ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler &...
Transcript of ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler &...
![Page 1: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/1.jpg)
![Page 2: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/2.jpg)
Agenda
Project Introduction & Background
LCA Methods & LCIA by Phase
Assessment & Recommendations
![Page 3: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/3.jpg)
MontereyBayAquarium:NewSeawaterTankNeeded
Criteria for Choosing a Tank
Performance: Lifetime of 10-20 years and withstand aquarium conditions
Cost: Lowest cost or cost-competitive
Environmental Impact: Tank with the smallest environmental “footprint” was desired
![Page 4: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/4.jpg)
Performance Service Life and Durability: both tank systems expected to last for 20 years.
Functional Unit: 20 year storage of aquatic ecosystem.
Maintenance: Not a factor in this analysis. The only required maintenance is an annual cleaning by divers (similar for both tanks) to maintain tank surfaces. Use phase costs and environmental impacts cancel out, and are probably negligible regardless.
![Page 5: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/5.jpg)
EnvironmentalImpacts(KeyMetrics)
Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract
EMISSIONS Carbon dioxide Carbon monoxide NOx SOx Particulates Volatile Organic Compounds Specific Process‐ and Material‐
specific waste issues
IMPACT CATEGORIES Total Energy Resources Greenhouse Gas Emissions Ozone Depletion Acidification Eutrofication Heavy Metals Carcinogens Summer Smog Formation Winter Smog Formation Solid Waste
![Page 6: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/6.jpg)
Agenda
Project Introduction & Background
LCA Methods & LCIA by Phase
Assessment & Recommendations
![Page 7: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/7.jpg)
Op9on#1:Concrete
Engineered and estimation by Rutherford and Chekene
![Page 8: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/8.jpg)
ConcreteProcessFlowDiagram
Construction& Transportation
Raw Material Production
Use Phase
End-of-Life Phase
![Page 9: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/9.jpg)
Op9on#2:FRP
Kreysler & Associates (winning bid)
![Page 10: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/10.jpg)
FRPProcessFlowDiagram
Construction& Transportation
Raw Material Production
Use Phase
End-of-Life Phase
![Page 11: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/11.jpg)
LifeCycleAssessmentMethodandReferences Objective: Determine whether the FRP or Concrete tank liner
has a lower overall environmental footprint
LCA Method: Used a process‐based rather than an EIO LCA to compare specific systems for which we had process and materials data.
Main References: SimaPro – Eco‐Indicator 99 Owens‐Corning Low‐Energy Glass Fiber Process Data Cost and fabrication data from Kreysler & Associates and MBARI Ashland Resin Data
![Page 12: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/12.jpg)
MajorAssumpDonsMaterial Production Phase Sandblasting: 150 hp electric LP air 3 hours 5% waste factor glass fiber 2% waste factor resin 3% waste factor for timber formwork
Construction Phase Forklift (50 hp diesel assumed) Concrete pump (33 hp diesel assumed)
End‐of‐Life Phase 100% Steel Salvaged 100% Concrete and FRP landfilled 75% Formwork reused
![Page 13: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/13.jpg)
Agenda
Project Introduction & Background
LCA Methods & LCIA by Phase
Assessment & Recommendations
![Page 14: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/14.jpg)
Concrete:TotalLifeCycleImpactAssessment
![Page 15: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/15.jpg)
FRP:TotalLifeCycleImpactAssessment
![Page 16: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/16.jpg)
TotalLifeCycleImpacts:Concretevs.FRP(Epoxy)
![Page 17: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/17.jpg)
The FRP tank has smaller overall environmental footprint (lower solid waste, greenhouse gas emissions, and acidification)
However, FRP consumes about three times as much energy as the concrete option. This is primarily because of the energy required to produce the resin.
Regardless of this drawback, FRP is the superior environmental option.
RecommendaDon:FRPTank
![Page 18: ACMA Discussion - LepechEnvironmental Impacts (Key Metrics) Monterey Bay Aquarium asked Kreysler & Associates to complete an LCA as a condition of taking the contract EMISSIONS Total](https://reader035.fdocuments.in/reader035/viewer/2022071016/5fcf1b839d2a990f1e707f59/html5/thumbnails/18.jpg)
EnvironmentalBenefitsofChoosingFRPcomparableto:
CO2: Not driving 42,364 miles in a standard automobile
Acidification: Not burning 6.14 metric tonnes of unscrubbed coal
On the other hand, the extra electricity used for the FRP tank could power 40 San Francisco households for an entire year.