A STUDY OF THE CAUSES AND EFFECTS OF …eprints.uthm.edu.my/8901/1/DHARMASEGARAN_K._NAGAMANY.pdf ·...
Transcript of A STUDY OF THE CAUSES AND EFFECTS OF …eprints.uthm.edu.my/8901/1/DHARMASEGARAN_K._NAGAMANY.pdf ·...
A STUDY OF THE CAUSES AND EFFECTS OF
ABANDONED RESIDENTIAL PROJECTS IN
MALAYSIA
DHARMASEGARAN A/L K. NAGAMANY
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
A STUDY OF THE CAUSES AND EFFECTS OF ABANDONED
RESIDENTIAL PORJECTS IN MALAYSIA
DHARMASEGARAN A/L K. NAGAMANY
A thesis submitted in
fulfillment of the requirement for the award of the
Degree of Master of Science in Real Estate and Facilities Management
Faculty of Technology Management and Business
Universiti Tun Hussein Onn Malaysia
JUNE 2016
iv
ACKNOWLEDGEMENT
This thesis is dedicated to my wife and children, especially my wife, who has
constantly encouraged me to carry out this study due to my own background
knowledge in this field of study, as a contribution and eye-opener to those
unfortunately affected by abandonment and others in our society. Without their love,
support and understanding, it would have been a difficult task to complete this
course. I would also like to thank my late parents who had always placed the utmost
importance on education as I would not be where I am today if not for them. The
invaluable knowledge and experience gained was made possible by the dedicated
supervisor of this thesis. A word of thanks also goes to the ever-helpful staff of
UTHM. The cooperation of the national regulatory bodies involved in the property
industry and the respondents where this study was carried out is also very much
appreciated. They have made this study a memorable and pleasurable one.
v
ABSTRACT
The ever increasing demand for property has brought about numerous problems
involving the stakeholders in the property industry, resulting in the widespread
abandonment of residential projects in the country. The purpose of this study is to
reveal the causes relating to the phenomenon of abandoned residential projects in a
structured manner and its effects from a social, economic and environmental
perspective. A preliminary research on literature review using content analysis
identified the key stakeholders involved. A quantitative research methodology was
conducted in the collection of data through a well-designed questionnaire which was
structured based on literature review and preliminary interviews and discussions with
10 key stakeholders of the property industry. A total of 52 respondents representing
developers, contractors, consultants, REHDA, HBA, Abandoned Property Owners
Association and banks participated in the survey. Data was analysed using
descriptive statistics whereby the mean scores were obtained. The findings conclude
that the main root causes of abandoned residential projects in Malaysia are financial
closely followed by administrative/strategy and policy factors. They also confirm
that the effects are mainly social and economic with some environmental effects;
sub-categorized as financial, administrative and policy perspectives. An analytical
framework in the form of a Fishbone Diagram illustrates the causes and effects of
abandonment categorized under the different perspectives with respect to the relevant
key stakeholders. The findings of this research contribute valuable knowledge and
solutions to the key stakeholders enabling them in making informed choices and
decisions in avoiding future entrapment.
vi
ABSTRAK
Permintaan untuk hartanah yang sentiasa meningkat telah banyak membawa masalah
yang melibatkan pemegang taruh dalam industri hartanah hingga mengakibatkan
projek perumahan terbengkalai secara berleluasa di negara ini. Tujuan kajian ini
adalah untuk mengkaji dan mendedahkan punca-punca berkaitan fenomena projek-
projek perumahan yang terbengkelai secara berstruktur and kesan-kesannya dari
perspektif sosial, ekonomi dan alam sekitar. Kajian awal yang menggunakan analisis
kandungan ke atas ulasan literatur telah mengenal pasti pemegang taruh utama.
Metodologi kajian kuantitatif telah dijalankan dalam pengumpulan data melalui
borang soal selidik yang distruktur berdasarkan ulasan literatur serta temu ramah
awalan dan perbincangan dengan 10 orang pemegang taruh dalam industri hartanah.
Seramai 52 orang responden yang mewakili pemaju, kontraktor, perunding, REHDA,
HBA, Abandoned Property Owners Association dan bank telah menyertai kajian ini.
Data telah di analisis menggunakan statistik deskriptif untuk mendapatkan purata
skor. Hasil kajian ini merumuskan bahawa punca utama projek-projek perumahan
terbengkalai di Malaysia ialah faktor kewangan dan diikuti oleh faktor
pentadbiran/strategi dan polisi. Hasil kajian ini juga mengesahkan bahawa kesan-
kesan yang utama ialah kesan sosial, ekonomi dan alam sekitar; dikategorikan
selanjutnya sebagai perspektif kewangan, pentadbiran dan polisi. Satu kerangka
analitik dalam bentuk kerangka ikan mengilustrasikan punca-punca dan kesan-kesan
terbengkalai dikategorikan mengikut perspektif yang berlainan serta penglibatan
pemegang taruh yang relevan. Hasil kajian ini dapat menyumbang pengetahuan dan
penyelesaian yang tidak ternilai kepada pemegang taruh utama agar mereka dapat
membuat pilihan pilihan dan keputusan yang wajar bagi mengelakkan diri daripada
terperangkap pada masa depan.
vii
TABLE OF CONTENTS
TITLE i
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENT vii
LIST OF TABLES xiii
LIST OF FIGURES xv
LIST OF APPENDICES xvi
CHAPTER 1 INTRODUCTION 1
1.1 General overview 1
1.2 Background of study 4
1.2.1 Recent developments 6
1.3 Problem statement 9
1.4 Scope and focus of research 13
1.5 Research questions 14
1.6 Research aims and objectives 14
1.7 Theoretical framework of research 15
1.8 Scope of study 17
1.9 Research methodology 17
1.9.1 Preliminary research 18
1.9.2 The quantitative research 18
viii
1.9.2.1 Research population & sample 18
1.9.2.2 Research instrument 19
1.9.3 Data analysis 19
1.10 Significance of study 19
1.11 Conclusion 21
CHAPTER 2 LITERATURE REVIEW 23
2.1 Introduction 23
2.1.1
Government’s action and inaction 26
2.1.2
Introduction of special bodies and
incentivisation to revive abandoned projects 28
2.2
A review of the specific causes of abandoned
projects in Malaysia
29
2.2.1 Causes related to financial perspectives 29
2.2.2 Causes related to policy perspective 34
2.2.3
Causes related to administrative/strategy
perspective 40
2.2.4 Causes related to other perspectives 46
2.3
A review of the effects of abandoned projects in
Malaysia
48
2.3.1 Social effects 49
2.3.2 Economic effects 53
2.3.3 Environmental effects 56
2.4 Literature research findings 58
2.5 Conclusion 60
CHAPTER 3 RESEARCH METHODOLOGY
61
3.1 Introduction 61
ix
3.1.1 Recent developments in Penang 63
3.2 Research design 65
3.3 Research methodology 68
3.3.1 Quantitative method 69
3.4 Research participants and sampling 70
3.5 Research instruments 73
3.5.1 Survey questionnaire 73
3.6 Data analysis procedures 75
3.6.1 Descriptive data analysis 76
3.7 Summary 77
CHAPTER 4 RESEARCH FINDINGS & DATA ANALYSIS 78
4.1 Chapter overview 78
4.2 Weightages and responses 80
4.3 Calculation of mean score 81
4.4 Results of quantitative analysis 82
4.5
Objective 1: Root causes of abandoned residential
projects
82
4.5.1 Root causes - Developers 82
4.5.2 Root causes - Contractors 83
4.5.3 Root causes - Consultants 84
4.5.4
Root causes – Real Estate and Housing
Developers Association
86
4.5.5 Root causes – House Buyers Association 87
4.5.6
Root causes – Abandoned Property
Owners Association 89
4.5.7 Root causes – Banks 91
x
4.6
Objective 2: Effects of abandoned residential
projects 92
4.6.1 Effects - Developers 94
4.6.2 Effects - Contractors 94
4.6.3 Effects - Consultants 95
4.6.4
Effects – Real Estate and Housing
Developers Association
96
4.6.5 Effects – House Buyers Association 97
4.6.6
Effects – Abandoned Property Owners
Association 98
4.6.7 Effects – Banks 99
4.7 Overall findings 99
4.7.1
Main root causes of abandoned of
residential projects 100
4.7.2
Main effects of abandoned residential
projects 101
4.7.3
Relationship between the causes of
abandoned projects to the various
stakeholders
102
4.7.4
Formulation of a conceptual framework
showing relationship between main root
causes and main effects 103
4.8
Other root causes and effects stated by respondents
in questionnaire 104
4.8.1 Other root causes 104
4.8.2 Other effects 106
4.9
Suggestions and recommendations by respondents 106
4.9.1
Suggestions and recommendations by
consultants
107
4.9.2
Suggestions and recommendations by 107
xi
REHDA
4.9.3
Suggestions and recommendations by
House Buyers Association 107
4.9.4
Suggestions and recommendations by
Abandoned Property Owners Association
(Victims Malaysia) 108
4.9.5
Suggestions and recommendations by
banks 108
4.10
Summary 108
CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 110
5.1 Introduction 110
5.2
Summary of main root causes of abandoned
residential projects
112
5.2.1 Main root causes - Financial perspective 112
5.2.2 Main root causes - Policy perspective 113
5.2.3
Main root causes – Administrative/Strategy
perspective 113
5.2.4 Main root causes – Other perspectives
114
5.3
Summary of main effects of abandoned
residential projects
114
5.3.1 Major effects – Social
115
5.3.2 Major effects – Economic
115
5.3.3 Major effects – Environment
116
5.4 Relationship between causes to the stakeholders
117
5.5 Formulation of a conceptual framework
117
5.6
Limitations of the current research
117
5.7 Recommendations for future research
119
xii
5.7.1
Contributing factors relating to developers,
contractors, banks and local authorities 119
5.7.2
Increase in legal action against purchasers,
developers and contractors 120
5.7.3 Larger sample population 120
5.7.4 Involve other stakeholders left out 120
5.7.5 Qualitative research 121
5.7.6
Study existing laws, regulations and
policies 121
5.7.7
Well-developed compensation,
expropriation and ruin declaration
procedures 121
5.7.8
Research specific to every single
stakeholder 122
5.7.9 The Build-Then-Sell (BTS) system 122
5.8
Conclusion 123
REFERENCES
126
APPENDIX
142
xiii
LIST OF TABLES
1.1 Abandoned housing projects In Peninsular Malaysia (January
2009 to March 2013)
8
1.2 Government expenditure to revive abandoned projects 9
1.3 Abandoned housing projects by state until 30 June 2015 10
1.4 Overall statistics of problematic private housing projects -
delayed and sick as at 28 February 2014
11
2.1 Total number of abandoned housing projects (Peninsular
Malaysia)
24
3.1 Overall statistics of problematic private housing projects 64
3.2 Targeted samples of population for survey 72
4.1 Number of respondents and questionnaires received 78
4.2 Weightage for responses 80
4.3 Calculation of mean score 81
4.4 Range of mean scores 82
4.5 Root causes of abandoned residential projects by developers 83
4.6 Root causes of abandoned residential projects by contractors 83
4.7 Root causes of abandoned residential projects by Consultants 85
4.8 Root causes of abandoned residential projects by REHDA 86
4.9 Root causes of abandoned residential projects by HBA 87
4.10 Root causes of abandoned residential projects by Abandoned
Property Owners Association Malaysia
89
4.11 Root causes of abandoned residential projects by Banks 91
4.12 Effects of abandoned residential projects by Developers 94
4.13 Effects of abandoned residential projects by Contractors 94
4.14 Effects of abandoned residential projects by Consultants 95
4.15 Effects of abandoned residential projects by REHDA 96
4.16 Effects of abandoned residential projects by HBA 97
4.17 Effects of abandoned residential projects by Abandoned
xiv
Property Owners Association (Victims Malaysia) 98
4.18 Effects of abandoned residential projects by banks 99
4.19 Summary of main root causes of abandoned residential
projects
100
4.20 Summary of main effects of abandoned residential projects 101
4.21 Relationship between main root causes and main effects 103
4.22 Other root causes of abandoned residential projects not stated in
questionnaire
104
4.23 Other effects of abandoned residential projects not stated in
questionnaire
106
4.24 Suggestions and recommendations by Consultants to avoid
further and continuous abandonment of residential projects
107
4.25 Suggestions and recommendations by REHDA to Avoid
Further and continuous abandonment of residential projects
107
4.26 Suggestions and recommendations by HBA to avoid further
and continuous abandonment of residential projects
107
4.27 Suggestions and recommendations by Victims Malaysia to avoid
further and continuous abandonment of residential projects
108
4.28 Suggestions and recommendations by Banks to avoid further
and continuous abandonment of residential projects
108
xv
LIST OF FIGURES
1.1 Scope and focus of research 13
1.2 Theoretical framework of research 16
2.1 Cause and effect diagram of abandoned residential projects 59
3.1 The framework of research design 65
3.2 Communication process of primary data collection 67
4.1 Number of questionnaires distributed and returned 79
4.2 Root causes of abandoned residential projects according
to Developers
82
4.3 Root causes of abandoned residential projects according
to Contractors
83
4.4 Root causes of abandoned residential projects according
to Consultants
84
4.5 Root causes of abandoned residential projects according
to REHDA
86
4.6 Root Causes of abandoned residential projects according
to HBA
87
4.7 Root causes of abandoned residential projects according
to Abandoned Property Owners Association Malaysia
89
4.8 Root causes of abandoned residential projects according
to Banks
91
4.9 Effects of abandoned residential projects according to all
respondents
93
4.10 (Ishikawa) Fishbone diagram (Analytical Framework) – Cause &
Effect analysis of abandoned residential projects
102
xvi
APPENDIX
LIST OF APPENDICES
TITLE
PAGE
A Questionnaire 142
B Mean scores tabulated in questionnaire (Master sheet) 157
C (Ishikawa) Fishbone diagram (Analytical Framework) -
Cause & effect analysis of abandoned residential projects
167
D Seminars / Papers presented 168
E Vita 169
CHAPTER 1
INTRODUCTION
1.1 General overview
The construction industry is a developing industry and it is an important component
in Malaysia’s economic growth (Chia, et al., 2011). Generally, the development rate
of a country is critically related to the infrastructure development. The housing
industry is an important sector that plays a major role in the development of a
country and its economy.
According to Nuarrual Hilal (2008a) the demand for residential property over
the past three decades has resulted in numerous problems being encumbered by
developers, contractors and buyers in the building industry in Malaysia. One such
problem is that it is contributing to an alarming surge in the number of abandoned
residential projects in the country. Although the housing industry is one of the main
priorities of the government, persistent major problems are being encountered,
resulting in the sui generis (unique) abandoned housing projects. There have been
initiatives to remedy this problem by the government, very much driven by growing
concerns by key stakeholders regarding the increasing number of abandoned
projects. Although efforts of the research community has drawn attention to various
aspects of the problem, however little has been done to identify the causes and
effects of abandonment of housing projects with respect to the key stakeholders.
Hence, this study has been undertaken to identify the causes of abandoned residential
projects as well as gauge the effects of such projects on the building industry and
2
developers, the key stakeholders in general, especially the innocent buyers, the
funding financial institutions and other related parties of the housing industry.
It was also mentioned (Nuarrual Hilal, 2008a) that the housing industry has
brought about numerous benefits and contributed towards the economic and social
development and growth of the nation, but along with it came a nightmare and a
barrage of problems related to abandoned housing projects. In Malaysia, the demand
for housing is relatively high compared to existing supply. This has contributed to a
strong interest amongst property developers to over-capitalize on the continuing
demand leading to some negative impacts on the property industry, such as that of
abandoned projects. It gives a person great excitement and satisfaction when they
book their first home in the hope of finally owning a property which they can call
their own but when the project is stalled for various reasons, they are left stranded,
financing an incomplete house which is indefinitely abandoned.
Nuarrual Hilal (2008a) stated that the buyers feel cheated and are furious
when their dream houses are not completed or abandoned for long periods of time.
The question commonly asked is as to whether buyers have sufficient knowledge or
whether they have any knowledge at all of their rights as buyers. Buyers accuse the
banks of being inhumane, as to why the loan should be paid when the house is
incomplete and undelivered as promised. The issue of abandonment is never
stipulated in the loan agreement between the buyer and the bank. Thus, there is no
linkage between a loan agreement and the sale and purchase agreement. The loan
agreement is merely a kind of loan product offered by a bank. The completion of a
housing project within the stipulated period, with quality as per specifications laid
down in the Sale and Purchase Agreement and in compliance to and the satisfaction
of interested parties, requires cooperation amongst the relevant key players, such as
the contractors, developers, financial institutions, suppliers and buyers, amidst tight
project management
Consumers Association of Penang (2007) classifies Housing Projects as
abandoned projects when:-
i. Construction work in the project site has stalled continuously for 6
months or more, whether during the project completion period or past
the scheduled date of completion, in accordance to the Sales and
Purchase Agreement.
3
ii. A developer is unable to complete the project, or when the Housing
Controller considers that the developer can no longer carry out their
responsibilities as a developer.
It is without doubt that projects that end up being classified as abandoned do
have the recognizable associated symptoms that render them being categorized as
‘delayed project’, and worse still as a ‘sick project’. These categories are defined
accordingly by Abdul Aziz and Abdelnaser (2011) as below:
i. Delayed Project: Project facing delay between 10% - 30% compared to actual
expected development;
ii. Sick Project: Project facing delay more than 30% compared to actual
expected development or the expiry period of the Sale and Purchase
Agreement.
The Consumers Association of Penang (2007) in its article “Abandoned
Housing Projects – Who Suffers & What Can Be Done”, are convinced that the
buyers are the worst affected when housing projects are abandoned, whereby they
have to start and continue making payments on their housing loans even if their
houses are not completed and unfit to live in. Failing which, legal action would be
taken against the house buyers, followed by bankruptcy proceedings and eventually
being adjudicated bankrupt. According to the Consumers Association of Penang
(2007) between 1990 to 2005, 261 projects involving 88,410 houses in Peninsular
Malaysia were abandoned. A total of 58,685 buyers were affected by this problem.
This problem of abandoned housing projects is indeed serious and the root causes,
irrespective of whether it is that of the house buyers’, the developers’ or the Housing
Ministry, has to be identified immediately.
The implementation of the Housing Development (Control and Licensing
Amendment) Act, 2007 made bold changes to revamp the local property sector and
contributed to improving the efficiency of the country’s new housing development
delivery system. The fast track approval system was implemented for greater
efficiency and transparency in the Housing Industry. The One-Stop Centre was set
up for a speedier process in handling and approving housing projects, replacing the
Certificate of Fitness for Occupation (CFO) with the Certificate of Completion and
Compliance (CCC) and incentives for developers to adopt the Build Then Sell (BTS)
concept, in contrast to the existing Sell Then Build (STB) method. The changes
4
were expected to bring about more transparency, full disclosure and practical
flexibility with no overlapping of processes, better building delivery system, fast
track approval and cutting down red tape, thereby making the country investment
friendly and ensuring that the housing industry would be more competitive (Housing
Development Control and Licensing (Amendment) Act, Act A1289, 2007).
However, the issue of abandoned housing projects is still a persistent problem.
Despite attempts being made to identify some of the causes of abandonment
of housing and commercial projects (Mohamed Sukeri, 2005; Ibrahim, 2006;
Norharnila, 2006), the problem of abandonment seems to have persisted since the
1970s mainly due to the lack of political will in implementing significant and radical
changes in the housing sector as noted by Nuarrual Hilal (2009). The unresolved
state of affairs regarding abandonment has prompted certain quarters to propose for
the implementation of the ‘build then sell’ concept in Malaysia in order to resolve the
problem of abandoned housing projects (National House Buyers Association, 1991).
This system has long been implemented in other countries such as Singapore and
New South Wales, Australia and the responsibility is entrusted upon the Housing
Development Board under the perview of the Minsitry of National Development in
Singapore (Nuarrual Hilal, 2009).
It is undeniable that the seriousness of the problem regarding abandoned
housing projects warrants for a detailed research and study on the causes that lead to
residential projects being abandoned and the effects of the said abandonment on all
key stakeholders.
1.2 Background of the study
Since the independence of Malaysia in 1957 there has been a gradual increase in
demand for residential property, in tandem with the population and economic growth
of the country (Nuarrual Hilal, 2011). This problem of abandoned housing projects
is indeed serious, and has to be resolved immediately irrespective of whom the finger
should be pointed at. The Federal Government’s top priority has always been to
provide sufficient and suitable housing accommodation to all residents. This
enormous task of constructing and building housing accommodation has been given
5
to the developers who are subjected to rules and regulations laid down by the
government. Private Developers licensed under the Housing Development (Control
and Licensing) Act, 1966 and the respective Regulations have been given the task of
constructing and completing the residential and industrial buildings to fulfil the
demands of buyers who comprise of the various categories of society.
Abandoned housing has become a severe and perpetual headache to the
government, financial institutions and purchasers. The cause has often been assumed
to be due to legal problems and the recession, often attributed to the East Asian
Financial Crisis which drastically affected the Malaysian economy in 1997, which
was compounded by the ongoing Global Financial Crisis. The Consumers
Association of Penang (2007) in its article ‘Abandoned housing projects-Who suffers
& What Can be Done?’ identified the following common causes of abandoned
housing projects:
i. Delays in the approval of projects by the government agency, responsible for
the escalation of house prices.
ii. Developers encounter financial problems in the course of development.
iii. Delay in the issuance of Certificate of Fitness for Occupation although the
houses have been completed.
iv. Developers take a deposit and keep it or use it for another project being
developed elsewhere, at the same time.
v. Construction work not in accordance to specifications.
vi. Construction work is incomplete.
vii. Buyers pay in cash or through end financing but fail to get their titles from
the bank that is funding the project because the developer fails to settle his
loan (bridging or term).
viii. Interest rates imposed by banks are too high.
ix. Developers complete the project but eventually abandon it due to their failure
in meeting all the specifications.
The timely completion and delivery of the houses to the purchasers is
significant but it becomes an issue when the houses are delayed beyond the
completion period mentioned in the sale and purchase agreement (Ng, 2007). House
buyers are further blacklisted by the banks when they fail to service their bank loans
6
(Yip, 2009a; Yip, 2009b). Having been blacklisted, they are unable to buy another
property unless they pay back their loans (Yip, 2009b).
For over two decades, the property industry has been grappling with the surge
of abandoned housing projects which has caused hardship to many buyers and has
remained a major thorn in the flesh until today. According to the Ministry of
Housing and Local Government (2009), there was a total of 34 Abandoned Housing
Projects nationwide in Malaysia, between 1990 and 2009 at various levels of
completion, involving 9,155 units and 5,484 buyers, requiring Developers or White
Knights to salvage, revive or rehabilitate the said projects. This problem of
abandoned housing projects is indeed serious. Thus, the root cause, irrespective of
who is to be blamed has to be resolved immediately.
Accordiing to Nuarrual Hilal and Sharifah Zubaidah (2012), when a housing
developer company is wound up, a private liquidator or provisional liquidator or the
official receiver under the Department of Insolvency takes over the affairs and
business of the company. The liquidator may only rehabilitate the abandoned
projects if the projects are viable for rehabilitation with the approval of the creditors,
contributories, the committee of inspection and the court and where there are
adequate funds to finance the rehabilitation. On the other hand, if it is not viable, due
to insufficient funds or the complexity the projects, they may be stalled forever
without any prospects for rehabilitation, to the detriment of the purchasers.
1.2.1 Recent developments
According to a professor of law at Universiti Utara Malaysia, Nuarrual Hilal
(2008b), the Malaysian Housing and Local Government Ministry records show that
abandoned housing projects had been reported since the 1970s and due to the Global
Financial Crisis, their numbers have increased. In June 2005 the numbers were 277,
with 50,183 buyers, 75,356 dwellings and the projects were worth RM7.033 billion.
However, these numbers do not give a true picture as some of the projects are not
listed and thus the actual figure is much higher (Nuarrual Hilal, 2008b).
Consumers Association of Penang (2007) reported the following. In 1983,
abandoned housing projects were identified by the government for the purpose of
rehabilitation. In 1990, an Abandoned Housing Project Revival Fund (TPPPT) was
7
established by Bank Negara and the Abandoned Housing Project Revival Pvt. Ltd.
was given the responsibility to conduct feasibility studies in view of reviving those
projects. The government then set up a special purpose vehicle, similar to the
Pengurusan Danaharta Nasional Bhd (Danaharta), to be placed under the
responsibility of the National Housing Corporation (Perbadanan Perumahan
Negara). Hence, Syarikat Perumahan Negara Berhad, a wholly owned subsidiary of
the Ministry of Finance, was appointed to take over and revive abandoned housing
projects; and the Housing and Local Government Ministry set up a special fund to
revive abandoned projects.
The Housing and Local Government Ministry (2009) in an article published
in the New Straits Times (2009) entitled “Rescue plans for abandoned projects”,
gave its assurance that housing projects launched will not be abandoned following
the enforcement of new laws and the introduction of a special purpose vehicle. The
Housing and Local Government Minister said that the challenge was to instill
confidence in developers and buyers to ensure the industry continues to be active
despite the unsupportive economic situation.
Pemudah (Pasukan Petugas Khas Pemudahcara Perniagaan), a special task
force comprising 23 highly respected individuals from both the private and public
sectors, set up by the government on 7th
February 2007 to facilitate business and
reporting directly to the Prime Minister (Pemudah, 2007), suggested ways to reduce
the number of abandoned housing projects in Malaysia. There were 423 housing
projects that were either delayed, ailing or abandoned, being monitored by the
Ministry of Housing and Local Government (MHLG) as at 30 June 2010. MHLG
implemented stiffer actions by compounding and prosecuting errant developers and
blacklisting some. Pemudah in their annual report in 2010 proposed that the deposit
required to get a developer's licence from the current RM200,000 be raised by 5 per
cent. They also suggested that it be made mandatory for developers to take on the
build-then-sell concept (BTS) and introduce the housing insurance scheme as
suggested by the Real Estate and Housing Developers' Association of Malaysia
(Rehda), to provide a boost to buyers. Developers on the other had complained that
they would have to build the properties with no assurance that buyers would stay.
Projects are often abandoned due to mismanagement, financing issues, mismatched
development components and fraud by developers (Sharen, 2011).
8
Sanjugtha (2013) in her article “White Knights Galloping In”, disclosed that
the government has spent RM156 million over the past four years to revive 126
abandoned housing projects, completing 29,799 homes, an average of RM5,238
spent to revive a house in an abandoned project. A total of 178 housing projects
have been abandoned since 2009, involving more than 50,000 low to medium cost
income households. Sanjugtha (2013) further elaborated that to overcome this
problem, the Ministry of Housing and Local Government (MHLG) set up the
Abandoned Project Rehabilitation Division (APRD) under the purview of the
National Housing Division. This division has revived 126 projects with another 66
in the pipeline (see Table 1.1). APRD has been negotiating revival packages
between white nights and financial institutions to minimise the government’s need to
top up and ensure smooth revival of abandoned projects (see Table 1.2).
Table 1.1: Abandoned housing projects in peninsular Malaysia
(January 2009 to 2015)
Year
NO OF PROJECTS DEVELOPMENT STATUS
Current New Total Planned Under
Construction Completed
2009 144 4 148 87 58.80% 46 31.10% 15 10.10%
2010 133 13 146 50 34.20% 60 41.10% 36 24.70%
2011 110 6 116 22 19.00% 62 53.40% 32 27.60%
2012 84 11 95 9 9.47% 51 53.68% 35 36.84%
2013 60 27 87 24 27.50% 33 37.90% 30 34.50%
2014 57 10 67 32 47.70% 20 29.90% 15 22.40%
2015 52 1 53 30 56.60% 22 41.51% 1 1.89%
144 72 216 30 13.89% 22 10.19% 164 75.92%
Source: Abandoned Project Rehabilitation Division, National Housing Department
(2015)
9
Table 1.2: Government expenditure to revive abandoned projects
Government Expenditure to Revive Abandoned Projects
Year RM (Million) No. of Projects
2011 14.5 5
2012 51.4 7
2013 62.1 (Committed) 10
37.9 (Budgeted) 4
2014 28.1 (Budgeted) 1
Total 194 27
Source: Abandoned Project Rehabilitation Division, National Housing Department
(2014)
1.3 Problem statement
The seriousness of the problem of abandoned residential projects has forced the
government to step in and splash huge sums of money to rehabilitation these
projects, more so in the interests of the house buyers. The Housing Developers
(Control and Licensing) Act of 1996 too has been amended in the hope of resolving
this problem. Unfortunately, abandoned residential projects still exist and the
problem has not been solved. Thus, there is a need to study the factors that continue
to contribute towards residential projects being abandoned and their effects from a
socio-economic perspective in avoiding this problem form recurring continuously.
The National House Buyers Assosiation (2008) has noted that abandoned
housing projects are an eyesore and proof of business failures especially when
abandoned buildings become breeding grounds for mosquitoes and other unwanted
activities like shelters for drug addicts. Abandoned buildings remain uncompleted
whilst the unlucky buyers cry out of frustration. Thick undergrowth and weeds creep
over concrete house pillars and dark moss discolour concrete pillars. The empty
building sites turn into ghost towns whilst the ugly and unstable abandoned buildings
pose danger and affects the environment.
Based on recent statistics, it appears that the issue of abandoned housing
projects is still a presistent problem in Malaysia (see Table 1.3). Moreover, the
prime indicators leading towards abandonment, which is delayed and sick projects,
are still aplenty (see Table 1.4). The tables further indicate that Penang is an average
10
of the worst and best case of delayed and sick projects, especially in terms of the
number of units and house buyers involved. Penang is a fair representative of the
issues ralated to abandoned housing projects in Peninsular Malaysia and thus the
researcher’s choice in conducting this research in Penang. Syafril Idzwan (2008), in
his research found that housing projects are continuously being delayed and
eventually some ending up in an abandoned state despite the existence of the relevant
laws, regulations and statutory provisions governing the housing industry. Syafril
Idzwan (2008) argued that there are some pertinent questions that need to be
answered, especially as to whether these laws, rules, regulations and statutory
provisions or any improvements to them, can help prevent and avoid this catastrophe
from recurring in the future or help protect the rights and interests of the parties
involved.
Table 1.3: Abandoned housing projects by state until 30 June 2015
STATE NUMBER OF
PROJECTS
NUMBER OF HOUSE
UNITS
NUMBER OF
BUYERS
Johor 8 2,734 2,051
Kedah 2 765 169
Kelantan 1 39 29
Melaka - - -
Negeri Sembilan 4 973 807
Pahang 4 761 589
Perak 9 962 600
Perlis - - -
Pulau Pinang 2 1,550 1,337
Selangor 22 7,288 4,798
Terengganu - - -
Kuala Lumpur 1 134 23
TOTAL 53 15,206 10,403
Source: National Housing Department (MHLG, 2015)
11
Table 1.4: Overall statistics of problematic private housing projects - delayed and
sick as at 28 February 2014
NO. STATES NO. OF DELAYED
PROJECTS
NO. OF SICK
PROJECTS
1. PERLIS 1 0
2. KEDAH 11 14
3. PULAU PINANG 2 12
4. PERAK 0 51
5. SELANGOR 18 72
6. WILAYAH PERSEKUTUAN 6 3
7. NEGERI SEMBILAN 1 10
8. MELAKA 0 2
9. JOHOR 19 28
10. PAHANG 1 10
11. TERENGGANU 0 10
12. KELANTAN 1 13
TOTAL 60 225
Source: Official Portal National Housing Department (2014)
According to Mohd Rafick Khan (2010), the Housing Development Act ( Act
118) which governs housing development in Malaysia, forces purchasers and
developers to sign the standard Sale and Purchase Agreement strictly without any
deviation, as provided in schedule G or H of the said Act, upon a purchase of any
property from a developer. However, it is common knowledge that the SPA is a
contract between a willing buyer and a willing seller in the purchase of residential
property. The agreement does not give much rights to the house buyers but plenty of
obligations, and a freehand to the developer who will dictate the property
development. There is no avenue for the buyers to take any action against the
developer when the project is delayed. Buyers may make a claim for late delivery
charges (LAD) against developers but they may only do so when the project is fully
completed. The Ministry of Housing and Local Government (2010) statistics showed
that 252,000 house buyers were affected as at February 2010 and that it was a
RM37.8 billion problem.
According to the National House Buyers Assosiation (2008), there is no
protection for buyers or a comprehensive method of preventing or dealing with
abandoned or stalled housing projects. Buyers are often left all alone to face this
dilema of abandoned housing projects. However, of late some serious attention has
12
been directed at this problem, but not enough, as the problem seems to persist with
serious consequences. The trend in abandoned housing projects on the other hand,
appears to be on the decline, maybe due the the Government’s intervention and
measures taken.
The Consumers Association of Penang (2012) revealed that unlicensed
housing developers had scandalously carried out 195 housing projects right under the
eyes of the relevant parties in the housing industry.
According to Sanjugtha (2013), to date 187 housing projects have been
registered under APRD as abandoned, an addition of 43 to the initial 144 projects
registered with the department since its inception in 2009. A total of 67.38% of the
abandoned housing projects have been completed with another 24.6% currently
under construction, whilst a further six projects have been planned for this year.
Sanjugtha (2013) further reported that in 2013, Abandoned Project Rehabilitation
Division’s (APRD) records showed 69 abandoned housing projects, comprising 60
brought forward from 2012 that were not completed. Whilst nine new projects have
been reported as of end-March 2013, with a total of eight projects that have been
completed and 46 that were still under construction.
There has been public opinion calling on the government to intervene and
take over the rehabilitation of abandoned projects and at the same time to impose
legal provisions in preventing abandoned housing in future (Harian Metro, 2003). In
a report in the Utusan Malaysia (2004) the Prime Minister Abdullah Ahmad Badawi
in acknowledging the seriousness of abandoned housing projects, advised private
developers to not merely think of profit but also to be more fully responsible when
completing the projects. Previous researches such as Kamariah (1993) and Nuarrual
Hilal (2001) contended that the existence of abandoned housing projects is a national
problem affecting mainly private purchasers and leading to other problems like
encouraging criminal activities at project sites. The President of the Federated
Association of Consumer Malaysia (FOMCA) argued that the existence of
abandoned housing projects could also be related to the housing system based on the
‘sell the build system’ being practiced in Malaysia (Mingguan Malaysia, 1999).
Notably, the Ministry of Housing and Local Government [MHLG] (2013) has
highlighted complaints regarding project abandonment pertaining to rejection of
planning approvals, delays in hand-overs, refusal to pay compensation for late
13
delivery and conflicts involving local authorities, developers, consultants and
contractors occurring at different stages of housing delivery.
Previous research has mainly focused on generalizing the causes and effects
of abandonment, not providing a clear identification of ownership of the issues. Thus
this research aims to evaluate the main root causes and effects of abandoned
residential projects from the financial, administrative and policy perspectives
relevant to the key stakeholders involved in the housing industry due to the wide
array of multiple causes and effects of abandonment.
1.4 Scope and focus of research
The focus of this research is to reveal the causes relating to the phenomenon
of abandoned residential projects in a structured manner and its effects from a social,
economic and environmental perspective. Once the causes and the problems which
lead to the abandonment are identified, solutions can then be readily identified so
that the risk of housing projects getting abandoned can be eradicated or at the least
minimized to an acceptable level. However, this research does not serve to identify
and discuss specific solutions to this phenomenon.
Figure 1.1: Scope and focus of research
Source: Adapted from Vinetta Bell (2009)
Administrative
Policy
Financial
KEY STAKEHOLDERS Internal & External
(Key Drivers) 1 Developers 2 Contractors 3 Consultants 4 House Buyers 5 Banks & Fin. Institutions 6 Real Estate & Housing
Developers Association 7 House Buyers Association 8 Abandoned Property
Owners Association (Victims Malaysia)
Causes Effects Abandoned
Housing Projects
14
To start with, this research focuses on the study of factors causing the
abandonment of residential projects by conducting literature review and preliminary
discussions and interviews with selected stakeholders such as consultants,
developers, contractors and purchasers involved in the study in order to structure a
comprehensive data collection questionnaire primarily aimed at identifying the root
causes and effects of abandonment. The respondents chosen were the key
stakeholders within the property sector, adequately knowlegable on the issue of
abandonment of residential projects. Hence, recommendations for overcoming the
issue of abandonment are forwarded based on stakeholder feedback. The diagram in
Figure 1.1 shows the scope and focus of this research.
1.5 Research questions
i. What are the causes of abandoned residential projects in the property industry
in Peninsular Malaysia according to specific categories of stakeholder
responsibility?
ii. What are the effects of abandoned residential projects in the property industry
in Peninsular Malaysia from a social, economic and environmental
perspective?
iii. What is the relationship between causes of abandoned projects with respect to
the various stakeholders in the property industry in Peninsular Malaysia?
iv. Can a conceptual framework be formulated for mitigating the problems
leading to abandonment of residential projects in Peninsular Malaysia be
developed as a guide?
1.6 Research aims and objectives
The aim of this research is to identify the main causes and effcts of abandoned
residential projects specific to the key stakeholders in the property industry in
Peninsular Malaysia from a financial, administrative/strategy and policy perspective.
Thus, this research will evaluate the main root causes and effects of abandoned
residential projects in formulating an analytical (fish-bone diagram) and conceptual
15
frameworks to ascertain if there lies a relationship between the causes and effects
with respect to the various key stakeholders.
Based on the aims of this research, the following research objectives are
formulated. The following objectives will function as the guidelines of this research:
i. To identify the main root causes of abandoned residential projects in the
property industry in Peninsular Malaysia attributed to the various key
stakeholders.
ii. To identify the main effects of abandoned residential projects in the property
industry in Peninsular Malaysia from a social, economic and environmental
perspective.
iii. To evaluate the relationship between causes of abandoned projects with
respect to the various stakeholders in the property industry in Peninsular
Malaysia.
iv. To formulate a conceptual framework for mitigating the problems leading to
abandonment of residential projects in Peninsular Malaysia.
1.7 Theoretical framework of research
Feedback in the form of preliminary interviews and questionnaires from the said
parties gave a comprehensive insight on the main causes and as to the surge in the
number of abandoned housing projects in Peninsular Malaysia.
In aiming to identify the main causes and effects of abandoned residential
projects, it was considered as of equal importance to establish the relationship
between the causes and effects based on a cause-and-effect fishbone diagram
methodology to establish the causal relationship achievable by designing the
questionnaire in a categorical sense. This is considered valid based on matching
causes and effects according to pre-specified categories; as a pioneering piece of
work having to deal with complex array of variables. Additionally, this research sets
out to identify the parties involved and to what extent these causes relate to them.
Earlier researchers such as (Sambasivam and Yau, 2006), National House Buyers
Association (2006b), Chan (2009) and Hussin and Omran (2011) have already
indicated that there are several effects on certain innocent parties brought about by
this perennial problem in Malaysia.
16
Theories are formulated to explain, predict, and understand phenomena and
in many cases, to challenge and extend existing knowledge within the limits of
critical bounding assumptions. The theoretical framework is the structure that can
hold or support a theory of a research study. The theoretical framework introduces
and describes the theory that explains why the research problem under study exists
(Swanson, 2013). The variables of the research are represented as a form of
theoretical framework. Following the determination of the variables, a research
strategy was drawn up (see Figure 1.2). The theoretical framework describes the
relationship amongst the variables in the research and the effects of that relationship
that can also be seen as an input-output process. The theoretical framework in Figure
1.2 shows the focus of this research.
The research flow shows the separation between the factors and parties
related to the Causes of Abandoned Projects and the Effects of those causes on the
respective parties. From the feedback during the preliminary interviews and
discussions with selected stakeholders in the property industry and literature review,
it was noted that amongst the parties who are knowledgeable and able to give initial
feedback on the causes of abandoned projects are the Real Estate and Housing
Developers Association, the House Buyers Association, Consultants in the Housing
Industry such as Architects, Engineers and Surveyors, Developers and Contractors,
House Buyers, Banks and Financial Institutions, the Abandoned Property Owners
Association and the Ministry of Housing and Local Government.
Figure 1.2: Theoretical framework of research (Adapted from Owston, 2007)
Sim
ple
Ind
ep
en
de
nt
Var
iab
les
(Fac
tors
)
Policy Perspective
Perspective
Financial Perspective
Administrative Perspective
Abandoned
Housing
Projects
Economic Recession / Financial Crisis Environmental Factors
Culture Clash / Selfish Behaviour
Project Characteristics
Management /
Participants Procurement
Risk & Uncertainty
Litigation, Bribery &
Fraudulent Practices
Co
mp
lex In
dep
en
de
nt V
ariable
s
(Factors)
17
1.8 Scope of study
The scope of this study was limited to Property Developers, Contractors, Consultants
in the housing industry, House Buyers, the Real Estate and Housing Developers
Association (REDHA), House Buyers Association (HBA), Abandoned Property
Owners Association of Malaysia (Victims Malaysia), Banks and Financial
Institutions, records with the Ministry of Housing and Local Government, Local
Authorities, Syarikat Perumahan Negara Berhad (SPNB), the Abandoned Project
Rehabilitation Division and other relevant parties involved in abandoned projects.
This study was carried out based on data retrieved from the relevant parties involved
in the housing industry primarily in Penang, which is quite representative of
Peninsular Malaysia in relation to the issue of housing project abandonment. Penang
is an average of the worst and best cases of the number of abandoned housing
projects in Peninsular Malaysia by virtue of the number of delayed and sick projects,
abandoned projects and the number of units and buyers involved (See Tables 1.3 and
1.4), (National Housing Department, 2014) and (National Housing Department,
2015). Additionally, to ensure key stakeholder (respondent) representation, some
national bodies based in Kuala Lumpur, like the Real Estate and Housing Developers
Association, House Buyers Association and the Abandoned Propety Owners
Association Malaysia were included.
Hence, this research focused on abandoned residential projects in the state of
Penang as a representative sample, and the study also focused on the causes and
effects of specifically abandoned residential projects in the property industry. The
relevant parties, viewed as key stakeholders to the issue of abandonment were
interviewed and questionaires that were answered by them were analysed with
respect to the relevant research objectives.
1.9 Research methodology
This research was undertaken primarily using a quantitative methodology. In order
to elicit a clear understanding of the issues related to the problem of abandoned
residential projects, a brief preliminary research was undertaken. However, the
preliminary research is not described in particular detail as it served to structure the
18
main quantitative research, especially in the design of the research questionnaire. A
summary description is provided below.
1.9.1 Preliminary research
In ascertaining the problems that exists with respect to abandoned housing projects,
preliminary discussions with professionals were undertaken, study of relevant
published articles, internet resources and other forms of relevant literature were
analyzed briefly. Site visits to the abandoned housing projects gave a better
understanding of the actual conditions of the abandoned construction sites in terms of
effects.
In conclusion, this preliminary research involved collection of information
through personal discussions with selected developers, contractors, consultants and
house buyers in order to identify and/or refine the issues relating to abandoned
residential projects that helped to formulate and test the conceptual framework.
1.9.2 The quantitative research
A quantitative research analysis was used involving data collection through survey
questionnaires. Questionnaires were distributed to the target population followed by
personal visits, telephone calls and electronic mail messages reminding the
respondents to complete and return the completed questionnaires. Additional space
was also provided in the questionnaire to enable the respondents to state other causes
and effects of abandoned residential projects not mentioned in the questionnaire.
The respondents were also encouraged to make suggestions in overcoming
abandonment of residential projects.
1.9.2.1 Research population & sample
The population of this study consisted of key stakeholders such as house buyers,
property developers, contractors, consultants, the Abandoned Property Owners
Association Malaysia, the Real Estate and Housing Developers Association, the
House Buyers Association and Banks. Stratified Purposive Sampling Design was
19
used as the stratified sample of the research population was based on sample of the
various key stakeholders. A suitable sampling frame was identified for each
startified sample, thus determining a suitable sample size based on selecting an
appropriate sampling technique and the sample.
1.9.2.2 Research instrument
The main research instrument of this study was the survey questionnaire, in order to
achieve the objectives stated above. In designing the questionnaire, the researcher
ensured that the respondents were able to decode the questions the way it was
intended and to participate in providing other possible causes and effects of
abandonment and propose suggestions in resolving them. This was achieved by
consulting representative/s from each category of stakeholders not involved in the
actual research, namely 2 directors, 2 contractors, a consultant, an office bearer of the
Real Estate & Housing Developers Association, Penang, an office bearer of the
House Buyers Association, a senior bank officer and a house buyer with an
experience of an abandoned housing project.
1.9.3 Data analysis
Data analysis was undertaken after all the required data was collected before making
any inferences. Numbers were crunched to obtain the mean score for each item in
the questionnaire by multiplying the frequency of responses in each Likert Scale (f)
with the respective weightage (w). The sum of this value (∑) was then divided by
the total number of respondents in each category (n). Quantitative data was treated
and analysed in detail as described accordingly in the methodology chapter.
1.10 Significance of study
Abandoned residential projects are projects that are left without care in abandoned
construction sites either temporarily or permanently stalled for a long period of time.
Besides the fact that it brings misery and financial heartache to the purchaser, the
structures are completely left idle and unprotected, constantly at the mercy of
20
weather conditions. The concrete and other construction materials used deteriorate
over time, sometimes resulting in the project being incapable of revival or
rehabilitation and being abandoned indefinitely. This is especially true in Malaysia
where a drive around major cities, housing or industrial construction areas as well as
the outskirts, would reveal the eyesore of abandoned projects stalled at various stages
of incompletion.
This study will benefit all the key stakeholders involved in the Property
Industry, such as the Real Estate and Housing Developers Association, the House
Buyers Association, the Consumer Associations, Abandoned Property Owners
Association, Consultants in the Housing Industry such as Architects, Engineers and
Surveyors, Receivers and Managers, Liquidators, White Knights, Developers and
Contractors, Banks and Financial Institutions, the Ministry of Housing and Local
Government and the Local Authorities, Homeowner’s Tribunal and especially the
innocent House Buyers. The parties involved in the drawing up of laws and
regulations, development, construction and completion of the housing projects will
be made aware of how and where they had gone wrong in the past in contributing to
the increase in the number of abandoned residential projects. The banks and
financial institutions will be made aware that they have to play a more significant
and important role in scrutinising and monitoring the progress of the projects. This is
to ensure that in future, there is an early detection of delays in the construction and
completion of housing projects and thereby possibily rescuing projects from being
eventually abandoned.
The house buyers too, will be made aware of their legal rights and
responsibilities and they too, will realise that they have to be more aware of the laws
and procedures as well as monitor the progress of construction work carried out. The
house buyers who are usually the sole victims of any failed or stalled residential
projects will be made more fully aware of the consequences of a failed project on
them and how they can play a greater role from the signing of the Sale and Purchase
Agreement (SPA) to the issuance of the Certificate of Completion and Compliance,
to ensure that their unit in the said residential project does not end up being
abandoned or incomplete.
This study will inadvertently educate the relevant parties in the property
industry on the awareness regarding the issues relating to the abandonment of
21
residential projects in terms of clear economic, social and environmental causes and
implications. Thereby helping to correct, reduce or completely eradicate unnecessary
errors and risks of abandonment in the future attributed to the specific key
stakeholders of the problem. The relevant parties in the residential industry will be
aware that the completion of a housing project with Certificate of Completion and
Compliance is not merely as simple as entering into an SPA and collecting a 10%
deposit of the purchase price and obtaining loan facilities vide, loan agreements for
bridging/term/end-financing facilities. Developers have to realise that they have to
be financially sound before entering into these contracts and are capable of seeing
through the completion of the projects in compliance to the existing laws and specific
rules and regulation
1.11 Conclusion
This research was carried out to study the causes and effects of abandoned residential
projects in the property industry which is still considered to be a problematic issue
discussed daily and argued upon in the media and parliament; by authorities and
politicians directly responsible and affected by their abandonment. Statistics from
the Minsitry of Housing and Local Government show that there is a steady ever
increasing trend in the number of abandoned housing projects which has also
resulted in an increase in the number of personal and corporate insolvencies amongst
the purchasers, developers and contractors. It is apparent that due to this stigma
within the property industry in Malaysia, which is one of the main income
contributors of our nation’s economy has over the past two decades, a negative
image of the socio-economic sector both within Malaysia and to the outside world
has been projected. The social responsibilities of developers and contractors in the
modern day are more demanding than in the 1970´s. There are demands for well-
developed compensation, expropriation and ruin declaration procedures. New
mechanisms are being introduced to try and avoid the repetition of past mistakes and
efforts to better facilitate the management of abandoned projects through competent
public administration in more advanced economies. The amendments to laws are
attempting to protect the rights of citizens and to increase the responsibility of the
urbanizing agents (developers, contractors, etc.).
22
This study serves as an eye opener and will contribute in unearthing the
actual root causes, negligence and lack of commitment by key stakeholders that has
resulted in continuous abandonment of residential projects.
23
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
There are numerous problems faced by developers, contractors and buyers in the
property industry resulting in an alarming surge in the number of abandoned projects
in the country (Zairul and Rahinah, 2008). This research is vital, as the property
industry is one of the main priorities of the government in Malaysia and plays a
major role in the development of the country and its economy. This research has
attempted to identify the causes and effects of abandoned projects as well as scope
the areas for action of key stakeholders in the property industry, especially the
innocent buyers, developers and the funding financial institutions.
Developers constantly advertise their proposed projects in beautiful brochures
and make special offers, tempting buyers to rush into purchasing these houses
although the project will be completed much later. A house buyer would still have to
pay his housing loan and interest to the bank in accordance to the progress payments
released to the developer, even if the housing project is eventually abandoned.
Hence, a member of the lower income group will have the devastating consequence
of never being able to survive financially, thus ending his dream of owning his very
own house (Nuarrual Hilal, 2008b; National House Buyers Association, 2008).
In terms of avoiding the unpleasant situation of property development being
abandoned, it is implied in previous research that key stakeholders need to secure a
cooperative mode rather than resorting to legal action while having to face the
consequence of project abandonment by a contractor and the related negative effects.
24
For instance, Ismail (2008) noted that the completion of a housing project within the
stipulated period, with quality as per the specifications laid down in the Sale and
Purchase Agreement and in compliance to and the satisfaction of interested parties,
requires cooperation amongst the relevant key players such as the contractors,
developers, banks, suppliers and buyers, amidst tight project management.
Based on the statistics in Table 2.1, it is clear that the number of house buyers
affected by the problem of abandoned housing projects does not show any marked
decreasing trend. The Ministry of Housing and Local Government (2009) confirmed
that as at 2005, 261 projects involving 88,410 houses and 58,685 buyers in
Peninsular Malaysia were abandoned. An obvious knee-jerk reaction is to conclude
that legal action needs to be taken against the developers by the relevant parties,
which could lead to the developer ending up in liquidation. Obviously, this is not an
ideal or viable solution.
Table 2.1: Total number of abandoned housing projects (Peninsular Malaysia)
Year Ending
No. of
Abandoned
Projects
No. of
Affected
Houses
No. of
Affected
Buyers
Estimated Value (RM
million)
2000 514 107,702 68,340 7,524.51
2001 544 125,649 80,070 9,496.68
2004 227 75,356 50,813 7,033.08
2005 261 88,410 58,683 8,043.00
Source: Ministry of Housing and Local Government (Monitoring and Enforcement
Division) (2009)
Nuarrual Hilal (2008b) in his research suggested that insurance coverage for
housing projects such as that implemented in New South Wales, Australia, can also
be implemented in Malaysia. This is to ensure that in the event the developer
defaults in his obligation, the buyers still have an avenue to see their homes
completed. A comprehensive review is needed on the National Land Code (1965),
planning laws, building and housing laws, Town and Country Planning 1976, Street,
Drainage and Building Act 1974, Building By-laws 1984 and Housing Development
(Control and Licensing) Act, 1966. There should also be a review of the provisions
for special laws to regulate the rehabilitation of abandoned projects. Although
several provisions were introduced in some of the legislations in 2007, it remains
126
REFERENCES
Abdul Aziz, A., Anuar, A., Khor, H. T. and Guan, N. M. (2014). The causes and
Effects of housing project abandonment in Malaysia. World Academy of
Science, Engineering and Technology. International Journal of Civil and
Environmental Engineering. Vol: 1, No: 12, 2014. London, United Kingdom.
Abdul Rahman, H., Alashwal, A. M., Ayub, M. and Abdullah, A. A. (2013).
Abandoned Housing Projects In Malaysia: Pressing Issues during the
Rehabilitation Process. International Journal of Architectural Research,
Archnet-IJAR, Volume 7 - Issue 1 - March 2013 - (65-73)
Abdul Rashid, A. (2003). Five of the 14 Abandoned Housing Projects in
Penang will be Revived by Syarikat Perumahan Negara Bhd (SPNB), State
Housing, Entrepreneur Development and Cooperative Committee Chairman.
June 28, 2003. Retrieved from www.skyscrapercity.com.
Alreck, P. L. and Settle, R. B. (1995) The Survey Research Handbook, 2nd (eds),
Irwin, Boston.
Amade, B., Ubani, E. C., Amaeshi, U. F. and Okorocha, K. A. (2015). Factors for
containing failure and abandonment of public sector construction project in
Nigeria. Journal of Building Performance ISSN: 2180-2106 Volume 6 Issue 1
2015, University Kebangsaan Malaysia. The Royal Institution ofo Surveyors
Malaysia, Page 63.
Arni Nadhirah, A. H., Nurul Huda, M. S. and Tan, G. M. (2015). Abandoned
Housing Project: Issues and Challenges in Malaysia, 15 Me1 2015. School
of Housing, Building & Planning, University Science Malaysia.
Asian Development Bank Institute (2009). Impact of the Crisis on the Malaysian
Economy.ADBInstitute.Retrieved2014,June18from:http://www.adbi.org/work
ingpaper/2009/08/26/3275.
Ayodele, E. O. and Alabi, O. M. (2011). Abandonment of Construction Projects in
Negeria. Causes and Effects: Journal of Emerging Trends in Economics and
Management Sciences (JETEMS). Vol. 2, Iss. 2, pp. 142-145.
127
Babbie, E. R. (2010). The Practice of Social Research. 12th ed. Belmont, CA:
Wadsworth Cengage, 2010;
Bailey, K. D. (1982). Methods of Social Research, Publishing Co. Inc. New York.
Bassett, E. M., Schweitzer, J. and Panken, S. (2006). Understanding Housing
Abandonment and Owner Decision-Making in Flint, Michigan: An
Exploratory Analysis. Retrieved August 25, 2010 from
http://www.geneseeinstitute.org/downloads/Bassett_Understanding_Owner_
Decision.pdf
Bavani, M. (2009, June 2). Abandoned Jelatek fire station now an eyesore. The Star
Online.Retrieved:December20,2009,fromhttp://thestar.com.my/metro/story.as
p?file=/2009/6/2/central/4024468&sec=central
Bell, V. (2009). A writing process. Using Graphic Organizers. Retrieved from:
http://www.learnnc.org/lp/editions/writing-process/5809/7/03/2015
Bennett, D. (2012). Don’t Let Delays Derail Your Construction Project. Available at:
http://www.constructioncrossing.com/article/480016/Dont-Let-DelaysDerail-
Your-Construction-ProjectFive-common-reasons-for-project-delaysand-how-
to-prevent-them/
Bryne, P. and Cadman, D. (1984). Risk, Uncertainty and Decision-Making in
Property, Spon, London, UK, 1984.
Carrero, R., Malvarez, G., Navas, F. and Tejada, M. (2009). Negative Consequences
on Abandoned Urbanization Projects in the Spanish Coast and its Regulation
in the Law. Journal of Coastal Research, SI 56 (Proceedings of the 10th
International Coastal Symposium), 1120 – 1124, Lisbon, Portugal.
Challal, A. and Tkiouat, M. (2012). "Identification of the Causes of Deadline
Slippage in Construction Projects: State of the Art and Application," Journal
of Service Science and Management, Vol. 5 No. 2, 2012, pp. 151-159.
doi:10.4236/jssm.2012.52019.
Chan, K. Y. (2007). Degradation of Abandoned Construction Material. A thesis
submitted in fulfillment of the requirements for the award of the degree of
Bachelor of Civil Engineering, Faculty of Civil Engineering, Universiti
Teknologi Malaysia, April 2007.
128
Chan, K. L. (2009). Revival of Failed and Abandoned Projects - Protection for
Property Purchaser? Paper presented at National Housing & Property
Summit at a boutique hotel in Petaling Jaya, November 13, 2009.
Chan, S. (2007). Financial Crisis Was Avoidable, New York Times. Between 1997
and 2006, the price of the typical American house increased by 124%.
Retrieved from http://en.wikipedia.org/wiki/Late-2000s_financial_crisis
Chan, T. H. (2007). Asian Financial Crisis, Volatility and Malaysia Commercial
Bank. Retrievedfromwww.gsb.usm.my/index.php/en/admin/academic.../289
chan-tze-haw
Chang, K. L. (2009, November 10). It's time to switch to BTS for homes. NST
Online.RetrievedDecember20,2009,fromhttp://www.nst.com.my/Current_Ne
ws/NST/articles/19HOMEY/Article/index_html
Chang, S. C., Aminah, M. Y. and Hadina, H. (2015). Delay Mitigation in the
Malaysian Housing Industry: A Structural Equation Modelling Approach.
Journal of Construction in Developing Countries, 20(1), 65–83, 2015 ©
Penerbit Universiti Sains Malaysia, 2015.
Chen, E. (2007). Far from being rotten. New Straits Times Property. Retrieved
September9,2009from:http://properties.emedia.com.my/listvp.php?propNews
ID=162&CatID=V00[Accessed September 9, 2008].
Cheong, E. Y. Y. (2012, October 05). Revival of abandoned housing projects.
Real Estate and Déco. New Straits Times. Retrieved April 11, 2014 from
http://www.nst.com.my/red/revival-of-abandoned-housing-projects 1.152637
Chia, F. C., Skitmore, M., Runeson, G. and Bridge, A. (2011). Property investment,
construction and economic growth: the case of Malaysia. In The Asian
Conference on Real Estate (ACRE 2011): Sustainable Growth, Management
Challenges, 3-5 October 2011, Thistle Johor Bahru, Malaysia. (Unpublished)
Chin, M. (2012). Abandoning Property Development Projects is now a Crime!
Crowe Horwath AF 1018, July E-Newsletter, 25 May 2012. Retrieved from
www.crowehorwath.com.my
Consumers Association of Penang (2007). Abandoned housing projects-Who suffers
& What Can be Done? Retrieved July 24, 2010 from
http://www.consumer.org.my/complaints/services/86-abandoned-housing-
projects
129
Consumers Association of Penang (2012). Abandoned housing projects: Is Malaysia
Alawlesscountry?RetrievedApril4,2012fromhttp://www.consumer.org.my/ind
ex.php/development/public-sector/556-abandonedhousing-projects-is-
malaysia-a-lawless-country
Cooper, D. R. and Schindler, P. S. (2003). Business Research Methods. (8th
Ed).
McGraw Hill.
Creswell, J. W. (1994). Research Design: Qualitative and Quantitative Approaches.
Sage publications, California.
Creswell, J. W. (2003). A Framework for Design, in Research Design: qualitative,
quantitative and mixed methods approaches. 4th edition. SAGE publications,
2455 Teller Road, Thousnd Oaks, California, 91320.
Doraisamy, S. V., Akasah, Z. A. and Yunus, R. (2014). “A review on abandoned
construction projects: causes and effects,” in Proceedings of the International
Integrated Engineering Summit (IIES '14), pp. 1–4, December 2014.
Doraisamy, S. V., Zainal Abidin, A. and Riduan, Y. (2014). An Overview on the
Issue of Delay in the Construction Industry. International Civil &
Infrastructure Engineering Conference 2014 (INCiEC 2014), 28th
September-
1st October, 2014, Kota Kinabalu, Sabah.
Doraisamy, S. V. and Zainal Abidin, A. (2015). Substantial Consequences and
Factors Leading Towards Construction Project Success and Failure.
Australian Journal of Basic and Applied Sciences, 9 (25): 10-52, 2015.
Dzuljastri, A. R., Mustafa Omar, M. and Kazi, M. T. (2015). Abandoned Housing
Projects in Malaysia and the Prospect of DP: An Overview. Procedia
Economics and Finance. International Accounting and Business Conference
2015, IABC 2015Volume 31, 2015, Pages 813–822
Easterby-Smith, M., Thorpe, R. and Lowe, A., 2002, Management Research: An
Introduction, 2nd Edition, Sage Publications, London.
Enshassi, A., Khalid, A-H. and Sherif, M. (2006). Causes of Contractor's Business
Failure in Developing Countries: The Case of Palestine. Journal of
Construction in Developing Countries, Vol. 11, No. 2, 2006
Fernandez, P. (2009). Market Risk Premium Used in 2008 by Professors: A Survey
with 1,400 Answers. University of Navarra - IESE Business School, April
16, 2009.
130
Fink, A. (1995). The survey handbook. Sage Publications, 1995 – Medical – 129
pages.
Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). “Causes of delay and cost
overruns in construction of groundwater projects in a developing countries;
Ghana as a case study,” International Journal of Project Management, vol.
21, no. 5, pp. 321–326, 2003.
Fugar, F. D. K., Agyakwah-Baah and Adwoa, B. (2010). Delays in Building
Construction Projects in Ghana. Australasian Journal of Construction
Economics and Building, Volume 10 Issue 1/2 (2010)
Gay, L. R. and Airasian, P. (2003). Educational research. Competencies for analysis
and applications (7th ed.), New Jersey, USA; Pearson Education.
Greenberg, M. R., Popper, F. J. and West, B. M. (1990). "The Toads: A New
American Urban Epidemic." Urban Affairs Quarterly 25: 435-54. Retrieved
March 13, 2015 from
http://www.trincoll.edu/depts/tcn/Research_Reports/resrch23.htm
Greenberg, M. R., Popper, F. J., Schnieder D. and West, B. M. (1993).Community
Organizing to Prevent Toads in the United States. Community Development
Journal 28:5565.
Government of Western Australia (2008). Home indemnity insurance - Consumer
Protection-Department of Commerce. Department of Commerce, the
Government of Western Australia. Retrieved March 5, 2010, from
http://www.commerce.wa.gov.au/ConsumerProtection/Content/Real_Estate/
Home_building/Before_construction_starts/Home_indemnity_insurance.htm
Hamzah, A. R., Alashwal, A. M., Maryam, A. and Abdul Aziz, A. (2013).
"Abandoned Housing Projects in Malaysia: Pressing Issues during the
Rehabilitation Process," in ArchNet-IJAR: International Journal of
Architectural Research, vol. 7, issue 1 (2013): 65-73.
Hamzah, A. R., Roshana, T. and Wong, S. M. (2009). Financial-related causes
contributing to project delays. Journal of Retail & Leisure Property (2009) 8,
225–238. doi:10.1057/rlp.2009.11.
Hamzah, A. R., Chen, W. and Nur Hamizah, A. (2015). Identification of Risks
Pertaining to Abandoned Housing Projects in Malaysia. Journal of
Construction Engineering, Volume 2015 (2015), Article ID 524717, 12 pages.
131
Harian Metro (2003). Kerajaan perlu campurtangan-tambahkan denda, hukuman
sedia ada untuk pemaju sebagai ikhtibar, July 15, 2003.
Hart, C. (1998). Doing a Literature Review: Releasing the Social Science Research
Imagination. SAGE Publications, London, 1998. Open University. Social
Science Masters.
Hill, C. W. L. (1998). The Asian Financial Crisis. University of Washington. Jan 6,
1998. Retrieved June18, 2014 fromhttp://www.wright.edu/~tdung/asiancrisis-
hill.htm
Hoe, Y. E. (2013). Causes of abandoned construction projects in Malaysia [Ph.D.
thesis], Department of Surveying, Faculty of Engineering and Science,
Universiti Tunku Abdul Rahman, Petaling Jaya, Malaysia, 2013.
Horwath, C. (2012). Abandoning Property Development Projects is now a Crime!
Crowe Horwath AF 1018, Member Crowe Horwath International. July E-
Newsletter | 25 May 2012
Housing Development (Control and Licensing) Act (1966). (Act 118). [P.U.(B)
212/69], International Law Book Services, Direct Art Company, Kuala
Lumpur, Malaysia.
Housing Development (Control and Licensing) (Amendment) Act (2007). (Act A
1289), International Law Book Services, Direct Art Company, Kuala
Lumpur, Malaysia.
Housing Development (Control and Licensing) (Amendment) Regulations (2007).
(PU(A) 58/1989). International Law Book Services, Direct Art Company,
Kuala Lumpur, Malaysia.
Hutcheson, G. and Sofroniou, N. (1999). The multivariate social scientist:
Introductory statistics using generalized linear models. London and
Thousand Oaks: Calif. 224-225.
Hussey, J. and Hussey, R. (1997). Research Design is the ... Describe Descriptive
Research as a ... and Data Management System. Basingstoke; Macmillan.
Retrievedfromhttp://uir.unisa.ac.za/bitstream/handle/10500/1935/06chapter6.
Hussin, A. A. and Omran, A. (2011). Implication of Non-Completion Projects in
132
Malaysia. ACTA Technica Corviniensis–Bulletin of Engineering. Tome IV
(year 2011).ISSN 2067-3809. 2011. Fascisule 4 (October-December). Faculty
of Engineering-Hunedoara, Romania.
Ibrahim, F. (2006). Faktor-faktor kritikal bagi pemulihan projek perumahan
terbengkalai. Master’s thesis, Universiti Teknologi Malaysia. Retrieved
August10,2010fromhttp://eprints.utm.my/142/1/fadzilahma041148d06ttt.pdf
Ihuah, P. W. and Benebo, A. M. (2014). “An assessment of the causes and effects of
abandonment of development projects on real property values in Nigeria.”
International Journal of Research in Applied, Natural and Social Sciences,
vol. 2, no. 5, pp. 25–36, 2014.
iProberty.com (2011). Charting a new era in Malaysian housing industry? The HBA
discusses implications of the mandatory BTS 10:90 “from 2015 onwards”.
Posted Date: Jul 12, 2011 by: HBA. Retrieved March 13, 2015 from
http://www.iproperty.com.my/news/3907/bts-10-90-%C2%A0charting-a-
new-era-in-malaysian-housing-industry.
Ismail, A. F. (2008). Completion of housing project within stipulated period.
Prevention of Abandoned Housing Projects. Essays, UK. (November 2013).
RetrievedMarch9,2015fromhttp://www.ukessays.com/essays/construction/pre
vention-of-abandoned-housing-projects.php?cref=1
Ishikawa, K. (1980) [original Japanese ed. 1970]. QC Circle Koryo : General
Principles of the QC Circle. Tokyo: QC Circle Headquarters, Union of
Japanese Scientists and Engineers.
JB Jurunilai Bersekutu Sdn Bhd (2013). Abandoned Housing Projects, Part 1.
RetrievedJanuary21,2015fromhttp://www.jurunilai.com.my/abandonedhousin
gproject-part1.html-
Kamariah, O. (1993). Meeting Housing Needs, (ISIS) Malaysia, Kuala Lumpur.
Kerlinger, F. N. (1986). Foundations of Behavioral Research, 3rd (eds) Rinehart and
Winston, Inc, New York.
Kong, L. (2009, December 3). Fairness for house buyers. The Star Online. Retrieved:
December20,2009,fromhttp://thestar.com.my/news/story.asp?file=/2009/12/3/
nation/5203993&sec=nation
Kotangora, O. O. (1993). Project Abandonment, Nigerian Tribune.
133
Lin, Z., Rosenblatt, E. and Yao, V. W. (2007). Spill over Effects of Foreclosures on
Neighborhood Property Values. The Journal of Real Estate Finance and
Economics. Volume 38, Number 4, 387-407, DOI: 10.1007/s11146-007-9093-
z.
McCormack, B. and Hill, E. (1997). Conducting a Survey: the SPSS Workbook. UK:
Cengage Learning EMEA.
Miller, C. D. (1991). Handbook of Research Design and Social Measurement.
Newbury Park, California: Sage Publications.
Mingguan Malaysia (1999). 60% pembeli rumah jadi mangsa sistem ‘jual dan beli’,
January 24, 1999.
Ministry of Housing and Local Government (2009). ‘Rescue Plans for Abandoned
Projects’. New Straits Times, July 08, 2009.
Ministry of Housing and Local Government (2009). Abandoned housing projects:
Govt mulls amendment. Daily Express, Independent National Newspaper of
EastMalaysia.RetrievedJuly24,2010fromhttp://www.dailyexpress.com.my/ne
ws.cfm?NewsID=69402
Ministry of Housing and Local Government (MHLG), (2009). Statistics for Problem
Based Housing Projects in Malaysia, Putrajaya, Kuala Lumpur.
Ministry of Housing and Local Government (2010). Monitoring and Enforcement
Division. KPKT statistics on abandoned housing projects until February
2010.
Ministry of Housing and Local Government Malaysia (MHLG). (2013). eHome,
Official Portal National Housing Department. Available at:
http://ehome.kpkt.gov.my/main.php?Content=vertsections&SubVertSecti
onID=123&VertSectionID=116&CurLocation=119&IID=
Ministry of Housing & Local Government (MHLG), (2014). Statistics for
Abandoned Housing Projects in Malaysia, Putrajaya, Kuala Lumpur.
Mohd Hasyim, M. and Fakhrul Anwar, Z. (2015). An overview of the antecedents
and consequences of abandoned residential housing projects in Malaysia –A
solution from Blue Ocean Strategy (BOS) perspective. International Journal
of Academic Research in Business and Social Sciences. Volume 5, 2 February
2015, pages 201-221.
134
Mohamed Sukeri, K. (2005). The abandoned housing projects in Malaysia: An
Institutional Analysis of Real Estate Development Process. Paper presented at
the 2nd College of Arts and Socials Sciences Postgraduate Conference,
University Aberdeen pp. 43
Mohamad Sukeri, K. (2010). Abandoned Housing Development: The Malaysian
Experience. School of Built Environment, Heriot-Watt University
Edinburgh.Degree of Doctor of Philosophy. February 2010.
Mohd Rafick Khan, A. R. (2010).Government Fully Responsible for Abandoned
Housing Projects. Abandoned Property Owners Association of Malaysia. New
Straits Times, 23 July, 2010.
Moser, C. A., and K. Kalton (1971). Survey methods in social investigation,
Heineman Educational Books Limited, London.
Muijs, D. (2010). Doing Quantitative Research in Education with SPSS. 2nd edition.
London: SAGE Publications, 2010.
Nachmias, C. F. and Nachmias, D. (1996). Research methods in the social sciences.
Arnold, London.
National House Buyers Association (1991). Build then Sell (BTS),Must the Govt
pandertothedevelopers?10/04/1991.Retrievedfromhttp://www.hba.org.my/arc
hive/focus/build_then_sell/PG1.htm/31/01/2015
National House Buyers Association (2000). Pros and cons of build then sell.
The Malay Mail, 26/12/2000. Retrieved from
http://www.hba.org.my/news/2000/1200/pros_and_cons.htm/16/02/2016.
National House Buyers Association (2006a). Blind to victims. A Buyer Watch
Article published in NST-PROP. The New Straits Times, 15 April 2006.
National House Buyers Association (2006b). More laws doesn't mean less
abandoned projects. Published in NST-PROP. A Buyer Watch Article by
National House Buyers Association 27/05/2006. Retrieved July 26, 2010
fromhttp://www.hba.org.my/articles/buyer_watch/2006/more_laws.htm
National House Buyers Association (2008). Review Needed To Avoid Abandoned
Housing Projects. Bernama 26/11/2008.
National House Buyers Association (2009a). Abandoned Housing Projects – A
Nightmare.RetrievedJuly26,2010fromhttp://www.iproperty.com.my/news/99
0/Abandoned-Housing-Projects-%E2%80%93-A-Nightmare
135
National House Buyers’ Association (2009b). Cleaning up abandoned or Stalled
HousingProjects.RetrievedAugust13,2010fromhttp://www.iproperty.com.my/
news/724/Cleaning-up-abandoned-or-stalled-housing-projects
National House Buyers Association (2009c). Revival of Failed and Abandoned
Projects - Protection for Property Purchaser? (Part One of Three) Retrieved
August13,2010fromhttp://www.iproperty.com.my/news/1152/Revival-of-
Failed-and-Abandoned-Projects---Protection-for-PropertyPurchaser?-(Part-
One-of-Three)
National House Buyers Association (2009d). Revival of Failed and Abandoned
Projects - Protection for Property Purchaser? (Part Two of Three).
RetrievedAugust13,2010fromhttp://www.iproperty.com.my/news/1186/Reviv
al-of-Failed-andAbandoned-Projects---Protection-for-Property-Purchaser?-
%28Part-Two-of-Three%29
National House Buyers Association (2010). Time to Phase out Sell-Then-Build.
Retrieved July 23, 2010 from
http://www.iproperty.com.my/news/2283/Time-to-Phase-out-Sell-Then-
Build/
National Housing Department (2014). Government expenditure to revive abandoned
projects. Abandoned Project Rehabilitation Division.
National Housing Department (2015). Abandoned housing projects by state until 30
June 2015. Ministry of Urban Wellbeing, Housing and Local Government
selected statistics until 30 June 2015. Retrieved form
www.kpkt.gov.my/Buku _Perangkaan_30Jun2015.
National Housing Department (2015). Abandoned housing projects in peninsular
Malaysia (January 2009 to 2015). Abandoned Project Rehabilitation
Division.
Ng, L .F. (2007). Determinant factors of implementing build then sell in Malaysia:
Housing developers point of view. MSc diss. Universiti Sains Malaysia, Pulau
Pinang, Malaysia.
Norharnila, R. (2006). Salah urus risiko dalam projek pembangunan projek
perumahan: kajian keatas projek perumahan terbengkalai di Malaysia
.Master’s thesis, Universiti Teknologi Malaysia. Retrieved August 12, 2010
fromhttp://eprints.utm.my/4601/1/NorharnilaRusliKPFKA2006TTT.pdf
136
Nuarrual Hilal, M. D. (2001). Projek Perumahan Terbengkalai: Fenomena, Masalah
dan Penyelesaian - Satu Kajian Kes di Daerah Timur Laut, Pulau Pinang.
Unpublished Master Dissertation, Universiti Kebangsaan Malaysia, Kuala
Lumpur.
Nuarrual Hilal, M. D. (2008a). Abandoned Housing Projects In Malaysia-An
Introduction. College of Law, Government and International Studies
(COLGIS), Universiti Utara Malaysia. Retrieved July 26, 2010 from
http://nuarrualhilal.wordpress.com/2008/09/05/abandoned-housing-projects-
in-malaysia-an-introduction/
Nuarrual Hilal, M. D. (2008b). Abandoned Housing Projects In Peninsular
Malaysia: Problems And Suggestions. College of Law, Government and
International Studies, Universiti Utara Malaysia. Retrieved July 26, 2010
fromhttp://nuarrualhilal.wordpress.com/2008/09/09/abandoned-housing
projects-the-problem/
Nuarrual Hilal, M. D. (2008c). New Research Findings on the Legal Meaning of
‘Housing Developer’ and ‘Housing Development’ in Peninsular Malaysia.
College of Law, Government and International Studies, Universiti Utara
Malaysia.RetrievedJuly26,2010fromhttp://nuarrualhilal.wordpress.com/2008/
11/05/new-research-findings-on-the-legal-meaning-of-‘housing developer’-
and-‘housing-development
Nuarrual Hilal, M. D. (2009). Is The Statutory Standard Sale And Purchase of
Housing Accommodation Agreement (Schedules G, H, I and J) In Peninsular
Malaysia Compatible With Islamic Law? Part 4. Retrieved July 26, 2010
from http://nuarrualhilal.wordpress.com/2009/03/31/is-the-statutory-standard-
sale-and-purchase-of-housing-accommodationagreement-schedules-g-h-i-
and-j-in-peninsular-malaysia-compatible-with-islamic-law-part-4/
Nuarrual Hilal, M. D. (2011). Legal Issues in the Rehabilitation of Abandoned
HousingProjects of the Liquidated Housing-Developer-Companies in
Peninsular Malaysia. European Journal of Social Sciences – Volume 23,
Number 3 (2011) 392.
Nuarrual Hilal, M. D. & Sharifah Zubaidah, S. A. D. (2012). Rehabilitation of
abandoned housing projects of liquidated housing-developer-companies: A
137
comparative legal analysis between the position in Malaysia and in the United
Kingdom. Malayan Law Journal, 4 (2012). pp. 1-22. ISSN 0025-1283
Nuarrual Hilal, M. D. (2013). Issues on Remedies for Aggrieved Purchasers in
Abandoned Housing Projects in Malaysia: Time and Manner for Delivery for
Vacant Possession. In: 1st International Conference on Innovation and
Sustainability (ICOIS 2013), 3-4 April 2013, Sunway Resort Hotel & Spa
Kuala Lumpur, Malaysia. Official URL: http://www.icois2013.uum.edu.my/
(Unpublished).
Odeyinka, H. A. and Yusif, A. (1997). “The causes and effects of construction delays
on completion cost of housing projects in Nigeria,” Journal of Financial
Management of Property and Construction, vol. 2, no. 3, pp. 31–44, 1997.
Olalusi, O. and Otunola, A. (2012). Abandonment of Building Projects in Nigeria-
Review of Causes and Solutions. International Conference on Chemical, Civil
and Environment Engineering (C.C.E.E) Dubai.
Omoniyi, M. I. (1996). A critical analysis of abandonment projects. Journal of
Building Science and Management. 11 (1), 4-10.
Ong, K. C. (2009). Ministry of Housing and Local Government. No More Abandoned
Housing Projects. Retrieved July 23, 2010 from
http://www.hba.org.my/news/2009/01/ka_chuan.htm
Onikute, A. B. (1988). Effects of Contract termination on the cost of building
project. Builders Magazine 5, 15 – 18.
Open University Malaysia (2006). Business Research Method. Meteor Doc. Sdn.
Bhd., Selangor. Fifth printing, January 2006.
Oppenheim, A. N. (1983). Questionnaire Design and Attitude Measurement.
Heineman, London.
Osemenan, I. (1987). Project Abandonment; New Watch Magazine, Vol. 1, pp. 15.
Owston, R. (2007). Contextual factors that sustain innovative pedagogical practice
using technology: an international study. Journal of Educational Change,
8(1), 61-77. doi:10.1007/s10833-006-9006-6
Pemudah (2007). Official Portal of Pemudah. The Special Task Force to Facilitate
Business.Retrievedfromhttp://www.pemudah.gov.my/background1/19/02/201
6.
Perry, J. G. and Hayes, R. W. (1985). Construction Project—Know the Risks.
138
Chartered Mechanical Engineer, 1985.
Perumal, E. (2009, July 22). Builder seeks Hishamuddin‟s help to revive
project.TheStarOnline.RetrievedDecember20,2009,from http://thestar.com.m
y/metro/story.asp?file=/2009/7/22/central/4356570&sec=central
Phuah, K. L. (2009, December 14). Recreational pond for tourists. NST Online.
Retrieved:December20,2009,fromhttp://www.nst.com.my/articles/13pnd/Arti
cle/index_html
Portal Rasmi Jabatan Perumahan Negara (2015). Kementerian Kejahteraan Bandar,
Perumahan dan Kerajaan Tempatan. Projek perumahan terbengkalai.
Retrieved from http://ehome.kpkt.gov.my/index.php/pages/view/244
Real Estate and Housing Developers’ Association (REDHA) (2008). Mitigating the
Global Economic Crisis-Faster Strata Titles. REHDA Bulletin December
2008, pp9309/12/2008(020070). Retrieved August 12, 2010 from
http://www.rehda.com/bulletin/08/bulletin-0812.pdf/
Rossi, P. H., Wright, J. D. and Anderson, A. B. (1983). Handbook of Survey
Research. Academic Press, NewYork.
Sambasivan, M. and Yau, W. S. (2006). Causes and effects of delays in Malaysian
construction industry. Graduate School of Management, Universiti Putra
Malaysia, 43400 UPM, Serdang Selangor, Malaysia. Received 21 April 2006;
received in revised form 27 June 2006; accepted 21 November 2006.
International Journal of Project Management Volume 25, Issue 5 July 2007,
pages 517–526.
Sanjugtha, V. (2013, April 13). White Knights Galloping in. FucusM – Realty &
Retail. April 13-19, 2013, Page 30.
Sekaran, U. (2003). Research Methods for Business: A Skill Building Approach, 4th
(eds), John Wiley and Sons, Inc, New York.
Setterfield, M. (1997). Abandoned Buildings: Models for Legislative & Enforcement
Reform. Trinity College·Hartford, CT 06106·(860)297-2132, Trinity Center
for Neighborhoods, 190 New Britain Avenue, Hartford, CT 06106-3100
(860)297-5170.
Sharen, K. (2011). Proposals to reduce number of abandoned housing projects,
[email protected]. New Straits Times, 2011/02/19.Retrieved from
139
http://www.pemudah.gov.my/proposals-to-reduce-number-of-abandoned
housing-projects, 16/01/2016.
Stewart, C. J. and Cash, W. B. Jr. (2008). Interviewing: Principles and Practices.
12th
ed., New York: Irwin/McGraw-Hill; (February 1, 2008).
Stuart, M. (2009, March 31). Abandoned project poses risks. The Star Online.
Retrieve:December20,2009,fromhttp://thestar.com.my/metro/story.asp?file=/
2009/3/31/central/3568336&sec=central
Swanson, R. A. (2013). Theory Building in Applied Disciplines. San Francisco, CA:
Berrett-Koehler Publishers 2013.
Syafril Idzwan, A. K. (2008). Kajian Lanjutan Perlaksanaan Konsep Win-Win
Dalam Menangani Masalah Perumahan Terbengkalai di Malaysia. Fakulty
Kejuruteraan Awam, University Teknologi Malaysia, April 2008.
Tan, C. and Rajendra, E. (2009, November 12). Selangor releases “secret”
documents to the public. The Star Online. Retrieved December 20, 2009,
from
http://thestar.com.my/news/story.asp?file=/2009/11/12/parliament/5096611&
sec=parliament
Tayib, M. (1998). The Determinants of Assessment Tax Collection: The Malaysian
Local Authority Experience. PhD Thesis, University of Glamorgan.
Unpublished.
The Star (2003, October 14). Five projects to be revived. Five of the 14 abandoned
housing projects in Penang will be revived by Syarikat Perumahan Negara
Bhd (SPNB). The Star.
The Star Special (2007). Bold changes improve efficiency of country’s delivery
system,14/04/2007,Thestar.Retrievedfromhttp://www.hba.org.my/news/2007/
407/bold_changes.htm on 16/02/2016.
The Star (2014, April 03). Stiffer Penalties in Store for Builders who Abandon
Projects. (April 3, 2014). The Star, p 22.
The Star Online (2014, May 26). Errant Developers Face Jail and RM500,000 Fine.
The Star Online. Published: Monday, May 26,
2014.Retrievedfromhttp://www.thestar.com.my/News/Nation/2014/05/2.
140
The Sun (2006, April 13). Still Hope for Abandoned Projects. Retrieved
April18,2015fromhttp://aplikasi.kpkt.gov.my/akhbar.nsf/8521d968204e8b45
4825697400224ca6/8d38c5bb83d734f648257150000a5d8d?OpenDocument
The sun daily (2015). Rahman Dahlan: 165 abandoned housing projects recovered
since 2009. Posted on 21 May 2015. Retrieved
from http://www.thesundaily.my/news/1426477/,17/02/2016.
Toor, S. U. R. and Ogunlana, S. O. (2008). “Problems causing delays in major
construction projects in Thailand”. Journal on Construction Management
and Economics, vol. 26, issue no. 4, pp. 395–408, April 2008.
Tufte, E. R. (1997). Envisioning information. Cheshire, CY: Graphics Press.
Twumasi-Ampofo, K., Osei-Tutu, E., Decardi-Nelson, I. and Ofori, A. (2014). A
Model for Reactivating Abandoned Public Housing Projects in Ghana. Civil
and Environmental Research, Building and Road Research Institute, UPO
Box 40, KNUST, Kumasi-Ghana, ISSN 2224-5790 (Paper) ISSN 2225-0514
(Online) Vol.6, No.3, 2014.
UKEssays (2016). Construction/prevention of abandoned housing projects.
RetrievedFormhttp://www.ukessays.com/essays/construction/prevention-of-
abandoned-housing-projects.php/Retrieved on 5/2/2016.
Utusan Malaysia (2004). Rumah terbengkalai satu masalah, August 8, 2004.
Yap, E. H. and Tan, H. C. (2009).Abandoned Projects in Malaysia – A Preliminary
Study of the Causes. University of Tunku Abdul Rahman, Malaysia.
Yap, E. H., (2013). Causes of Abandoned Construction Projects in Malaysia. A
thesis submitted in the Department of Surveying, Faculty of Engineering and
Science, University of Tunku Abdul Rahman. Degree of Master of Science in
Construction Management, May 2013.
Yip, Y. T. (2009a, March 3). Kayu Ara needs an urgent facelift. The Star Online.
Retrieved:December20,2009,fromhttp://thestar.com.my/metro/story.asp?file=
/2009/3/3/central/3370657&sec=central
Yip, Y. T. (2009b, March 11). Double blow for businessman. The Star Online.
Retrieved:December20,2009,fromhttp://thestar.com.my/metro/story.asp?file=
/2009/3/11/central/3427511&sec=central
Zaherawati, Z., Zaliha, H., Nazni, N. and Mohd Zoolhilmie, M. S. (2010). Financial
Crisis of 1997/1998 in Malaysia: Causes, Impacts and Recovery Plans.
141
University of MARA Technology. Voice of Academia, Vol.5 No.1 2010.
Zairul M, M. N. and Rahinah, I. (2008). Abandoned Housing Projects in Malaysia:
Proposal For Promoting The BTS (Build Then Sell) Concept For Malaysian
Housing Development. Department of Architecture, Faculty of Design &
Architecture, Universiti Putra Malaysia, Serdang, Selangor, Malaysia.