A PRESENTATION ON DELIVERING BANGAORE …icn.org.au/sites/default/files/15.50 - Sudhir...
Transcript of A PRESENTATION ON DELIVERING BANGAORE …icn.org.au/sites/default/files/15.50 - Sudhir...
NAMMA METRO
A PRESENTATION ON
DELIVERING BANGAORE METRO PHASE-2
DETERMINING PROJECT ALIGNMENTS,FUNDING
& CONSTRUCTION
BY B.S.SUDHIR CHANDRA
DIRECTOR (PROJECT & PLANNING) BANGALORE METRO RAIL CORPORATION LIMITED
HONG KONG DATE: 12-14 MARCH 2013
PRESENTATION TOPICS Brief Report about Phase-1 progress
Project Highlights of Phase-2
Funding options for Phase-2
Sources of Funding Phase-2
Financial parameters of Phase-2
Technical parameters of Phase-2
Challenges in Tunnel Construction
Metros in India
16.7
29.2
41.3
56.2
67
85
105
1971 1981 1991 2001 2005 2011 2021
( in Lakhs)
1971- 2001 : Census
2005 extrapolated & 2011-2021 as per draft CDP
BANGALORE POPULATION
Cars
15%
Two
Wheelers
55%
others
6%
Buses
1%
Trucks
6%
Auto
s 8
%
Two Wheelers Autos
Cars Buses
Trucks others
Total No. of vehicles as on
Aug.2011 -39.52 Lakhs
About 1250 new vehicles are being registered in Bangalore everyday.
Source : Transport Department
Two Wheelers – 69 % Three Wheelers (Autos) - 3 %
BANGALORE VEHICLES
Reach – 1
Reach – 3
Under Ground
Reach – 4
Reach – 2
South Extension
North Extension
Nagasandra
East West Corridor Elevated Section 13.02 Km Underground Section 4.88 Km Elevated Stations 12 Underground Stations 4
North South Corridor Elevated Section 20.20 Km Underground Section 4.00 Km Elevated Stations 21 Underground Stations 3
Srirampura
Sampige Road
KRMarket
National College
RVROAD
Attiguppe
Vijayanagar
Hosahalli
kempegowda
Sir.MV
CubbonPark
Halasuru
Indiranagar
EAST – WEST CORRIDOR 18.10 KMS
NORTH-SOUTH CORRIDOR 24.20 KMS
TOTAL 42.30 KMS
ELEVATED 33.48 KMS
UNDERGROUND 08.82 KMS
GAUGE Standard Gauge
TRACTION 750V dc Third Rail
SPEED Max 80Kmph ; Avg. 34Kmph
NO. OF STATIONS 40 (33 elevated, 7 UG)
TRAVEL TIME 33 / 44 Mins. (end to end)
HEAD WAY 4 Mins at start; later 3 Mins
NAMMA METRO
Construction Cost (Total Network of 42.30kms)
Total Length: Elevated 33.48km &Underground 8.82km SL No Particulars
Completion Construction Cost in
Millions (Rupees) Millions (US$)
1 Land 14084.2 312.43
2 Civil Engineering Works 57379.8 1272.84
3 Electrical Works 11045.3 245.02
4 S & T Works 8152.3 180.84
5 Depots 4191.4 92.98
6 Rolling Stock 17490.7 387.99
7 Total 112343.7 2492.10
8 General charges including administration, contingency etc.
6745.5 149.63
GRAND TOTAL 119089.2 2641.73
9 Interest During Construction 700 15.53
10 Less : Expected tax reimbursement (3700) (82.08)
TOTAL PROJECT COST 116089.2 2575.18
Exchange Rate Taken 1US$ = `45.08 2.5 billion US$
Construction Cost (Total Network of 42.30kms)
Total Length: Elevated 33.48km &Underground 8.82km
FUNDING PATTERN Figs in Rs. Crores
1 Crore = 10 million
Sl. No.
Particulars GoI GoK Total
1 Equity 1635 1635 3270
2 Subordinate Debt 1090 2215 3305
3 Sub total (1+2) 2725 3850 6575
4 Senior Term Debt - - 5034
5 Grand Total (3+4) - - 11609 (100%)
Senior Term Debt - JICA 2849 - ADB 1250 - SBI 800 - HUDCO 700
On Opening 2021
Designed phpdt 30075 40100
TRAIN HEADWAY 4 Min
3 Min E-W
4 Min N-S
TRAIN COMPOSITION 3 CARS 6 CARS
Capacity of 3 Car consist 975 Passengers
Capacity of 6 Car consist 2005 Passengers
TRAIN OPERATION
Parameter On Opening
Daily Ridership (lakhs) 12.22
Daily Passenger kms (lakh) 99.31
Avg. trip Length (km) 8.13
Progress of Phase 1 (in brief)
Reach No Designation of lineLength
KmsNo of Stns
Percentage Progress Likely Commissioning
date Viaduct/Tunnel
Stations
Reach 1E-W Corridor, Eastern Sector, Baiyappanahalli to MG Road
6.7 6 100% 100%Commissioned on
20.10.2011
Reach 2E-W Corridor, Western Sector, Magadi Road to Mysore Road
Terminal
6.9 6 98% 66% 31.05.2014
Reach 3 &3a
N-S Corridor, Northern Sector, Sampige Rd to Peenya Village
9.8 10 98% 68% 30.09.2013
Reach 3bN-S Corridor, Northern Sector, Peenya Village to Nagasandra
3.4 3 96% 49% 28.02.2014
Reach 4 & 4a
N-S Corridor, Southern Sector, National College to Puttenahalli
6.7 8 99% 72% 31.07.2014
Underground (E-W)
MG Road to Magadi Road 4.8 5** 77% 64% 28.02.2015
Underground (N-S)
Sampige Road to National College 4.0 3** 6% 28% 31.03.2015
** Includes one common interchange station– Kempegowda Station
BANGALORE METRO RAIL PROJECT, PHASE-II THE PHASE.2 OF THE PROJECT WILL INVOLVE CONSTRUCTION OF FOLLOWING LINES (EXCHANGE RATE : 1US$ = INR 50.00)
SL. NO
PARTICULARS LENGTH COST IN RS.
MILLION COST IN US$
MILLION DATE OF
COMMISSIONING
1 EXTENSION FROM BYAPPANAHALLI TO WHITEFIELD ON THE EAST (FULLY ELEVATED)
15.5 kms 14 stations
48450.00 969 4 Years from date of sanction by GOI
2 EXTENSION FROM MYSORE ROAD AT JUNCTION OF RING ROAD TO KENGERI ON THE WEST (FULLY ELEVATED)
6.5 kms 5 stations
18679.50 374 -D0-
3 EXTENSION FROM NAGASANDRA TO BANGALORE INTERNATIONAL EXHIBITION CENTRE (BIEC) ON THE NORTH (FULLY ELEVATED)
3.8 kms 3 stations
11680.22 203 -D0-
4 EXTENSION FROM PUTTENAHALLI TO ANJANAPURA ON THE SOUTH (FULLY ELEVATED)
6.3 kms 5 stations
17658.80 353 -D0-
5 NEW LINE FROM R.V. ROAD STATION ON EXISTING N-S CORRIDOR (PASSENGER INTERCHANGE STATION) TO BOMMASANDRA (FULLY ELEVATED)
18.8 kms 16 stations
57440.09 1149 -D0-
6 NEW LINE FROM GOTTHIGERE (IIMB) TO NAGAWARA (ELEVATED 7.0 KMS AND UNDERGROUND 14.2 KMS)
21.2 kms 6 elevated stations 12 underground stations
110140.00 2203 5 Years from date of sanction by GOI
Total 72.1 kms Elevated 57.9kms U/G 14.2 kms Elevated Stns 49 U/G Stns 12
264052 Rs. 26405 .20 crores
5281 5.28 billion US$
Namma Metro Phase 2
Mysore Road
Hesarghatta Cross
Puttenahalli Cross
BIEC
Anjanapura Township
Kengeri
Nagawara
IIM(B)
Bommasandra
RV Road
Arabic College
Venkateshpura
Tannery Road
Pottery Town
Cantt Rly
JP Nagar IV Phase
KR
pu
ram
Nar
ayan
apu
ra
Mah
adev
apu
ra
Gar
ud
ach
arp
aly
a
Rag
i G
ud
da
Tem
ple
Hebbagodi
Banashankari
JPNagar
Anjanapura Road
Krishnaleela Park (ISCKON0
Vajrahalli Thalaghatapura
Nayandahalli
Rajarajeshwarinagar Bangalore university
RV College
Hulimavu
Gottigere
MGRd
Phase -1
East West Line
North South Line
Phase-II Extension of Phase-1
North South & East West Lines
RV Road to Bommasandra
Gottigere to Nagavara
Underground section of
Gottigere to Nagavara line
Funding Options for Phase-2
Follow as in Phase-1 - Govt.of India and Govt.of Karnataka Joint
Stake holders- 54 % total contribution.
Senior Term Debt- from International
and Domestic Financial Institutions- 46 % of
tot al contribution.
Public Private Partnership - Being tried in Mumbai and Hyderabad metros
with 20% . Viability Gap Funding by the Govt
of India and Land given free by the State Govt..
- Civil structures Viaducts,Tunnels and Stations
construction by Govts.
- All others Systems and O&M by
Concessionaire for 30/35 years.
SOURCES OF FUNDING PHASE-2
1 USD= INR 50.00
INR Million USD Million %
Total Project cost 26,4052. 00 52810.00 100.00
GoK Equity Contribution 38700.00 7740.00 14.65
GoI Equity Contribution 38700.00 7740.00 14.65
Grant Contribution from GoK 17005.00 3401.00 6.40
Sub debt from GoK 33987.00 6797.40 12.97
Sub debt from GoI 14212.00 2842.40 5.35
Senior Term Debt 121448.00 24289.60 45.98
GoI share 52912.00 10582.40 20.00
GoK share 89692.00 17938.40 34.02
Senior Debt 121448.00 24289.60 45.98
SOURCES OF FUNDING PHASE-2(CONTD)
Funding agencies being tied up are JICA, ADB, AFD, World Bank, HUDCO,
Domestic Banks and Financial Institutions.
While approving Phase.2 of Metro project, the GoK has approved the
following measures for additional resource mobilisation through land
monetization :
a) Development cess: Levy of development cess on new layouts by BDA
and private layouts . This levy is estimated to yield revenue of Rs. 1250
Crores in five years.
b) Cess on additional floor area ratio(FAR): Allowing additional FAR along
the Metro Rail Corridor. This is estimated to yield Rs.430 crores in five years.
c) TDR in lieu of compensation of land: cost of land.
d) Issue of taxable bonds. Depending on the market appetite BMRCl may
float Bonds to pay off costlier loans.
FINANCIAL PARAMETERS OF PHASE-2
Line(s) FIRR EIRR
Four extensions to Phase -1 6.40 13.40
RV Road –Bommasandra line 4.40 16.70
Gottigere- Nagawara line 4.00 13.20
Total cost of Phase 2 INR 264051millions(USD
5. 281 billion)
Salient Technical Parameters of Phase-2
Civil Works Maximum speed - 80 kmph
Minimum Radius of curves - Elevated section 120m
-Underground section 200m
Grade Compensation on curves - 0.04% per degree of curvature
Maximum cant/super elevation - 125mm
Maximum cant deficiency - 100mm
Maximum length of Horizontal Transition curves - 55m
Maximum gradient of line - 4% (going from elevated to under ground and vice versa)
- 2.5 to 3% (generally)
Minimum distance between centres of two tracks - Straights 3.650m(U/G
3.750m( Elevated)
- Curves 4.20m
Salient Technical Parameters of Phase-2(contd)
Minimum radius of Vertical curves - 1500m
- 2500m (generally)
Stations on Curves ,minimum radius - 1000m
Stations on Grade ,maximum gradient - 1 in 1000(0.1%)
Tunnels- Minimum inside clear diameter - 5.40m
-Track centres minimum - 2D
-Minimum over burden - 1D
Emergency Evacuation - NFPA 130 regulations to be followed
Rolling Stock
Axle load 15 tonnes
Acceleration 1.1m /s2
Deceleration 0.9m/S2
Emergency 1.3 m/s2
Regenerative braking – almost 20% between 60kmph and 5 kmph
Wheel mounted Disc brakes
Electrical Works
Net work 33 KV separate feeders for Traction and
Auxiliary services.
Mode of Traction 750 V dc ,Third rail,bottom shoe collection
Traction motors 180 KW capacity
Percent powered 67%
All substations are SCADA controlled.
Signalling and Train Control System
Automatic Train Protection( ATP)
Automatic Train Operation ( ATO)
Automatic Train Supervision( ATS)
Audio frequency Track Circuits (AFC)
Communication Based Train Control System(CBTC)- for two new lines
Unattended Train Operation (UTO) for two new lines
Operations
Commercial speed - 34 kmph
Headway – Designed 120 seconds
-Operating 150 seconds
- with CBTC may go down to 90 seconds
Train consist- 6 cars (DMC+TC+MC+MC+TC+DMC)
Carrying capacity - 6 cars ,2005 persons( AW4State
loading)
Daily Ridership in 2021 1.72million
Cutter-head and Cutter chamber Shield Front Body Dia.= 6,450 mm Cutting Diameter By New Scrapper Bits= 6,490 mm
Cutting Diameter By Gauge Disc Cutter= 6,520~6,490 mm
( Preliminary Dimensions)
8-Center Cutter
80-Cutter Bit 1-Copy Cutter
4-Mixing Blade
34-Inner Cutter
16x4-Scrapper Bit 2-Gauge Cutter
RotaryPiping for Copy Cutter
Scrapper bit 64
Salient Features ofTunnel Construction
DEPTH BELOW GROUND LEVEL : 15 TO 18 METRES
TYPE OF TUNNELS : TWIN TUNNELS, ONE FOR EACH TRACK
DISTANCE CENTRE TO CENTRE OF TUNNELS
: 15.04M
DIAMETER (CLEAR INSIDE) : 5.60M
BORE DIAMETER : 6.44M
CONCRETE LINING THICKNESS 280MM
TUNNEL CONSTRUCTION BY : i) SLURRY TBMS ii) EARTH PRESSURE BALANCED
MACHINES (EPBM)
UNDERGROUND STATION CONSTRUCTION
: CUT & COVER, BOTTOM-UP METHOD
RAMPS CONSTRUCTION : CUT & COVER METHOD
CROSS ADITS CONSTRUCTION : NATM
Challenges in Tunnel Construction(contd) Underground alignment is only in One corridor(line 6)- Gottigere-Nagawara line. Approximate length 13.790 kms No. of stations 12 (one station-MG Road U/G – is an interchange station with the elevated MG Road station of Reach 1 of Phase.1) • There will be traffic interchanges at - Shivajinagar U/G station with Intra-City Bus terminal - Bangalore Cantonment U/G station with the National Railways station contd..
Challenges in Tunnel Construction ( contd)
Geo Strata is ‘ Mixed soil ‘ - Sandy silt
Weathered Rock
Soft Rock
Hard rock (comp strength 50 to 30mpa)
Water table is hardly 3 m below ground at places
Extensive ground stabilization measures are involved by Soil nailing, Rock anchoring, Grouting, etc.
Temporary support arrangements are massive- Solder piles, Secant piles, etc.
Rock excavation - Controlled Blasting with instrumentation.
- Sawing of rock by chain saws
Water proofing at Stations
- Anti Base slab flotation measures
- Road diversions and Decking of roads.
Cut and Cover Station excavations- On site Visualization program
Tendering for U/G Works- Phase -2
Geo Tech exploratory bores work has just started and will be completed by Aug.2013. It will be a combination of ‘Design and Construct’ and ‘Construct only’ package.s 1 USD=INR 50.00 There will be 3 packages 3.34 kms twin tunneling, 4 .stations Cost INR 14030m USD 280.60m 3.19kms twin tunneling , 4 stations Cost INR 13450 m USD 269.00m 4.01 km twin tunneling ,4 stations Cost INR 15140 m USD 302.80m Tunneling will be ‘Design and construct’ U/G stations may be ‘Construct only’ or ‘Design and construct’ Three envelope system - Qualification - Technical proposal - Financial proposal ‘D & C’ will be a lump sum quote ‘C only’ will be based on Bill of Quantities(BoQ) on which contractor quotes a premium percentage. There will be Price Variation Clause(incl.Lumpsum portion) Tender Notification likely to be issued in January- March 2014.
Metros in INDIA
Operational Metros(3) : Kolkata, Delhi and Bangalore.
Metros under construction(7) : Chennai, Gurgaon,
Hyderabad, Jaipur,
Kochi, Mumbai, Ahmedabad
Metros on the anvil(8) : Navi Mumbai, Pune, Chandigarh
Lucknow, Ludhiana, Nagpur, Bhopal and Indore