A REPORT TO FORTRESS MUNIR 2013 INC. A SOIL … · A REPORT TO FORTRESS MUNIR 2013 INC. A SOIL...
Transcript of A REPORT TO FORTRESS MUNIR 2013 INC. A SOIL … · A REPORT TO FORTRESS MUNIR 2013 INC. A SOIL...
A REPORT TO FORTRESS MUNIR 2013 INC.
A SOIL INVESTIGATION FOR
PROPOSED TOWNHOUSE DEVELOPMENT (PHASE 2)
2055 BROCK ROAD
CITY OF PICKERING
REFERENCE NO. 1603-S066
JULY 2016
DISTRIBUTION 2 Copies - Kohn Partnership Architects Inc. 1 Copy - Fortress Munir 2013 Inc. 1 Copy - Soil Engineers Ltd. (Oshawa) 1 Copy - Soil Engineers Ltd. (Toronto)
Reference No. 1603-S066 ii TABLE OF CONTENTS
1.0 INTRODUCTION ...................................................................................... 1
2.0 SITE AND PROJECT DESCRIPTION ..................................................... 2
3.0 FIELD WORK ............................................................................................ 3
4.0 SUBSURFACE CONDITIONS ................................................................. 4
4.1 Topsoil.................................................................................................. 4 4.2 Silty Clay .............................................................................................. 5 4.3 Silty Clay Till ....................................................................................... 7 4.4 Silty Fine Sand ..................................................................................... 9 4.5 Fine to Coarse Sand .............................................................................. 11 4.6 Compaction Characteristics of the Revealed Soils .............................. 12
5.0 GROUNDWATER CONDITIONS ........................................................... 15
6.0 DISCUSSION AND RECOMMENDATIONS ........................................ 17
6.1 Foundations .......................................................................................... 19 6.2 Garages, Driveways and Landscaping ................................................. 22 6.3 Underground Services .......................................................................... 22 6.4 Trench Backfilling ................................................................................ 24 6.5 Pavement Design .................................................................................. 26 6.6 Soil Parameters ..................................................................................... 27 6.7 Preloading Scheme ............................................................................... 28 6.8 Excavation ............................................................................................ 28
7.0 LIMITATIONS OF REPORT .................................................................... 31
Reference No. 1603-S066 iii
TABLES
Table 1 - Estimated Water Content for Compaction ..................................... 12
Table 2 - Groundwater Levels ....................................................................... 15
Table 3 - Pavement Design ............................................................................ 26
Table 4 - Soil Parameters ............................................................................... 28
Table 5 - Classification of Soils for Excavation ............................................ 29
ENCLOSURES Borehole Logs ...................................................................... Figures 1 to 7 Grain Size Distribution Graphs ........................................... Figures 8 to 10 Borehole Location Plan ....................................................... Drawing No. 1 Subsurface Profile ................................................................ Drawing No. 2
Reference No. 1603-S066 1
1.0 INTRODUCTION
In accordance with written authorization dated March 17, 2016, from
Mr. Vince Petrozza, of Fortress Munir 2013 Inc., a soil investigation was carried
out at 2055 Brock Road, in the City of Pickering, for a proposed Townhouse
Development (Phase 2).
The purpose of the investigation was to reveal the subsurface conditions and to
determine the engineering properties of the disclosed soils for the design and
construction of the proposed project.
The geotechnical findings and resulting recommendations are presented in this
Report.
Reference No. 1603-S066 2
2.0 SITE AND PROJECT DESCRIPTION
The Town of Pickering is situated on Iroquois (glacial lake) plain where, in places,
the glacial till stratigraphy has been partly eroded by the water action of the glacial
lake and filled with lacustrine sands, silts, clays and reworked till.
The subject site is situated at the northeast sector of Finch Avenue and Brock Road,
in the City of Pickering. The investigated area is a weed-covered open field. The
ground surface is relatively flat and level, with minor undulations.
The proposed project consists of the construction of new townhouses, the new
development will be provided with municipal services, landscaped areas, roadways
and paved areas meeting municipal standards.
Reference No. 1603-S066 3
3.0 FIELD WORK
The field work, consisting of 7 boreholes to depths ranging from 6.6 to 9.6 m, was
performed on April 18, 2016, at the locations shown on the Borehole Location Plan,
Drawing No. 1, enclosed.
The holes were advanced at intervals to the sampling depths by track-mounted,
continuous-flight power-auger machines equipped for soil sampling. Standard
Penetration Tests, using the procedures described on the enclosed “List of
Abbreviations and Terms”, were performed at the sampling depths. The test results
are recorded as the Standard Penetration Resistance (or ‘N’ values) of the subsoil.
The relative density of the granular strata and the consistency of the cohesive strata
are inferred from the ‘N’ values. Split-spoon samples were recovered for soil
classification and laboratory testing.
In situ vane shear and remoulded vane shear tests were performed using a four-
bladed vane with dimensions of 51 mm in diameter and 150 mm in length. The
tests determine the undrained shear strength of the cohesive soil, and ratio of the
values of the undisturbed and remoulded shear strengths indicates the sensitivity of
the soil.
The field work was supervised and the findings recorded by a Geotechnical
Technician.
The geodetic elevation at each of the borehole locations was obtained by Soil
Engineers Ltd. using a hand-held Global Navigation Satellite System (GNSS)
surveying equipment (Trimble Geoexplorer 6000) having an accuracy of 0.1 m.
Reference No. 1603-S066 4
4.0 SUBSURFACE CONDITIONS
Detailed descriptions of the encountered subsurface conditions are presented on the
Borehole Logs, comprising Figures 1 to 7, inclusive. The revealed stratigraphy is
plotted on the Subsurface Profile, Drawing No. 2, and the engineering properties of
the disclosed soils are discussed herein.
This investigation has disclosed that beneath a veneer of topsoil, the site is
underlain by strata of silty clay, silty clay till, silty fine sand and fine to coarse sand
at various depths and locations.
4.1 Topsoil (All Boreholes)
The revealed topsoil ranges from 20 to 61 cm thick. It is dark brown in colour,
indicating that it contains appreciable amounts of roots and humus. These materials
are unstable and compressible under loads; therefore, the topsoil is considered to be
void of engineering value. Due to its humus content, it may produce volatile gases
and generate an offensive odour under anaerobic conditions. Therefore, the topsoil
must not be buried below any structures or deeper than 1.2 m below the finished
grade, so that it will not have an adverse impact on the environmental well-being of
the developed areas.
Since the topsoil is considered void of engineering value, it can only be used for
general landscaping and landscape contouring purposes. A fertility analysis can
determine the suitability of the topsoil as a planting material.
Reference No. 1603-S066 5
4.2 Silty Clay (All Boreholes)
The silty clay was found to dominate the revealed soil stratigraphy. The clay was
encountered below a layer of silty fine sand and extends to the maximum
investigated depth at Borehole 2. It is laminated with sand and silt seams and
layers, showing it is a lacustrine deposit. The sand and silt seams and layers are
generally wet.
The clay within a depth of 1.5± to 2.0± m from the prevailing ground surface has
generally been weathered.
The obtained ‘N’ values range from weight of hammer to 16, with a median of
4 blows per 30 cm of penetration, indicating that the consistency of the clay is very
soft to stiff, being generally soft. Eighteen in situ shear vane tests were performed
on the very soft to soft clay (with ‘N’ values ranging from weight of hammer to 4).
The obtained shear strength values range from 21.5 to 120 kPa. The sensitivity of
the clay, as assessed by the remoulded shear strength, ranges from 2.8 to 10,
showing that the sensitivity to remoulding of the clay is medium sensitive to
slightly quick.
The Atterberg Limits of 3 representative samples and the water content values of all
of the samples were determined. The results are plotted on the Borehole Logs and
summarized below:
Liquid Limit 33%, 40% and 42%
Plastic Limit 18%, 19% and 21%
Natural Water Content 21% to 41% (median 26%)
Reference No. 1603-S066 6
The above results show that the clay is a cohesive material with medium plasticity.
The natural water content values generally lie above its plastic limits and below its
liquid limits.
Grain size analyses were performed on 3 representative samples; the results are
plotted on Figure 8.
According to the above findings, the following engineering properties are deduced:
• High frost susceptibility and, due to the high silt content and high moisture
content, it has a high soil-adfreezing potential.
• Low water erodibility.
• Practically impermeable, with an estimated coefficient of permeability of
10-7 cm/sec, an estimated percolation rate of over 80 min/cm, and runoff
coefficients of:
Slope
0% - 2% 0.15
2% - 6% 0.20
6% + 0.28
• A cohesive soil, its shear strength is primarily derived from its consistency
which is inversely dependent on soil moisture.
• The very soft to soft clay is highly susceptible to consolidation under surcharge
loads.
• In steep cuts, the very soft to soft clay will slough readily, and a cut face in the
sound clay may collapse as the wet silt slowly sloughs.
• Bottom heaving will occur in trenches cut steeply into the very soft to soft silty
clay. Therefore, the spoil from the excavations should be placed at a
Reference No. 1603-S066 7
distance from the edge of the excavation at least equal to 3 times the height of
the excavation, and the sides should be cut at 1 vertical:3 + horizontal.
• A very poor material to support flexible pavement, with an estimated
California Bearing Ratio (CBR) value of 3% or less.
• Moderately high corrosivity to buried metal, with an estimated electrical
resistivity of 2500 ohm⋅cm.
4.3 Silty Clay Till (All Boreholes, except Borehole 2)
The silty clay till was found beneath a stratum of silty clay and extends to the
maximum investigated depth at Boreholes 1, 3, 4, 5 and 7. It consists of a random
mixture of soils; the particle sizes range from clay to gravel, with the clay fraction
exerting the dominant influence on its soil properties. Occasional sand and silt
seams and layers were also detected in the clay till mantle. The till is
heterogeneous in structure, indicating that it is a glacial deposit.
The obtained ‘N’ values range from weight of hammer to 60 blows per 15 cm, with
a median of 33 blows per 30 cm of penetration, indicating that the consistency of
the clay is very soft to hard, being generally hard.
Hard resistance was encountered during augering, showing that the till is embedded
with cobbles and boulders.
The Atterberg Limits of 1 representative sample and the natural water content
values of all the samples were determined; the results are plotted on the Borehole
Logs and summarized below:
Reference No. 1603-S066 8
Liquid Limit 28%
Plastic Limit 16%
Natural Water Content 6% to 24% (median 8%)
The results show that the clay till is a cohesive material with low plasticity. The
natural water content values generally lie below its plastic and liquid limits,
confirming the generally hard consistency of the till as determined by the ‘N’
values.
A grain size analysis was performed on 1 representative sample of the silty clay till.
The result is plotted on Figure 9.
Based on the findings, the engineering properties related to the project are as
follows:
• High frost susceptibility, with low water erodibility.
• Low permeability, with an estimated coefficient of permeability of
10-7 cm/sec, with an estimated percolation rate of 80 min/cm, and runoff
coefficients of:
Slope
0% - 2% 0.15
2% - 6% 0.20
6% + 0.28
• A cohesive soil, its shear strength is primarily derived from consistency
which is inversely related to its moisture content. It contains sand; therefore,
its shear strength is augmented by internal friction.
• The very soft clay till is highly susceptible to consolidation under surcharge
loads.
Reference No. 1603-S066 9
• It will generally be stable in a relatively steep cut in the stiff to hard till;
however, prolonged exposure will allow the fissures in the weathered zone
and the wet sand and silt seams and layers to become saturated, which may
lead to localized sloughing.
• Bottom heaving will occur in trenches cut steeply into the very soft to soft
silty clay till. Therefore, the spoil from the excavations should be placed at a
distance from the edge of the excavation at least equal to 3 times the height
of the excavation, and the sides should be cut at 1 vertical:3 + horizontal.
• A very poor pavement-supportive material, with an estimated CBR value of
3% or less.
• Moderately high corrosivity to buried metal, with an estimated electrical
resistivity of 3500 ohm⋅cm.
4.4 Silty Fine Sand (All Boreholes)
The silty fine sand deposit was encountered below a veneer of topsoil and overlying
a stratum of silty clay. Sample examinations show that it is non-cohesive and is
embedded with silt seams. The laminated structure shows the deposit was derived
from a lacustrine environment. The silty fine sand layer is weathered.
The obtained ‘N’ values range from weight of hammer to 5, with a median of
2 blows per 30 cm of penetration; therefore, the relative density of the sand is very
loose to loose, being generally very loose.
The natural water content was determined and the results are plotted on the
Borehole Logs. The values range from 12% to 25%, with a median of 20%,
showing that the sand deposit is in a wet condition. The wet samples are water
bearing and displayed appreciable dilatancy when shaken by hand.
Reference No. 1603-S066 10
A grain size analysis was performed on 1 representative sample of the silty fine
sand; the result is plotted on Figure 10.
Accordingly, the following engineering properties are deduced:
• Highly frost susceptible with high soil-adfreezing potential.
• Highly water erodible.
• Relatively pervious, with an estimated coefficient of permeability of
10-3 cm/sec, an estimated percolation rate of 30 min/cm, and runoff
coefficients of:
Slope
0% - 2% 0.04
2% - 6% 0.09
6% + 0.13
• A frictional soil, its shear strength is derived from internal friction and is
density dependent. Due to its dilatancy, the shear strength of the wet sand is
susceptible to impact disturbance; i.e., the disturbance will induce a build-up
of pore pressure within the soil mantle, resulting in soil dilation and a
reduction of shear strength.
• In relatively steep cuts, the sand will be stable in a damp to moist condition,
but will slough if it is wet and run with water seepage. The bottom will boil
under a piezometric head of 0.3 m.
• A fair material to support pavement, with an estimated CBR value of at least
8%.
• Moderately low corrosivity to buried metal, with an estimated electrical
resistivity of 5000 ohm·cm.
Reference No. 1603-S066 11
4.5 Fine to Coarse Sand (Borehole 6)
The fine to coarse sand was encountered below a stratum of silty clay till and
extends to the maximum investigated depth. It is well-graded, with some silt and a
trace of gravel.
The obtained ‘N’ value is 50 blows per 15 cm of penetration, indicating that the
relative density of the sand is very dense.
The natural water content value of the sample was determined, and the result is
plotted on the Borehole Log; the value is 10%, showing the sand is in a wet
condition. Due to the pervious nature of the sand, some of the water may have
drained during sampling, and the determined value may not represent the actual
water content of the deposit. The wet sand sample is water bearing.
The deduced engineering properties pertaining to the project are given below:
• Low frost susceptibility and high water erodibility.
• Pervious, with an estimated coefficient of permeability of 10-3 cm/sec, an
estimated percolation rate of about 10 min/cm, and runoff coefficients of:
Slope
0% - 2% 0.04
2% - 6% 0.09
6% + 0.13
• A frictional soil, its shear strength is derived from internal friction and is soil
density dependent.
• In relatively steep cuts, the sand will be stable in a damp to moist condition,
but will slough if it is wet and run with water seepage. The bottom will boil
under a piezometric head of 0.3 m.
Reference No. 1603-S066 12
• A fair to good pavement-supportive material, with an estimated CBR value
of 20% to 30%.
• Low corrosivity to buried metal, with an estimated electrical resistivity of
6500 ohm·cm.
4.6 Compaction Characteristics of the Revealed Soils
The obtainable degree of compaction is primarily dependent on the soil moisture and,
to a lesser extent, on the type of compactor used and the effort applied. As a general
guide, the typical water content values of the revealed soils for Standard Proctor
compaction are presented in Table 1.
Table 1 - Estimated Water Content for Compaction
Soil Type
Determined Natural Water Content (%)
Water Content (%) for Standard Proctor Compaction
100% (optimum) Range for 95% or +
Silty Clay 21 to 41 (median 26) 21 and 22 17 to 27
Silty Clay Till 6 to 24 (median 8) 16 12 to 21
Silty Fine Sand 12 to 25 (median 20) 11 6 to 16
Fine to Coarse Sand 10 10 5 to 15
Based on the above findings, the majority of the silty clay till and some of the silty
clay and fine to coarse sand are generally suitable for a 95% or + Standard Proctor
compaction; however, the silty fine sand and the major portion of the silty clay are
too wet and will require aeration prior to structural compaction. Some of the silty
clay till is too dry and will require the addition of water prior to structural
compaction.
Reference No. 1603-S066 13
The silty clay and silty clay till should be compacted using a heavy-weight,
kneading-type roller. The sands can be compacted by a smooth roller with or
without vibration, depending on the water content of the soils being compacted.
The lifts for compaction should be limited to 20 cm, or to a suitable thickness as
assessed by test strips performed by the equipment which will be used at the time of
construction.
When compacting the very stiff to hard silty clay till on the dry side of the optimum,
the compactive energy will frequently bridge over the chunks in the soils and be
transmitted laterally into the soil mantle. Therefore, the lifts of these soils must be
limited to 20 cm or less (before compaction). It is difficult to monitor the lifts of
backfill placed in deep trenches; therefore, it is preferable that the compaction of
backfill at depths over 1.0 m below the road subgrade be carried out on the wet side
of the optimum. This would allow a wider latitude of lift thickness. Wetting of the
sound till will be necessary to achieve this requirement.
One should be aware that with considerable effort, a 90%± Standard Proctor
compaction of the wet sand is achievable. Further densification is prevented by the
pore pressure induced by the compactive effort; however, large random voids will
have been expelled, and with time the pore pressure will dissipate and the
percentage of compaction will increase. There are many cases on record where
after a few months of rest, the density of the compacted mantle has increased to
over 95% of its maximum Standard Proctor dry density.
If the compaction of the soils is carried out with the water content within the range
for 95% Standard Proctor dry density but on the wet side of the optimum, the
surface of the compacted soil mantle will roll under the dynamic compactive load.
This is unsuitable for pavement construction since each component of the pavement
Reference No. 1603-S066 14
structure is to be placed under dynamic conditions which will induce the rolling
action of the subgrade surface and cause structural failure of the new pavement.
The foundation or bedding of the sewer and slab-on-grade will be placed on a
subgrade which will not be subjected to impact loads. Therefore, the structurally
compacted soil mantle with the water content on the wet side or dry side of the
optimum will provide an adequate subgrade for the construction.
The presence of boulders in the silty clay till will prevent transmission of the
compactive energy into the underlying material to be compacted. If an appreciable
amount of boulders over 15 cm in size is mixed with the material, it must either be
sorted or must not be used for structural backfill.
Reference No. 1603-S066 15
5.0 GROUNDWATER CONDITIONS
Groundwater seepage encountered during augering was recorded on the field logs.
The boreholes were checked for the presence of groundwater and the occurrence of
cave-in upon their completion. The data are plotted on the Borehole Logs and
summarized in Table 2.
Table 2 - Groundwater Levels
BH No. Borehole
Depth (m)
Soil Colour Changes Brown to
Grey
Seepage Encountered
During Augering
Measured Groundwater/ Cave-In* Level On Completion
Depth (m) Depth (m) Amount Depth (m) El. (m)
1 9.6 4.5 0.5 Some 1.2* 89.5*
2 6.7 3.0 0.5 Some 1.2* 88.6*
3 9.3 3.0 0.5 Some 6.4 82.1
4 6.7 3.0 0.5 Some 4.6 83.6
5 6.7 4.5 0.5 Some 0.5 86.5
6 9.5 3.0 0.5 Some 1.2/8.7* 87.6/80.1*
7 6.6 3.0 0.7 Some 1.2 88.7 * Cave-in level (In wet sand and silt, the level generally represents the groundwater regime at the borehole location at the time of investigation.)
Groundwater was detected at depths ranging from 0.5 to 6.4 m; cave-in was
detected at depths of 1.2 m and 8.7 m below the prevailing ground surface.
Groundwater will fluctuate with the seasons and the measured levels generally
represent the groundwater regime at the time of the investigation.
Reference No. 1603-S066 16
The soil colour changes from brown to grey at depths of 3.0 m and 4.5 m below the
prevailing ground surface; the brown colour indicates that the soils have oxidized
and the groundwater will fluctuate with the seasons.
The groundwater yield from the silty clay and silty clay till, due to their low
permeability, will be small and limited in quantity. The groundwater yield from the
sands is expected to be appreciable and likely persistent.
Reference No. 1603-S066 17
6.0 DISCUSSION AND RECOMMENDATIONS
This investigation has disclosed that beneath a veneer of topsoil, the site is
underlain by strata of very soft to stiff, generally soft silty clay; very soft to hard,
generally hard silty clay till; very loose to loose, generally loose silty fine sand and
very dense fine to coarse sand at various depths and locations. The surficial native
soil layer is weathered to depths of 1.5± to 2.0± m below the prevailing ground
surface.
Groundwater was detected at depths ranging from 0.5 to 6.4 m; cave-in was
detected at depths of 1.2 m and 8.7 m below the prevailing ground surface.
Groundwater will fluctuate with the seasons and the measured levels generally
represent the groundwater regime at the time of the investigation.
The groundwater yield from the silty clay and silty clay till, due to their low
permeability, will be small and limited in quantity. The groundwater yield from the
sands is expected to be appreciable and likely persistent.
The geotechnical findings which warrant special consideration are presented below:
1. The topsoil is highly compressible and will generate volatile gases under
anaerobic conditions, and it is not suitable for engineering applications.
Therefore, the topsoil should be placed in the landscaped areas only and
should not be buried below any structures, or deeper than 1.2 m below the
exterior finished grade of the project.
2. The building site is underlain by a deposit of very soft to soft silty clay that
extends from depths of 1.5 m or 3.0 m to approximately 7.3± m below the
prevailing ground surface. The very soft to soft clay is only suitable to
support lightly loaded foundations. As a result, a raft foundation can be
Reference No. 1603-S066 18
used to support the building loads. A compacted granular base, 500 mm
thick, can be placed for the raft foundation. In this case, the site needs to
be preloaded. Alternatively, the proposed building foundations can also be
supported by Helical Piles extending into the very stiff to hard silty clay till
stratum, at depths of over 7 m below the prevailing ground surface. In this
case, deeper boreholes will be necessary.
3. The underlying very soft to soft clay and clay till will consolidate under
surcharge loads. If the site grade will be raised or if a raft foundation is
considered, the site will have to be pre-loaded and the ground settlement
should be monitored for at least 9 to 18 months prior to any construction.
This can be determined by the installation and monitoring of settlement
plates. The required surcharge load for the pre-loading program can be
determined once the site grading and townhouse sitings and their loadings
are available.
4. For slab-on-grade construction, any weathered, soft or loose soils, should
be subexcavated, aerated and properly compacted prior to the placement of
the slab. Any new material for raising the grade should consist of organic-
free soil compacted to at least 98% of its maximum Standard Proctor dry
density. The slab should be constructed on a granular base, 20 cm thick,
consisting of 20-mm Crusher-Run Limestone, or equivalent, compacted to
its maximum Standard Proctor dry density.
5. For services constructed in saturated soils, the pipe joints should be leak-
proof or wrapped with a waterproof membrane. A Class ‘B’ bedding is
recommended and it should consist of 19-mm Crusher-Run (graded)
Limestone. Where extensive dewatering is necessary, a Class ‘A’ bedding
consisting of concrete may be required. In the very soft to soft clay, the
bedding must be thickened and/or a Class ‘A’ bedding can be considered.
Reference No. 1603-S066 19
In extreme cases, concrete cradles supported by piles to refusal may be
necessary.
6. The in situ soils with high silt content are considered to be high in soil-
adfreezing potential; therefore, the foundation walls or the perimeter grade
beams must be either backfilled with non-frost-susceptible pit-run granular,
or shielded with a polyethylene slip-membrane.
7. Excavation into the silty clay till containing boulders will require extra effort
and the use of a heavy-duty backhoe equipped with a rock-ripper. Boulders
larger than 15 cm in size are not suitable for structural backfill.
8. Bottom heaving will occur in trenches cut steeply into the very soft to soft
clay. Therefore, the sides should be cut at 1 vertical:3 or + horizontal and
the spoil from the excavation must be placed at a distance from the edges of
the excavation and/or trenches equal to 3 times the depth of the excavation.
Alternatively, proper shoring by sheeting will be necessary.
The recommendations appropriate for the project described in Section 2.0 are
presented herein. One must be aware that the subsurface conditions may vary
between boreholes. Should this become apparent during construction, a
geotechnical engineer must be consulted to determine whether the following
recommendations require revision.
6.1 Foundations
The borehole investigation has revealed that the building site is underlain by a
deposit of very soft to soft silty clay and silty clay till that extends from depths of
1.5 m or 3.0 m to approximately 7.3± m below the prevailing ground surface. The
soft soil is only suitable to support lightly loaded foundations. As a result, a raft
foundation designed with a Maximum Allowable Soil Pressure (SLS) of 30 kPa and
Reference No. 1603-S066 20
a Factored Ultimate Soil Bearing Pressure (ULS) of 50 kPa can be used to support
the building loads. A compacted granular base, 500 mm thick, can be placed for
the raft foundation.
Alternatively, the proposed building foundations can also be supported by Helical
Piles extending into the very stiff to hard silty clay till stratum, at depths of over
7 m below the prevailing ground surface. In this case, deeper boreholes will be
necessary.
The load carried by the Helical Piles is directly related to the installation torque of
the pile anchor in the underlying competent soil stratum. The founding elevations,
design loads and number of Helical Piles should be determined by the prospective
Helical Piles Foundation Systems contractor.
The recommended soil pressure (SLS) for raft foundation incorporates a safety
factor of 3. The total and differential settlements of the foundation are estimated to
be 40 mm and 25 mm, respectively.
The foundations or grade beams exposed to weathering, and in unheated areas,
should be provided with at least 1.2 m of earth cover for protection against frost.
Due to the shallow groundwater encountered, it is recommended that the floor slab
be at least 0.5 m above the highest level of groundwater fluctuation.
Perimeter and under floor subdrains will be required. The subdrains should be
shielded by a fabric filter to prevent blockage by silting. These subdrains should
drain into a positive outlet or they should be connected to a sump-pit and drained
by pumping. A vapour barrier should be placed above the obvert of the subdrain to
Reference No. 1603-S066 21
prevent upfiltration of moisture from dampening the floor surface; the requirements
for this should be assessed at the time of footing construction.
Due to the presence of topsoil and weathered soil, the foundation subgrade must be
inspected by a geotechnical engineer, or a geotechnical technician under the
supervision of a geotechnical engineer, to assess its suitability for bearing the
designed foundations.
The foundation must meet the requirements specified in the latest Ontario Building
Code. As a guide, the structure should be designed to resist an earthquake force
using Site Classification ‘E’ (soft soil).
The in situ soils with high silt content are considered to be high in soil-adfreezing
potential; therefore, the foundation walls or the perimeter grade beams must be
either backfilled with non-frost-susceptible pit-run granular, or shielded with a
polyethylene slip-membrane.
Depending on site grading, where earth fill is required to raise the site or where raft
foundation is being used, the overburden will cause the underlying very soft to soft
clay to consolidate. Therefore, the foundation and project construction must not
commence prior to the completion of soil consolidation, which can be determined
by the monitoring of settlement plates. A preloading program will need to be
implemented prior to the project construction. The requirements for the preloading
program can be determined once the site grading and the townhouse sitings and
their loadings are available.
Reference No. 1603-S066 22
6.2 Garages, Driveways and Landscaping
As noted, the silty fine sand and silty clay are highly frost susceptible, thus, heaving
of the pavement is expected to occur during the cold weather.
The driveways at the entrances to the garages must be backfilled with non-frost-
susceptible granular material, with a frost taper at a slope of 1 vertical:1 horizontal.
The garage floor slab and the side of the foundation must be insulated with
50-mm Styrofoam, or equivalent.
The slab-on-grade in open areas should be designed to tolerate frost heave, and the
grading around the slab-on-grade must be such that it directs runoff away from the
surface.
Interlocking stone pavement and slab-on-grade to be constructed in areas
susceptible to ground movement must be constructed on a free-draining granular
base, at least 0.3 to 1.2 m thick, depending on the degree of tolerance to ground
movement, with proper drainage which will prevent water from ponding in the
granular base.
6.3 Underground Services
The subgrade for the underground services should consist of natural soils or
compacted organic-free earth fill. Where topsoil and badly weathered soils are
encountered, these materials must be subexcavated and replaced with properly
compacted bedding material. If earth fill is required to raise the site, a preloading
scheme will be necessary prior to underground services construction.
Reference No. 1603-S066 23
A Class ‘B’ bedding, consisting of compacted 20-mm Crusher-Run Limestone, is
recommended for the construction of the underground services. Where water-
bearing sand occurs, the sewer joints should be leak-proof, or wrapped with an
appropriate waterproof membrane to prevent subgrade migration. Where extensive
dewatering is necessary, a Class ‘A’ bedding consisting of concrete may be
required. This can be assessed by a geotechnical engineer during construction.
In areas where the subgrade consists of very soft clay, the granular bedding should
be thickened to at least 50 cm, or stone immersion techniques should be employed
to stabilize the base for sewer construction. If the recommended measures do not
succeed in stabilizing the subgrade, consideration should be given to supporting the
sewer on concrete cradles resting on piles driven to depths of refusal. The necessity
to implement this measure can best be determined by a geotechnical engineer when
the subgrade is exposed to inspection.
In order to prevent pipe floatation when the sewer trench is deluged with water, a
soil cover with a thickness equal to the diameter of the pipe should be in place at all
times after completion of the pipe installation.
Openings to subdrains and catch basins should be shielded with a fabric filter to
prevent blockage by silting.
Since the silty clay has moderately high corrosivity to buried metal, the water main
should be protected against corrosion. In determining the mode of protection, an
electrical resistivity of 2500 ohm·cm should be used. This, however, should be
confirmed by testing the soil along the water main alignment at the time of sewer
construction.
Reference No. 1603-S066 24
6.4 Trench Backfilling
The backfill in the trenches should be compacted to at least 95% of its maximum
Standard Proctor dry density and increased to 98% or + below the floor slab. In the
zone within 1.0 m below the pavement subgrade, the backfill should be compacted
to at least 98% of its maximum Standard Proctor dry density with the moisture
content 2% to 3% drier than the optimum. In the lower zone, a 95% or + Standard
Proctor compaction is considered to be adequate; however, the material must be
compacted on the wet side of the optimum.
Below the floor slab, the backfill must be compacted to 98% or + of its Standard
Proctor dry density.
In normal underground services construction practice, the problem areas of road
settlement largely occur adjacent to manholes, catch basins, services crossings,
foundation walls and columns, and it is recommended that a sand backfill be used.
Unless compaction of the backfill is carefully performed, the interface of the native
soils and the sand backfill will have to be flooded for a period of several days.
The narrow trenches should be cut at 1 vertical:2 or + horizontal so that the backfill
can be effectively compacted. Otherwise, soil arching will prevent the achievement
of proper compaction. The lift of each backfill layer should either be limited to a
thickness of 20 cm, or the thickness should be determined by test strips.
One must be aware of the possible consequences during trench backfilling and
exercise caution as described below:
Reference No. 1603-S066 25
• When construction is carried out in freezing winter weather, allowance should
be made for these following conditions. Despite stringent backfill monitoring,
frozen soil layers may inadvertently be mixed with the structural trench
backfill. Should the in situ soils have a water content on the dry side of the
optimum, it would be impossible to wet the soils due to the freezing condition,
rendering difficulties in obtaining uniform and proper compaction.
Furthermore, the freezing condition will prevent flooding of the backfill when
it is required, such as in a narrow vertical trench section, or when the trench
box is removed. The above will invariably cause backfill settlement that may
become evident within 1 to several years, depending on the depth of the trench
which has been backfilled.
• In areas where the underground services construction is carried out during
winter months, prolonged exposure of the trench walls will result in frost
heave within the soil mantle of the walls. This may result in some settlement
as the frost recedes, and repair costs will be incurred prior to final surfacing of
the new pavement and the slab-on-grade construction.
• To backfill a deep trench, one must be aware that future settlement is to be
expected, unless the side of the cut is flattened to at least 1 vertical:
1.5 + horizontal, and the lifts of the fill and its moisture content are stringently
controlled; i.e., lifts should be no more than 20 cm (or less if the backfilling
conditions dictate) and uniformly compacted to achieve at least 95% of the
maximum Standard Proctor dry density, with the moisture content on the wet
side of the optimum.
• It is often difficult to achieve uniform compaction of the backfill in the lower
vertical section of a trench which is an open cut or is stabilized by a trench
box, particularly in the sector close to the trench walls or the sides of the box.
These sectors must be backfilled with sand. In a trench stabilized by a trench
box, the void left after the removal of the box will be filled by the backfill. It
Reference No. 1603-S066 26
is necessary to backfill this sector with sand, and the compacted backfill must
be flooded for 1 day, prior to the placement of the backfill above this sector,
i.e., in the upper sloped trench section. This measure is necessary in order to
prevent consolidation of inadvertent voids and loose backfill which will
compromise the compaction of the backfill in the upper section. In areas
where groundwater movement is expected in the sand fill mantle, seepage
collars should be provided.
6.5 Pavement Design
Based on the borehole findings, the recommended pavement design is given in
Table 3.
Table 3 - Pavement Design
Course Thickness (mm) OPS Specifications
Asphalt Surface 40 HL-3
Asphalt Binder 50 HL-8
Granular Base 150 20-mm Crusher-Run Limestone, or equivalent
Granular Sub-base Light-Duty Heavy-Duty
350 450
50-mm Crusher-Run Limestone, or equivalent
In preparation of the subgrade, the subgrade surface should be proof-rolled; any
soft subgrade, organics and deleterious materials within 1.0 m below the underside
of the granular sub-base should be subexcavated and replaced by properly
compacted organic-free earth fill or granular material.
Reference No. 1603-S066 27
All the granular bases should be compacted to their maximum Standard Proctor dry
density.
In the zone within 1.0 m below the pavement subgrade, the backfill should be
compacted to at least 98% of its maximum Standard Proctor dry density, with the
water content 2% to 3% drier than the optimum. In the lower zone, a
95% or + Standard Proctor compaction is considered adequate.
The road subgrade will suffer a strength regression if water is allowed to infiltrate
prior to paving. The following measures should therefore be incorporated in the
construction procedures and road design:
• If the road construction does not immediately follow the trench backfilling,
the subgrade should be properly crowned and smooth-rolled to allow interim
precipitation to be properly drained.
• Lot areas adjacent to the roads should be properly graded to prevent the
ponding of large amounts of water during the interim construction period.
• Curb subdrains will be required. The subdrains should consist of filter-
sleeved weepers to prevent blockage by silting.
• If the roads are to be constructed during the wet seasons and extensively soft
subgrade occurs, the granular sub-base may require thickening. This can be
assessed during construction.
6.6 Soil Parameters
The recommended soil parameters for the project design are given in Table 4.
Reference No. 1603-S066 28
Table 4 - Soil Parameters
Unit Weight and Bulk Factor
Unit Weight (kN/m3)
Estimated Bulk Factor
Bulk Loose Compacted
Weathered Soil and Silty Clay 20.5 1.20 1.00
Sound Till 22.0 1.33 1.05
Sands 20.0 1.20 0.95
Lateral Earth Pressure Coefficients
Active Ka
At Rest Ko
Passive Kp
Weathered Soil and Silty Clay 0.50 0.65 2.00
Sound Till 0.40 0.50 2.50
Sands 0.35 0.45 2.86
6.7 Preloading Scheme
The overburden for building construction or grade raise will consolidate the
underlying very soft to soft silty clay and clay till strata; therefore, if the site is to be
raised or if a raft foundation is considered, the site will have to be pre-loaded and
the ground settlement should be monitored for at least 9 to 18 months prior to any
construction. This can be determined by the installation and monitoring of
settlement plates. The required surcharge load for the pre-loading program can be
determined once the site grading and townhouse sitings are available.
6.8 Excavation
Excavation should be carried out in accordance with Ontario Regulation 213/91.
Reference No. 1603-S066 29
Excavations should be sloped at 1 vertical:1 horizontal for stability.
The till contains occasional boulders. Extra effort and a properly equipped backhoe
will be required for excavation.
For excavation purposes, the types of soils are classified in Table 5.
Table 5 - Classification of Soils for Excavation
Material Type
Sound Till 2
Silty Clay, Weathered Soil and Sand above groundwater 3
Very soft to soft Clay and Sands below groundwater 4
Bottom heaving will occur in trenches cut steeply into the very soft to soft silty
clay. Therefore, the sides should be cut at 1 vertical:3.0 + horizontal and the spoil
from the excavation must be placed at a distance away from the edge of the
excavation at least equal to 3 times the depth of the excavation. Alternatively, the
excavation can be stabilized by proper shoring. It must be extended to a sufficient
depth below the bottom of the excavation to support the earth pressure, hydrostatic
pressure and all the applicable surcharge loads. This must be properly designed by
a structural engineer.
The yield of groundwater from the silty clay and silty clay till, due to their low
permeability, is expected to be small and limited and can generally be controlled
by pumping from sumps.
When excavating into the water-bearing sand at a shallow depth, groundwater
should be controlled by vigorous pumping from closely spaced sump-wells for
Reference No. 1603-S066 30 excavations to a depth of 0.3 m or less below the groundwater level. For
excavation deeper than 0.3 m below the groundwater level, a well-point
dewatering system will be required. This should be assessed by test pits and/or
test pumping prior to the project construction.
Prospective contractors must be asked to assess the in situ subsurface conditions
for soil cuts by digging test pits to at least 0.5 m below the intended bottom of
excavation. These test pits should be allowed to remain open for a period of at
least 4 hours to assess the trenching conditions and the means to control
groundwater, if encountered.
LIST OF ABBREVIATIONS AND DESCRIPTION OF TERMS The abbreviations and terms commonly employed on the borehole logs and figures, and in the text of the report, are as follows: SAMPLE TYPES
AS Auger sample CS Chunk sample DO Drive open (split spoon) DS Denison type sample FS Foil sample RC Rock core (with size and percentage
recovery) ST Slotted tube TO Thin-walled, open TP Thin-walled, piston WS Wash sample PENETRATION RESISTANCE
Dynamic Cone Penetration Resistance:
A continuous profile showing the number of blows for each foot of penetration of a 2-inch diameter, 90° point cone driven by a 140-pound hammer falling 30 inches. Plotted as ‘ • ’
Standard Penetration Resistance or ‘N’ Value:
The number of blows of a 140-pound hammer falling 30 inches required to advance a 2-inch O.D. drive open sampler one foot into undisturbed soil. Plotted as ‘’
WH Sampler advanced by static weight PH Sampler advanced by hydraulic pressure PM Sampler advanced by manual pressure NP No penetration
SOIL DESCRIPTION
Cohesionless Soils:
‘N’ (blows/ft) Relative Density
0 to 4 very loose 4 to 10 loose
10 to 30 compact 30 to 50 dense
over 50 very dense
Cohesive Soils:
Undrained Shear Strength (ksf) ‘N’ (blows/ft) Consistency
less than 0.25 0 to 2 very soft 0.25 to 0.50 2 to 4 soft 0.50 to 1.0 4 to 8 firm 1.0 to 2.0 8 to 16 stiff 2.0 to 4.0 16 to 32 very stiff
over 4.0 over 32 hard
Method of Determination of Undrained Shear Strength of Cohesive Soils:
x 0.0 Field vane test in borehole; the number denotes the sensitivity to remoulding
Laboratory vane test
Compression test in laboratory
For a saturated cohesive soil, the undrained shear strength is taken as one half of the undrained compressive strength
METRIC CONVERSION FACTORS 1 ft = 0.3048 metres 1 inch = 25.4 mm 1lb = 0.454 kg 1ksf = 47.88 kPa
Reference No: 1603-S066
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Proposed Townhouse Development (Phase 2) BH./Sa. 1/7 4/6 6/6
Location: 2055 Brock Road, City of Pickering Liquid Limit (%) = 40 33 42
Plastic Limit (%) = 21 18 19
Borehole No: 1 4 6 Plasticity Index (%) = 19 15 23
Sample No: 7 6 6 Moisture Content (%) = 41 27 33
Depth (m): 6.3 4.7 4.7 Estimated Permeability
Elevation (m): 84.4 83.5 84.1 (cm./sec.) = 10-7 10-7 10-7
Classification of Sample [& Group Symbol]: SILTY CLAY
a tr. of fine sand
GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
SILT & CLAY
Figure: 8
COARSE
MEDIUM
FINE
CLAY
SAND
MEDIUMFINE
GRAVEL
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100
Perc
ent P
assi
ng
Grain Size in millimeters
BH.6/Sa.6
BH.1/Sa.7
BH.4/Sa.6
Soil Engineers Ltd. Reference No: 1603-S066
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Proposed Townhouse Development (Phase 2)
Location: 2055 Brock Road, City of Pickering Liquid Limit (%) = 28
Plastic Limit (%) = 16
Borehole No: 3 Plasticity Index (%) = 12
Sample No: 7 Moisture Content (%) = 19
Depth (m): 6.3 Estimated Permeability
Elevation (m): 82.2 (cm./sec.) = 10-7
Classification of Sample [& Group Symbol]: SILTY CLAY, Till
sandy, a tr. of gravel
GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
SILT & CLAY
Figure: 9
COARSE
MEDIUM
FINE
CLAY
SAND
MEDIUMFINE
GRAVEL
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100
Perc
ent P
assi
ng
Grain Size in millimeters
Soil Engineers Ltd. Reference No: 1603-S066
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Proposed Townhouse Development (Phase 2)
Location: 2055 Brock Road, City of Pickering Liquid Limit (%) = -
Plastic Limit (%) = -
Borehole No: 1 Plasticity Index (%) = -
Sample No: 2 Moisture Content (%) = 22
Depth (m): 1.0 Estimated Permeability
Elevation (m): 89.7 (cm./sec.) = 10-3
Classification of Sample [& Group Symbol]: SILTY FINE SAND
a tr. of clay
GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
SILT & CLAY
Figure: 10
COARSE
MEDIUM
FINE
CLAY
SAND
MEDIUMFINE
GRAVEL
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100
Perc
ent P
assi
ng
Grain Size in millimeters