Agile in Public Procurement Projects
Aleksej Kovaliov, TEO LT, Agile Lietuva
The impossible is often the untried (Jim Goodwin)
![Page 2: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/2.jpg)
Me
• Aleksej Kovaliov
• aleksej.kovaliov @ gmail.com
• https://www.linkedin.com/in/aleksejkovaliov
• http://www.slideshare.net/akovaliov
• http://www.bdcinstitutas.lt/autorius/23
• http://akovalyov.wordpress.com/
![Page 3: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/3.jpg)
What first comes to you mind when you hear….
Some stereotypes. Any resemblance to real persons, projects and organizations, living or dead, is purely coincidental
![Page 4: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/4.jpg)
…Public Procurement
• Low Efficiency and High Waste
• Legalized Over-complication
• Fierce Competition
• Claims & Lawsuits
• Corruption
DEREK HUETHERZombie procurement
![Page 5: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/5.jpg)
…Public IT Projects
• High CAPEX
• Fixed price & Fixed scope & Fixed deadlines
• Unqualified Customer
• Requirements Over Goals
• Undefined Complexities
• Overdefined Simplicities
• Outdated Architectures
• Poor Usability
• “SaaPA” – Software as a Political Asset
• Big Boys’ Club
• Redundancies
DEREK HUETHERZombie procurement
![Page 6: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/6.jpg)
Infinitely Long Requirements Lifecycles
EU / Government
Program
Feasibility study
Technical specification
Procurement specification
Tender Contract Analysis
1-3 years 0,5 year
0,5-1,5 yearimplementation
![Page 7: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/7.jpg)
Barriers for Improvements
• Legal Focus on HOW do organizations buy• Not WHAT do they buy
• Lack of the Championship for Change• Disperse ownership among ministries• Top-to-bottom Command and Control
• Lack of Economic Motivation for Change• EU Financing models• Buyers Not Interested• Sellers Not Interested
![Page 8: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/8.jpg)
How Can Agile Help?
• No Need To Define The Indefinite
• Faster Study to Project Lifecycle
• Faster and Usable GO LIVE
• Quota for Intermediate Mistakes
• Requirements Aligned To Reality
• Stop When It’s Enough
• Suppliers’ Risk Management
• Innovation Enablement
http://blog.projectassistants.com/tag/agile-methodology/
![Page 9: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/9.jpg)
Not Easy, but Still Possible to be Agile
http://mathtourist.blogspot.com/2011/05/riding-on-square-wheels.html
![Page 10: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/10.jpg)
Situation in Lithuania
![Page 11: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/11.jpg)
Public IT Procurement in 2013
• IT Services etc.• 298,2M LTL = 86,3M EUR
• 447 purchases
• Software and Information Systems• 102,1M LTL = 29,6M EUR
• 225 purchases
http://www.vpt.lt/vpt/uploaded/2014/vp/Informacija%20apie%202013%20m.%20viesuosius%20pirkimus.pdf
![Page 12: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/12.jpg)
Legal Background
• Law on Public Procurement
• Law on Information Assets
• Information Systems Lifecycle Methodology (AGILE included!)
• Ministry of Justice
• Ministry of Transport and Communications
• Ministry of Interior
• Information Society Development Committee• Ministry of Transport and Communications
• Public Procurement Office• Ministry of Economy
• Focus on Transparency & Control
![Page 13: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/13.jpg)
Agile Under Cover … - 2014
• Not Forbidden, Not Welcomed
• Mandatory External Waterfall 99%
• Rare Agile at Home
• Unofficial Intermediate Reviews and Product Owners
• Agile Lietuva Association, www.agile.lt• Agile Alliance
• Scrum Alliance
• Agile Lean Europe Network
![Page 14: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/14.jpg)
Legally Agile 2014 - ….
• Information Systems Lifecycle Methodology• Appendix#1: Implementation Approaches #3: Iterative-incremental
• Appendix#2: Recommendations
Scope Detail requirements
Waterfall Modular Iterative-incremental
Big Defined X X
Undefined X X
Small Defined X
Undefined X
![Page 17: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/17.jpg)
But How Would It Work?
http://www.condenaststore.com/-sp/Great-but-how-is-he-in-bed-New-Yorker-Cartoon-Prints_i8541755_.htm
![Page 18: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/18.jpg)
Ken Schwaber says…Scrum’s principle
is “the art of the possible,”
not “you give me what I paid for, when you said that you’d
deliver it.”
http://www.incrementor.com/agilenyc/past-events/2010-2/110310-ken-schwaber/
Agile Project Management with Scrumby Ken SchwaberMicrosoft Press © 2004
![Page 19: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/19.jpg)
Agile Waterfalls
![Page 20: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/20.jpg)
Typical Milestones in Public IT Project
![Page 21: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/21.jpg)
Approach1: Agile Under Cover
![Page 22: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/22.jpg)
Approach2: Project-as-a-Product
+• Plan as a Product to Market
• Strategic Roadmap
• Beta Milestones
• Go Live Milestones
• Draw a Poster!
• PjM Formalities is a just a Package
• Filter Real Goals and Priorities
• Slice the Scope
• Cut the Redundancies
![Page 23: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/23.jpg)
Map BETAs to Waterfall Milestones
![Page 24: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/24.jpg)
Product Release Plan / Roadmap (example)
Prioritized Features Alpha1 Alpha2 Alpha3 Alpha4 Alpha5 Alpha6
Data exchange module Beta1
Documents and tasks module Beta1
Execution module Beta1
Control module Beta1
Operator module Beta1
User provisioning module Beta1
Bendrųjų klasifikatorių posistemis Beta1
Utilities modules Beta1
Documentation
IT Platform
“Product” is growing with every releaseThe same features are being improved with every releaseBacklog is filled in with scenarios
![Page 25: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/25.jpg)
Split BETAs to Agile Sprints for Each Milestone
1 2 3 4 5 6In
tern
al in
DEV
En
viro
nm
en
t
Exte
rnal
in
DEV
En
viro
nm
en
t
Alpha6XAlpha2X Alpha4X
Alpha4Alpha1 Alpha2 Alpha3 Alpha6Alpha5
Exte
rnal
in
PR
OD
Envi
ron
me
nt
BETA1
BETA 1Candidate
![Page 26: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/26.jpg)
Approach3: Standard Methodologies
• PRINCE2 – Management and Control• Business Justification• Stakeholder Engagement• Management Control and Direction• Manage by Stages• Manage by Exception
• Agile DSDM (Atern) – Delivery and Development• Focus on Business Needs• Deliver on Time• Collaborate• Build Incrementally from Firm Foundations• Develop Iteratively• Demonstrate Control
![Page 27: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/27.jpg)
Whitebook: PRINCE2 combined with Scrum
Waterfall PRINCE2 is Agile
![Page 28: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/28.jpg)
Controlling a Stage, Managing a Stage Boundary, Directing a Project
Managing Product Deliveryhttp://www.slideshare.net/apmg-inter/prince2-agile-management-delivery-apmginternational-webinar
![Page 29: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/29.jpg)
Agile Procurement
![Page 30: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/30.jpg)
Fundamental Changes
• In the Way Suppliers are Selected and Contracted• Selecting a Supplier and not a solution
• Thinking Business Outcomes rather than Detailed Requirements• Goals over Requirements
• Public Procurement Regulations• From Transparent to Transparent + Efficient
![Page 31: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/31.jpg)
Agile Contracts <> Risky Contracts
Risk
CustomerIn-house
Team
Outcome Based Contract
for Supplier
Waterfall Approach
Agile Apporach
http://www.westminster-briefing.com/fileadmin/westminster-briefing/pastevents/IPL.pdf
T&M
T&M
Risk Reward Fixed Price
Fixed PriceFor Fixed Effort
Volume-based:Fixed Price for committed
+Velocity/Price for additional
![Page 32: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/32.jpg)
More Agile Contracts Types
• Contracting to Support Modular Development• http://www.whitehouse.gov , 2012, June
• Indefinite delivery / quantity contracts
• Single contract with options
• Successive contracts
• Performance-based Work Statements
• Fixed-price contracts and task orders
• Cost-reimbursement contracts
• Time-and-materials contracts
• Incentive contracts
• Hybrid contracts
![Page 33: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/33.jpg)
What Next?
![Page 34: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/34.jpg)
Roadmap
Past
• Start Using Agile in Public IT Projects
• Update LT Public IS Development Methodology
2014
• Recommendations and Guidelines
• Educating the Institutions and Suppliers
2014+• Feasibility Study of the Agile Public Procurement
model for LT
???
• Update LT Law on Public Procurement
• Update LT Law on Public Information Resources
![Page 35: A kovaliov agile public procurement - pm days 2014](https://reader033.fdocuments.in/reader033/viewer/2022042816/5596eedd1a28ab35778b464c/html5/thumbnails/35.jpg)
Thank you! Questions?