Access Process Timeline and Key DatesAccess Impacts resulting from the HE 9.0 Upgrade
CoveredTimeline of access events resulting from the HE upgrade.
Impacts to users as a result of upgrade
Week of May 12thFinal Security Report prior to Upgrade
Impacts, Actions needed:– Review for any access changes– Please submit access changes as soon as possible
Wednesday, May 28th, End Of Business DayOARS access requests will be accepted for processing through the end of the business day on May 28
Impacts, Actions needed:– Please submit any access changes via OARS by this date– Requests submitted after this date will be processed after the
upgrade, June 9th
Monday, June 2nd
Freeze on any changes in HEPROD.
Impacts, Actions needed:– No access requests will be processed after this date– Processing means CPU Approvals and granting of access in
HEPROD
Wednesday, June 4th, End Of Business Day
All incomplete e-learning HE/SA-related courses will be cancelled in My LINC
Impacts, Actions needed:– Users have until the end of business to complete e-learning
courses for which they’ve registered prior to June 4th
– Incomplete e-learning courses will be cancelled• Users will be able to register for e-learning courses June 9th
Monday, June 9th, 8 am
Processing of HR and SA requests, including RDAs, recommences – Processing includes CPU approvals and granting of access– Any requests on hold will be processed first
Changes to OARS will be available
Users can register for HR and SA e-learning courses in My LINC
Impacts, Actions needed:– No actions needed– If there is a rollback, there will be impacts to the access process
Tuesday, June 10th, 8 am
RDA changes in the HEODS will be available
Impacts, Actions needed:– None