A GUIDE FOR HOSPITAL AHU REPLACEMENT · What components does the existing AHU have? Make a sketch,...
Transcript of A GUIDE FOR HOSPITAL AHU REPLACEMENT · What components does the existing AHU have? Make a sketch,...
-
A GUIDE FOR HOSPITAL AHU REPLACEMENT
Alan E. Fritsche, Principal, Garner Fritsche Engineering
-
Alan E. FritscheLEED AP BD+C,
Principal
-
Objectives• System analysis considerations
• Minimizing down time (or Zero Down Time)
• Temporary AHU’s and ducting strategies
• Infection Control Risk Assessment (ICRA) planning
• C-Suite & Departmental buy-in presentation
• Implementation of the program
-
System Analysis ConsiderationsWhat components does the existing AHU have?
Make a sketch, take pictures• Cooling coil or coils; count the rows of tubes
• Heating coils
• Type of fan, quantity of fans, motor horsepower
• Blow thru or draw thru
• Horizontal or vertical
• Filters – get MERV ratings, number of filter banks location/position, size
• Control dampers, smoke detectors, UV lights, humidifier
-
System Analysis Considerations
Determine Capacity• Look for existing drawings, schedules
• Measure cooling coil size
• Space take-off; check HHSC 133 for code required amounts
• Outside air quantity
• Supply air temperature required
• Chilled water supply temperature available at the AHU
• Hot water supply temperature
• Air side static pressure required
-
System Analysis Considerations
Code Requirements• Most AHJ’s (City, HHSC) will require the AHU
system be updated to all current codes
• HHSC considers AHU replacements a minor project
-
Minimizing Down TimeHow long will AHU be down?
• Consider hours of operation for areas served
• Consult with contractor for duration estimate
• Temporary AHU may be required
• Season of year for project
-
Temporary AHU’s and Ducting Strategies
• Temporary AHU considerations:• Where will the temp AHU be placed?
• How many yellow flex ducts will be needed?
• Temporary ducts need to be insulated
• Most rental AHU’s DO NOT have final filtration option
• CHW, HW, electric services need to be pre-planned
-
Infection Control Risk Assessment(ICRA) Planning
• Get this department engaged as soon as possible
• Plan on temporary isolation walls • Negative air HEPA filtration
machines• Noise scheduling• Spot-cooler air conditioners
-
C-Suite & Departmental Buy-In Presentation• Infrastructure projects are generally needed, NOT
wanted
• Prepare for this meeting
• Benefits
• Lower energy consumption
• Better climate control = Patient satisfaction
• Bring up to current code standards keeps the facility compliant with HHSC, TJC/CMS
• Have a cost analysis
• Time frame of the project
-
Implementation
• Develop a full schedule for the project
• AHU’s are long-lead items
• Consider how the unit will get into the mechanical room
• Hire an engineer for system analysis
-
Don’t forget the 7 P’s
-
Questions?
Alan E. Fritsche, LEED AP BD+C, Principal
Garner Fritsche Engineering, Inc.
713.432.1422
GarnerFritsche.com
mailto:[email protected]