LABORATORY TESTING OF INTEGRAL ABUTMENT BRIDGE DETAILS FOR ABC
PROJECTS
FIU Webinar By: Sam Redd
July 2016
1
![Page 2: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/2.jpg)
Overview: Integral Abutment
Integral Abutment Jointed Abutment
2
![Page 3: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/3.jpg)
Overview: Integral Abutment in ABC
3
![Page 4: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/4.jpg)
Overview: Grouted Coupler
4
![Page 5: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/5.jpg)
Edison Bridge in Florida
Overview: Grouted Couplers
5
![Page 6: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/6.jpg)
1) Cast-in-place (CIP) – Iowa DOT design
2) Grouted Rebar Coupler – Dayton Superior Sleeve-Lock Coupler
3) Pile Coupler – HP pile section using CMP voids and grout
Laboratory Specimen 6
![Page 7: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/7.jpg)
• Integral Connection - #8 bars @ ~12 in. O.C. along front and back face
Control: Cast-In-Place (CIP) Specimen Iowa DOT Design Detail
7
![Page 8: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/8.jpg)
• Splice the pile cap and integral diaphragm for ABC application
• Seventeen #8 Bars and Grouted Couplers
Grouted Coupler Specimen
8
![Page 9: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/9.jpg)
Grouted Couplers: Conceptual
9
![Page 10: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/10.jpg)
24” CMP
Section A - A Section B - B
Pile Coupler Specimen 10
![Page 11: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/11.jpg)
Pile Coupler Specimen
11
![Page 12: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/12.jpg)
Pile Coupler Concept
12
![Page 13: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/13.jpg)
Laboratory Specimen Construction
13
![Page 14: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/14.jpg)
Typical dimensions for all specimens
Laboratory Specimens
8’
14
![Page 15: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/15.jpg)
Control: Cast-In-Place (CIP) Specimen Iowa DOT Design Detail
15
![Page 16: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/16.jpg)
Grouted Coupler – Pile Cap 16
![Page 17: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/17.jpg)
Grouted Coupler - Template 17
![Page 18: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/18.jpg)
Grouted Coupler – Integral Diaphragm
18
![Page 19: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/19.jpg)
Grouted Coupler - Alignment 19
![Page 20: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/20.jpg)
Grouted Coupler Specimen 20
![Page 21: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/21.jpg)
Pile Coupler – Pile Cap 21
![Page 22: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/22.jpg)
Pile Coupler – Integral Diaphragm 22
![Page 23: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/23.jpg)
Pile Coupler – HP Guides and Lid
23
![Page 24: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/24.jpg)
• CMP Lid - 1/8” Sheet metal circle or octagon w/ #4 Rebar guides welded in place • U-bolt and aircraft cable to lower pile
CMP Lid and HP section 24
![Page 25: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/25.jpg)
Pile Coupler – Grout Vent 25
![Page 26: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/26.jpg)
Pile Coupler – 3” Grout Duct 26
![Page 27: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/27.jpg)
Pile Couplers Suspended
27
![Page 28: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/28.jpg)
Pile Coupler Specimen – Construction Process
Step 2: Place grout bed dams
28
![Page 29: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/29.jpg)
Pile Coupler Specimen – Construction Process
Step 3: Place grout bed; remove dams
29
![Page 30: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/30.jpg)
Step 4: Lower HP Section
Pile Coupler Specimen – Construction Process 30
![Page 31: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/31.jpg)
Step 5: Grout HP Voids
Pile Coupler Specimen – Construction Process 31
![Page 32: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/32.jpg)
Testing Methodology
32
![Page 33: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/33.jpg)
Strength • How strong is the pile cap /
integral diaphragm connection?
Durability • Does any cracking occur? • If so, what are the crack
widths under service level loads
Constructability • Ease of construction
Scope of Laboratory Testing 33
![Page 34: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/34.jpg)
Test Philosophy
P vertical
P horizontal
Plastic moment of pile
34
![Page 35: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/35.jpg)
Test Setup
A. 100 Kip horizontal B. 400 kip vertical
A
B
35
![Page 36: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/36.jpg)
Test Results
36
![Page 37: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/37.jpg)
Before and After – CIP
37
![Page 38: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/38.jpg)
Before and After – Grouted Rebar Coupler
38
![Page 39: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/39.jpg)
Pile Coupler - After
39
![Page 40: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/40.jpg)
0.00
0.01
0.02
0.03
0.04
0.05
0.06
0 50 100 150 200 250 300
Cra
ck (i
n.)
Moment (k-ft)
Durability – Horizontal Load
Pile Coupler Grouted Rebar Coupler CIP
40
![Page 41: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/41.jpg)
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
0.18
0.20
0.22
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Cra
ck (i
n.)
Moment (k-ft) Pile Coupler Grouted Rebar Coupler CIP
Durability – Vertical Load HP 14x117 Strong Axis
HP14x117 Weak Axis
HP 10x57 Strong Axis
HP 10x57 Weak Axis
41
![Page 42: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/42.jpg)
0
5
10
15
20
25
30
35
40
45
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Reb
ar T
ensi
le S
tres
s (k
si)
Moment (ft-k) Grouted Rebar Coupler Cast-in-place
Strength – Vertical Load HP14x117 Weak Axis
HP 10x57 Strong Axis
HP 10x57 Weak Axis
HP 14x108 Strong Axis
42
![Page 43: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/43.jpg)
Pile Type and Allowable Crack Width
Reasonable crack width ACI – 0.012 in (soil)
43
![Page 44: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/44.jpg)
1) Cast-in-place (CIP) – Iowa DOT design ▫ Strong in comparison to foundation piles
2) Grouted Rebar Coupler – Dayton Superior Sleeve-Lock Coupler ▫ Two grouted coupler failures ▫ Similar performance to CIP ▫ Template facilitated erection
3) Pile Coupler – HP pile section using CMP voids and grout ▫ Construction process was successful ▫ Structural performance less than ideal
Conclusions 44
![Page 45: ABORATORY TESTING OF INTEGRAL BUTMENT BRIDGE DETAILS …](https://reader030.fdocuments.in/reader030/viewer/2022012015/615a003dcf20ce58bf27fb5b/html5/thumbnails/45.jpg)
Questions?