Accounting Methods

45
FRS 111 CONSTRUCTION CONTRACTS

Transcript of Accounting Methods

Page 1: Accounting Methods

FRS 111CONSTRUCTION

CONTRACTS

Page 2: Accounting Methods

GROUP MEMBERS

CHOOI KAH HOE

YOON KOK WAI

SAW BENG GUAN

LIM HUAI EN

LAI CIAN SHING

YEE HUI CHING

09ABB07113

10ABB01142

11ABB00498

09ABB06243

10ABB02585

09ABB07024

Page 3: Accounting Methods

OBJECTIVE AND SCOPE

To prescribe the accounting treatment of revenue and costs

associated with construction contracts.

This Standard shall be applied in accounting for construction

contracts in the financial statements of contractors. This Standard

supersedes FRS111 2004 Construction Contracts.

This Standard becomes operative for financial statements

covering periods beginning on or after 1 July 2007.

Page 4: Accounting Methods

DEFINITION

A construction contract is a contract specifically negotiated for the

construction of an asset or a combination of assets that are closely

interrelated or interdependent in terms of their design, technology

and function or their ultimate purpose or use.

Fixed price contracts a construction contract in which the

contractor agrees to a fixed contract price, or a fixed rate per unit of

output, which in some cases is subject to cost escalation clauses.

Cost plus contract is a construction contract in which the

contractor is reimbursed for allowable or otherwise defined costs,

plus a percentage of these costs or a fixed fee.

Page 5: Accounting Methods

COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS

The requirements of this Standard are usually applied

separately to each construction contract. However, there are

certain circumstances where there is a need to apply the

Standard to the separately identifiable components of a single

contract or to a group of contracts together in order to reflect

the substance of a contract or a group of contracts.

Page 6: Accounting Methods

SITUATION 1

When a contract covers a number of assets:

The construction of each asset shall be treated as a separate

construction contract when:

(a) separate proposals have been submitted for each asset;

(b) each asset has been subject to separate negotiation and the

contractor and customer have been able to accept or reject that

part of the contract relating to each asset; and

(c) the costs and revenues of each asset can be identified

Page 7: Accounting Methods

SITUATION 2

A group of contracts, whether with a single customer or with

several customers, shall be treated as a single construction

contract when:

(a) the group of contracts is negotiated as a single package;

(b) the contracts are so closely interrelated that they are, in

effect, part of a single project with an overall profit margin; and

(c) the contracts are performed concurrently or in a continuous

sequence

Page 8: Accounting Methods

SITUATION 3

Additional asset in the construction contract:

The construction of the additional asset shall be treated as a

separate construction contract when:

(a) the asset differs significantly in design, technology or

function from the asset or assets covered by the original

contract; or

(b) the price of the asset is negotiated without regard to the

original contract price.

Page 9: Accounting Methods

CONTRACT REVENUE Contract revenue shall comprise:

(a) the initial amount of revenue agreed in the contract; and

(b) variations in contract work, claims and incentive payments:

(i) to the extent that it is probable that they will result in revenue; and

(ii) they are capable of being reliably measured.

Contract revenue is measured at the fair value of the consideration received or receivable. The measurement of contract revenue is affected by a variety of uncertainties that depend on the outcome of future events.

Page 10: Accounting Methods

CONTRACT REVENUE The estimates often need to be revised as events occur and

uncertainties are resolved. Therefore, the amount of contract revenue may increase or decrease from one period to the next. For example:

(a) a contractor and a customer may agree variations or claims that increase or decrease contract revenue in a period subsequent to that in which the contract was initially agreed;

(b) the amount of revenue agreed in a fixed price contract may increase as a result of cost escalation clauses;

(c) the amount of contract revenue may decrease as a result of penalties arising from delays caused by the contractor in the completion of the contract; or

(d) when a fixed price contract involves a fixed price per unit of output, contract revenue increases as the number of units is increased.

Page 11: Accounting Methods

VARIATION A variation is an instruction by the customer for a change in

the scope of the work to be performed under the contract. A variation may lead to an increase or a decrease in contract revenue.

Examples of variations are changes in the specifications or design of the asset and changes in the duration of the contract. A variation is included in contract revenue when:

(a) it is probable that the customer will approve the variation and the amount of revenue arising from the variation;

and

(b) the amount of revenue can be reliably measure.

Page 12: Accounting Methods

CLAIM A claim is an amount that the contractor seeks to collect from

the customer or another party as reimbursement for costs not included in the contract price. A claim may arise from, for example, customer caused delays, errors in specifications or design, and disputed variations in contract work. The measurement of the amounts of revenue arising from claims is subject to a high level of uncertainty and often depends on the outcome of negotiations. Therefore, claims are included in contract revenue only when:

(a) negotiations have reached an advanced stage such that it is probable that the customer will accept the claim; and

(b) the amount that it is probable will be accepted by the customer can be measured reliably.

Page 13: Accounting Methods

INCENTIVE PAYMENT Incentive payments are additional amounts paid

to the contractor if specified performance standards are met or exceeded. For example, a contract may allow for an incentive payment to the contractor for early completion of the contract. Incentive payments are included in contract revenue when: (a) the contract is sufficiently advanced that it is probable that the specified performance standards will be met or exceeded; and (b) the amount of the incentive payment can be measured reliably.

Page 14: Accounting Methods

CONTRACT COST Contract costs shall comprise:

(a) costs that relate directly to the specific contract;

includes; site labor costs, costs of materials used in construction, costs of hiring plant and equipment & etc.(b) costs that are attributable to contract activity in general and

can be allocated to the contract; and

includes; insurance, costs of design and technical assistance that are not directly related to a specific contract; and construction overheads.

(c) such other costs as are specifically chargeable to the customer under the terms of the contract.

Page 15: Accounting Methods

CONTRACT COST Costs that cannot be attributed to contract activity or cannot be

allocated to a contract are excluded from the costs of a construction contract. Such costs include:

(a) general administration costs for which reimbursement is not specified in the contract;

(b) selling costs;

(c) research and development costs for which reimbursement is not specified in the contract; and

(d) depreciation of idle plant and equipment that is not used on a particular contract.

Page 16: Accounting Methods

RECOGNITION OF CONTRACT REVENUE

AND EXPENSES

Use the stage of completion of the contract activity at the

balance sheet date when:

outcome of contract can be estimated reliably

any expected loss shall be recognized as expense

immediately

Page 17: Accounting Methods

Criteria To Estimate Outcome Of A Construction

Contract

For cost plus contract, when following conditions are satisfied:

it is probable that the economic benefits associated with the

contract will flow to the entity; and

the contract costs attributable to the contract, whether or not

specifically reimbursable, can be clearly identified and

measured reliably.

Page 18: Accounting Methods

Contract revenue is recognized as revenue in the income statement

in the accounting periods in which the work is performed.

Contract costs are usually recognized as an expense in the income

statement in the accounting periods in which the work to which they

relate is performed. However, any expected excess of total contract

costs over total contract revenue for the contract is recognized as an

expense immediately.

A contractor may have incurred contract costs that relate to future

activity on the contract. Such contract costs are recognised as an

asset provided it is probable that they will be recovered. Such costs

represent an amount due from the customer and are often classified

as contract work in progress

Page 19: Accounting Methods

For fixed price contract, when following condition

are satisfied:

total contract revenue can be measured reliably;

it is probable that the economic benefits associated with the contract

will flow to the entity;

both the contract costs to complete the contract and the stage of

contract completion at the balance sheet date can be measured reliably;

and

the contract costs attributable to the contract can be clearly identified

and measured reliably so that actual contract costs incurred can be

compared with prior estimates.

Page 20: Accounting Methods

The outcome of a construction contract can only be estimated

reliably when it is probable that the economic benefits associated

with the contract will flow to the entity.

However, when an uncertainty arises about the collectability of

an amount already included in contract revenue, and already

recognized in the income statement, the uncollectable amount or

the amount in respect of which recovery has ceased to be

probable is recognized as an expense rather than as an adjustment

of the amount of contract revenue.

Page 21: Accounting Methods

An entity is generally able to make reliable estimates after it has agreed to a contract which establishes:

each party’s enforceable rights regarding the asset to be

constructed;

the consideration to be exchanged; and

the manner and terms of settlement

Page 22: Accounting Methods

HOW TO DETERMINE THE STAGE OF

COMPLETION OF A CONTRACT?

the proportion that contract costs

incurred for work performed to date

bear to the estimated total contract costs

surveys of work performed

completion of a physical proportion of

the contract work

Page 23: Accounting Methods

EXCLUDED CONTRACT COSTS

COSTS THAT RELATE

TO FUTURE ACTIVITY ON

THE CONTRACT

     PAYMENTS MADE TO

SUBCONTRACTORS IN ADVANCE

Page 24: Accounting Methods

When the outcome of a construction contract

cannot be estimated reliably :

•Revenue shall be recognized only to the extent of contract costs

incurred

•Contract costs shall be recognized as an expense (para 33 of FRS

111)

•An expected loss on the construction contract shall be recognized

as an expense immediately

Page 25: Accounting Methods

(a) That are not fully enforceable

(b) The completion of which is subject to the outcome of pending

legislation.

(c) Relating to properties that are likely to be condemned or

expropriated.

(d) Where the customer is unable to meet its obligations.

(e) Where the contractor is unable to complete the contract or

otherwise meet its obligations under the contract..

Examples of circumstances in which the recoverability of contract costs incurred may not be probable and in which contract costs may need to be recognised as an expense immediately include contracts:

Page 26: Accounting Methods

RECOGNITION OF

EXPECTED LOSSES

Total contract Costs >

Total contract revenue

Recognised as an expense

How loss amount

is determined

?

work has commenced?

stage of completion of contract

?

Page 27: Accounting Methods

CHANGES IN ESTIMATES

The percentage of completion method is

applied on a cumulative basis in each accounting

period to the current estimates of contract revenue and contract

costs.

Any change in the estimate of contract revenue or

contract costs are used in the determination of the amount of revenue and

expenses recognised in the income statement in the

period in which the change is made and in subsequent

periods.

Page 28: Accounting Methods

ACCOUNTING METHODS

Page 29: Accounting Methods

1) Completed Contract Method

Does not recognize any profit until the construction project is

complete.

 Even if payments are received while the project is in progress,

no revenues are recorded until its completion.

During the construction period, all costs incurred are debited to

an inventory account called “Construction in Process“. 

Billings are debited to account receivables and credited to an

account called “Billings on Construction“.  

Page 30: Accounting Methods

COMPLETED CONTRACT METHOD(CONT.)

Finally, at completion, the construction and billings accounts

are closed, and the difference between them is recognized as

gross profit.

Usually this method used by contractors and manufacturers to

reduced the annual revenue which initially elected as their tax

accounting method.

Page 31: Accounting Methods

Advantages

  It does not accurately reflect revenues, expenses, and profits in

the period in which they are earned. It lead tax liabilities are

postponed.

Disadvantages

The company is unable to count its expenditure while the

project is still process. Thus, it can't use this expenditure to

reduce its overall tax liability.

Page 32: Accounting Methods

2) Percentage of Completion Method

Revenue is recognized on a long term construction contract

as it is earned gradually during the construction period.

The measure of revenue to be recognized each year is equal

to percentage completed x contract price.

It should be used when reliable estimates of the degree of

completion are possible, otherwise, completion contract

method be used.

 

Page 33: Accounting Methods

Reliable estimate:

The contract clearly specifies the rights regarding goods or

services to be provided, and the consideration to be

exchanged.

The buyer can be expected to satisfy all the contractual

obligations.

The contractor can be expected to perform the contractual

obligations.

Page 34: Accounting Methods

Advantages

The accurate reporting of the status of the uncompleted

contracts and the periodic recognition of income currently as

contracts are completed.

Disadvantages

The necessity of relying on estimates of the ultimate costs.

Page 35: Accounting Methods

FRS 111 require an company to disclose:

• The amount of contract revenue recognized as revenue in the

period

• The method used to determine the contract revenue recognized in

the period

• The amount of contract cost recognized as expenses in the period

• The methods used to determine the stage of completion of

contracts in progress

Page 36: Accounting Methods

IN RELATION TO THE CONSTRUCTIONS IN PROGRESS AS AT THE BALANCE SHEET DATE, FRS 111 REQUIRES THE FOLLOWING DISCLOSURE:

The aggregate amount of costs incurred and the recognized profits/ losses to

date, less the progress billings to date

*Note that if the net amount of above is a positive value figure, the

construction in progress should be shown under the current asset section.

Otherwise, it should be shown under the current liability section in the

balance sheet

*Note further that if one contract has a positive figure and another has negative

figure, they should be shown separately and no netting-off is allowed.

The amount of advanced received

The amount of retention

Page 37: Accounting Methods

ILLUSTRATION

Page 38: Accounting Methods

In 2010, Max Bhd had an contract between Vsoft

Bhd to build a plant in Kampar. The contract price is

RM 1,000,000 and expected complete in year 2010.

Max Bhd determine the stage of completion by

percentage and use cost to cost basis to measure.

Page 39: Accounting Methods

Information of the contract during the period:

year 2010

RM ’000

2011

RM ’000

Actual cost 600 220

Estimated cost to complete 200 -

Progress billing 400 600

Collection for the year 300 700

Page 40: Accounting Methods

PERCENTAGE OF COMPLETION

2010 2011

600/800 75% -

820/820 - 100%

Page 41: Accounting Methods

THE CONSTRUCTION PROFIT/(LOSS) FOR YEAR 2010 AND 2011

2010

RM ’000

2011

RM ’000

200x75% 150 -

180x100% - 180

Previously recognised - 150

For current period 150 30

Page 42: Accounting Methods

CONSTRUCTION REVENUE

2010

RM ’000

2011

RM ’000

1,000x75% 750 -

1,000x100% - 1,000

Previously recognized - 750

Current period 750 250

Page 43: Accounting Methods

STATEMENT OF COMPREHENSIVE INCOME FOR YEAR 2010 AND 2011

2010

RM ’000

2011

RM’ 000

Construction revenue 750 200

Construction costs 600 220

Gross profit 150 30

Page 44: Accounting Methods

STATEMENT OF FINANCIAL POSITION FOR YEAR 2010 AND 2011

2010

RM’ 000

2011

RM’ 000

Construction in process:

•Cost incurred

•Add attributable profit

•Less progress billings

Account receivables

600

150

400

350

100

820

180

1,000

-

-

Page 45: Accounting Methods

THANK YOUQ & A