![Page 1: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/1.jpg)
A plan for Modularization of Tritium Components
Randy Davis
Davis Consultants
M-TRT-H-00089
Savannah River Nuclear Solutions, LLC April 22, 2014
![Page 2: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/2.jpg)
M-TRT-H-00089
Current Approach
• All “tritium wetted components” are located inside a glovebox – Why
• Explosion Prevention – Ar/N2 filled • Fire Prevention - Ar/N2 filled • Tritium Leak/Spill Mitigation • Tritium Leak/Spill Recapture – Strippers
• Provides access to components for maintenance
2
![Page 3: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/3.jpg)
M-TRT-H-00089
Current Approach
3
TEF
249H
ATLA
S
![Page 4: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/4.jpg)
M-TRT-H-00089
Current Approach
• Implications – Large glass surface area – Leads to large number of gloves installed over time – Large equipment replacement difficult
• Usually requires Open Glovebox Maintenance • Preparation very time consuming
– Hut Construction – Fire Suppression Issues
• Compensatory measures required for fire/explosion hazard • Compensatory measures required for worker hazard • Re-establishing confinement time consuming • Overall very time and labor consuming • SRS OGMs run several weeks to several months in duration.
4
![Page 5: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/5.jpg)
M-TRT-H-00089
Current Approach
• Implications (cont’d) – Stripping glovebox atmosphere using catalytic oxidation is not
efficient • Majority of hydrogen loading is from permeation of humidity into the glovebox.
– Gloves – Gaskets
• Typically tritium concentration less than 0.1% tritium, balance protium. • Through-put required for isotope separation to reclaim this tritium has to be
orders of magnitude larger than necessary. – Energy intensive – Space consuming – Increases Operational/Maintenance demand
5
![Page 6: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/6.jpg)
M-TRT-H-00089
Proposed New Approach
6
Typical Hydride Bed, Diffuser, Cat Bed, etc.
Secondary Jacket common w/glovebox
Typical Column/Vessel
Glovebox Boundary Valves, Instruments and Fittings
Electrical Instrument Connector
• Locate components which require periodic replacement in easily removable “modules.”
![Page 7: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/7.jpg)
M-TRT-H-00089
Maintenance Progression
7
Break line
![Page 8: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/8.jpg)
M-TRT-H-00089
Maintenance Progression
8
Apply cap
![Page 9: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/9.jpg)
M-TRT-H-00089
Maintenance Progression
9
Bag item to be removed
![Page 10: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/10.jpg)
M-TRT-H-00089
Maintenance Progression
10
Remove item
![Page 11: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/11.jpg)
M-TRT-H-00089
Maintenance Progression
11
Reverse process for installation
![Page 12: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/12.jpg)
M-TRT-H-00089
Maintenance Progression
12
Reverse process for installation
![Page 13: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/13.jpg)
M-TRT-H-00089
Maintenance Progression
13
Reverse process for installation
![Page 14: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/14.jpg)
M-TRT-H-00089
Modularization Benefits
• Reduces water processing – Significantly reduces glovebox volume/surface area – Reduces glass/gaskets – Reduces gloves – Reduces “water” loading
• Reduces maintenance cost – Complicated Open Glovebox Maintenance eliminated
• OGM can add several hundred thousand dollars to work cost
• Reduces maintenance duration
14
![Page 15: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/15.jpg)
M-TRT-H-00089
Estimated Savings
• Converting from current approach to modularization estimated to result in: – 30% less glovebox volume. – 50% less glass/glove surface area.
• Floor space requirements will be reduced as well. • Estimate large equipment/ limited life component maintenance
cost reduction of 30%. • Study currently being performed for the SRS Tritium Facility
to validate these estimates.
15
![Page 16: A Plan for Modularization of Tritium Components - Randy...A plan for Modularization of Tritium Components Randy Davis Davis Consultants M-TRT-H-00089 Savannah River Nuclear Solutions,](https://reader031.fdocuments.in/reader031/viewer/2022030511/5abaffb77f8b9ad1768c3792/html5/thumbnails/16.jpg)
M-TRT-H-00089
Questions?
16