Business Process Modeling for EPLC Facilitated By Angela Thomas Ryan Kahn.
A Case Study: EPLC and PM Support at NIDCR...A Case Study: EPLC and PM Support at NIDCR PMCOE...
Transcript of A Case Study: EPLC and PM Support at NIDCR...A Case Study: EPLC and PM Support at NIDCR PMCOE...
A Case Study:EPLC and PM Support at NIDCR
PMCOE PresentationApril 14, 2010
Peter D. Carothers, PMP Program Manager, NIDCR, NIDCD
Agenda• The business need
• Requirements / success criteria
• Options explored
• Why this solution
• Solution details
4/16/2010 2
EPLC @ NIDCR
The Business Need• The Mandate
– Adopting EPLC is not a choice
• Managing Risk– Underperforming projects are a management risk
• Managing Change– How do we implement new processes successfully
4/16/2010 3
EPLC @ NIDCR
EPLC Framework - Overview Document
“Implementation of the EPLC framework will require significant training and
guidance for the entire IT investment stakeholder community.”
4/16/2010 4
EPLC @ NIDCR
Primary Stakeholders• CIO
• PMs
• Governance Team
• Project Team Members
• Executive Management
4/16/2010 5
EPLC @ NIDCR
EPLC Framework - Overview Document
4/16/2010 6
EPLC @ NIDCR
NIDCR Requirements• Provide intuitive, step-by-step EPLC project
management guidance
• Create a central location where project managers can get the resources and guidance they need
• Integrate with existing processes and infrastructure
4/16/2010 7
EPLC @ NIDCR
NIDCR Requirements (cont’d)• Support additional processes as needed
• Do not require significant investment or support costs
4/16/2010 8
EPLC @ NIDCR
Options Explored• Enterprise software solutions
• COTs products
• Custom development
4/16/2010 9
EPLC @ NIDCR
Why This Solution• Simplicity
– A good cultural fit
• Return on investment– Low initial investment
– Low support costs
• Integration with existing software plans– i.e. SharePoint
4/16/2010 10
EPLC @ NIDCR
Why This Solution (cont’d)• Leverages existing hardware
• Quick to deploy
• Immediate ROI
• Uses beyond EPLC
• Adaptable as processes evolve
4/16/2010 11
EPLC @ NIDCR
Why SharePoint?• Document management and collaboration
• Integration with MS Office Suite
• Out of box SharePoint 2010 is really cool!
4/16/2010 12
EPLC @ NIDCR
Process Overview
EPLC @ NIDCR
CPIC• Funding
Decisions
EPLC• PM
Framework
POD• Process
Guidance & Training
SP• Project
Management Workspace
4/16/2010 13
Solution Architecture
4/16/2010 14
EPLC @ NIDCR
CPIC EPLC POD SP
Solution Details
4/16/2010 15
EPLC @ NIDCR
CPIC EPLC POD SP
Roles and Responsibilities
4/16/2010 16
EPLC @ NIDCR
CPIC EPLC POD SP
Process Descriptions
4/16/2010 17
EPLC @ NIDCR
CPIC EPLC POD SP
Step by Step Guidance
4/16/2010 18
EPLC @ NIDCR
CPIC EPLC POD SP
Hyperlinks
Training Materials• Over 40 hours of videos and podcasts
• PM glossary
• Just-in time training
• PMP exam prep
4/16/2010 19
EPLC @ NIDCR
CPIC EPLC POD SP
Training Materials
4/16/2010 20
EPLC @ NIDCR
CPIC EPLC POD SP
Templates by Phase• Blank
• Completed Versions from Other Projects
4/16/2010 21
EPLC @ NIDCR
CPIC EPLC POD SP
Project Sites• Form driven site requests
• Team collaboration
• Phase selection
• Document libraries
4/16/2010 22
EPLC @ NIDCR
CPIC EPLC POD SP
Project Sites
4/16/2010 23
EPLC @ NIDCR
CPIC EPLC POD SP
Project Tailoring• Phase selection
• Deliverable reviewer selection
4/16/2010 24
EPLC @ NIDCR
CPIC EPLC POD SP
Document Management• Templates by phase
• Versioning, workflow, check-in/check-out
4/16/2010 25
EPLC @ NIDCR
CPIC EPLC POD SP
Project Dashboards• Project status at a glance
4/16/2010 26
EPLC @ NIDCR
CPIC EPLC POD SP
Project Central
EPLC @ NIDCR
CPIC EPLC POD SP
Projects Dashboard• Indicate “Phase” status at a glance
4/16/2010 28
EPLC @ NIDCR
CPIC EPLC POD SP
Project Budget • Projects budget
overview charts
4/16/2010 29
EPLC @ NIDCR
CPIC EPLC POD SP
EPLC Framework - Overview Document
“The EPLC framework
does not
preclude OPDIVs
from requiring more rigor.”
4/16/2010 30
EPLC @ NIDCR
CPIC EPLC POD SP
Process Builder• Build custom linked workflows
4/16/2010 31
EPLC @ NIDCR
CPIC EPLC POD SP
Design Flexibility
4/16/2010 32
EPLC @ NIDCR
CPIC EPLC POD SP
Design Flexibility
4/16/2010 33
EPLC @ NIDCR
CPIC EPLC POD SP
Design Flexibility
4/16/2010 34
EPLC @ NIDCR
CPIC EPLC POD SP
Solution Benefits
4/16/2010 35
EPLC @ NIDCR
CPIC EPLC POD SP
• Within NIDCR budget constraints…
Solution Benefits• Integrates with existing processes and
infrastructure
• Creates a central location where project managers can get the resources and guidance they need
• Provides intuitive, step-by-step EPLC project management guidance
4/16/2010 36
EPLC @ NIDCR
Solution Benefits (cont’d)• Supports additional processes as needed
• Does not require significant investment or support costs
• Deployed in three days
• Easy incremental improvements
• Simplicity fosters adoption
4/16/2010 37
EPLC @ NIDCR
Follow Up InformationPeter D. Carothers, PMPContractor: Program Manager, NIDCD, [email protected] (mobile)301-984-4004 x 317 (office)
Program Manager, PMOLCG Systems, [email protected]
4/16/2010 38
EPLC @ NIDCR
A couple of my projects…
4/16/2010 39
EPLC @ NIDCR