Accelerator Systems Division

FACET Accelerator Overview

John Seeman for the FACET Study GroupPPA Directorate

Stanford Linear Accelerator Center

DOE FACET ReviewFebruary 19-20, 2008

Accelerator Systems Division

Topics

• FACET accelerator overview• Brief look at science program• Changes since the SABER review of Dec 2006• Brief budget overview

Accelerator Systems Division

FACET Accelerator Team• Management: R. Erickson, S. Kahn, J. Jaros, D.

MacFarlane, T. Raubenheimer, J. Seeman• Mechanical engineers: L. Bentson, D. Blankenship, S.

DeBarger, N. Li, H. Shin• Area Manager: A. Baker, T. Graul• Optics: Y. Nosochkov, M. Woodley, T. Fieguth• Alignment: C. LeCocq• Beam dynamics: K. Bane, P. Emma• Radiation physics: J. Bauer, A. Prinz• Personnel Protection System: P. Bong, K. Turner• Experimental region: M. Hogan, D. Walz, M. Woods, C.

Hast• Physics consultants: R. Iverson, P. Krejcik

Accelerator Systems Division

Overview

• There was a constant demand for electron and positron beams in the Final Focus Test beam (FFTB) and End Station A (ESA) from a wide variety of accelerator physics users.

• However, the FFTB has been removed to make room for the Linac Coherent Light Source (LCLS). ESA is still in use.

• Many locations at SLAC have been studied for FACET. The optimum location is Linac Sector 20 for the Accelerator Science Facility (ASF) where the FFTB accelerator beam capabilities (final focus) can be relocated in a straight forward fashion.

• FACET makes use of the PEP-II HER bypass line to take a damped e- beam to End Station A, independent of LCLS.

• The existing electron longitudinal bunch compressor at the 1/3 point in the linac can be modified to compress positron bunches, as well, opening new worldwide unique opportunities for accelerator research.

• A Hadron Production Facility (for single particles) can be added to the A-Line to ESA.

Accelerator Systems Division

FACET Layout

• Hadron Production Facility

FACET has four areas:Accelerator Science Facility (ASF) (Sector 20)e+ bunch compressor (Sector 10)Electron Bypass Line (EBL) extension to ESAHadron Production Facility in A-Line to ESA

Accelerator Systems Division

Basic FACET areas

• Final Focus (ASF) in Sector 20: Makes a small beam spot (<10 microns) for experimenters. Similar design and layout as FFTB final focus.

• Sector 10 compressor for e+: Allows the production of positrons by e-

and the delivery of short bunch length e+ to the experimenter. Same design and layout as present e- compressor.

• Bypass line (EBL): Allows independent operation from LCLS. Use PEP-II HER injection bypass lines with 9 to 12 GeV e- with extension built to join to A-line transport to ESA.

The technology is the same as the former FFTB, SLC arcs, and existing PEP-II injection bypass lines. Many components salvaged from SLC, FFTB, and PEP-II.

Minimal design and engineering needed!

Accelerator Systems Division

Proposed Construction Timeline• Fall 2008: Installation of shielding wall in linac tunnel between Sectors 20

and 21. This allows tunnel installation work to proceed in Sector 20 while the LCLS injector and other downstream systems operate in 2009.

• January through September 2009: Installation of Sector 20 magnets and vacuum systems while LCLS commissioning activities proceed in downstream sectors.

• Fall 2009: Removal of existing components of the PEP-II injection transport systems in the BSY, as needed for FACET EBL. Modifications will be done to the common line vacuum system in the BSY.

• FY 2010: First operation of Sector 20 ASF final focus with electrons. Installation of positron compressor system in Sector 10.

• Fall 2010: Installation of the bypass line in the BSY and Hadron Production Facility.

• FY 2011: All FACET systems fully operational, independent of LCLS operations.

Accelerator Systems Division

Basic FACET ASF Beam Parameters

• Beam Energy = 30 GeV

• Single bunch per pulse

• 30 Hz (120 Hz possible)

• Charge per bunch (e- or e+) = 1 x 109 to 3.5 x 1010

• Bunch length = 15-30 microns

• Transverse spot size at experiment <10 microns

• Energy spread = 0.5 to 4 % (full width)

Accelerator Systems Division

Sector 20 Final Focus

Accelerator Systems Division

FACET Sector 20 Area

e- e+ target

Accelerator Systems Division

LCLS Injector (Sector 21)

New FACET Wall

Accelerator Systems Division

Linac Housing: Site of ASF

Accelerator Systems Division

Linac Tunnel• ASF has a bunch compression

dog-leg beam line and a final focus for the experiment.

• Longitudinal space for experiments will be the same as the FFTB.

• Transverse space is adequate for accelerator experiments and many detector experiments.

• Electric carts can travel in the linac tunnel aisle now and will be able to after the ASF and experiments are installed. 120 inches

66 inches

Alignmentlight pipe

~2 meters(~6.5ft)

Optical table

Tunnel penetration

Water header e

bypass line

e

bypass line

132 inches

Plasma wakefield experiment at focal point

120 inches

66 inches

Alignmentlight pipe

~2 meters(~6.5ft)

Optical table

Tunnel penetration

Water header e

bypass line

e

bypass line

132 inches

Plasma wakefield experiment at focal point

HERBypass

LINAC

FACET / ASF

LIGHT PIPE

132 inches

120 inches

Water header

66 inches

LERBypass

HERBypass

LINAC

FACET / ASF

LIGHT PIPE

132 inches

120 inches

Water header

66 inches

LERBypass

Accelerator Systems Division

Many places for User Counting Houses

Accelerator Systems Division

Basic FACET EBL-ESA Beam Parameters

• Beam Energy = 9-12 GeV using PEP-II HER line

• Single bunch per pulse

• 30 Hz (120 Hz possible)

• Charge per bunch = 1 x 109 to 3.5 x 1010

• Bunch length = ~1 mm

• Transverse spot size at experiment < 1mm

• Energy spread = <1 %

Accelerator Systems Division

Extension of HER Line to A-Line

Accelerator Systems Division

Plasma Wakefield Acceleration Studies (ASF)

• Electron acceleration

• Positron acceleration

• Drive witness beam tests

• Beam emittance preservation

Accelerator Systems Division

Dielectric Wakefield Accelerators (ASF)

• Acceleration (e- and e+)

• CSR studies

• Coating optimization

• Beam propagation tests

• Theory/simulation cross checks

• Channel diameter optimization

Accelerator Systems Division

Detector Development (ESA)• Development of beamline

instrumentation for ILC or other applications– New position monitors– Precise beam energy measurements– Collimator wakefield studies

• Detector development for ILC, LHC and many other applications– Proof-of-principle for new detectors – Detector characterization and

calibration– EMI & radiation damage studies– Gas/air fluorescence for particle

astrophysics experiments

Accelerator Systems Division

Material Science (ASF and ESA)

• Pulsed magnetic fields

• THz radiation

• Photon detector development

• Electronic structure of metals

• Ferroelectric switching

Accelerator Systems Division

Old Proposal:SLAC Overview with SABER in SLC South Arc

SABER consists of three main components:

•(1) Experimental area with final focus and beam dump in SLC South Arc tunnel.•(2) Linac Pulse Compressor upgrade to compress positron bunches.•(3) Bypass Line to deliver e- or e+ beams to SABER, bypassing the LCLS.

(1)

(2)

(3)

e-

e+

Accelerator Systems Division

Old SABER: Reuse 1 km of PEP-II Injection Bypass Line

• Linac Sector 21-30 (exists)Sector 20 (exists)

South Arc (exists)Extraction

Line (new)

Drift Line(exists but 12 30 GeV)

Re-injectionLine (new)

~50 m ~1000 m ~50 m

Drift Line:Reuse: Vacuum chambers, pumps and controls Beam position monitors

Beam size monitorsSteering corrector magnetsQuadrupole magnets and power supplies

New: Extra quadrupole magnets, power supplies, supports, water

51 Line (exists)

Accelerator Systems Division

Suggestions from SABER Review

• FACET team has answered the committee recommendations from the DOE “SABER” review held December 6-7, 2006:

• Broader science program:– Added ESA beam for detector and accelerator studies.– Added hadron production facility for single particle

detector studies.• New location and lowest cost:

– Final focus in Sector 20 saves bypass line upgrade costs and has easier beam tuning. (Saves 3.6 M$)

– ASF and ESA can operate simultaneously, independent of LCLS.

• Manage the construction as a project:– Project management team is now proposed.

Accelerator Systems Division

Budget changes from SABER FACET (FY2007$)

• SABER budget total: 12.4 M$– South Arc final focus: 2.4 M$– Linac bypass line (30 GeV) upgrade: 8.3 M$– Positron Bunch Compressor: 1.5 M$– Personnel Protection System upgrade: 0.2 M$

• FACET budget total: 15.5 M$– Sector 20 ASF final focus: 7.1 M$– Positron bunch compressor: 1.5 M$– EBL Bypass line extension to ESA (12 GeV): 4.3 M$– ESA Hadron Production Facility: 0.6 M$– Project management: 2.0 M$

• Operations costs: ~6 M$ for 4 months for running both ASF and ESA together.

Accelerator Systems Division

Conclusions• FACET (ASF and ESA) is a solid advance over the old

design.• The breath of the experimental program has been

significantly expanded.• There are four components to the facility allowing staging

of the program.• FACET construction matches the LCLS staff ramp down

plan and accelerator operations schedule.• Budget estimates have been carefully managed to be as

low as possible.