ABB – Roger Rosenqvist: August 30,...
Transcript of ABB – Roger Rosenqvist: August 30,...
ABB – Roger Rosenqvist: August 30, 2012
Cable Systems for EHV TransmissionCable Systems for EHV Transmission
Cable Systems for EHV TransmissionCable Systems for EHV Transmission
Speaker name: Roger Rosenqvist Speaker name: Roger Rosenqvist
Speaker title: Vice President, Business Development
C ( S ) Company name: ABB (Power Systems Division)Raleigh, North Carolina
Cable Systems for EHV TransmissionCable Systems for EHV Transmission ABB is a technology provider, not a developer of transmission
projects. There are many complex issues that arise in connection with the
development and siting of new transmission projects. Some of thosedevelopment and siting of new transmission projects. Some of those issues cover subjects that are outside ABB’s experience and expertise.ABB d t h ffi i t b k d k l d t t ABB does not have sufficient background or knowledge to comment on the reasons as to why a specific technology was chosen by an owner or developer of a new transmission project.
Our presentation will focus on technical characteristics of polymer insulated cable systems, including ABB’s HVDC Light technology, and commercially available capacity ratings for such systemscommercially available capacity ratings for such systems.
We will also discuss recent experiences from the design, construction and operation of cable projects around the world.
Background
N l i i i i ill b d d li i
Background
New electric transmission capacity will be needed to support policies to retire older fossil fuel based power plants, expand access to renewable generation resources and maintain reliability.
Significant public opposition to overhead transmission line construction has raised legal and permitting barriers that can severely delay new projectsseverely delay new projects.
Factors commonly cited against construction of new overhead transmission lines: Aesthetics
Land use constraints
EMF
History of Polymer Insulated Cable Systems for TransmissionHistory of Polymer Insulated Cable Systems for Transmission
1970’s: Deliveries of polymer insulated (“XLPE”) cable systems for voltage ratings up to 145 kV.
1980’s: XLPE transmission cable systems rated 230 kV.
1990’s: XLPE transmission cable systems rated 345 kV, 420 kV and 500 kV.y ,
Typical EHV AC Cable Design (Laminate Sheath)
CONDUCTOR Copper / round, segmented
CONDUCTOR SHIELD Conductive PE
INSULATION- Type Triple extruded, dry cured
Material XLPE- Material XLPE
INSULATION SHIELD Conductive PE
LONGITUDINAL WATER SEALING Swell able tape
METALLIC SCREEN Copper wire
TEMPERATURE MONITORING FIMT in metallic screen
RADIAL WATER SEALING Laminate (Al or Cu) and PE
OUTER JACKET Polyethylene
History of Polymer Insulated Cable Systems for TransmissionMiddleton / Norwalk Project Length: 69 Miles of new 345-kilovolt (kV) line 45 Miles of overhead 24 Miles of underground
Project was energized in Dec. 2008
Typical EHV AC Submarine Cable Design
Conductor material: Copper
Conductor screen material: Conductive PE
Insulation material: Polymer (XLPE)
Insulation screen: Conductive PE
Longitudinal water seal: Swell able tapes
Metallic sheath material: Lead alloy
Inner sheath material: Conductive PE
Assembling: Polymeric profiles
Cable core binder: Polymeric tape
Bedding: Impregnated tape
Armor material: Galvanized steel
Outer serving material: Polypropylene yarn
Typical EHV AC Submarine Cable Design
Conductor material: Copper
Conductor screen material: Conductive PE
Insulation type/material: Dry cured triple extruded XLPE
Insulation screen: Conductive PE
Longitudinal water seal: Swelling tapes
Metallic sheath material: Lead alloy
Inner sheath material: Conductive PEInner sheath material: Conductive PE
Armor material: Copper wires
Outer serving material: Polypropylene yarn
Bayonne Energy Center Project – 345 kV AC Cable Systemy gy j y
Brooklyn
Bayonne Energy Center Project – 345 kV AC Cable Systemy gy j y
Polymer Insulated Cable Systems for HV and EHV TransmissionPolymer Insulated Cable Systems for HV and EHV Transmission
Charging current in AC cables increases cumulatively with distance. (For example, 25 miles of 345 kV XLPE cable requires approximately ( p q pp y600 Amps. charging current.)
Capacity to transmit real power diminishes with distance, limiting the practical length of AC underground and submarine cable transmission circuits.
HVDC bl h i t l d i i ti HVDC cables carry charging current only during energization.
History of Polymer Insulated Cable Systems for TransmissionHistory of Polymer Insulated Cable Systems for Transmission
1970’s: Deliveries of polymer insulated (“XLPE”) cable systems for voltage ratings up to 145 kV.
1980’s: XLPE transmission cable systems rated 230 kV.
1990’s: XLPE transmission cable systems rated 345 kV, 420 kV and 500 kV.y ,
1999: The world’s first polymer insulated cable system for direct current transmission.
Gotland HVDC Underground Cable Project
ApplicationConnect a new onshore wind power facilityIn-Service Year – 1999 Connect a new onshore wind power facility on the southern part of the island to Gotland’s main load centre. Fast reactive power regulation to supportFast reactive power regulation to support integration of wind power facility to the island’s grid.
S l iSolution43 miles long, 160 kV (±80 kV), 50 MW, HVDC underground cable circuit. (HVDC underground cables made it much easier to obtain permits for the new line.)Compact HVDC voltage source converters p gthat provide dynamic voltage support to the island’s AC grid.
ABB HVDC Classic Projects Around the WorldABB HVDC Classic Projects Around the World
Quebec – New England ±450 kV HVDC Line
HVDC Bipole (Traditional Layout for DC OH-Lines)
UDC+ UDC
~~ UDC
Pole conductor
~~ Electrode
UDC
Metallic return conductor
ElectrodeUDC
Pole conductor
- UDC
Sandy Pond 2×1000 MW HVDC Converter Station
Sandy Pond 1000 MW HVDC Converter
World’s First HVDC Transmission – Gotland
HVDC Cable System withHVDC Cable System withMercury Arc Valve Technology
Capacity Rating:Capacity Rating:100 kV 20 MW
Cable Type: Cable Type:Mass-Impregnated Paper (MIND) 1×90 mm2 Cu
Cable Length:100 km (62 miles)
In-Service Year:1954
HVDC MIND Cable Systems for HV and EHV Transmission
Mass Impregnated Non Draining (“MIND”) paper insulation
y
Mass Impregnated Non Draining ( MIND ) paper insulation
Significant submarine HVDC cable technology milestones:
1953 Gotland I: ±100 kV 20 MW 62 miles• 1953 – Gotland I: ±100 kV, 20 MW, 62 miles
• 1968 – KontiSkan I: ±285 kV, 300 MW, 40 miles
• 1989 – FennoSkan: ±400 kV, 500 MW, 124 miles
• 1994 – Baltic Cable: ±450 kV, 600 MW, 155 miles
• 1999 – SwePol Cable: ±450 kV, 600 MW, 143 miles
• 2008 – NorNed Cable: ±450 kV, 700 MW, 360 miles
Due to worker skills and time required for splicing, MIND cable technology is not a practical option for most long distance
d d t i i li tiunderground transmission applications.
Typical Solid Dielectric DC Cable Design
Conductor material Copper or Aluminum
Conductor screen material Conductive PE
Insulation type/material Dry cured HVDC polymer (XLPE)
Insulation screen Conductive PE
Bedding Conductive swelling tapesg g p
Metallic screen Copper wires
Bedding Conductive swelling tapesBedding Conductive swelling tapes
Radial moisture barrier Aluminum-PE laminate
Outer jacket Polyethylene
Typical HVDC Light Submarine Cable Design
Conductor material Copper
Conductor screen material Conductive PE
Insulation type/material Dry cured HVDC polymer (XLPE)Insulation type/material Dry cured HVDC polymer (XLPE)
Insulation screen Conductive PE
L it di l i t b i S lli tLongitudinal moisture barrier Swelling tapes
Metallic sheath material Lead alloy
Inner sheath material Polyethylene
Armor material Galvanized steel wires
Outer serving material Polypropylene yarn
Symmetric Monopole (Typical Layout for DC Cables)
+ UDCPole conductor
~~ 2×UDC (Circuit Voltage)
- UDCPole conductor
HVDC VSC 640 kV (±320 kV), 350-1100 MW
Less than 5 acres
Gotland HVDC Underground Cable Project
ApplicationConnect a new onshore wind power facilityIn-Service Year – 1999 Connect a new onshore wind power facility on the southern part of the island to Gotland’s main load centre. Fast reactive power regulation to supportFast reactive power regulation to support integration of wind power facility to the island’s grid.
S l iSolution43 miles long, 160 kV (±80 kV), 50 MW, HVDC underground cable circuit. (HVDC underground cables made it much easier to obtain permits for the new line.)Compact HVDC voltage source converters p gthat provide dynamic voltage support to the island’s AC grid.
Gotland HVDC Underground Cable Project
Näs converter station
Bäcks converter stationBäcks converter station
Solid Dielectric Cables for HVDC Transmission
1999G
2002 2007-2009QGotland
160 kV (±80 kV)50 MW43 miles
2000
Murray Link300 kV (±150 kV), 220 MW112 miles
2006E Li k
Type and PQ tests2500 mm2 (≈5000 kcmil) Cu or Al640 kV (±320 kV), up to 1100 MW
2013D lWi 12000
Direct Link160 kV (±80 kV) 3×60 MW3×40 miles
EstLink300 kV (±150 kV), 350 MW20 miles (+46 miles subsea)
2009B Wi 1
DolWin1640 kV (±320 kV), 800 MW60 miles (+47 miles subsea)
2015N dB ltBorWin 1
300 kV (±150 kV), 400 MW47 miles (+80 miles subsea)
2012EWIP
NordBalt600 kV (±300 kV), 700 MW31 miles (+248 miles subsea)
2015EWIP400 kV (±200 kV), 500 MW46 miles (+116 miles subsea)
DolWin 2640 kV (±320 kV), 900 MW56 miles (+28 miles subsea)
In the FutureIn the FutureType and PQ tests2500 mm2 (≈5000 kcmil) Cu or Al1000 kV (±500 kV), up to 1700 MW
HVDC Light® projects
Date is when theTjäreborg 2000, 7 MW
Estlink2006 350 MW
Valhall 2010, 78 MW
Date is when the project entered into service, or is scheduled to enter into service.
EWIP 2012, 550 MW
Troll 2004, 2X40 MW
Gotland1999, 50 MW
2006, 350 MWCross Sound 2003, 330 MW
Hällsjön1997, 3 MW
E l P
Directlink
Eagle Pass 2000, 36MW
Caprivi link
Murraylink 2002, 220 MW
2000, 3X60 MW
BorWin 12010, 400 MW
DolWin 12013, 800 MW
Caprivi link2010, 300 MW
DolWin 22015, 900 MW
NordBalt2015, 700 MW
HVDC VSC 640 kV (±320 kV), 350 – 1100 MW
Less than 5 acres
HVDC VSC 640 kV (±320 kV), 350 – 1100 MW
Two-level converter
+ Ud
Cascade connection
IGBT current limit: 1 880 Amp DCIGBT current limit: 1,880 Amp. DC
Power losses: Less than 1%- Ud
HVDC VSC 640 kV (±320 kV), 350-1100 MW
P-Q Diagram
Operating Arear (
p.u.
)Operating Area
Act
ive
Pow
erA
Reactive Power (p.u.)
HVDC VSC Operating RangeHVDC VSC Operating Range
Examples of Existing and PlannedPolymer Insulated DC Cable Projectsy j
Murray Link HVDC Cable Project
ApplicationInterconnection of remote parts of the transmission systems in South Australia and Victoria.
Electricity trading in deregulated power market.
SolutionSolution112 miles long, 300 kV (±150 kV), 220MW, HVDC underground cable circuit.
Compact HVDC voltage source converters that provide dynamic voltage support to the grid.
In-Service Year: 2002
Murray Link HVDC Cable Project
Murray Link HVDC Cable Project
Murray Link HVDC Cable Project
Less than 13 ft. (4 meters)right-of-way widthright of way width
Murray Link HVDC Cable Project
Approximately 400field jointsfield joints
Other Arrangements for Cable Installation
Duct bank system:
Cross Sound HVDC Cable Project
ApplicationApplicationIncreased power transmission capacity between electricity markets in New E l d d L I l dEngland and Long Island.
Solution25 mile long, 300 kV (±150 kV), 330 MW, g, ( ), ,submarine HVDC cable circuit.
Compact HVDC voltage source converters that provide dynamic voltage support tothat provide dynamic voltage support to the grid.
In-Service Year: 2002
Cross Sound HVDC Cable Project
Hew Haven converter station Shoreham converter stationHew Haven converter station Shoreham converter station
Cross Sound HVDC Cable Project
Mid-Atlantic Power Pathway Projectd t a t c o e at ay oject
ApplicationApplicationNew transmission path from Pepco to DPL.
SolutionTwo parallel 43 miles long, 640kV (±320kV) submarine (39 miles) and underground (4 miles) HVDC cable circuits plus approximately 40 miles of HVDC overhead circuit.
Compact on-shore HVDC voltage source converters.
Mid-Atlantic Power Pathway Projectd t a t c o e at ay oject
500 kV Transmission Corridors
Mid-Atlantic Power Pathway Projectd t a t c o e at ay oject
Mid-Atlantic Power Pathway Projectd t a t c o e at ay oject
Mid-Atlantic Power Pathway Projectd t a t c o e at ay oject
Champlain Hudson Power Express (CHPE)Champlain Hudson Power Express (CHPE)
• 1,000 MW buried over 333 miles• Two cables approximately 6
inch diameter• Connecting clean hydro and• Connecting clean hydro and
wind with NYC• Significant environmental
benefitsbenefits• Significant power price reduction
across the state
Source: www.chpexpress.com
Northeast Energy Link (NEL)Northeast Energy Link (NEL)
A feasibility study, completed in 2010, found the NEL to be a highly achievable project based on the significant need for new electric transmission, a positive regulatory environment, proven and reliable DC cable and converter
Source: www.northeastenergylink.com
environment, proven and reliable DC cable and converter station technology, geographic location, and ease of constructability.
The proposed project concept includes:• Direct current (DC) technology that reduces line losses ( ) gy
and is more efficient for long distance electric transmission and underground construction;
• An underground cable circuit extending approximately 230 miles from Orrington, ME to Tewksbury, MA;
• Capacity of 1,100 MW at +/-320kV DC;• AC/DC converter stations on each end;• AC upgrades north of Orrington to collect renewable
energy generated in northern and eastern Maine.
Source: www.atlanticwindconnection.com
BorWin 1 HVDC Cable Project
ApplicationApplicationInterconnection of large off-shore wind generation facility to the German electric
t i i idpower transmission grid.
Solution127 miles long, 300 kV (±150 kV), 400 MW, g, ( ), ,submarine (80 miles) and underground (47 miles) HVDC cable circuit.
Compact off-shore and on-shore HVDCCompact off-shore and on-shore HVDC voltage source converters.
I S i Y 2009In-Service Year: 2009
BorWin 1 HVDC Transmission System – Cable DesignsBorWin 1 HVDC Transmission System Cable Designs
North Sea segment (75 miles)1200 mm2 Cu
Wadden Sea segment (5 miles)Wadden Sea segment (5 miles)1600 mm2 Cu
Underground segment (47 miles)2300 mm2 Al
BorWin 1 HVDC Cable Project
BorWin Alpha converter stationBorWin Alpha converter station
Diele converter station
BorWin 1 HVDC Cable System in GermanyBorWin 1 HVDC Cable System in Germany
Power cables and fiber optic cable in common trenchtrench
Installation of Underground Cable SegmentInstallation of Underground Cable Segment
Installation of Underground Cable SegmentInstallation of Underground Cable Segment
Installation of Underground Cable SegmentInstallation of Underground Cable Segment
Installation of Underground Cable SegmentInstallation of Underground Cable Segment
Mobile splicing unit
I t ll ti f U d d C bl S tInstallation of Underground Cable Segment
Other HVDC Cable Interconnections under Construction in Germany
DolWin1N th S t N th GNorth Sea to Northern Germany
ApplicationApplicationInterconnection of large off-shore wind generation facility to the German electric power transmission
idgrid.
Solution107 miles long, 640 kV (±320 kV), 800 MW, g, ( ), ,submarine (47 miles) and underground (60 miles) HVDC cable circuit.
Compact off-shore and on-shore HVDC voltageCompact off-shore and on-shore HVDC voltage source converters.
In-Service Year: 2013
DolWin 2N th S t N th GNorth Sea to Northern Germany
ApplicationApplicationInterconnection of large off-shore wind generation facility to the German electric power transmission
idgrid.
Solution84 miles long, 640 kV (±320 kV), 900 MW, g, ( ), ,submarine (28 miles) and underground (56 miles) HVDC cable circuit.
Compact off-shore and on-shore HVDC voltageCompact off-shore and on-shore HVDC voltage source converters.
In-Service Year: 2015
Polymer Insulated Cable for HV and EHV Transmission Systems
ABB Kabeldon, Alingsås
ABB High Voltage Cables,Karlskrona
One of the world’s most modern cable factories Extruded cables for AC and DC Submarine and underground systems
Polymer Insulated Cable for HV and EHV Transmission Systems
Huntersville, North CarolinaExtruded cables for AC and DCSame manufacturing process as in KarlskronaFocus on underground cable systemsEmployees – Approximately 120Employees Approximately 120Investment – Approximately $90 millionManufacturing commences in 2012
Polymer Insulated Cable for HV and EHV Transmission Systems
© ABB Group August 30, 2012 | Slide 74