A New Loading Dock Design
-
Upload
dale-hudson -
Category
Design
-
view
57 -
download
0
Transcript of A New Loading Dock Design
1
A New Loading Dock
Design JAMAS Enterprises, LLC
404 N Midler Ave.Syracuse, NY 13206
(315) 463-5356www.JAMASenterprises.com
2
Cost Effective Methodof Constructing a Dock
Upfront cost savings include:1. This design requires only two concrete pours to complete the dock leveler pits.
Conventional forming of pits, along with the potential for irregular pits, is eliminated.
2. CentraAir levelers utilizing compressed air rather than 460/3 electrical power. These levelers are less costly than hydraulic levelers.
3. The only electrical drops at the docks are 110 volt, between every other set of doors, to power the BeLights and BeLock Controllers.
4. Dock equipment controls are integrated into the Twins, thus eliminating drilling, welding or anchoring to new walls and door jambs.
5. Infill pads or other means of guarding against impact from equipment is incorporated into the Twins.
6. Security contacts at each door are eliminated and door monitoring takes place within the BeLock Controller.
Please review this presentation and contact me with any questions.Thank you,Dale Hudson(315) 463-5356
3
Cost Effective Methodof Constructing a Dock
Equipment Used:
Poweramp CA Dock Levelers
JAMAS BeLight TwinsJAMAS BeLock Controllers
Fairborn USA Dock Shelters
Amarr Dock Doors
Durable Steel Faced Bumpers
4
Dock Foundation Wall
Dock Pit Openings are 2’2” deep by 9’1” wide
5
Preparing Continuous6” Pit Floor
6
Installing Three Sided Pit Kits
Lay out and bolt together the sides and back.
7
Installing Three Sided Pit Kits
Level, Shim, and Square up the kits
8
Installing Three Sided Pit Kits
Anchor and Brace
9
Poweramp Rapid Form Pan
10
Installing the Twins
Position to a Straight LineDistance off the wall is determined by Track Guard plus door track projection
11
Installing the Twins
Square to Pan Shim to level
12
Installing the Twins
Conduit runs – Wall to BeLights to Leveler Pit
Installing the Twins
Conduit runs for air lines to CA Levelers
13
14
Installing Rebar
15
Ready to pour Infills and Floors
16
Infills and Floors Poured
17
Assembly of Twins and Installation of Levelers
18
Assembly of Twins and Installation of Levelers
19
Finished Dock
20
In Use
21
BeLight Twins B.O.M.
6” Schedule 40 Pipe Upright posts
10” x 10” x ½" Base Plates For mounting to pit floor
6” Pipe Tee Houses the BeLight
6” Structural C-channel (2) Rails spanning the BeLight pipe posts
6” x 5/16" Structural Angle Overlapping pipe posts and anchored to the floor
2” x 2” x ¼” Wall Steel Tube Track Guard rails and control panel station supports
3” x 3” x ¼” Structural Angle For door track protection
3/16” Steel Plate For control panel station and BeLight cap
22
23
CentraAir Series Leveler
Size:Widths
6’, 6.5’, 7’
Lengths6’, 8’, 10’
Capacities:25,00030,00035,00040,00045,00050,000