Transcript of A short story about Earned Value Management
Performance = Earned Value / Cost
$1,000 / $2,000 = 0.5
Forecast = Budget / Performance
$10,000 / 0.5 = $20,000
Performance = Earned Value / Cost
$5,000 / $6,000 = 0.833
Forecast = Budget / Performance
$10,000 / 0.833 = $12,000