Activity Networks Example 3matematik
Transcript of Activity Networks Example 3matematik
-
7/28/2019 Activity Networks Example 3matematik
1/24
Activity networks Example 3
Task Duration (days) Immediate
predecessors
A 2 -
B 4 -
C 5 A, B
D 3 B
E 6 C
F 3 C
G 8 D
H 2 D, F
The table below shows the tasks involved in a project,
with their durations and immediate predecessors.
Draw an activity network and use it to find the critical
activities and the minimum duration of the project.
-
7/28/2019 Activity Networks Example 3matematik
2/24
Activity networks Example 3
Begin with a start node,
labelled 1.
Activities A and B have no
preceding activities, so can
both begin at the start node.
A(2)
B(4)
1
-
7/28/2019 Activity Networks Example 3matematik
3/24
Activity networks Example 3
Activity C depends on both A
and B, but activity D
depends on B only.
We can deal with this by
adding a dummy activity.
A(2)
B(4)
1
3
2
-
7/28/2019 Activity Networks Example 3matematik
4/24
Activity networks Example 3
Now add activity C, which
depends on both A and B ...
and activity D, which
depends on B only.
A(2)
B(4)
1
3
2
C(5)
D(3)
-
7/28/2019 Activity Networks Example 3matematik
5/24
Activity networks Example 3
Activities E and F depend on
C only
A(2)
B(4)
1
3
2
C(5)
D(3)
and activity G depends on
D only.
4
5
E(6)
F(3)
G(8)
-
7/28/2019 Activity Networks Example 3matematik
6/24
Activity networks Example 3
Activity H depends on
activities D and F.
A(2)
B(4)
1
3
2
C(5)
D(3)
To deal with this, we need a
dummy activity from event 5.
4E(6)
F(3)
G(8)
5
Now activity H can be added.
6
H(2)
-
7/28/2019 Activity Networks Example 3matematik
7/24
Activity networks Example 3
A finish node is now needed.
A(2)
B(4)
1
3
2
C(5)
D(3)
4E(6)
F(3)
G(8)5
6
H(2)
E(6)
G(8)
7
-
7/28/2019 Activity Networks Example 3matematik
8/24
Activity networks Example 3
The next step is to find the
early event times (EETs).
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
7
-
7/28/2019 Activity Networks Example 3matematik
9/24
Activity networks Example 3
Event 1 occurs at time zero.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
-
7/28/2019 Activity Networks Example 3matematik
10/24
Activity networks Example 3
Event 2 cannot occur until B
has finished, so the earliest
time for event 2 is 4.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
-
7/28/2019 Activity Networks Example 3matematik
11/24
Activity networks Example 3
Event 3 cannot occur until
both A and B have finished,
so the earliest time for event
3 is 4.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4
-
7/28/2019 Activity Networks Example 3matematik
12/24
Activity networks Example 3
Event 4 cannot occur until C
has finished, so the earliest
time for event 4 is 4 + 5 = 9.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
-
7/28/2019 Activity Networks Example 3matematik
13/24
Activity networks Example 3
Event 5 cannot occur until D
has finished, so the earliest
time for event 5 is 4 + 3 = 7.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
-
7/28/2019 Activity Networks Example 3matematik
14/24
Activity networks Example 3
Event 6 cannot occur until both D and F
have finished. The earliest time that D can
finish is 7, and the earliest time that F can
finish is 9 + 3 = 12, so the earliest time for
event 6 is 12.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
-
7/28/2019 Activity Networks Example 3matematik
15/24
Activity networks Example 3
Event 7 cannot occur until E, G and H have all finished.
The earliest time that E can finish is 9 + 6 = 15, the
earliest time that G can finish is 7 + 8 = 15, and the
earliest time that H can finish is 12 + 2 = 14, so the
earliest time for event 7 is 15.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15
-
7/28/2019 Activity Networks Example 3matematik
16/24
Activity networks Example 3
The next step is to find the late event
times (LETs), working backwards
through the network.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15
-
7/28/2019 Activity Networks Example 3matematik
17/24
Activity networks Example 3
The latest time that event 7 can occur
without delaying the project is 15.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
-
7/28/2019 Activity Networks Example 3matematik
18/24
Activity networks Example 3
The latest time that activity H can start
is 13, so the latest time for event 6 is
13.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
-
7/28/2019 Activity Networks Example 3matematik
19/24
Activity networks Example 3
Activity G and a dummy activity both lead out of
event 5. The latest time that activity G can start is
7, and the latest time that the dummy activity can
start is 13, so the latest time for event 5 is 7.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
7
-
7/28/2019 Activity Networks Example 3matematik
20/24
Activity networks Example 3
Activities E and F both lead out of event 4. The
latest time that activity E can start is 9, and the
latest time that activity F can start is 9, so the
latest time for event 4 is 9.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
7
9
-
7/28/2019 Activity Networks Example 3matematik
21/24
Activity networks Example 3
The latest time that activity C
can start is 4, so the latest time
for event 3 is 4.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
7
94
-
7/28/2019 Activity Networks Example 3matematik
22/24
Activity networks Example 3
Activity D and a dummy activity both lead out of
event 2. The latest time that activity D can start
is 6, and the latest time that the dummy activity
can start is 4, so the latest time for event 2 is 4.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
7
94
4
-
7/28/2019 Activity Networks Example 3matematik
23/24
Activity networks Example 3
Finally, the latest time for event 1 is zero.
A(2)
B(4)
1
3
2
C(5)
D(3)
4
F(3)
5
6
H(2)
E(6)
G(8)
70
4
4 9
7
12
15 15
13
7
94
4
0
-
7/28/2019 Activity Networks Example 3matematik
24/24
Activity networks Example 3
The minimum duration of the project is 15 days.
A(2)
B(4)
C(5)
D(3)
F(3)
6
H(2)
E(6)
G(8)
0
4
4 9
7
12
15 15
13
7
94
4
0
The critical activities are B, C, D, E and G.
2
1
3 4
7
5
Notice that there are two critical paths: BCE
and BDH.
The float in this example
is analysed in the Notes
and Examples.
http://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_10/4.1.pdf