Achieving strategic benefits from business IT projects ...

41
1 Achieving strategic benefits from business IT projects: The critical importance of using the business case across the entire project lifetime Frank Einhorn a Carl Marnewick b * Jack Meredith c a Department of Applied Information Systems, College of Business and Economics, University of Johannesburg, PO Box 524, Auckland Park, 2006, Johannesburg, South Africa b Department of Applied Information Systems, College of Business and Economics, University of Johannesburg, PO Box 524, Auckland Park, 2006, Johannesburg, South Africa c Broyhill Distinguished Scholar and Chair in Operations, Emeritus, School of Business, Wake Forest University, 515 Robert Ct., Hillsborough, NC 27278, USA * Corresponding author. E-mail address: [email protected] Tel: +27-11-559-1316

Transcript of Achieving strategic benefits from business IT projects ...

1

Achieving strategic benefits from business IT projects: The critical

importance of using the business case across the entire project lifetime

Frank Einhorn a

Carl Marnewick b *

Jack Meredith c

a Department of Applied Information Systems, College of Business and Economics,

University of Johannesburg, PO Box 524, Auckland Park, 2006, Johannesburg, South Africa

b Department of Applied Information Systems, College of Business and Economics,

University of Johannesburg, PO Box 524, Auckland Park, 2006, Johannesburg, South Africa

c Broyhill Distinguished Scholar and Chair in Operations, Emeritus, School of Business,

Wake Forest University, 515 Robert Ct., Hillsborough, NC 27278, USA

* Corresponding author. E-mail address: [email protected] Tel: +27-11-559-1316

2

Abstract

Business projects with an information technology component are referred to here as

‘business IT’ projects. Their success rate is found to be unsatisfactory, resulting in wasteful

expenditure running to billions of dollars annually. Literature indicates that sound business

cases, used effectively throughout the project lifetime, underpin governance and have a major

positive impact on the project success rate. However, it also suggests that business case

processes are seldom used properly.

The goal of this study is to determine the extent to which business case processes are

used in practice, and to understand the implications of the pattern that emerges.

The data analysis from a survey reveals that business case usage diminishes

significantly after approval is given to proceed, with potentially serious negative

consequences. The findings give valuable insights to management as to the required

processes and how to avoid the prevailing pitfalls and achieve the intended strategic project

benefits.

Keywords:

Project governance, business case, process group, information technology, project lifetime.

3

1 Introduction

Literature continues to indicate that the success rate of business projects with

information technology content, referred to here as ‘business IT’ projects, remains

unsatisfactory. It is known that 60 percent of such projects are either challenged or fail

outright, resulting in the wasteful expenditure of billions of dollars annually (Standish,

2014a).

Literature also indicates that the success rate can be improved through sound

governance, underpinned by a robust business case which spells out the justification for

proceeding with the project. To be effective, such governance needs to prevail throughout the

project’s ‘lifetime’, whose duration is from when the project is first considered until all

planned benefits are, or continue to be, realised. That is, the business case still needs to be

actively used, and updated, during project planning, project execution, and user

implementation. Indeed, according to Musawir, Serra, Zwikael, and Ali (2017), disciplined

governance, applied consistently across the project’s lifetime, has a major positive effect on

project and investment success.

Using a ‘process theory’ lens (Niederman, Muller, & March, 2018), it emerges that

many processes are required for effective use of the business case. From literature it is

apparent that, although senior managers recognise the need, many of the processes are

seldom followed. However, the extent of this situation is unknown, and this paper is unique

in that it is the first measurement of the use of business case processes in practice. Therefore,

the goal of the study is to contribute to project management knowledge concerning the use of

the business case by organizations and thereby improve the success rate of business IT

projects. We address this goal through research that first, determines the current usage of

business case processes, second, assesses the likely consequences of the pattern that emerges,

and third, gives insights into the changes needed to organisational practice.

4

Business IT projects, which are further explained in the literature review, differ from

other types of projects in a number of ways. They typically experience more rapid change,

which requires updates to the business case. For example, updates may be generated by

senior management, whose goals for the project often change as it progresses due to a

multitude of reasons such as: competitors’ actions, new regulations, changes in strategy, or

events regarding the progress of the project, like cost increases, technical issues, or delays.

Another issue is that the professionals who produce the project outputs, such as new software

for the organisation, are not the ones who will be using the output to produce the desired

business benefits. But these two groups tend not to communicate well, having different

backgrounds, terminology, and even cultures.

This paper reveals, through a survey, the extent to which these business case

processes are used in practice. Inferences are then made which show how, by changing some

widely-used practices, the likelihood of incurring wasteful expenditure can be reduced via

ongoing decisions informed by the business case. It also notes the need for further research

on the organisational facilitators which support the continual use of the business case

throughout the duration of the project.

The paper is structured as follows: It begins with a literature review of the business

case and its special importance in the field of IT. It explains the process theory employed in

the study and outlines the processes required. It illustrates where new and updated

information is needed to support the processes, and shows how there is a two-way flow of

information whereby processes require, but also generate, information on which to base

decisions. The literature review concludes with two research questions. This is followed by

an explanation of the research method, the survey questionnaire and the data analysis. Next,

results are presented, followed by discussion of their findings, and finally conclusions.

5

2 Literature review

2.1 Governance of business IT projects

Business IT projects are those where business benefits are achieved through the use of

IT deliverables. The following background offers perspective on their unique aspects and

success rate. Particularly in the case of business IT, the deliverables alone are insufficient and

concomitant business changes are needed to take advantage of them in order to produce the

business benefits (Coombs, 2015; Peppard, Ward, & Daniel, 2007). Therefore, from here, the

term ‘IT project’ implies a business IT project. Moreover, IT projects have two parts:

developing the IT products, and then using them to create value (Coombs, 2015; Ward,

Daniel, & Peppard, 2008). The two parts are done by IT and business staff respectively, who

often have different backgrounds and use different terminology. Nevertheless,

communication between them is essential as neither group knows all aspects of the complete

project (Sauer & Reich, 2009; Zwikael & Smyrk, 2012). IT projects are known to be

particularly difficult and surveys show that up to 20% of IT projects fail outright, with a

further 40% being challenged, resulting in considerable wasteful expenditure (Joseph,

Erasmus, & Marnewick, 2014; Standish, 2014a).

However, effective project governance, espoused by several practice guides (APM,

2006; OGC, 2009; PMI, 2016), can mitigate many of the causes of project failure. For

example, the problem of overambitious objectives mentioned by both Standish (2014b) and

Al-Ahmad et al. (2009) is addressed by several governance aspects, such as clear authority

with appropriate information for decision-making, independent review, and stakeholder

involvement (APM, 2006; PMI, 2016). Hence, sound project governance makes an important

contribution to achieving project success. Moreover, because several governance aspects

require a business case, such as including business case reviews in project plans, it is clear

that the business case underpins sound project governance (APM, 2006; OGC, 2009; PMI,

6

2016). The above conclusions are endorsed by Musawir et al. (2017) who stated that, of all

their measurement items on project governance, a business case supported by relevant and

realistic information on which to base decisions has the greatest overall effect on project

success.

2.2 The business case and the need to use it throughout the project lifetime

The purpose of a business case is to set out the rationale for a project investment,

justify it, and obtain management’s commitment and authorisation to proceed (APM, 2006;

Maes, Van Grembergen, & De Haes, 2014; PMI, 2017). It is not necessarily a formal

document and may not even be called a ‘business case’. It summarises the anticipated

benefits, both tangible and intangible, for all the stakeholders while considering alternative

options and recommending a preferred solution (APM, 2006; Krell & Matook, 2009).

Responsibility for achieving the benefits is assigned to a person termed the ‘project owner’

(Olsson, 2018; Zwikael & Meredith, 2018), indicating how each benefit will be measured

(Zwikael, Chih, & Meredith, 2018) and what process and organisational changes may be

expected. The business case also provides an overview of the scope of work, the costs, the

time frame and the risks (OGC, 2009). Last, it should offer a projection on what can be

expected for the organisation should the project not be approved or successfully executed

(OGC, 2009).

This is not the end of the use of the business case however, since it is subject to

review and ongoing viability testing throughout the project’s lifetime (Cooke-Davies, 2005;

Franken, Edwards, & Lambert, 2009; OGC, 2009; PMI, 2017). The business case not only

supports project governance from inception, through delivery and eventually to benefits

realisation, but it also supports the governance of related projects (e.g., a program or

portfolio) in all or part of an organisation where project selection and prioritisation are

needed (Kopmann, Kock, Killen, & Gemunden, 2015; Müller, Pemsel, & Shao, 2014). Thus,

7

in summary, the business case should contribute to project success and minimise the risk and

impact of failure in the following ways (Einhorn & Marnewick, 2016; Ward et al., 2008;

Zwikael et al., 2018):

o The business case contains the ongoing justification for the project. By creating and

tracking it, stakeholders get a better understanding of the benefits, costs and risks of

the project, leading to informed decisions.

o The benefits are made measurable and quantifiable, with responsibility assigned,

increasing the commitment to realising them.

o Business case reviews allow on-going optimisation of the project in response to

business and other changes, inside or outside the organisation.

o Finally, after the deliverables are live, the business case allows results to be compared

with expected benefits, thus ensuring that none are overlooked.

Research by Ward et al. (2008) shows a strong link between use of the business case

in the aforementioned ways and the achievement of project success in terms of business

value. Thus, such use of the business case can be considered ‘effective’. Use of the business

case is even effective where it leads to the project being terminated, due to the justification to

proceed no longer being valid (Royer, 2003). Projects other than IT projects may likely also

benefit from ongoing review of the business case, but are beyond the scope of this paper.

In recent years, much has been written on how to develop a compelling business case

(Keen, 2011; Messner, 2013; Ward et al., 2008). However, the incidence of failed and

challenged IT projects has diminished little over a similar period (Standish, 2014a). A

possible reason is that, while there is ample literature on how to develop a business case and

win approval, there is little guidance on how to use the business case to review the ongoing

justification for the project and to ensure that the intended benefits are in fact realised. The

latter possibility is borne out by literature which suggests that the business case is seldom

8

used to full effect. Eckartz, Daneva, Wieringa, and Van Hillegersberg (2009) find that the

business case is rarely used to manage execution of the project and the realisation of its

benefits, while Marnewick (2016) finds that project results are seldom checked against the

business case. Maes, De Haes, and Van Grembergen (2014) provide a possible explanation

for inadequate use of the business case. They find that, while most business case processes

are considered important (above 70 on a scale of 0 – 100), they are also difficult to do (ease

of execution is below 25 on a similar scale).

2.3 Process theory as used in this study

The research is based on process theory (Koskinen, 2012; Langley, 1999; Niederman

et al., 2018; Pentland, 1999). To be useful, the theory needs to guide what actions related to

the business case need to be taken to produce positive project outcomes (Niederman et al.,

2018). Two possible bases for such theory are variance theory and process theory (Langley,

1999). The former uses covariation of dependent and independent variables; the latter is

concerned with sequences of activities that lead to certain outcomes after starting at an initial

position (Langley, Smallman, Tsoukas, & Van de Ven, 2013). Process theory gives the more

suitable framework to describe the use of the business case (Soh & Markus, 1995).

Although process theory has broad application across disciplines (Bizzi & Langley,

2012; Langley et al., 2013), Niederman et al. (2018) have specialised its use to build

knowledge in the project management sphere to which the business case belongs. It supports

business case use being broken into discrete processes and analysed as such. Process theory

refers to antecedents, describing the initial position, and consequents describing the outcomes

of the processes (Niederman et al., 2018; Pentland, 1999). The antecedents may be the output

of a prior processes, while the consequents would feed into subsequent processes. In the

context of the business case, the consequents are often information on which to base

decisions, or the decisions themselves, as reflected in the next subsection. Because projects

9

are value creation processes (Laursen & Svejvig, 2016), it is useful to identify the critical

processes that may be insufficiently used (Soh & Markus, 1995).

Niederman et al. (2018) categorise processes to facilitate their description and

analysis. For example, there are different process categories depending on: (i) whether one or

multiple outputs are expected, (ii) the variability of actions, and their sequence within the

process, (iii) intermediate states being identified, or found to be essential, and (iv) whether

the process would behave similarly across many business domains. Due to the contextual

nature of projects, some of the processes require several of the categories to describe them.

Here, the business case processes are considered at two levels. The upper level,

described in the next subsection, is comprised of eight process groups. At the lower level,

each process group is broken down into individual processes.

2.4 The business case processes and information

The 37 business case processes identified in Einhorn and Marnewick (2016) are

divided into ‘process groups’ (PGs), which are described in the paragraphs that follow. The

processes making up each PG are given later in Table 1. Figure 1 illustrates (i) the numbered

PGs and (ii) their alphabetized interaction with the categories of information, where each

information category consists of many information types (Marnewick & Einhorn, 2019). It

should be noted that some of the business case PGs overlap with project management process

groups as described in PMI (2017).

10

Figure 1. The business case process and information model

The diamonds ‘D’ associated with the PGs denote typical decision points. While they

are shown in broad chronological sequence, it is accepted that what happens in practice is

situational. PGs 1 to 3, which create the business case, are generally done pre-approval. In

PG4, approved projects are prioritised and resourced, while PGs 5 to 8 are done after project

initiation. If a project happens to be initiated without a business case, then PGs 2 and 3

should be done early in the immediately-following project planning stage.

2.4.1 Process group (PG) descriptions

PG1 covers preparation for the business case (Maes, De Haes, et al., 2014; Ward et

al., 2008). A high-level project proposal stating the business drivers is submitted to

whichever person or body is responsible for receiving proposals such as the Project

Management Office (PMO) or the portfolio manager for projects in the organisation. The

proposal is then screened along with others. If it is selected, the project owner is confirmed

and authorisation given to expand the proposal into a business case; if not, the proposal is

archived (Keen, 2011).

PG2 covers the groundwork for the business case. It might involve considerable

investigation, especially involving the main stakeholders whose requirements and decision

11

criteria need to be thoroughly understood. The main implementation alternatives are

considered and the preferred one noted (Samset & Volden, 2015). The initial scope definition

is then detailed for the preferred alternative, which includes not only the business process

changes but also any organisational changes required to enable the benefits. As noted

previously, the expected costs and completion dates for the project are estimated and the

expected business benefits are detailed with their estimated value over time (Messner, 2013).

An initial risk assessment is also conducted, with an estimate of a risk contingency amount.

The project owner, who is responsible for achieving the benefits, is informed as to how each

benefit will be measured, and also the impact of not completing the project.

PG3 covers assembly, review and presentation of the business case. Based on the

groundwork during PG2, explanations and estimation methods are documented with relevant

evidence, while the underlying assumptions, dependencies and constraints are set out. Where

appropriate, the overall financial benefit is calculated, and recommendations are stated,

emphasising the key themes. Quality assurance is done to ensure that content is sound,

relevant and clear, preferably involving an independent reviewer for major initiatives (Keen,

2011). Finally, the business case is presented to key stakeholders, leading to either a final

decision or a request for further investigation (Maes, De Haes, et al., 2014).

PG4 covers prioritisation of projects which have been approved in principle

(Kopmann et al., 2015). This could involve several steps, depending on the organisation. The

outcome is a decision whether and when the project will be initiated, based on resource

availability and project urgency.

PG5 starts immediately after the project is initiated. It involves developing the project

plan and integrating information from the business case into the plan. It may also lead to an

update of the benefits management plan (PMI, 2017). At the end of planning it is important to

12

ensure that the business case still aligns to the project plan and remains viable (OGC, 2009).

Future reviews involving the business case should be included in the plan.

PGs 6 and 7 should be done iteratively and in parallel throughout project execution

and into benefits realisation. PG6 covers regular monitoring and reporting of project scope,

schedule, costs and risks (Maes, De Haes, et al., 2014). When ad-hoc or planned reviews are

done, in PG7, the business case should be updated and checked for ongoing viability (OGC,

2009).

PG8, the last group, involves measurement and assessment of outcomes. Realised

benefits are compared with those in the business case and action taken where there is a

significant shortfall (Marnewick, 2016). After the final assessment, lessons-learned are

documented to inform future projects.

The PGs, which cover the project’s lifetime, should ideally be followed in the

sequence given, but in practice there is usually iteration. For example, assumptions may be

revisited during later project stages, and constant reprioritisation is done. Processes within the

groups are often omitted, sometimes justifiably and sometimes to the detriment of the project.

2.4.2 Information categories

Figure 1 also shows the linkages between the business case PGs and the business case

information categories (Marnewick & Einhorn, 2019). Indeed, it is the information, or lack

thereof, that often constitutes the antecedent and consequent states referred to in process

theory. As can be seen, much of the information required during tracking is different from

information that is available when the business case is first presented (Brandon, 1998; OGC,

2009; Samset & Volden, 2015). Additional information is generated during planning, and still

more during execution and benefits realisation, underlining the need for ongoing business

case review. As it is essential to understand what information to seek at different times in the

13

project’s lifetime, such information is categorised into the blocks in Figure 1. Their

interactions with the business case PGs are as follows:

Information to create BC (business case, unshaded) serves as input to the first four PGs,

as shown by the arrows ‘a, b, c, d’. The information ‘a’ needed for the first group would

be at a high level and might lack detail. Arrow ‘c’ is double-ended, as the analysis and

quality assurance processes, both use information and generate further information.

Information ‘e’ from the approved business case is a major input to project planning

(Cooke-Davies, 2005), which also generates further information.

BC information from planning (light shading) is used in several ways. First, it may

update the business case ‘f’, as more detail emerges (IPMA, 2009; ISACA, 2012; Nelson

& Morris, 2014; OGC, 2009; PMI, 2017; Thamhain, 2013). But it also creates

information ‘g’, like planned values, that enable the project to be tracked during

execution (Brandon, 1998). Here, ‘tracking’ covers both monitoring of progress and

business case review.

Information for review of BC (dark shading) is gathered as the project is executed, like

progress and actual costs (Brandon, 1998; Herman & Siegelaub, 2009; OGC, 2009; PMI,

2017; Thamhain, 2013). Such information is compared to what was planned and related

back to the business case (flows ‘h’ and ‘i’). The comparisons should indicate whether

the project, or benefits realisation, is proceeding according to plan or whether an ad-hoc

review is needed. Whether scheduled or ad-hoc, reviews could lead to governance

decisions, i.e., the diamonds (Larson & Gray, 2014).

As indicated by the double-ended arrows, all business case PGs, after project start,

both use and generate information. Also, because the business case is updated regularly, the

‘to create’ and ‘from-planning’ information is effectively used in all subsequent processes.

2.5 Research questions arising from the literature

14

This literature review confirms that the business case underpins sound project

governance, which should in turn greatly improve the probability of IT project success.

However, the business case’s potential may not be fully met because of the PGs outlined

above being only partially followed due to their difficulty, rendering business case

information incomplete. Where this is true, business case support for the governance of

business IT projects would be inadequate, thus undermining their success rate. This

convergence of the literature raises the following research questions:

1. To what extent is each business case process used in practice?

2. What can be inferred from literature regarding the consequences

of the business case process usage patterns?

Both questions require a broad understanding of the business case processes and the

information that they require and generate. Question 2, besides using the findings from

question 1, may be answered by seeking from literature the merits of following business case

processes and inferring the likely consequences if such processes are not followed. Literature

also indicates pitfalls in business case use, caused by processes being omitted or inadequately

followed.

3 Research method

3.1 Research design and survey population

To answer research question 1, a quantitative research design was selected, as it

needed input from a broader group than is possible with individual interviews. A cross-

sectional approach, as opposed to longitudinal research, was taken using a survey covering a

limited geographical area. The scope of the survey was organisations based in South Africa

that implement IT projects.

However, because it is difficult to engage with organisations as a whole, the survey

was done at the level of the people in organisations who play a variety of roles that relate to

15

the business case. Therefore, people were the units of analysis that make up the survey

population. More specifically, they were individuals involved in the use of business cases

(having responsibility, providing input, collating input, or managing any aspects of the

process). Therefore, the following roles, amongst others, were covered: executives, project

owners, business managers, business specialists, programme or project managers, portfolio

staff, PMO staff, senior IT people, reviewers of projects, and senior service providers or

consultants.

With about 10 million people in formal employment in South Africa, the following

order of magnitude estimates are given for the survey population: The survey population

could be about 100 000 people associated with about 20 000 organisations of varying sizes

that do business IT work in project mode. The organisations were broadly classified into 10

industry sectors: government, utilities, non-government organisations, financial services,

other services, IT / communications, wholesale / retail, mining / manufacturing, health, and

education. It is estimated that the survey sample of 151 people covered about 120 different

organisations. Thus, the survey sample was small compared with the estimated population.

3.2 The survey questionnaire and sampling approach

The first section of the survey covered demographic data about the respondents: role

in the organisation, years of business experience, industry sector, and size of the organisation.

In subsequent sections, the 37 business case processes were presented as shown in

Table 1, divided into the eight PGs from Figure 1. Respondents were asked to rate the degree

to which each process is used (practiced) in their organisations. Rating were done on a five-

point Likert scale: 1: never used, 2: seldom used, 3: sometimes used, 4: often used, 5: very

often used.

16

Table 1. Rating items for business case (BC) process usage

BC Process group No BC Process description

PG1. Initial preparation

1 Produce a high-level project proposal with business drivers

2 Do initial map of business benefits to proposed process changes and IT deliverables

3 Do initial screening of the proposal, and terminate if deemed non-viable

4 Authorise a person or team to create a business case

PG2. Groundwork for the BC

5 List project goals and objectives to understand what must be achieved

6 State how the goals and benefits align to corporate strategy

7 Document stakeholder requirements, expectations and decision criteria

8 Describe expected business benefits (monetary and intangible)

9 Estimate the value of business benefits (taking operating costs into account)

10 Assign responsibility to individuals for the achievement of benefits

11 Define how benefits will be measured, after they are realised

12 Identify organisational or process changes that use IT deliverables to enable benefits

13 Identify the preferred implementation alternative

14 Do scope definition for the project

15 Estimate the cost of the project, including organisational and process changes

16 Assess initial risks, plan response actions, and where appropriate, estimate a contingency amount

PG3. Assembly and presentation of the BC

17 Gather supporting evidence and provide explanations / calculations for stakeholders

18 Confirm that financial figures meet organisational criteria

19 State assumptions, dependencies and constraints

20 State recommendations, emphasising key themes

21 Quality assure the business case (e.g. sound content, relevant, clear)

22 Present the business case to stakeholders who will influence, or take, the decision to proceed with the project

PG4. Prioritisation and resource allocation

23 Prioritise the project using the business case as input 24 Decide on project timing based on resource availability

PG5. Planning using the BC

25 Incorporate business case content into the project plan and benefits-realisation plan

26 Schedule business case reviews that will be held during project execution

27 Update the business case, to align with the project management plan

PG6. Monitoring of the project

28 Monitor project scope / quality

29 Monitor the project schedule

30 Monitor project costs

31 Monitor project risks

PG7. Review of the BC during execution

32 Refer to the business case, during IT and business process design

33 Conduct periodic business case reviews using input from monitoring

34 Realign the business case with the project management plan

PG8. Measurement and assessment of benefits realisation

35 Monitor benefits realisation and costs (after IT delivery), based on the business case

36 Conduct post-project assessment based on business case benefits

37 Document lessons learned

17

The questionnaire went through two review processes. First, the questions were

reviewed by an experienced statistician to check that the wording was suitable and

unambiguous (Fox & Bayat, 2007). Second, the questionnaire was sent to a selected pilot

group of 12 experienced people covering a variety of the above-mentioned roles. The

corrected survey was then entered into an automated survey tool. The link to the automated

survey was sent by email with guidance to ensure that respondents fully understood the

purpose and context of the survey.

No list exists of all the suitable respondents, precluding the use of probability

sampling. The aim of the non-probability sampling approach was to get a representative

sample. Accordingly, the following were the main approaches: Convenience sampling was

used by having the survey circulated by three different professional bodies. Judgment

sampling was used by selecting from published lists of organisations and making telephone

contact before emailing the survey. Snowball sampling was also used by inviting respondents

to forward the survey link to further eligible people (Walliman, 2001). The principle of self-

selection was effective throughout, whereby recipients of the email and link went no further

if they did not relate to the survey (Fox & Bayat, 2007). Responses were received from 209

people, of which 58 incomplete responses were discarded, leaving 151 responses to be used

in the analysis.

3.3 Demographic analysis of the survey population

This subsection analyses the demographic information supplied by survey respondents

whose data is included in the analysis. The purposes are: (i) to understand the survey sample

and their organisations, (ii) to show that they are representative, and (iii) to give context to

the results. The survey was only distributed in South Africa, and care was taken to make it

clear that the survey was about business IT projects, as distinct from, for example,

construction projects. This limitation was explained within the survey itself and also in the

18

invitation letters sent out. However, no organisation was prevented from responding, as

construction companies also make extensive use of IT, for supply chain, HR, and other

purposes.

The survey respondents were analysed according to their roles in the organisation, the

industry sector of the organisation, the size of the organisation, and their years of experience.

The cross-tabulation of respondents across all industries and all roles given in Table 2 shows

that no intersection has more than 6.6% of the respondents. The ‘executive / business

manager’ role is represented in all industries, and all roles are represented in the financial and

government industry sectors.

Table 2. Cross-tabulation of job role against industry sector

Cross tabulation of Organisational roles

with Industry sectors

Figures are percentages

Which industry sector best covers your organisation, or the one you are involved with?

Total G

over

nme

nt o

r p

ublic

ad

min

istr

atio

n

Util

ities

e.g

. tra

nspo

rt, e

nerg

y,

wat

er

NG

O (

Non

-Gov

ern

men

tal

Org

ani

satio

n)

Fin

anci

al s

ervi

ces,

e.g

. ba

nkin

g,

insu

ranc

e, in

vest

men

ts

Oth

er s

erv

ices

, e.

g. c

onsu

lting

, le

gal,

HR

, lo

gist

ics,

fac

ilitie

s

IT a

nd c

omm

unic

atio

ns

Who

lesa

le,

reta

il, m

arke

ting

(incl

udin

g on

line)

Min

ing

or m

anuf

actu

ring

Hea

lth c

are

Edu

catio

n an

d tr

aini

ng

Wh

ich

of

the

follo

win

g b

est

des

crib

es

you

r ro

le in

th

e o

rgan

isat

ion

?

Executive, senior business manager, or project sponsor / owner 0.7 1.3 2.6 6.6 4.0 5.3 1.3 5.3 1.3 2.0 30.5

Business analyst or business specialist 2.0 2.0 0.7 5.3 0.7 0.7 11.3

Portfolio manager / specialist 1.3 0.7 3.3 0.7 6.0

PMO (Project Management Office) manager / specialist 2.6 0.7 6.6 4.0 0.7 0.7 1.3 1.3 17.9

Project manager or programme manager 3.3 1.3 1.3 3.3 3.3 0.7 0.7 1.3 15.2

IT manager or specialist 0.7 1.3 1.3 0.7 2.0 1.3 1.3 8.6

Quality assurance, risk, or audit person 0.7 0.7 0.7 0.7 1.3 4.0

External consultant or service provider 0.7 2.0 0.7 1.3 0.7 1.3 6.6

Total 11.9 7.3 5.3 29.1 5.3 17.2 6.0 7.3 4.6 6.0 100.0

19

In terms of experience, 38% of the respondents had less than 15 years of business IT

experience but there was a skew towards the higher levels of experience with 26% having

between 15 and 20 years, and 36% having more than 20 years of business IT experience - not

surprising due to the level of skill and experience required in all aspects of business case use.

Just over half the respondents were from organisations with over 1000 employees, 21% were

from organisations with 100-1000 employees and 28% were from organisations with below

100 employees.

3.4 Overview of the analysis for research question 1

Descriptive statistical analysis was done to determine the usage in practice of the

business case processes. The results were considered in two ways. First, for each PG, the

mean process usage was calculated. Second, the 37 individual processes were analysed by

refining the results into low, medium, and high usage. High usage combined the item 4

(often) and 5 (very often) scale responses to give a perspective of which processes are used

more than others. These results were then summarised at the PG level, which became input to

research question 2. Further analysis was done to determine whether there are significant PG

usage differences across the 10 industry sectors and the three organisation size categories.

3.5 Validity and reliability checks

Data collection is relatively automatic as the survey tool allows data to be extracted

into SPSS (IBM’s Statistical Package for the Social Sciences). Data could then be exported to

Excel to produce certain charts. There are two criteria that data must meet for credible results

to be produced: data must be both valid and reliable (Field, 2013). A further distinction can

be made between internal validity and external validity (generalizability).

There are several ways of assessing internal validity. Logical validity is based on

subjective judgment that the measurement items relate to the stated research questions. This

is addressed via the statistician and pilot group reviews. Content validity relates to the

20

domains being measured, and whether the scale items measure those domains (Pallant, 2010).

For this research, all business case processes are drawn from the published literature and are

believed to be valid. Process validity relates to the way in which data is gathered. In this

research, the demographic spread of responses was continuously monitored during the survey

period, allowing adjustments to be made to ensure a representative spread.

From an external validity point of view, the data is believed to be generalizable within

South Africa. However, because the rating items arise mainly from ‘Western world’

literature, it is believed that the findings should therefore also apply to IT projects in such

countries. However, the findings might not be generalizable outside of IT projects, or to

countries where a different decision-making culture prevails.

There are a number of criteria for data reliability. The data must be consistent, with

the same method being used to gather it, and must exhibit independence among the

respondents. It must be stable, meaning that gathering more data would produce similar

results, and reproducible, meaning that if the research were repeated, it would also produce

similar results (Exeter, 2017). A commonly accepted way of measuring reliability is by using

Cronbach’s alpha test, where an alpha of 0.7 or above is considered satisfactory (Pett,

Lackey, & Sullivan, 2003). The results are that the Cronbach’s alphas for the PGs range from

0.703 to 0.914, with an arithmetic average of 0.834, indicating that the data is adequately

reliable.

An assessment is made of the independence of the 151 responses, meaning that the

respondents do not influence one another. Independence is a requirement for parametric tests

like correlations and desirable for most others (Pallant, 2010). In this survey, lack of

independence could result from multiple respondents belonging to the same organisation,

where they might communicate about the survey answers. Analysis of the data indicates that

21

no more than 5 respondents (less than 4%) belong to any individual organisation, supporting

the view that the responses are largely independent.

Another requirement for many types of statistical data analysis is that the data for

each rating item are normally distributed. Normality is measured by skewness and kurtosis,

which are calculated for each of the rated items. The parameters skewness / standard error of

skewness, and kurtosis / standard error of kurtosis are used. Ratios above 2.58 indicate that

the data may not be normal (Rose, Spinks, & Canhoto, 2015). Based on this ratio, and

inspection, ratings for the business case items are normally distributed. Having done

reasonable checks on the data, the conclusion is that the data can be used for analysis.

4 Results

4.1 Analysis of business case process usage in practice

The finding from the literature review that some business case processes are difficult

to conduct, especially during project execution, suggests that some processes may not be

practiced regularly. This section assesses the degree to which each of the business case PGs

and processes within the groups are followed in practice for IT projects in South Africa.

Table 3 shows, for each of the PGs, the mean for the group. It also shows the minimum and

maximum values of the means and standard deviations, among all of the processes in each

group. The five-point Likert scale was: 1 never used; 2 seldom used; 3 sometimes used;

4 often used; 5 very often used.

22

Table 3. Business case process usage means and standard deviations

Process Group Number of processes

In PG

Mean usage for

PG

Minimum process mean

Maximum process mean

Minimum process

Std. Dev.

Maximum process

Std. Dev.

PG1: Do initial preparation 4 3.78 3.51 3.98 0.98 1.11

PG2: Do groundwork for BC 12 3.69 3.19 4.20 0.87 1.26

PG3: Assemble BC and present 6 3.73 3.48 4.10 1.01 1.18

PG4: Prioritise using BC 2 3.43 3.38 3.48 1.19 1.22

PG5: Plan using BC and update BC 3 2.86 2.64 3.19 1.19 1.31 PG6: Monitor project 4 4.11 3.96 4.26 0.90 1.02

PG7: Review BC 3 2.90 2.74 3.17 1.09 1.28

PG8: Measure, assess using BC 3 3.08 2.86 3.49 1.14 1.29

Table 3 shows that there is a substantial spread in the PG means. This is confirmed by

Table 4 which shows the results of paired samples t-tests to compare the PG means. The only

comparisons where the means are not significantly different at a 95% confidence level

(2-tailed) are shaded. For all the unshaded t-statistics the differences are significant, most

with a significance of 0.000. Thus, there are no significant differences in usage between

PGs 1, 2, and 3. However, after the decision to proceed has been taken (in PG 3), there are

significant differences, except for PG5 (plan using the business case) and PG7 (review the

business case) where there is no significant difference in usage.

Table 4. Mean difference t-statistics for business case PG usage means

Process Group PG1 PG2 PG3 PG4 PG5 PG6 PG7 PG8

PG1: Do initial preparation 1.06 0.97 4.57 11.57 4.66 9.86 8.46

PG2: Do groundwork for BC 0.98 3.69 12.61 6.90 10.32 9.99

PG3: Assemble BC and present 4.14 11.81 5.92 10.14 8.71

PG4: Prioritise using BC 7.77 8.02 6.08 4.27

PG5: Plan using BC and update BC 13.73 0.79 3.26

PG6: Monitor project 13.40 13.73

PG7: Review BC 2.54

PG8: Measure, assess using BC

This finding is corroborated by considering the minimum and maximum means of the

processes within each PG in Table 3. The bolded process means range from 2.64 (between

‘seldom’ and ‘sometimes’) to 4.26 (between ‘often’ and ‘very often’), indicating that certain

23

processes are used far more consistently than others. The bolded process standard deviations

range from 0.87 to 1.31, indicating that there is a spread of ratings, supporting the view that

the practices vary widely across organisations. It is of interest that the process means

generally decrease as the project proceeds, indicating that the business case is used less and

less after approval. Particular values in the table are also insightful. For example, the lowest

mean, indicating that it was the least often conducted, was for a process in PG5 (using and

updating the business case when constructing the project plan). On the other hand, the

highest mean was for a process in PG6 (monitoring the project), a PG that is invariably

conducted whether or not a business case exists. Similarly, the smallest standard deviation,

indicating a well-known and prescribed process, was for a process in PG2 (doing the

groundwork for the business case), while the highest, indicating the least-prescribed process,

was again for a process in PG5.

While the item means are useful for gathering some general insights about practice,

the percentages of respondents’ ratings, by item, allows more detailed understanding of these

trends and answers research question 1. Figure 2 shows the percentages graphically. The

processes are given vertically in their PGs, indicated by the tabs on the right-hand side. To

simplify the diagram, the ‘never’ and ‘seldom’ responses and the ‘often’ and ‘very often’

responses are combined as shown in the key. The rounded percentages are given in the bars.

24

Process usage key: Never / seldom Sometimes Often / very often

Figure 2. The usage in practice of business case processes

The first three PGs are reasonably well used, indicated by longer dark-shaded bars,

with PG1 at 67%, PG2 at 61% and PG3 at 61%. It is interesting that even among the

relatively well used processes in PG1, the lowest at 54% is mapping the business benefits to

proposed organisational process changes. Two items in PG2 that are notably lower than

average are: defining benefits measurement (42%) and identifying organisational process

25

changes to enable benefits (43%). Another weak item is that responsibility for obtaining the

benefits is not always assigned (51%). These lower percentages indicate that even if the

business case is created and approved, there will be potential difficulties later with the

tracking of benefits realisation. Perhaps the organisation assumes that it will not use the

business case to support any changes that will affect people or processes.

The two items of PG4, at 50% and 54% respectively, show that prioritisation uses the

business case to a fair extent. However, the three processes in PG5, show that use of the

business case reduces considerably after project initiation. In particular, scheduling of

reviews (29%) and checking / updating the business case (28%) have very low usage. These

large differences support the view that the business case is mainly used to get initial funding,

and is hardly used thereafter (Eckartz et al., 2009). The 28% for updating the business case to

align with the plan also shows that a mandatory part of OGC (2009) methodology, requiring

such an update, is seldom followed.

A dichotomy appears during execution, with PG6 and PG7 showing stark contrasts.

PG6, which involves routine project monitoring, enjoys a 77% average. While these

processes provide essential information to track the business case, they do not use the

business case directly. However, the three processes of PG7, which do use the business case,

only average 34%, and notably the two business case review processes stand at 31% and 30%

respectively. PG8, averaging 38%, includes use of the business case during benefits

realisation and benefits assessment, which also have low usage at 31% and 30% respectively.

Only lessons-learned is higher at 52%, but this could be because lessons-learned sessions can

be conducted without comparing achievements against what was proposed in the business

case.

26

The above findings may now be summarised in Figure 3 which shows averages by

PG, highlighting the ‘high’ usage percentage. It shows clearly the dramatic reduction in PG

use during project planning, execution and benefits realisation.

Figure 3. Business case usage summary by process group (PG)

As indicated in the dark shading, usage (often and very often) averages 63% for PG1

to PG3 which correspond to preparation for project approval. Following approval, usage

drops to 52% for prioritisation in PG4, and down to about 33% for PG5, PG7 and PG8a. PG6

and PG8b are generally done irrespective of a business case, hence their higher percentages.

4.2 Organisation size and sector effects

It is also of interest to determine whether there are significant differences in process

usage based on the industry sector and the size of the organisation. For each respondent, the

organisation’s mean process usage was calculated for the eight PGs. The results were then

used to calculate the means for each organisation size and for each industry sector, the results

of which are shown in Figures 4 and 5.

27

Figure 4. Mean business case process usage by organisation size

Figure 5. Mean business case process usage by industry sector

Examining the figures, it appears that there isn’t much difference due to size of the

organisation, but that there might be by industry sector, especially the top rows compared to

the bottom rows. To understand the significance of such differences, independent samples

t-tests were done to compare their means. The results show that for organisation sizes, there

are no significant differences of means at a 95% confidence level. However, the industry

sectors do show a few significant differences in terms of business case process usage,

highlighted in Table 5.

28

Table 5. Industry sector mean difference t-statistics for business case process use Industries are ordered from greatest to least usage of processes;

t-scores are rounded, and if bolded with * denote: significance < 0.05)

Industry Description

N

Sample size

Mean

Util

ities

Hea

lth c

are

Min

ing,

m

anuf

actu

ring

Oth

er s

ervi

ces

Who

lesa

le,

reta

il

IT a

nd c

omm

s.

Gov

ernm

ent

Fin

anci

al

serv

ices

Edu

catio

n

NG

O

Utilities 11 3.96   0.24 0.80 0.65 0.75 1.81 1.68 1.94 2.53* 2.72*Health care 7 3.88 0.45 0.36 0.45 1.26 1.19 1.34 2.01 2.16

Mining, manufacturing 11 3.77 0.05 0.16 1.11 1.08 1.19 2.27* 2.53*Other services 8 3.76 0.09 0.85 0.82 0.94 1.72 1.95

Wholesale, retail 9 3.73 0.76 0.74 0.86 1.65 1.92

IT and comms. 26 3.53 0.09 0.14 1.48 2.01

Government 18 3.52 0.03 1.25 1.71

Financial services 44 3.51 1.43 2.02*

Education 9 3.14 0.47

NGO 8 2.93

As might be expected, the most significant differences occur for NGO and Education

sectors when compared with the Utilities and Mining, manufacturing sectors. One possible

explanation may be that the industry sectors higher in the table are more mature in terms of

projects than those lower down and hence tend to follow established standards for how to

manage projects. Comparisons between the other industry sectors do not produce any

significant differences. As a result, when examining projects in the education and NGO

sectors, we need to be aware that they will be less sophisticated in the use of business cases

than those in the utilities and mining/manufacturing industries.

The analyses were done for the mean of all 37 processes. Table 6 now considers the

means for each PG to determine whether there are differences across industry sectors. The

shaded blocks indicate sector means that are above the overall mean usage for each PG.

Table 6. Means for industry sectors by process group (PG)

Industry Description Sector Mean PG1 PG2 PG3 PG4 PG5 PG6 PG7 PG8

PG mean 3.78 3.69 3.73 3.43 2.86 4.11 2.90 3.08

Utilities 3.96 4.07 4.24 4.11 3.82 3.03 4.48 2.88 3.82

Health care 3.88 3.93 3.95 4.17 3.79 3.43 4.14 3.29 3.76

29

Mining, manufacturing 3.77 4.27 3.83 4.12 3.23 3.09 4.52 3.12 2.88

Other services 3.76 3.94 3.93 3.96 3.63 3.25 3.94 3.33 3.25

Wholesale, retail 3.73 3.94 3.80 3.63 3.67 3.37 4.11 3.33 3.67

IT and comms. 3.53 3.73 3.67 3.58 3.35 2.76 4.27 2.91 3.18

Government 3.52 3.72 3.67 3.61 3.08 2.81 4.10 3.04 3.11

Financial services 3.51 3.82 3.63 3.78 3.64 2.67 4.10 2.73 2.83

Education 3.14 3.36 3.16 3.33 2.89 2.70 3.69 2.56 2.78

NGO 2.93 2.84 3.17 3.10 3.00 2.46 3.31 2.29 2.29

The results in the table are as expected but with minor variations. For example: The

financial services sector has relatively higher usage of PGs up to prioritisation (PG4),

possibly because their standards insist on business case use up to, but not beyond, project

initiation. While utilities have high use of other PGs, their usage of business case review

(PG7) is relatively lower. Mining and manufacturing use the business case less for planning

and during benefits realisation. IT and communications places relatively more emphasis on

monitoring the project, and tracking the business case during execution and into benefits

realisation.

5 Discussion

Figure 3 shows convincingly that usage of the business case falls off dramatically

after the business case has been approved. This finding is not contradicted by the relatively

high usage of process groups 6 and 8b which are generally done without reference to a

business case, but which may provide information for other business case processes. It is now

possible to answer research question 2. The consequences, derived from literature, are

discussed in rough PG sequence followed by general observations. In this discussion ‘high

usage’ applies to the ‘often’ or ‘very often’ responses. The percentages mentioned below are

drawn from Figure 3.

PG1 to PG3 take the proposed project to the point where a decision in principle is

taken to proceed, subject to organisational priorities and dependencies. Roughly 63% of

30

respondents report high usage of these PGs. For the remaining 37% the likely consequences

are that:

o Project goals will not be checked for alignment with organisational strategies

(Marnewick, 2016).

o Achievable benefits may be overlooked and never realised (Ward et al., 2008).

o The ‘do-nothing’ option will probably not have been considered (Herman &

Siegelaub, 2009; OGC, 2009).

o The owner or steering group will not know whether proposed benefits exceed the

investment costs (Olsson, 2018). Thus, projects undertaken may be unjustified and not

use resources in the most effective ways (OGC, 2009).

o Projects may lack agreement as to the preferred project concept and solution, which

are needed as a basis for estimates and which reduce the likelihood of costly changes

later (APM, 2006; Samset & Volden, 2015).

o Key information will be missing from ongoing reviews of the organisation’s portfolio

of projects (Franken et al., 2009).

PG4’s processes use the business case to prioritise the project against others that have

been approved in principle (Kopmann et al., 2015; Marnewick, 2016; Ward et al., 2008).

Only 52% of responses indicate high usage of the business case for prioritisation. For the

remaining 48%, influential executives may get their projects approved irrespective of the

strength of their business cases (Herman & Siegelaub, 2009). The value of the projects to the

organisation may not be adequately considered, while better understood factors like

availability of resources may be given undue weight (Eckartz et al., 2009; Herman &

Siegelaub, 2009). Without using business cases it becomes more difficult to rank projects and

put those of least value on hold, resulting in overcommitted resources (ISACA, 2012;

Marnewick, 2016).

31

PG5’s processes use the business case to develop the project and benefits realisation

plans, as well as to update the business case and align it to the plan. Only 33% of respondents

report high usage of PG5, which might have the following consequences for the remainder:

o The scope and other plans may not align to what is needed to produce the benefits

(Cooke-Davies, 2005).

o The project manager may not fully understand the business case and be incapable of

conveying the business goals to stakeholders (APM, 2006; Herman & Siegelaub,

2009).

o Even where knowledgeable stakeholders cooperated during business case creation,

much may have changed by the end of planning - especially if there is a delay

between approval and project initiation. Assumptions may need revision as more

information becomes available, requiring rethinking of the business case or any aspect

of the project (OGC, 2009; Samset & Volden, 2015) -

o A more detailed business case, required by OGC (2009) and ISACA (2012), will not

be produced, making it unlikely that any future gate reviews will be based on the

business case (APM, 2006).

PG6’s processes are used extensively with 77% of respondents reporting high usage,

indicating that these project monitoring processes are standards in most organisations. While

their output is needed for tracking the business case, they do not depend on a business case.

Although PG7’s business case review processes may be done at any time after

approval, they should be prevalent during execution, which is often the longest and most

resource-consuming part of the project’s lifetime (PMI, 2017). Only 34% of respondents

report high usage of PG7 with the following consequences where processes are not used:

o Focus on the expected benefits may be lost, with the project manager not using

benefits for guidance when considering technical or other options (Coombs, 2015;

32

Herman & Siegelaub, 2009; ISACA, 2012; Sauer & Reich, 2009). Thus,

implementation is likely to drift away from what was envisaged in the business case

(Maes, De Haes, et al., 2014; Musawir et al., 2017). Indeed, according to Kopmann et

al. (2015), the project manager should take some accountability for business benefits.

o Changes in the organisation’s internal and external environment that affect the

business case may go unrecognised (Marnewick, 2016; Musawir et al., 2017; Olsson,

2018).

o There is unlikely to be independent review of the project which, if done, might point

out overlooked issues or opportunities (Kopmann et al., 2015).

o Ongoing re-prioritisation against other projects becomes more difficult (Franken et

al., 2009), and where the justification for the project disappears, the project is unlikely

to be changed or stopped (APM, 2006; Eckartz et al., 2009; Herman & Siegelaub,

2009).

The two PG8a processes, to monitor and assess benefits realisation, are typically done

after the delivered IT products have been incorporated into business processes. Only 30% of

respondents report high usage with the following likely consequences for the remainder:

o There will be less focus on realising the planned benefits (Cooke-Davies, 2005).

Some benefits may be overlooked entirely because there is no check that each benefit

is realised, and solvable problems may not be attended to (ISACA, 2012; Marnewick,

2016). Stakeholders may even be unaware of what might have been achieved.

o Measurements of benefits, especially non-financial, will not be done, nor will the cost

of realising the benefits be understood (Eckartz et al., 2009).

o Success is unlikely to be assessed objectively as it is difficult for business owners to

measure success without referring to the business case (Maes, De Haes, et al., 2014;

33

Musawir et al., 2017; Peppard et al., 2007; Zwikael et al., 2018; Zwikael & Smyrk,

2012).

The PG8b process, documenting lessons learned, has 52% of respondents reporting

high usage; the remaining 48% are at risk of repeating mistakes in subsequent projects.

Nevertheless, if lessons-learned are discussed without using the business case a valuable

input will be missing and deviations from envisaged benefits are unlikely to be explained

(Franken et al., 2009; Ward et al., 2008).

Even for the 63% of responses reporting high usage of PG1-3, where the business

case is not used beyond approval, negative consequences are likely. There is a greater risk of

poor business case quality and unjustified projects being approved. The business case may be

misleading in any of the following ways:

o Promoters of projects, knowing that they can only be held to account if benefits are

tracked, may give overly-optimistic estimates (Kopmann et al., 2015). Benefits may

be imprecisely formulated, overstated or unachievable leading to unrealistic

expectations with risks being ignored (Eckartz et al., 2009; Ward et al., 2008). Worse

still, deliberate ‘strategic misrepresentation’ is possible (Flyvbjerg, 2014).

o The cost of process changes and organisational change management may be

overlooked or underestimated (Eckartz et al., 2009; Ward et al., 2008).

o Assumptions used in the justification may be unrealistic and are unlikely to be

revisited (APM, 2006; Kopmann et al., 2015).

o People may not be made accountable for benefits, with stated measurements and

baseline data captured for later comparison (Franken et al., 2009; OGC, 2009;

Zwikael et al., 2018). Interestingly, the process with the lowest usage in any of the

PGs leading to approval is ‘defining how benefits will be measured’.

34

A question might then become: “what is the purpose of a business case?” If it is

merely to obtain approval to proceed with the project, then the abovementioned shortcomings

are likely to prevail. If, on the other hand, the purpose is to ensure that projects are only

undertaken if they have a high probability of delivering net business and strategic value to the

organisation, then the emphasis would be entirely different. Developers of the business case

would be recognised for responsible work, rather than for getting a favourable decision,

(which might appear less favourable as the project unfolds).

Governance, at both project and portfolio levels, creates accountabilities and depends

on effective use of the business case (Franken et al., 2009; Marnewick, 2016; Musawir et al.,

2017). Therefore, for organisations where the business case is not used throughout the

project’s lifetime, governance is unlikely to be effective, to the detriment of the success rate

(Musawir et al., 2017; Ward et al., 2008). In addition, the business case will not be used to

guide the project through critical thinking and good communication, nor will it be used for

decision making at authorisation points or gate reviews (APM, 2006; Eckartz et al., 2009;

Franken et al., 2009).

Benefits, a focus area in recent literature, need to be stated and updated where

necessary to achieve success. Such ongoing ‘economic governance’ is particularly important

in the agile environment, where requirements evolve as the project progresses (Brown,

Ambler, & Royce, 2013). So, unless the business case is periodically reviewed, an agile

project may be unable to adapt to changes or new information; nor is it likely that the project

will be terminated if it is no longer justified.

Thus, it is more cost effective to revisit the business case regularly than to strive for

perfection up-front. This is compounded by the accelerating rate of change, both inside and

outside the organisation, which often affects strategic requirements and the needed benefits

(Sauer & Reich, 2009). Such changes can even affect the ownership of benefits and their

35

measurement. Additionally, if the business case were to be versioned, with changes from the

previous version highlighted, then business case history could provide valuable learning to

augment the lessons-learned activity. It would also be essential input to the project’s final

report upon completion.

6 Conclusions

To date no comprehensive theory relating to the business case for projects has been

found. Recently, Niederman et al. (2018) have shown how process theory can become a

valuable framework for the accumulation of project management knowledge. Accordingly,

the business case processes, their required information categories and conclusions on their

use serve as early building blocks of business case theory based on the Niederman

framework. Further, it is noted that business case theory has application beyond projects. It is

also relevant for initiatives such as strategy implementation, innovation or organisational

transformation, which might be undertaken over a longer period.

From literature it was concluded that, for business IT projects, lack of effective use of

the business case leads to poor governance, which in turn leads to an unsatisfactory success

rate. Because effective use of the business case requires it to be used throughout the lifetime

of the project, it appeared likely that lack of business case process usage is a root cause of

project failure. As no earlier research was found, this is the first time that conclusions can be

drawn based on actual measurements of business case process usage for business IT projects

and other similar projects such as innovation and Agile that operate in dynamic

environments.

6.1 Conclusions drawn from the findings

Measurements were done through a survey, which after being reviewed and piloted,

produced 151 valid, reliable responses. The constructs surveyed are business case processes

which, together with business case information, provide a basis for effective business case

36

usage. The findings may be summarised as follows: 63% of respondents reported high usage

of the business case up to approval being given to proceed. This drops to 52% for

prioritisation of the project against other projects, and further to 34% or less for processes

that use the business case to plan, review the project, and to support benefits realisation.

Further findings are that the practices in organisations vary widely and that, while size-of-

organisation does not appear to be an important factor, there are differences between industry

sectors, with some being more mature than others in terms of business case usage.

Besides offering an explanation for the unsatisfactory success rate of business IT

projects, the findings point to practical remedies which can be put in place at affordable cost.

What emerges should be educational for managers at all levels involved with projects and

their justification. It should allow them to evaluate their current practices related to the

business case and to determine where improvements might be made or standards enhanced.

In particular, they would understand that only using the business case to get approval to

proceed can lead to disappointing results. Ongoing business case review, in support of sound

governance, throughout execution and benefits realisation has far greater value.

Indeed, the purpose of the business case needs to shift from getting approval to

proceed, to adding significant business and strategic value via the project. Reviews using the

business case do not need to be time-consuming; an hour spent with key stakeholders,

reviewing expected benefits, costs, schedules and risks, may be all that is required for most

projects. Any such review is preferable to the prevalent norm of not revisiting the business

case at all.

6.2 Looking to the future

There is much scope for future research: First, the basic business case theory

mentioned above can be elaborated on by going into more detail on the processes and the

information categories that interact with them using the same Niederman framework. Second,

37

it appears from literature that effective use of the business case depends on the presence of

organisational facilitating factors, which are a natural extension of this study and highly

appropriate for in-depth research and theory development. The model given in Figure 1 could

then be expanded to show the influence of these facilitating factors on the business case

processes and benefits realisation. It should also be determined whether the presence of such

facilitators leads to higher usage of the business case in practice, especially after project

initiation.

Also, this study has only been done on a limited subset of projects (business IT) in a

limited geography (South Africa). Similar research could be done in other geographies to

determine similarities and differences. Research could also be conducted for a broader range

of projects, with possible modification to some of the survey rating items. It would be of

additional value to identify a measure of business case ‘effectiveness’. Although none is

known yet, it can be argued that any such measure might relate to use of the business case

processes identified in this paper.

7 Funding and conflicts of interest

This research did not receive any specific grant from funding agencies in the public,

commercial, or not-for-profit sectors. There are no conflicts of interest.

38

References

Al-Ahmad, W., Al-Fagih, K., Khanfar, K., Alsamara, K., Abuleil, S., & Abu-Salem, H. (2009). A taxonomy of an IT project failure: Root causes. International Management Review, 5(1).

APM. (2006). APM Body of Knowledge 5th edition. Buckinghamshire, UK.: Association for Project Management.

Bizzi, L., & Langley, A. (2012). Studying processes in and around networks. Industrial Marketing Management, 41, 224-234. doi:10.1016/j.indmarman.2012.01.007

Brandon, D. M. (1998). Implementing Earned Value Easily and Effectively. Project Management Journal, June 1998.

Brown, A., Ambler, S., & Royce, W. (2013). Agility at scale: Economic governance, measured improvement, and disciplined delivery. Paper presented at the Proceedings of the 2013 International Conference on Software Engineering, San Francisco, CA, USA.

Cooke-Davies, T. (2005). The Executive Sponsor--The Hinge Upon Which Organisational Project Management Maturity Turns? Paper presented at the PMI Global Congress Proceedings, Edinburgh, Scotland.

Coombs, C. R. (2015). When planned IS/IT project benefits are not realized: a study of inhibitors and facilitators to benefits realization. International Journal of Project Management, 33(2), 363-379. doi:http://dx.doi.org/10.1016/j.ijproman.2014.06.012

Eckartz, S., Daneva, M., Wieringa, R., & Van Hillegersberg, J. (2009). Cross-organizational ERP management: how to create a successful business case? Paper presented at the ACM symposium on Applied Computing, Honolulu, Hawaii.

Einhorn, F., & Marnewick, C. (2016). A Practical Model for the effective use of the Business Case in IT Projects. Paper presented at the PMSA Conference 2016, Johannesburg.

Exeter. (2017). Validity, Generalisability & Reliability. Retrieved from education.exeter.ac.uk/download.php?id=5346

Field, A. (2013). Discovering Statistics using IBM SPSS Statistics (4th Edition ed.). California: SAGE Publications Ltd.

Flyvbjerg, B. (2014). What You Should Know About Megaprojects, and Why: An Overview. Project Management Journal, 45(2 April-May). doi:10.1002/pmj.21409

Fox, W., & Bayat, M. S. (2007). A Guide to Managing Research. Landsdowne, Cape Town: Juta.

Franken, A., Edwards, C., & Lambert, R. (2009). Executing Strategic Change: Understanding the Critical Management Elements that Lead to Success. California Management Review, 51(3)(Spring 2009).

Herman, B., & Siegelaub, J. (2009). Is This Really Worth The Effort? The Need For A Business Case. Paper presented at the PMI Global Congress, Orlando, Florida.

IPMA. (2009). PM Baseline Version 3.0. Austria: IPMA - Projekt Management Austria. ISACA. (2012). COBIT 5 : Enabling Processes. Illinois. Joseph, N., Erasmus, W., & Marnewick, C. (2014). The Idle State of Information and

Communication Technology Project Management. Journal of African Business, 15(3), 184-196. doi:10.1080/15228916.2014.956641

Keen, J. M. (2011). Making Technology Investments Profitable: ROI Road Map from Business Case to Value Realization. Hoboken, N.J: Wiley.

39

Kopmann, J., Kock, A., Killen, C. P., & Gemunden, H. G. (2015). Business Case Control in Project Portfolios - An Empirical Investigation of Performance Consequences and Moderating Effects. IEEE Transactions on Engineering Management, 62(4), 529-543. doi:10.1109/TEM.2015.2454437

Koskinen, K. U. (2012). Organizational learning in project-based companies: A process thinking approach. Project Management Journal, 43(3), 40-49. doi:10.1002/pmj.21266

Krell, K., & Matook, S. (2009). Competitive advantage from mandatory investments: An empirical study of Australian firms. Journal of Strategic Information Systems, 18, 31-45. doi:10.1016/j.jsis.2008.12.001

Langley, A. (1999). Strategies for theorizing from process data. Academy of Management Review, 24(4), 691-710.

Langley, A., Smallman, C., Tsoukas, H., & Van de Ven, A. H. (2013). Process studies of change in organization and management: Unveiling temporality, activity, and flow. Academy of Management Journal, 56(1), 1-13.

Larson, E. W., & Gray, C. F. (2014). Project management: The managerial process. International edition. 6th edition. . New York: McGraw-Hill Education.

Laursen, M., & Svejvig, P. (2016). Taking stock of project value creation: A structured literature review with future directions for research and practice. International Journal of Project Management, 34(4), 736-747. doi:https://doi.org/10.1016/j.ijproman.2015.06.007

Maes, K., De Haes, S., & Van Grembergen, W. (2014). The Business Case as an Operational Management Instrument—A Process View. ISACA journal, 4.

Maes, K., Van Grembergen, W., & De Haes, S. (2014). Identifying Multiple Dimensions of a Business Case: A Systematic Literature Review. Electronic Journal of Information Systems Evaluation, 17(1), 47-59.

Marnewick, C. (2016). Benefits of information system projects: The tale of two countries. International Journal of Project Management, 34(4), 748-760. doi:http://dx.doi.org/10.1016/j.ijproman.2015.03.016

Marnewick, C., & Einhorn, F. (2019). The business case thrives on relevant information. South African Journal of Information Management, 21(1), 11. doi:https://doi.org/10.4102/sajim.v21i1.978

Messner, W. (2013). Making the Compelling Business Case: Palgrave Macmillan. Müller, R., Pemsel, S., & Shao, J. (2014). Organizational enablers for governance and

governmentality of projects: A literature review. International Journal of Project Management, 32(8), 1309-1320. doi:http://dx.doi.org/10.1016/j.ijproman.2014.03.007

Musawir, A. u., Serra, C. E. M., Zwikael, O., & Ali, I. (2017). Project governance, benefit management, and project success: Towards a framework for supporting organizational strategy implementation. International Journal of Project Management, 35(8), 1658-1672. doi:https://doi.org/10.1016/j.ijproman.2017.07.007

Nelson, R. R., & Morris, M. (2014). IT Project Estimation: Contemporary Practices and Management Guidelines. MIS Quarterly Executive, March 2014 (13:1), 15-31.

Niederman, F., Muller, B., & March, S. T. (2018). Using Process Theory for Accumulating Project Management Knowledge: A Seven-Category Model. Project Management Journal, 49(1), 6.

OGC. (2009). Managing Successful Projects with PRINCE2, 5th edition. In A. Murray (Ed.). Norwich: TSO (The Stationery Office) on behalf of Office of Government Commerce.

40

Olsson, N. O. E. (2018). Elaborations on the role of project owner: introducing project owners type 1 and 2. International Journal of Managing Projects in Business, 11(3), 827-844. doi:10.1108/IJMPB-08-2017-0102

Pallant, J. (2010). SPSS Survival Manual (4th edition ed.). Berkshire, England: McGraw Hill. Pentland, B., T. (1999). Building process theory with narrative: From description to

explanation. Academy of Management Review, 24(4), 14. Peppard, J., Ward, J., & Daniel, E. (2007). Managing the realization of business benefits from

IT investments. MIS Quarterly Executive, 6(1), 1-11. Pett, M., Lackey, N., & Sullivan, J. (2003). Making Sense of Factor Analysis. California:

SAGE. PMI. (2016). Governance of Portfolios, Programs, and Projects: A Practice Guide.

Pennsylvania, USA. PMI. (2017). PMBOK - Guide to the Project Management Body of Knowledge, 6th edition:

Pennsylvania, USA. Rose, S., Spinks, N., & Canhoto, A. (2015). Management Research: Applying the Principles,

Chapter 15. London: Routledge. Royer, I. (2003). Why Bad Projects Are So Hard to Kill. Harvard Business Review, 81(2),

48-56. Samset, K., & Volden, G. H. (2015). Front-end definition of projects: Ten paradoxes and

some reflections regarding project management and project governance. International Journal of Project Management. doi:http://dx.doi.org/10.1016/j.ijproman.2015.01.014

Sauer, C., & Reich, B. H. (2009). Rethinking IT project management: Evidence of a new mindset and its implications. International Journal of Project Management, 27(2), 182-193. doi:http://dx.doi.org/10.1016/j.ijproman.2008.08.003

Soh, C., & Markus, M. L. (1995). How IT creates business value: A process theory synthesis. Paper presented at the International Conference on Information Systems (ICIS), Amsterdam.

Standish. (2014a). Chaos Report. Retrieved from https://www.projectsmart.co.uk/white-papers/chaos-report.pdf

Standish. (2014b). Law of the Five Deadly Sins. Retrieved from http://cdn.infoq.com/statics_s1_20160217-0123/resource/articles/standish-chaos-2015/en/resources/5Deadly%20sins_2014-5.pdf

Thamhain, H. (2013). Managing Risks in Complex Projects. Project Management Journal, 44(2), 20-35. doi:10.1002/pmj.21325

Walliman, N. (2001). Your research project, a step-by-step guide for the first-time researcher. California: Sage.

Ward, J., Daniel, E., & Peppard, J. (2008). Building better business cases for IT investments. MIS Quarterly Executive, 7(1), 1-15.

Zwikael, Chih, Y.-Y., & Meredith, J. (2018). Project benefit management: Setting effective target benefits. International Journal of Project Management, 36, 650-658. doi:https://doi.org/10.1016/j.ijproman.2018.01.002

Zwikael, & Meredith, J. R. (2018). Who’s who in the project zoo? The ten core project roles. International Journal of Operations and Production Management, 38(2), 474-492. doi:10.1108/IJOPM-05-2017-0274

Zwikael, & Smyrk, J. (2012). A General Framework for Gauging the Performance of Initiatives to Enhance Organizational Value. British Journal of Management, 23, S6-S22. doi:10.1111/j.1467-8551.2012.00823.x

41