Aaron BarwickPORTFOLIO 2015 - 2016

Page 2: Aaron Barwick Data Centre Portfolio

Data Centre WorksCDCTP Certification helped me challenge and highlight 5 areas for change within the University Data Centre’s.

Data Centre Airflow

Access

Moves, Adds, Changes

Earthing & Bonding

Cabling Infrastructure Refresh

Page 3: Aaron Barwick Data Centre Portfolio

Data Centre: Airflow

1/5

Create an efficient data centre.

Page 4: Aaron Barwick Data Centre Portfolio

Data Centre AirflowIt is estimated that 50-80% of valuable conditioned (cooled) air does not reach the intake of IT equipment due to unsealed floors and openings.

Before After• Hot/Cold Aisle Containment• Fill Air Voids• Floor Tile Alignment• Cable Management• Server Fan Direction

Page 5: Aaron Barwick Data Centre Portfolio

Data Centre Airflow40% Annual Energy Savings in AS3 Data Centre, with more savings attainable.

Ambient temperature drop from 24 °C to 16°C

Change of 8 degrees

Lowered Air Conditioning demand to raise temperature back to 24°C

Estimated 40% Annual Energy Saving

Further 2°C change estimated!

Savings paying for HPC Chiller!

Page 6: Aaron Barwick Data Centre Portfolio

Data Centre AirflowAS3 Temperature Sensor Report

Maximum Temperature Minimum Temperature Average Temperature

Aug-14 30.8 18.5 24.2

Sep-14 29.7 18.3 21.6

Oct-14 29.7 18.1 22.6

Nov-14 30.3 19.2 20.0

Dec-14 28.7 17.1 19.9

Jan-15 28.2 17.2 20.2

Feb-15 27.8 18.5 19.9

Mar-15 27.8 18.2 23.9

Apr-15 26.6 14.1 19.8

May-15 24.3 14.1 18.3

Jun-15 23.2 13.7 18.0

Jul-15 21.8 13.4 16.0

Page 7: Aaron Barwick Data Centre Portfolio

Data Centre Airflow3 Tonnes, and counting ….

Page 8: Aaron Barwick Data Centre Portfolio

Data Centre AirflowCable Management….

Before After

Page 9: Aaron Barwick Data Centre Portfolio

Data Centre AirflowAir Void Solutions

Before After

Page 10: Aaron Barwick Data Centre Portfolio

Data Centre: Access

2/5

Audit Visitor Access : Who, What, Why?

Page 11: Aaron Barwick Data Centre Portfolio

Data Centre AccessNovember 2015 - New Access Policy ImplementedFully audited trail for Data Centre Visitors

Page 12: Aaron Barwick Data Centre Portfolio

Data Centre AccessJanuary 2015 - Draft copy of Data Centre Out Of Hours Access form.

Page 13: Aaron Barwick Data Centre Portfolio

Data Centre: Moves, Adds, Changes (MAC’s)

3/5

Audit and increase visibility for changes within the data centre.

Page 14: Aaron Barwick Data Centre Portfolio

Data Centre MAC’s2015 - New Policy Created

Page 15: Aaron Barwick Data Centre Portfolio

Data Centre: Safety

4/5

Ensure a safe working environment.

Page 16: Aaron Barwick Data Centre Portfolio

Earthing & BondingA server rack with 8 servers generates 10 mA-20 mA leakage currents – 50 mA is enough to kill.

Organised the appropriate earthing and bonding of each rack in AS3 DC.

Liaised with external Electricians

Organised access

Ensured job was completed without downtime

Each network rack now has the appropriate earthing ensuring a safe environment.

Page 17: Aaron Barwick Data Centre Portfolio

Data Centre: Cabling Refresh

5/5

Rework the way data cabling is connected.

Page 18: Aaron Barwick Data Centre Portfolio

Cabling Refresh“The decision to place network data and power cabling into overheadcable trays can lower cooling fan and pump power consumption by 24%.” Schneider Electric

Under-floor cabling contributes to energy losses in three ways:

• Blockage of air due to cables

• Bypass air from rack cable cut-outs

• Bypass air from (PDU) cut-outs

Liaised with external contractors

Organised access

Ensured job was completed without downtime

Each rack now has 24 port copper and fibre patch panels back to one central location.

Page 19: Aaron Barwick Data Centre Portfolio

Data Centre: Miscellaneous

Page 20: Aaron Barwick Data Centre Portfolio

Managed PDU RolloutFully managed Power Distribution Unit (PDU) solution

Rollout of managed PDU’s.

Liaised with equipment owners

Document Ownership

Plan Suitable Downtime

Label Commando Sockets / PDU / Fuse

Each network rack now has at least two fully manageable PDU’s.

Page 21: Aaron Barwick Data Centre Portfolio

LightingEfficient lighting system installed

Organised the install of new lights and emergency lighting in AS3 DC.

Liaised with external Electricians

Organised access

Ensured job was completed without downtime

PIR System implemented

20 minute no presence timeout.

Page 22: Aaron Barwick Data Centre Portfolio

DoorProactive over Reactive

Before After

Page 23: Aaron Barwick Data Centre Portfolio

Structural IssuesFloor Tile Arrangement

Problems such as rocking panels and gaps can cause permanent damage to a floor system, personal injuries and damage to equipment.

Page 24: Aaron Barwick Data Centre Portfolio

Data Centre Information ManagementDCIM

Research DCIM Solutions

Implement/Trial openDCIM

Organised On Site Demonstrations

5

Page 25: Aaron Barwick Data Centre Portfolio

High Performance Compute (HPC)

Page 26: Aaron Barwick Data Centre Portfolio

HPCUniversity invested £2M+ in owning a High Performance Compute facility

Preparation

Rigorous room planning and preparation for new contained area to accommodated HPC equipment.

Installation

Organised work and ensure contractors adhered to our standards working within a live environment.

Implementation

Worked with all parties to sign off project and assist in the handover to the HPC Viper team.

Page 27: Aaron Barwick Data Centre Portfolio

HPCInstallation

Before

After

Page 28: Aaron Barwick Data Centre Portfolio

Disaster Recovery (DR) Room

Page 29: Aaron Barwick Data Centre Portfolio

Backup DR SiteConvert an old computer room into a data backup site to house 300k worth of hardware.

Preparation

Room required clearing of old equipment, furniture & general mess.

Air Temperature

Old Air Condition unit was running insufficiently and would not cope with increased load in room.

Power

Source, order, install & configure UPS

Page 30: Aaron Barwick Data Centre Portfolio

Backup DR SiteProactive over Reactive

Page 31: Aaron Barwick Data Centre Portfolio

Uninterruptable Power Supply (UPS)

Page 32: Aaron Barwick Data Centre Portfolio

UPS ReplacementReplace old UPS with new more efficient system

Preparation & Planning

Planning for space, power and cooling efficiency

Installation

Organised work and ensure contractors adhered to our standards working within a live environment.

Commission

Worked with all parties to sign off project and assist in the commission of the new UPS.

Page 33: Aaron Barwick Data Centre Portfolio

UPSInstallation

Before

After

Page 34: Aaron Barwick Data Centre Portfolio

Top Of Rack (ToR) Migration

Page 35: Aaron Barwick Data Centre Portfolio

ToR MigrationCreate a central repository for the 6 Top of Rack switches.

Preparation

Rack Moves, Overhead Cabling, Equipment

Planning

Major Downtime Required

Implementation

Installation & Implementation

Page 36: Aaron Barwick Data Centre Portfolio

ToR MigrationCentral Location for ToR Switches