ABSTRACT
In India more than 35% of construction project are facing the problem of time over
run ranging from 1 to 195 months. Time and cost overruns are a result of delays in project
execution. Some of the reasons advanced for these delays and subsequent overruns in time
are inclement weather, shortage in labour and material supply, sub-contractors, changes after
contract execution has commenced, poor site management and government policies. The
delay in a project is also due to the poorly drafted contract clauses. Identification of the
contract clauses that affect the schedule of the construction project was which taken up by
CPWD has been carried out in this study.
The preliminary questionnaires were supplied to the Contractors and Engineers who
have undertaken the works in Trivandrum. Similarly the main questionnaires were supplied
to the Contractors and Engineers. Based upon the answer obtained from 30 persons towards
contract clauses were analyzed. From the analysis it was found that 16 clauses affecting the
schedule performance of a project. The result of the analysis could help the professional in
focusing on the few clauses that affect the schedule frequently so that schedule over runs and
possibly cost over runs could be avoided in future.
vi
CONTENTS
CHAPTER NO TITLE PAGE NO.
ABSTRACT V
LIST OF TABLES
LIST OF FIGURES
NOTATION
viii
ix
ix
1 INTRODUCTION 1
1.1 GENERAL 1
1.2 NEED FOR STUDY 2
1.3 AIM 3
1.4 OBJECTIVE 3
1.5 DEFINITIONS 3
1.6 CPWD CONTRACT
CLAUSES
4
1.7 GENERAL
CONTRACT CLAUSES
1.8 CONCEPT OF
CLAUSES AFFECTING
SCHEDULE
1.9 CONTRACTUAL
PROBLEMS
5
19
20
2 REVIEW OF
LITERATURE
25
3 METHODOLOGY 34
4 DATA COLLECTION 38
4.1 INTRODUCTION 38
4.2 QUESTIONNAIRE
SURVEY
38
vii
4.3 CPWD FORM OF
CONTRACT
44
5 SUMMARY AND
CONCLUSION
56
REFERENCES 58
APPENDICES 61A. CPWD PRELIMINARY 62
QUESTIONNAIREB. CPWD MAIN 72
QUESTIONNAIRE
viii
LIST OF TABLES
TABLE NO TITLE PAGE NO
4.3.2 Mean, standard deviation, t-
value and ranking of CPWD
contract clauses
44
4.3.3.1 Mean score and ranking of
the impact of various
schedule affecting clauses
on the Profitability of the
project – CPWD
51
4.3.3.2 Mean score and ranking of
the impact of schedule
affecting clauses on the
frequency of them affecting
the Schedule – CPWD
53
A.1 CPWD preliminary
questionnaire
63
B.1 CPWD main questionnaire 74
ix
LIST OF FIGURES
FIGURE NO TITLE PAGE
3.1.a Methodology 35
4.2.1.1(a) Pie chart for the contractors and 40
employers respondants
4.2.1.1(b) Respondent profile – Experience Wise – 40
CPWD Preliminary
4.2.1.2 (i) Respondent profile –Experience wise – 43
Profitability – CPWD
4.2.1.2 (ii) Respondent profile – Experience wise – 43
Frequency of clauses affecting schedule –
CPWD
NOTATION
CPWD- Central Public Work Department