ACM Using Project Controls to Better Plan and Manage Projects PROJECTS NEED PROJECT CONTROLS.

20
ACM ACM ACM ACM www.acmpm.com Using Project Controls to Better Plan and Manage Projects PROJECTS NEED PROJECT CONTROLS

Transcript of ACM Using Project Controls to Better Plan and Manage Projects PROJECTS NEED PROJECT CONTROLS.

ACM

ACM

ACM

ACMwww.acmpm.com

Using Project Controls

to

Better Plan and Manage Projects

PROJECTS NEED PROJECT CONTROLS

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

• What is a Project?

– Temporary undertaking providing a product or service

– Has set start and finish

– Requires resources to complete

– Has deliverables

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

– Reactive

– Crisis and conflict managers

– Seek solutions to present problems

– Fight fires

Without Project Controls, Managers are:

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

– Properly assess risks

– Define deliverables

– Control change

Without Project Controls

Planning & Execution of Projects Fail to:

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

– Unrecognized

– Not communicated

– Increase in backlog

Without Project Controls, Priorities are:

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

– Ineffectively utilized

– Not committed on a timely basis

– Faced with continuous re-assignment

Without Project Controls, Resources are:

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECTS NEED PROJECT CONTROLS

– Completion dates are missed

– Budgets are over-expended

– Quality will suffer

– Claims may materialize

Without Project Controls, (Timing & Cost)

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

• Become proactive

• Know which questions should be asked

• Perform adequate planning

• Manage scope (including cost, time, and quality)

Managers:

• Manage resources effectively

• Communicate priorities and resource needs

• Identify and manage risks

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

control it

communicate them to firstline supervision

listen

make themunderstood

mitigate occurrences

measure it

Managers will Plan, Then Execute

• Define the scope of work then

• Develop work plans then

• Provide a means to accommodate feedback then

• Identify priorities and responsibilities then

• Identify and assess risks then

• Identify performance then

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

Priorities Will be Established

• Focus team on achievable goals

• Define criteria for prioritization

- Needs / wants

- Evaluate risks

• Set standards for using limited resources

• Eliminate bottlenecks

ACM

ACM

ACM

ACMwww.acmpm.com

PRIORITIES

Critical Path Schedule with Logic

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

• Are defined by types and quantities required

• Usage is determined; when, where, and how long they will be needed

• Commitments can be obtained for their use

Resources:

• Availability can be used for advanced planning

• Resolve conflicts regarding pooled resources

ACM

ACM

ACM

ACMwww.acmpm.com

Resources and Baseline

Project Schedule

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

• Assess impact to projected completion dates and budgets

• Assess performance to meet delivery schedules

• Recognize and manage change

• Avoid penalties

• Project is completed as planned

Better Management of Time & Cost

ACM

ACM

ACM

ACMwww.acmpm.com

COST/SCHEDULE VARIANCE

$0

$20

$40

$60

$80

$100

$120

Thousands

20

B

C = $20,000

A

40 20 20 20 20

C D E F

C = $10,000 C = $20,000 C = $20,000 C = $20,000 C = $10,000

JAN FEB MAR APR MAY JUN JUL AUG

ProjectedSlippage

ScheduleVariance

ProgressDate

PROJECTED EARNEDPLANNED

EARNED

PROJECTED ACTUAL

ProjectedOverrun

CostVariance

ACTUAL

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

• Problem solvers become managers

• Work and backlog are managed

• Pooled resources are managed effectively

• Impact of changing priorities are evaluated

Multiple Project Environment

ACM

ACM

ACM

ACMwww.acmpm.com

USING PROJECT CONTROLS

Project management allows the project team to:

• Identify potential problems before they occur

• Plan for their solutions

Resulting in:

• Better planned and managed projects

• Finishing on time and within budget

• Performing to defined quality standards

ACM

ACM

ACM

ACMwww.acmpm.com

• Cost overruns minimized

• Timing objectives achieved

• Prioritized system

PROJECT CONTROLSSHORT TERM GOALS

ACM

ACM

ACM

ACMwww.acmpm.com

PROJECT CONTROLSLONG TERM GAINS

• Improved quality

• Ability to manage changing priorities

• Optimum utilization of resources

• Develop accountability

• Build a team approach

• Manage and control project changes

• Improved communication

ACM

ACM

ACM

ACMwww.acmpm.com

Administrative Controls ManagementBusiness Organization

Administrative Controls ManagementBusiness Organization

Administrative Controls Management, Inc.525 Avis Drive, Suite 2Ann Arbor, MI 48108Phone: (734) 995-9640Fax: (734) 995-9638 E-Mail: [email protected]

Website: www.acmpm.com

The staff of Administrative Controls Management, Inc. (ACM) includes Professional Engineers, Certified Cost Engineers/Consultants, Planning & Scheduling Professionals, Earned Value Professionals, Certified Estimating Professionals, Project Management Professionals, quality engineers, architects, graduate engineers, a LEED® Accredited Professionals, as well as a Certified Forensic Claims Consultant

ACM is the first Approved Education Provider as certified by AACE International, the Authority for Total Cost ManagementTM and a Project Management Institute Global Registered Education Provider