Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30...

4
nSQP’s Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30 1

Transcript of Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30...

Page 1: Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30 1.

nSQP’s

Activities Status and Plan for the week

D. Giugni / INFN Milano

D. GiugniMonday Meeting 2011-01-30

1

Page 2: Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30 1.

nSQP’s

Monday Meeting 2011-01-30 2

Harnesses Stacking Status• Set 1 C34 (X0)

– Open Issues• Need to repair the bend of the OSP stack at the

tapes• Set 2

– General• Set has NOT been assigned yet.• Decided to put in hold: too many faults.

– Status• All usable Harnesses “Prepared” and tested

– Open Issues• Need several repairs

• Set 3– General

• Set assigned to C12– Status

• done– Open Issues

• OSP LV to stack. Problems in the wire bends

D. Giugni

• Set 4 – General

• Set assigned to C78– Status

• Done EXCEPT OSP LV STACK– Open Issues

• OSP LV STACK to fix.• Set 5

– General• Set assigned to C56

– Status• Done EXCEPT OSP LV STACK

– Open Issues• Need testing

• Set 6 – General : only pre-tested

Page 3: Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30 1.

nSQP’s

Monday Meeting 2011-01-30 3

Soldering

Agreed sequence :– ISP C34 (X0) almost finished– ISP C12 (X1) in the pipe line– ISP C78 (X2) Ready to go– ISP C56 (X3) Ready to go (but needs another week for training the last

soldering team)

D. Giugni

Page 4: Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting 2011-01-30 1.

nSQP’s

4

Schedule for this week• Stacking

– Keep going with SET 6 and the others.– Activity will be slowed down by 50% due to the ELCO connector pins removal (not quite an issue)

• Corrugated panel bonding:Delay in the SLA parts. 2 panels done for the C34 already assembled in the panel. – Restart the production this week as soon as parts are delivered (parts have been shipped).

• BackBone Not at high priority this week.

• PP0 boards stiffening and Alu Block bondingDone C5, C6, C7 and C8 . C Side has been finished.

Actually we are not working on the OSP.– Priority on the ISP A side boards. Not foreseen this week for stiffening.

• Soldering– Keep going with the ISP C34 (X0) HV routing.– Load the C12 PS PS soldering– Kick off the C78 HV-NTC

• Post Soldering Assembly Final Assembly Trial (X-1)– Low priority in loading the OSP 3 and ISP 3 on the trial . Needs ER_bundles!!