A GUIDE FOR HOSPITAL AHU REPLACEMENT · What components does the existing AHU have? Make a sketch,...

13
A GUIDE FOR HOSPITAL AHU REPLACEMENT Alan E. Fritsche, Principal, Garner Fritsche Engineering

Transcript of A GUIDE FOR HOSPITAL AHU REPLACEMENT · What components does the existing AHU have? Make a sketch,...

  • A GUIDE FOR HOSPITAL AHU REPLACEMENT

    Alan E. Fritsche, Principal, Garner Fritsche Engineering

  • Alan E. FritscheLEED AP BD+C,

    Principal

  • Objectives• System analysis considerations

    • Minimizing down time (or Zero Down Time)

    • Temporary AHU’s and ducting strategies

    • Infection Control Risk Assessment (ICRA) planning

    • C-Suite & Departmental buy-in presentation

    • Implementation of the program

  • System Analysis ConsiderationsWhat components does the existing AHU have?

    Make a sketch, take pictures• Cooling coil or coils; count the rows of tubes

    • Heating coils

    • Type of fan, quantity of fans, motor horsepower

    • Blow thru or draw thru

    • Horizontal or vertical

    • Filters – get MERV ratings, number of filter banks location/position, size

    • Control dampers, smoke detectors, UV lights, humidifier

  • System Analysis Considerations

    Determine Capacity• Look for existing drawings, schedules

    • Measure cooling coil size

    • Space take-off; check HHSC 133 for code required amounts

    • Outside air quantity

    • Supply air temperature required

    • Chilled water supply temperature available at the AHU

    • Hot water supply temperature

    • Air side static pressure required

  • System Analysis Considerations

    Code Requirements• Most AHJ’s (City, HHSC) will require the AHU

    system be updated to all current codes

    • HHSC considers AHU replacements a minor project

  • Minimizing Down TimeHow long will AHU be down?

    • Consider hours of operation for areas served

    • Consult with contractor for duration estimate

    • Temporary AHU may be required

    • Season of year for project

  • Temporary AHU’s and Ducting Strategies

    • Temporary AHU considerations:• Where will the temp AHU be placed?

    • How many yellow flex ducts will be needed?

    • Temporary ducts need to be insulated

    • Most rental AHU’s DO NOT have final filtration option

    • CHW, HW, electric services need to be pre-planned

  • Infection Control Risk Assessment(ICRA) Planning

    • Get this department engaged as soon as possible

    • Plan on temporary isolation walls • Negative air HEPA filtration

    machines• Noise scheduling• Spot-cooler air conditioners

  • C-Suite & Departmental Buy-In Presentation• Infrastructure projects are generally needed, NOT

    wanted

    • Prepare for this meeting

    • Benefits

    • Lower energy consumption

    • Better climate control = Patient satisfaction

    • Bring up to current code standards keeps the facility compliant with HHSC, TJC/CMS

    • Have a cost analysis

    • Time frame of the project

  • Implementation

    • Develop a full schedule for the project

    • AHU’s are long-lead items

    • Consider how the unit will get into the mechanical room

    • Hire an engineer for system analysis

  • Don’t forget the 7 P’s

  • Questions?

    Alan E. Fritsche, LEED AP BD+C, Principal

    Garner Fritsche Engineering, Inc.

    713.432.1422

    [email protected]

    GarnerFritsche.com

    mailto:[email protected]