03-05-23 1
Evaluation of a visco-elastic anti-corrosion system
CASE HISTORY
Ing. S. HofsteeManager Business DevelopmentSTOPAQ B.V.The Netherlands
03-05-23 2
Contents
PRICE
Cost effective Maximise ROI
PERFORMANCE
Durable No maintenance No impact on the environment
APPLICATION
Wide range of applications Easy to apply Fast application Efficient
03-05-23 3
Relation of the content
Application related to investement:
One system wide range of applications
Easy Operation Management
Easy & Fast Application (on site)
SAVING $$
No special permits or shutdowns
03-05-23 4
Relation of the content
Performance related to investement:
Durability
30 years
LOW COST /YR/M2
Brunei LNG plant
Condensation
Conventional Coating
Deteriorating Coating
Stopaq application
Minor Surface Preparation
As found after 5 years
As opened
After scraping
Old tar coating
Stopaq after 5 years
Epoxy coating after 5 years
03-05-23 14