Florida mesothelioma treatment and compensation reforms pledged to reduce punitive damage awards
Activities of Nuclear Damage Compensation...
Transcript of Activities of Nuclear Damage Compensation...
Unauthorized reproduction prohibited. All rights reserved ©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Activities of
Nuclear Damage Compensation &
Decommissioning Facilitation Corporation (NDF)
June 3, 2015
Yasuharu Igarashi Executive Director
Nuclear Damage Compensation &
Decommissioning Facilitation Corporation (NDF)
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Road Map Revised
2015
Chronology
2
Cold Shutdown 2011.12.16
1st Road Map 2011.12.26
Road Map Revised
2012.12.26
ALPS Troubles 2014.05~
Contaminated Water Troubles
mid-2013~
Road Map Revised
2013.06.27
IRID 2013.08.01
NDF 2014.08.18
Change of Administration
2012.12
Emergency Response
Headquarters
Inter-Ministerial Council
for Contaminated Water and
Decommissioning
2011 2012 2013 2014
TEPCO D&D Co. 2014.04.01
2011.03.11
Government
Roadmap and Strategic Plan
Troubles
TEPCO
Emerging Entities
Policy
Strategy
R&D
Site Operation
2015
Strategic Plan
2015.04.30
IRID: International Research Institute for Nuclear Decommissioning
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Technology and Strategic Support
Decommissioning Policy
(Road Map)
Secretary=ANRE
R&D Plan
“Strategic Plan” R&D Plan
IRID Implementation of
R&D On-site
Decommissioning
JAEA
Inter-Ministerial Council
Government of Japan
Team for Decommissioning and Contaminated water
NDF
Delivery of Decommissioning
Tech. Development
TEPCO
Roles of Bodies for in Fukushima Daiichi Plant Decommissioning
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
As an organization of experts in a variety of technological fields, NDF develops a mid-and-long term technical strategy “The Strategic Plan” through the cooperation with external experts.
● Technology experts in NDF’s decommissioning
department (about 30 experts)
- Plant engineering - Robotics - Civil engineering and architecture - Materials, analysis, monitoring - Fuel and nuclear reactor
engineering ● Experts from external organizations (universities,
JAEA and other research institutions)
<Decommissioning Strategy Board>
1st
2nd
3rd
Aug. 21, Thu Sep. 30, Tue Oct. 28, Tue*
6th Jan. 28, Wed 7th Feb. 23, Mon* 8th Mar. 26, Thu 9th Apr. 16, Thu 4th Dec. 4, Thu
5th Jan. 6, Tue * With the participation of four international
special advisors. <Expert Committee> ・Fuel Debris Retrieval Expert Committee
1st
2nd
3rd
Oct. 20, Mon Nov. 26, Wed Dec. 22, Mon
4th Jan. 19, Mon 5th Feb. 13, Fri 6th
Mar. 18, Wed
・Waste Management Expert Committee
1st
2nd
Nov. 26, Wed Dec. 25, Thu
4th Feb. 25, Wed 5th Mar. 30, Mon
3rd Jan. 26, Mon
Intensive Workshop type Meetings have held repeatedly among ANRE, TEPCO and IRID under the Lead of NDF on specific Issues.
Development of “The Strategic Plan” by NDF
4
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
5
(i) Appoint overseas experts International Special Advisors and invite them to the Decommissioning Strategy Board Meeting.
(ii) Participate in international frameworks such as IAEA and OECD/NEA. (iii) Develop a cooperative relationship with overseas organizations.
Dr. Rosa Yang EPRI Fellow, Nuclear Power, U.S. Electric Power Research Institute (EPRI) Dr. Mike Weightman Former Chief Executive, the Office for Nuclear Regulation (ONR) Mr. Paul Dickman Senior Policy Fellow, U.S. Argonne National Laboratory Mr. Christophe Behar Director of Nuclear Energy Division, Commissariat a l'energie atomique et aux energies alternatives (France) (CEA)
International Relationship
NDA (UK) CEA (France)
Cooperative Agreement International Special Advisors
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
6
Strategic Plan for the Decommissioning of TEPCO’s
Fukushima Daiichi Nuclear Power Station
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
・Goals and policies presented by the Government ・Key elements of strategies, policies and plans determined by the Government
・Delivery of Decommissioning by TEPCO and research institutions (field work, engineering, R&D)
Strategic Plan
Mid-and-Long Term Roadmap
Implementation Plans
Strategic Plan and Mid-and-Long Term Roadmap
7
・Strategic Plan identifies the issues, ways how to address them and action plans for the most important challenges in terms of the technical judgment for 1) Fuel debris retrieval and 2) Waste management, embracing the organizations involved.
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Guiding Principles for the Strategic Plan
8
Principle The decommissioning of the Fukushima Daiichi Nuclear Power Plant is
a continuous risk reduction activity to protect people and the environment from the risk of radioactive materials, resulting from severe accident.
A risk reduction strategy along a mid- to-long-term timeline will be designed in the Strategic Plan.
5 Guiding Principles for Risk Reduction Principle 1: Safe Reduction of risks caused by radioactive materials*
and work safety
(*Environment impact and exposure to workers)
Principle 2: Proven Reliable and flexible technology
Principle 3: Efficient Effective utilization of resource
(human, capital, money, and space etc.)
Principle 4: Timely Awareness of time axis
Principle 5: Field Oriented Emphasize actual place, actual parts and actual
situation
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Risk Reduction in Strategic Plan
(i) Risk of radioactive materials
Risk = level of effect x likelihood of loss of containment function
(ii) Level of effect Level of effect = level of activity x
physical state (solid, liquid or gas)
(iii) Likelihood of loss of containment function
Likelihood of loss of containment function = possibility of occurrence of the factor x vulnerability of the facility
Likelihood of loss of containment function
(ⅳ ) How to reduce risk Move radioactive materials to a safer and more stable facility. - Reduce the degree of effect. Decay of radioactivity and change in the physical state. - Reduce the likelihood of loss of containment function.
De
gre
e o
f ef
fect
(Haz
ard
po
ten
tial
)
Used Absorbent
Column
Solid Waste
Waste Sludge
Risk necessitating long term actions
Fuel debris Risk necessitating utmost preparation and technics for safer conditions
Fuel in pool
Risk necessitating quick actions
Contaminat ed-water
in buildings, tanks and trenches
Risk Reduction
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Risks to be addressed safely, effectively and carefully with thorough preparations & technologies to realize more stable condition
Minimizing risk of radio-active materials
Risks to be addressed as expeditiously as possible
Risks to be addressed on a long-term basis
Contaminated water
Fuel in pool Fuel debris
Risk reduction of fuel debris
Radioactive Solid waste
Risk reduction of waste
Fuel Debris Retrieval
– Develop a workable scenario for fuel debris retrieval assuming several methods (submersion, dry) and a combination of the methods, taking into account the status of each Unit.
Waste Management
– Develop a policy for storage management, processing and disposal from a mid-to- long-term perspective, based on the principles for safe waste disposal and appropriate waste processing.
Logic Tree Diagram Regarding Risk Reduction
10
Secondary waste
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Submersion Image on condition that the removal of core internals above fuel debris has finished.
Three Priority Methods of Fuel Debris Retrieval
Partial submersion top access
Image on condition that the removal of core internals above fuel debris has finished.
Partial submersion side access
Image on condition that RPV pedestal exterior component inside PCV and the interference have been removed.
Road towards Fuel Debris Retrieval (Reference)
Time
Concept investigation
Understanding the plant and reactor conditions
Concept study
FS/Concept design
Basic/detail design
Technical Maturity*1
(TRL)
Selection of retrieval method
Securing accessibility (Decontamination, etc.)
Safety requirement (regulatory requirement)
Element test
Practical application/ verification test
Mock up and training
Preparation work
Screening
Prioritization
Safety Resource Site
Fuel debris Retrieval work
Prerequisite
High
12 Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Low
Equipment System performance guarantee
Decision of method
Start fuel debris retrieval
*1 The vertical axis does not represent the individual technology but an image of the technical maturity of the overall retrieval system.
Critical technology Important performance requirements
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
<Objective>
Risk reduction of the waste
Storage
management
Development of
necessary regulations **
Treatment and
disposal *
Characterization and
inventory estimation
Analysis
Applicability of
existed disposal
concept
Reduction of
generating waste
Ensuring
safety
Segregation storage
according to the doses
and property for exposure reduction
Investigation of new
disposal concept
Pretreatment Treatment Conditioning Control of materials and
equipment bringing
into the site
Reuse of
Materials and
equipment
Volume
reduction
treatment
Stabilization
treatment Recycle
* : HP SW-1 (2017) Fundamental policies of treatment and disposal
HP SW-2 (2021) Prospect of the safety of treatment and disposal
**: To be performed after the HP SW-2.
Structure of Strategic Plan for Waste Management
Disposal concept
according to waste
characteristics
Treatment
consistent with
disposal
Data evaluation
(Modeling)
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Basic Concept for Ensuring Safety for Radioactive Waste Disposal
NDF has reviewed relevant world’s standards for waste management. GSR-part5 and SSR-5 of IAEA are important references.
To contain the waste
To isolate the waste from the accessible biosphere and to reduce substantially the likelihood of, and all possible consequences of, inadvertent human intrusion into the waste
To inhibit, reduce and delay the migration of radionuclides at any time from the waste to the accessible biosphere
To ensure that the amounts of radionuclides reaching the accessible biosphere due to any migration from the disposal facility are such that possible radiological consequences are acceptably low at all times
To control the release of radioactive materials to ensure that their concentrations without having do not have significant health effects
Approaches to the radioactive waste treatment are also developed.
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Policy of Waste Management
Storage management Reduction of volume generated
Reduction of carry-in materials
Considerations on the secondary waste
Storage management
Plan for storage management
Storage management plan for the waste generated from fuel debris retrieval
Waste Treatment & Disposal
Understanding of waste properties
Waste sampling plan
Analysis ability for understanding of waste properties
Treatment and disposal methods according to the characteristics of the waste at the Fukushima Daiichi NPS
Study on treatment and disposal methods
Classification management and history information management
Regulatory system
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Basic research
Fundamental research
Application development
Practical application
IRID
JAEA
Universities/Research Institutes
METI - Decommissioning and contaminated water management
fund (subsidy for R&D projects) - Research center facilities development project
JAEA - Fundamental and basic research by Government funding
- Fundamental and basic research
MEXT - Fundamental research and HRD program - Nuclear Science and strategic fundamental research
program
- Onsite needs/ requirements
- Regulatory requirements
- Performance guarantee
- Basic founding - New idea for
breakthrough - HRD/ education
- Specific research facility/equipment Fundamental data
- Application of new technologies/system
- Equipment and device development
- Demonstration - Data for safety
Knowledge researchers
It is important to facilitate interaction and communication among researchers and engineers involved in a series of R&D initiatives.
TEPCO
Overall Diagram of R&D Activities
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
R & D Activities
R&D facilities (JAEA)
Mock-up test facility
Radioactive materials analysis and research facility
International joint research center for decommissioning
Fundamental Research Activities
JAEA & other research organizations
Universities
Development and securing of human resource
Mock-up test facility
Analysis & R&D facility
Overhead crane (2)
1/8-sector test Rubble assembly
Remote-controlled equipment demonstration test area
PCV repair demonstratio n
test area
Barrier
Water tank for testing
Mock-up stairs Motion capture area
Slope Annex
building
Camera (16)
Remote- controlled equipment
Demonstration
test
International joint research center for decommissioning
2014 FY 2016 FY 2015 FY 2017 FY & onward
△
○ Strategic Plan development/follow- up/revision
■ Initial plan Revision Revision
Products of research & development (data acquisition, assessment method, etc.)
appropriate Requirements for scenario
・Technical feasibility
・Ease of field work
・Assurance of safety
・Risk assessment
Revision as
■
Field work/survey conducted
Example: a method for water leakage stoppage, integrity, a method for debris retrieval, fuel debris detection, waste-related activities
■
Future Development of the Strategic Plan
18 Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Strategic Plan is living document !
Unauthorized reproduction prohibited. All rights reserved
©Nuclear Damage Compensation and Decommissioning Facilitation Corporation
19
Thank you for your attention