A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

14
05-07-22 1 Evaluation of a visco-elastic anti-corrosion system CASE HISTORY Ing. S. Hofstee Manager Business Development STOPAQ B.V. The Netherlands

Transcript of A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Page 1: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

03-05-23 1

Evaluation of a visco-elastic anti-corrosion system

CASE HISTORY

Ing. S. HofsteeManager Business DevelopmentSTOPAQ B.V.The Netherlands

Page 2: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

03-05-23 2

Contents

PRICE

Cost effective Maximise ROI

PERFORMANCE

Durable No maintenance No impact on the environment

APPLICATION

Wide range of applications Easy to apply Fast application Efficient

Page 3: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

03-05-23 3

Relation of the content

Application related to investement:

One system wide range of applications

Easy Operation Management

Easy & Fast Application (on site)

SAVING $$

No special permits or shutdowns

Page 4: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

03-05-23 4

Relation of the content

Performance related to investement:

Durability

30 years

LOW COST /YR/M2

Page 5: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Brunei LNG plant

Page 6: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Condensation

Page 7: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Conventional Coating

Page 8: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Deteriorating Coating

Page 9: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Stopaq application

Page 10: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Minor Surface Preparation

Page 11: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

As found after 5 years

Page 12: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

As opened

After scraping

Old tar coating

Stopaq after 5 years

Page 13: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

Epoxy coating after 5 years

Page 14: A_Case History of a visco-elastic anti-corrosion system LNG plant Brunei (1)

03-05-23 14

The end

STOPAQ SYSTEMS FAST & EFFICIENT!

Thank you for your attention!