A Three-Phase Fault Currents Calculation Method Used · PDF fileCalculation Method Used For...
Transcript of A Three-Phase Fault Currents Calculation Method Used · PDF fileCalculation Method Used For...
A Three-Phase Fault Currents Calculation Method Used For
Protection Coordination Analysis Khaled Saleh – [email protected]
Dr. Hatem Zeineldin – [email protected]
Dr. Amer Al-Hinai – [email protected]
1
Paper ID: 14TD0269
Introduction
• A reliable fault current calculation method is required to perform precise protection coordination analysis.
• The conventional short circuit calculation method is not valid for distribution power systems that are equipped with Inverter-Based Distributed Generation (IBDG) units.
• Usually, a transient model of the power system equipped with IBDG units are developed using either PSCAD or MATLAB to compute the short circuit currents flowing through each protective device.
2
Introduction • A simple method based on the superposition theorem is
proposed that calculates the three-phase fault currents for meshed distribution system in the presence of IBDG units.
• Most of the IBDGs are controlled using the current control scheme.
• During fault conditions, the fault contribution of IBDGs is bounded by their controller limiters.
• In this study IBDG during fault conditions is modeled as a constant current source injecting fault current equivalent to the upper boundary of its controller limiter.
3
Fault Current Calculation Method
Bus 1
Bus 2 Bus 3SBDG IBDG
F4
R2 R5
R1
R6
R3
R4
F5
F6
Substation
4
Three-bus system example.
Fault Current Calculation Method 5
Three-bus system superposition part 1.
R1
Bus 1
Bus 2
R3
R2 R5
Bus 3
R6 R4
F4
SBD
G
IBD
G
F6
F5Su
bstatio
n
Fault Current Calculation Method 6
Three-bus system superposition part 2.
R1
Bus 1
Bus 2
R3
R2 R5
Bus 3
R6 R4
F4
SBD
G
IBD
G
F6
F5
Sub
station
Fault Current Calculation Method 7
• In the first part of superposition, fault current passing through each DOCR for all fault locations on the system are computed.
• For the second part of superposition, fault current passing through each DOCR for all fault locations on the system are computed considering constant fault current magnitude with zero phase angle injected by the IBDGs.
• The final step towards implementing the proposed method is to sum the fault current contribution of the first and second part of superposition.
Proposed Method Verification 8
R3
Bus 1
Bus 5
R1
R5
R4 R13
R7
Bus 2
R9
Bus6
R14 R15
R6
F10
F14
Bus 3
R11 R8Bus 4
R2 R12
Bus 7
R16 R10
60 MVA60 MVA
F11F9
F8 F13
F12
F15
2 MVA
2 MVA
2 MVA
Power Distribution System of the IEEE 14-bus system under study
Proposed Method Verification 9
In order to be able to validate the proposed method, two simulation setups were developed:
1. Short circuit currents are computed based on the proposed method where each IBDG is set to inject fault current of 1.5 p.u of the DG capacity.
2. Short circuit currents are computed based on a transient model of the same test system developed on SIMULINK simpowersystems toolbox. – IBDG is a 2MVA photovoltaic plant with current controlled inverter
with controller limiters set to 1.5 p.u of the DG capacity.
Proposed Method Verification 10
Fault location
DOCR Three-Phase Fault currents (p.u.) Percentage
error (%) Transient Model Proposed Method
F8
R1 2.345 2.335 0.426
R2 1.191 1.181 0.832
R4 0.073 0.070 3.409
R11 1.177 1.174 0.219
R6 0.233 0.229 1.659
F9
R5 2.669 2.655 0.518
R6 0.917 0.907 1.105
R2 0.662 0.657 0.819
R13 0.233 0.227 2.676
R4 0.214 0.218 2.154
R16 0.684 0.680 0.560
F10
R3 2.289 2.279 0.435
R4 0.699 0.696 0.444
R2 0.600 0.594 0.959
R14 0.687 0.683 0.553
R6 0.1931 0.1929 0.084
F11
R13 1.006 0.989 1.752
R14 1.747 1.735 0.701
R3 0.983 0.981 0.221
R5 1.150 1.143 0.614
R16 0.599 0.593 0.981
Proposed Method Verification 11
Fault location
DOCR Three-Phase Fault currents (p.u.) Percentage
error (%) Transient Model Proposed Method
F12
R15 1.583 1.574 0.576
R16 1.140 1.132 0.697
R5 1.261 1.255 0.440
R9 1.128 1.124 0.347
R13 0.329 0.325 1.269
F13
R11 1.881 1.874 0.358
R12 1.423 1.414 0.670
R7 1.881 1.874 0.358
R1 1.411 1.406 0.339
F14
R9 2.265 2.257 0.338
R10 0.863 0.855 0.871
R8 0.429 0.425 1.045
R15 0.850 0.847 0.390
F15
R7 2.836 2.829 0.233
R8 1.026 1.021 0.498
R10 0.448 0.453 0.960
R12 1.026 1.021 0.498
Protection Coordination Problem 12
• One of the most popular solutions proposed in the literature to solve the protection coordination problem of interconnected systems is the use of optimization methods.
• The objective is to minimize the sum of primary and backup DOCRs operating time (T) while maintaining the conditions of protection coordination. Hence, the objective function is given as:
N
i
bx
ij
p
ij
M
j
ijttMinimizeT11
)(
Protection Coordination Problem 13
• Conventional Relay Tripping Characteristic (IEC 255-3 standard):
• TDS: Time Dial Setting
• M: Multiple of pickup
currents= (Isc/Ip)
• Isc=Short circuit current
• Ip=Pickup current setting
• A=0.14, B=0.02
2 4 6 8 10 12 14 16 18 200
0.5
1
1.5
2
2.5
Multiples of pickup currents (M)
trip
pin
g tim
e (
seconds)
TDS = 0.05
TDS = 0.1
TDS = 0.2
1
BM
ATDSt
Time-Current relay characteristic for different values of TDS
Protection Coordination Problem 14
• The protection coordination optimization (PCO) model considers three sets of constraints that must be satisfied so that optimal feasible solution is achieved.
• Relay settings:
• Relay operating time:
• Relay Coordination:
iTDSTDSTDS iii maxmin
iIII pipipi maxmin
},{,, min xjittt ij
bx
ij
p
ij
CTItt p
j
bx
j },{ xj
Simulation Results 15
Relay TDS (S) Ip (pu) Relay TDS (s) Ip (pu) 1 0.050 0.826 9 0.050 0.617
2 0.050 0.352 10 0.050 0.264
3 0.050 0.555 11 0.050 0.648
4 0.150 0.034 12 0.050 0.531
5 0.050 0.694 13 0.110 0.089
6 0.050 0.132 14 0.050 0.396
7 0.050 1.075 15 0.050 0.471
8 0.050 0.230 16 0.050 0.329
T(s)= 19.1675
Optimal TDS and Ip DOCR Settings
Simulation Results 16
Optimal primary and backup relay operating times
Fault location
Operating times of relays (s) (p= primary, b= backup) P b1 b2
F8 R1: 0.3332 R2: 0.2856
R4: 1.4532 R11: 0.5856
R6: 0.6332 -
F9 R5: 0.2573 R6: 0.1783
R2: 0.5573 R13: 0.8145
R4: 0.5573 R16: 0.4783
F10 R3: 0.2444 R4: 0.3388
R2: 0.6652 R14:0.6388
R6: 0.9203 -
F11 R13: 0.3120 R14: 0.2335
R3: 0.6120 R5: 0.6979
- R16: 0.5908
F12 R15: 0.2868 R16: 0.2797
R5: 0.5868 R9: 0.5797
R13: 0.5868 -
F13 R11: 0.3262 R12: 0.3537
R7: 0.6262 R1: 0.6537
- -
F14 R9: 0.2663
R10: 0.2944
R8: 0.5663 R15: 0.5944
- -
F15 R7: 0.3582 R8:0.2313
R10: 0.6582 R12: 0.5313
- -
Conclusion 17
• This paper proposes a method based on superposition theory that can be used to calculate the three-phase fault currents in a meshed distribution system equipped with IBDG units.
• The methodology is based on the fact that the current controlled IBDG units inject a specific amount of fault current that does not exceed 2p.u depending on the controller’s limiters (modelled as constant current source).
• The proposed method was tested and achieved reasonable accuracy when verified against a transient model.
• Finally, the fault currents computed using the proposed method were utilized by the CPC model developed to solve the protection coordination problem.
Thank you for your Attention
18