

  • 7/28/2019 Activity Networks Example 3matematik

    24/24

    Activity networks Example 3

    The minimum duration of the project is 15 days.

    A(2)

    B(4)

    C(5)

    D(3)

    F(3)

    6

    H(2)

    E(6)

    G(8)

    0

    4

    4 9

    7

    12

    15 15

    13

    7

    94

    4

    0

    The critical activities are B, C, D, E and G.

    2

    1

    3 4

    7

    5

    Notice that there are two critical paths: BCE

    and BDH.

    The float in this example

    is analysed in the Notes

    and Examples.

    http://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdf