Access Denied Your page is blocked due to a security policy that prohibits access to Category...

download Access Denied  Your page is blocked due to a security policy that prohibits access to  Category default

of 39

Transcript of Access Denied Your page is blocked due to a security policy that prohibits access to Category...

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    1/39

    J S Sastry

    Testing of Transformers

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    2/39

    I F YOU HAVE NO DOUBTSYOU HAVE NOT UNDERSTOOD

    ANYTHING.

    - a Spanish proverb.

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    3/39

    Categories of Tests

    1. Tests to prove transformer is built

    correctly Voltage Ratio, Polarity,Vector Group, Winding Resistance and

    tap change operation.

    2. Tests to prove guarantees no-loadand load loss, impedance, oil and

    winding temperatures, noise level

    3. Tests to prove satisfactory service life -

    Dielectric tests and Short-circuit test.

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    4/39

    Schedu le o f Tes ts

    Routine Tests Dielectric Tests

    Parametric Tests

    Type Tests Temperature Rise Test

    Impulse Test

    Special Tests Short-circuit Test

    Magnetic Balance Test

    Measurement of Zero sequence Test

    Measurement of Noise Level

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    5/39

    Ratio meter (working as potentiometer)

    having accuracy 0.1% to be used.

    Tolerance allowed : 0.5%.

    Ratio also confirms polarity as balance

    can not be obtained if winding

    connection is reversed.

    Ratio & Polar i ty Tes t

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    6/39

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    7/39

    Polar i ty Check Test

    V1

    V2

    HV LV

    V2 V1>

    for subtractive polarity

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    8/39

    Test fo r Vecto r Group

    1U 2u

    2v2w2n

    1N

    1W 1V

    Supply 440 V 3-phase supply

    across HV terminals 1U-1V-1W.

    Terminal Measured Voltage

    1V - 2v

    1W 2w

    1U 2nYy0

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    9/39

    Tes t fo r Vecto r Group

    Terminal Measured Voltage

    1W 2w

    1V 2w

    1V 2u

    2v 2n

    1W 2n

    1W 2u

    Supply 440 V 3-phase supply

    across HV terminals 1U-1V-1W.

    Dy1

    1U

    1V1W

    2u

    2v2w

    1U 2n

    1V1W

    2u

    2v2w

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    10/39

    Kelvin Double Bridge used

    25 30 Amps DC required

    Ambient/oil temperature to be noted

    If oil, average of top & bottom temperatures

    to be considered.

    Conversion to 750C by:

    R75 = Ra x (234.5 + 75)/(234.5 + Ta)

    where Ra is resistance at ambient

    temperature Ta.

    Measu remen t of Wind ing

    Resistance

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    11/39

    Measu rement o f Wind ing Resistance

    G

    P Q

    p q

    S RX L

    External Resistance E

    RX = S.Q/P where, RX = Resistance of winding under test

    S = Standard Resistance (part of measuring Bridge

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    12/39

    2 KV or 5 KV Insulation Resistance

    Tester (Megger) is used.

    IR Value at 1 minute and ambient /

    average oil temperature to be noted.

    15 seconds and 60 seconds or 1 minute

    and 10 minute readings also are noted

    sometimes to calculate PI of the

    insulation system.

    Measu remen t o f Insu lat ion

    Resistance

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    13/39

    Measu rement of Insulation Resistance

    LV

    2n 2u 2v 2w

    L

    G

    E

    1U 1V 1W

    HV

    LV

    2n 2u 2v 2w

    L

    G

    E

    1U 1V 1W

    HV

    LV

    2n 2u 2v 2w

    L

    G

    E

    1U 1V 1W

    (a) (b) ( c )

    (a) IR Value between HV and earth

    (b) IR value between LV and earth

    (c) IR Value between HV and LV

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    14/39

    Also called Separate Source Voltagewithstand test.

    Conducted at 50 Hz for 60 seconds.

    All windings other than the winding undertest are shorted and connected to earth.

    Checks the Major Insulation of thetransformer.

    Values for uniformly insulated windings

    are given in the standards. Non-uniformlyinsulated windings with neutral are testedat 38 KV. The transformer shouldwithstand the specified voltage withoutany breakdown.

    Power Frequency Test

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    15/39

    LV

    2n 2u 2v 2w

    1U 1V 1W

    HV

    LV

    2n 2u 2v 2w

    1U 1V 1W

    HV

    Power Frequency Test

    ~

    ~

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    16/39

    Usually conducted at 50 Hz from LV sidekeeping HV open.

    Core loss consists of Hysteresis and EddyCurrent losses.

    Hysteresis loss depends on average valueand eddy current loss on rms value of thesupply voltage.

    Hence two voltmeters (average voltmeter

    scaled to read 1.11 times the average voltageand rms voltmeter) are used.

    Generally 3-wattmeter method is used.

    N0-Load Loss Tes t

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    17/39

    N0-Load Loss Test

    1U

    1V

    1W

    2v

    2w

    2uCT

    VT3 PhaseVoltage at

    Rated Frequency

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    18/39

    Rated voltage as per average voltmeter

    (Ua) is applied and readings of rms

    voltmeter, no-load currents and lossesof the three phases are noted.

    Corrected loss Pm = Pm (1+d) where

    Pm = sum of the three wattmeter

    readings, and

    d = (Ua Urms)/Ua

    N0-Load Loss Tes t

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    19/39

    Load loss comprises of I2R loss and stray loss whereR is the resistance of the winding.

    I2R loss varies directly with temperature and strayloss varies inversely with temperature.

    Measured loss is to be corrected to 750C. Test is carried out by short circuiting usually LV

    windings and feeding rated current to HV windings.The voltage measured is the reactance voltage.

    3-wattmeter method is normally used formeasurement of losses. Load loss test to beconducted preferably at rated current or at any valuebetween 50 100% rated current.

    Load Loss & Impedance Test

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    20/39

    Load Loss & Impedance Test

    1U

    1V

    1W

    2v

    2w

    2u

    CT

    VT3 PhaseControlled Voltage

    at Rated Frequency

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    21/39

    Calculation of Load loss at 750C:

    Stray loss Sa at ambient / average oil

    temperature (Ta) = (Sum of three wattmeter

    readings sum of HV & LV I2R losses at Ta) Stray loss S75at 75

    0C = Sa x (234.5 + Ta)

    (234.5+75)

    Load loss at T75 = (Sum of HV & LV I2Rlosses at T75 + S75)

    Load Loss & Impedance Test

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    22/39

    Calculation of %Impedance Voltage (Iz):

    %Iz = (%Ir2 + %Ix2) where,

    %Ir = (Load loss at 750C)x100/Rated KVA

    of transformer, and

    %Ix = (Reactance voltage at rated

    current)x100/Rated voltage.

    Load Loss & Impedance Test

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    23/39

    Induced Over Vo ltage Test

    This test is conducted to check the Minor insulationof a transformer.

    In case of non-uniformly insulated windings itchecks total insulation (both major and minor).

    In case of transformers with uniformly insulatedwindings, 2 times normal voltage is applied to the LVwindings at 2 times normal frequency for 60 secondsduration keeping the HV open.

    In case of non-uniformly insulated windings, thevoltage equal to two times or more is applied to LVterminals in such a way that the specified voltage isinduced across the HV terminals.

    The duration and frequency can be so adjusted thatthe windings are subjected 6,000 cycles of therequired voltage.

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    24/39

    Induced Over Voltage Test(For Uniformly Distributed winding transformers)

    1U

    1V

    1W

    2v

    2w

    2uCT

    VT

    3 Phase2 x Rated Voltage

    At 2 x Rated

    Frequency for

    1 Minute

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    25/39

    2u 2v 2w

    1U 1V 1W

    LV

    ~

    Induced Over Voltage Test(For Non-uniformly Distributed winding transformers)

    HV154.33 KV

    38.1 KV

    at 100 Hz

    77.17 KV

    Note: Test circuit shown for a

    typical 132/33 KV Transformer.

    231.5 KV

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    26/39

    For system voltages < 300 KV, Lightning Impulse Testis a type test. For system voltages 300 KV, it is aroutine test.

    Chopped wave test is a type test in all cases.

    Wave shape of the impulse voltage:

    Front: 1.2 s 30% and tail: 50 s 20%. The transformer should withstand the specified voltage

    with out any breakdown.

    Breakdown is indicated by voltage collapse or changein the neutral current wave shape.

    Test sequence: 1 Reduced full wave1 100% Full wave1 Reduced chopped wave If required.2 100% Chopped waves2 100% Full waves

    Test for L ightn ing Impu lse

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    27/39

    Test for L ightn ing Impu lse

    1U

    1V1W

    2v

    2w

    2u

    For Neutral Current

    Wave shape through

    Oscilloscope.

    R1 R2

    R1 & R2 are external

    resistors used for

    obtaining wave shape

    if required.

    Circuit shown for HV

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    28/39

    OutputRf

    Rt

    Rf

    Rt

    Rf

    Rt

    Rf

    Rt

    Rc

    Rc

    Rc

    C1

    C3

    C2

    Cn

    G1

    G2

    G3

    Gn

    C1,C2,Cn : Stage CapacitorG1,G2,Gn : Stage GapsRc: Charging Resistance

    Rf : Series Resistance (Front)

    Rt : Discharge Resistance (Tail)

    Impu lse Generato r

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    29/39

    1.00.9

    0.5

    0.3

    0

    Time

    Voltag

    e T1T2

    1.0

    0.9

    0.50.3

    0Time

    Vol

    tage

    T1Tc

    Impu lse Wave Shapes

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    30/39

    Sw itch ing Impu lse test

    Switching over voltages due to switching-on orswitching-off of transformer.

    For system voltages > 300 KV, it is routine test.

    Switching impulse wave shape to have

    specified amplitude of at least 200 s and atotal duration of at least 500 s, but preferably1000 s.

    Sequence of impulse voltage application:

    1 Reduced full wave2 Full waves Voltage and neutral current wave shapes are

    recorded and examined for fault detection.

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    31/39

    1.00.9

    0.5

    0.3

    0

    Time

    Voltage

    Sw itch ing Impulse Wave Shape

    200 s

    100 s 1000 s(at least 500 )s

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    32/39

    Part ial Discharge Measurement

    Causes of Partial Discharges:

    Insufficient processing

    High stress zones

    Sharp points

    Cavities in insulation

    Bad contacts

    Foreign objects inside tank.

    Basically a quality control check

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    33/39

    Circuit similar to Open Circuit test (No-load loss test).

    Supply 1.5 times rated voltage at higher

    frequency for 30 minutes. Check electrical signals generated by

    discharges produced with a partial

    discharge detector. Discharges measured should be less

    than 500 pc.

    Part ial Discharge Measurement

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    34/39

    Zero-phase sequence impedance ismeasured on star connected windings withneutral earthed.

    This determines the amplitude of current that

    will flow in the event of a line to earth fault. Reluctance path for zero sequence flux is

    different in 3-limb core and 5-limb core.Hence value of ZPS Impedance depends

    upon type of core construction. %Z0 = 3 x voltage measured x rated current

    Vph x rated current

    Zero -Phase Sequence Tes t

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    35/39

    Zero -Phase Sequence Test

    2u 2v 2w

    1U 1V 1W

    HV

    3u 3v 3w

    SV

    HV

    LV

    ~

    1. Short 1U 1V 1W and supply 1U1V1W -1N, with 2u-2v-2w open and tertiary closed.

    Measure Z (H T).

    2. Short 1U 1V 1W and supply 1U1V1W -1N, with 2u 2v 2w shorted and tertiaryclosed. Measure Z (H /L T).

    3. Open 1U 1V 1W and supply 2u-2v-2w -2n, with 2u 2v 2w shorted and tertiaryclosed. Measure Z (L T).

    4. Short 1U 1V 1W and supply 1U1V1W -

    1N, with 2u 2v 2w shorted and tertiaryopen. Measure Z (H -L).

    5. Short 2u-2v-2w and supply 2u-2v-2w 2n,with 1U-1V-1W shorted and tertiary closed.

    Measure Z (L/H T).

    1N

    2n

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    36/39

    Short-Circu i t Tes t

    SC current is calculated by using

    measured SC impedance of the

    transformer plus the system impedance.

    Two types of SC Test procedures can be

    followed:

    Pre-set method: LV winding is shorted prior

    to application of power to HV winding. Post-set method: Here one of the windings

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    37/39

    Test calls for 3 shots per phase oneeach at maximum tap, normal tap and

    minimum tap.

    Impedance measured after the SC Test

    should not be more than 2% of thevalue measured before the test.

    Short-Circu i t Tes t

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    38/39

    Measu rement of Acous t ic Noise Level

    Acoustic noise due to core vibrations

    (magnetostriction).

    Measured under open circuit test

    conditions with all the oil pumps, fans

    etc. running.

    Test to be conducted as per NEMATRI 1971 and noise levels should notexceed the values specified.

  • 7/28/2019 Access Denied Your page is blocked due to a security policy that prohibits access to Category default

    39/39