“Interconnectivity and Energy Security in S.E. Europe”
15th National Energy Conference, “Energy & Development 2010”
Athens, 22-23 November 2010
A Presentation by A Presentation by CostisCostis StambolisStambolis, A.A. Dip. Grad., MIE,, A.A. Dip. Grad., MIE,Executive Director Executive Director
Institute of Energy for S.E. Europe (IENE), Athens Institute of Energy for S.E. Europe (IENE), Athens
INSTITUTE OF ENERGY
FOR SOUTH EAST EUROPE
-
Presentation Outline
� Existing gas & electricity interconnections
� Proposed Gas Interconnectors
� Proposed Electricity Grid Interconnections
� Benefits arising from the operation of interconnectors
� Interconnectors as key elements of long term energy strategy
-
Introductory Observations
� Energy security is key objective for all countries
in SE Europe
� Need to secure smooth flow of fuel supplies
within each country and between countries in within each country and between countries in
the region
� Interconnectors to be seen as effective energy
bridges
� Interconnectors can secure operation of
alternative and secondary energy routes,
therefore enhancing energy security
-
Existing Gas & Electricity Interconnectors
� In view of the size of gas volumes transported each
year in the region, (85 BCM’s) the number and size of
interconnectors is limited
� As plans are currently in progress to use SE Europe as
a transit area for large inter-regional gas pipelines the a transit area for large inter-regional gas pipelines the
need for interconnectors is paramount
� Electricity grid connections between countries in SE
Europe are more extensive than gas, thus contributing
to much bigger energy flows
� Interconnectors both gas and electricity, are essential
for the operation of integrated electricity & gas markets
as envisaged by the “Energy Community”
-
Existing Gas Networks
-
Regional Electricity Grid
-
Major gas projects under study and development (a)
-
Major gas pipeline projects under study and
development (b)
-
Major Proposed Inter Regional Gas
Pipelines
� Nabucco (30-32 BCM’s)
� South Stream (63.0 BCM’s)� South Stream (63.0 BCM’s)
� ITGI (10-12 BCM’s)
� TAP (10-20 BCM’s)
-
Proposed Gas Interconnectors – Group I (East Balkans)
� Greece-Bulgaria-Romania-Hungary Interconnectors and
Greek LNG Terminals to comprise:
� Komotini-Stara Zagora (170 kms) gas interconnector
(known as IGB)
� Kavala LNG terminal� Kavala LNG terminal
� Bulgaria-Romania interconnector known as IBR, (15 kms)
crossing the Danube
� Romania-Hungary Interconnector (109 kms) known as IRH
(to link Arad in Romania to Szeged in Hungary)
All three interconnectors to be built with reverse flow
capacity
-
Proposed Gas Interconnectors – Group II (West
Balkans)
� The Croatian-Hungarian Gas Interconnector and the
Krk/Adria LNG Project
� Crotia-Hungary, known as ICH
� Krk LNG terminal (10.0 BCM/y capacity)
� The objective of ICH is to increase Hungarian import diversification away from Russiadiversification away from Russia
� Bulgarian-Serbian Gas Interconnector
(80-100 kms, with 2.0 BCM/y capacity)
� Western Balkan Gas Ring Project� Entails the construction of several small to medium capacity n.gas
interconnectors between the whole region of former Yugoslavia (No
progress has been reported over the last 2 years)
-
South East Europe Gas Interconnectors
and LNG Projects
-
Electricity Grid Interconnections
A. Projects recently completed
B. Projects under construction
C. Projects under discussion
-
Main Electricity Interconnections in S.E. Europe
(existing and planned)
-
Table1 – Electricity Grid Connections in SE Europe
(recently completed)
Table 1: Projects recently completed in SE Europe
Project description Comment400kV HVDC submarine cable Galatina (IT)- Arachtos(GR)
Project completed in 2003.
Reconstruction of 400kV OHL- Trebinje-Gacko-Mostar (BH) – Konjsko (HR)- Mostar-Sarajevo (BH)- Sarajevo-Tuzla-Uglievik (BH)- Uglievik (BH) -Ernestinovo (HR)
Reconnection with the UCTE (9.11.2004)- Completed- Completed- Completed- Completed
Table 1: Projects recently completed in SE Europe
- Uglievik (BH) -Ernestinovo (HR)- Mostar substation (BH)
- Completed- Completed
Reconstruction of 220kV OHL- (BH)-Dakovo (HR) (2 lines)- Jaijce/Prijedor (BH) – Mraclin (HR)- Prijedor (BH) – Meduric (HR)
Reconnection with the UCTE (9.11.2004)- Completed- Completed- Completed
400kV T.L. (RO) and Sandorfalva (HU) Project completed.400kV T.L. Uglievik (BH) – Mitrovica (SR) Completed in mid 2006400kV T.L. Bitola (FYROM) – Florina (GR) In operation since July 2007.
400kV T.L. Filippi-Nea Santa (GR) - Babaeski (TR) Construction completed in summer 2008.Related to this project is the construction of the400kV double-circuit line Lagadas-Filippi in .
400kV T.L. Stip (FYROM) - Ch.Mogilla (BG) Completed by end of 2008.
400kV T.L. Nadad (RO) - Békéscsaba (HU) Completed by end of 2008.
400kV Maritsa3 – Hamitabat (TR) Completd 2030
-
Table2 – Electricity Grid Connections in SE Europe
(under construction)
Project description Comment
400kV T.L. Stip (FYROM) - Nis (SR) Project agreed and initiated.
To be completed by end of 2011.
400kV T.L. Tirana (AL) - Podgorica (ME) Project under construction.
Completed by end of 2009.
The internal Albanian 400kV line Tirana-Elbasan is directly related to this project
has also expressed an interest for thisinterconnection.
-
Table3 – Electricity Grid Connections in SE Europe
(planned)
Project description Comment
400kV Interconnection FYROM-Albania-Italy Project under investigation.
Feasibility study ongoing (BG, , IT).
400kV submarine link between and . Constanta (RO) –
Pasakoy (TR)
Project under investigation.
Preliminary studies ongoing.
400kV T.L. N.Santa (GR) – Maritsa 3 (BG) MoU signed last April in .
HVDC submarine cable between and Following the completion of the 400kV 500MWHVDC submarine cable between and Following the completion of the 400kV 500MW
submarine DC link in 2003, a second submarine DC
link is proposed.
400kV T.L. Sacalaz (RO) – Novisad (SR) Under discussion
400kV T.L. Bitola (FYROM) – Elbasan (AL) Under discussion
400kV Cable (AL) – (IT) Merchant Line
400kV T.L. Pecs (HU) – Ernestinovo (HR) In trial operation since
400kV Cable (IT) –(HR) Under discussion
400kV T.L. Circovce (SI) – Pince (HU) Under discussion
400kV T.L. Circovce (SI) – Heviz (HU) Under discussion
400kV T.L. Circovce (SI) – Zerjavinec (HR) Under discussion
400kV Cable Tirat (ME) – Villanova (IT) Under discussion
-
Conclusions
� Interconnectors are seen as key elements in the
region’s long term energy strategy
� Interconnectors, both electricity and gas, are
cost effective because of their relatively small cost effective because of their relatively small
size, therefore low capital cost and speedy
construction
� Interconnectors can be easily planned as their
operation does not depend on new gas or
electricity supplies
-
Conclusions
� They further contribute towards:
� import diversification
� increased security of supply
� improvement of system operation by providing
cushion supplies cushion supplies
� improvement of storage capacity (in the case of gas)
� greater system flexibility
� improvement of overall energy flows
� optimized economic system operation
� Governments must give priority to electricity & gas interconnections over large scale intercontinental projects
-