A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the...

download A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environment

of 9

Transcript of A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the...

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    1/9

    WAC-IC 2014

    Page 1/9

    A Case on Planning and Operation of a Small Hydro Power Project

    with Minimum Negative Effects to the Environment

    Samarakoon Banda. (B.Sc.( Eng.) Hons, P.G.Dip.( H&T Eng.), C. Eng., MIE(SL) )

    VS Consulting (Pvt) Ltd, No. 171-5/1, Fourth Floor, Keen Square

    Kensey Road, Colombo-0 8, Sri Lanka.

    E-mail: [email protected]

    Abstract

    Bulathwatha small hydropower project at Haldumulla in Badulla district in Sri Lanka is a run-of-the-river small

    hydropower scheme commissioned in May 2013. It has a generation capacity of 3.8 MW. The expected annual

    energy generation is 12.6 GWh. The electricity generated is fed to the national grid. The project covers a length of

    2.1 km from intake to the powerhouse. Lands within 1.6 km of project length were under the control of Forest

    department of Sri Lanka and remaining lands were owned by the villagers. The approval for the project had been

    granted and the lands were released by the Forest Department subject to several conditions applicable to construction

    and operations . The construction had to be carried out with minimum damage to the forest. Removal of old, giant

    trees were not permitted. The water way trace (head race canal & penstock) to the power house had to pass through

    a village and many agricultural lands. It was necessary to carry out the construction works without any adverse impact

    on the livelihood of the villagers and with bare minimum damage to the agricultural lands. Further, there were many

    wild animals in the project area due to existence of the forest reserve. Therefore, project planning was done giving

    due consideration to these social and environment elements, specifying mitigation measures and monitoring plans.

    This paper describes how the project planning and selection of structures were made to minimise the negative

    environmental effects during the construction and operation stages of Bulathwatha small hydro power project.

    1. Introduction

    Hydropower is certainly the largest, most mature application of renewable energy. Based on the generation capacity,

    hydropower projects are classified as Large, Medium, Small, Mini or Micro. Projects within the range of 500 kW and

    10 MW are considered as Small Hydropower Projects (SHPs) in Sri Lanka. There is a trend in developing more Small

    hydro schemes, as it is an environment friendly source of energy.

    Most of the SHPs are run-of-the river schemes, which means that the turbine operates only when water is available

    in the river. The river inflow is not regulated using a reservoir. Even though an SHP is a clean environment friendly

    source of energy, there are many negative environmental impact during construction of a SHPs. The environmental

    effects of an SHP are unique to the project. In some cases, very attractive SHPs cannot be implemented due to

    environmental considerations. Hence, the environmental sensitivity of a SHP project have to be properly identified by

    the approval agencies, stakeholders, environmentalists and the design engineers. The project approval can be given

    with conditions to minimise negative impacts to the environment rather than abandon the project in the name of

    negative environmental impacts.

    The negative impacts to the environment can be minimized while implementing a project, by identifying the negative

    impacts and incorporating them in the project designs, construction & maintenance. The SHPs project design

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    2/9

    WAC-IC 2014

    Page 2/9

    engineers have a major role to play in evaluation of various structural types & selection of the most suitable structural

    types to meet engineering & environmental challenges.

    2. The main structures of a Small Hydro Power (SHP) project

    The main structures of a small hydro power project and their functions are given below . The figure 1.0 depicts a

    layout of a small hydro power project.

    Weir a structure built across the river to divert water in to the intake

    Intake a structure built at one of the banks to abstract the water in to the Head race canal

    Head race canal or pipe a structure built to deliver water from the Intake to the Forebay tank with a

    minimum head loss

    De-sand tank a structure built to remove the sand particles which are harmful

    to the turbine runner, and constructed in the HRC path at a suitable location.

    Forebay tank a structure built to store water and serves as the intake to the penstock

    Spill way a structure built from the Forebay tank up to a nearest water way to direct water coming in when

    there is no power production Penstock - delivers water from the Forebay tank to the Turbine in the power house

    Power house Houses the turbines & generators

    Tail race delivers water from the power house back to the river

    Fig.1.0

    3. Planning stage of a small hydro power project

    At the planning stage of a hydro power project, the following documents or information are having significantimportance to carry out the layouts of the project and the structural engineering designs to minimize the negativeeffects to the environment. The main set of documents can be named as,

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    3/9

    WAC-IC 2014

    Page 3/9

    a. Environment approval conditionsThe impacts of the project to the environment are discussed at the environmental investigation report. Thenegative effects of the project are identified during the environmental study stage. Conditions related tomitigation of those negative effects are given in the project approval letter as conditions to be fulfilled by theproject proponent. The planning should be done to meet the conditions given in the approval letter.

    b. Flood volumes

    The design flood volumes at the weir and the power house are necessary in planning and designing the weir.The food levels of the river shall not be changed after construction of the weir across the river to a level whichaffects the houses, river crossings etc. In order to determine the flood level increase at the weir and the powerhouse after construction, a hydrology report shall be obtained from a hydrologist, which gives the 100 yearand 1000 year flood volumes.

    c. Project area detailed survey plan with contours

    To plan a small hydropower project, a detailed contour survey is essential. The detailed contour plan canindicate the ground levels as well as the existing structures, road network, locations and objects which shouldbe protected or avoided during implementation stage of the project. Further, the detailed contour survey plancan be used to develop a project lay out with optimum cost.

    d. Geological investigation report

    Excavation of slopes would be required to build the structures of the project. Also, the weir has to be

    constructed on the river bed across the river. It is necessary to safeguard the structures against water

    seepage, settlements, slope stability and foundation failures. In order to determine the slope stability and

    strength of the soil or rock at the foundation level of the structures, geology of the project area shall be studied

    and the findings of the geological investigation shall be presented in a geology report. Recommendations in

    the geology report shall be passed to the structural design engineer to have an optimal design solution.

    e. Construction material availability and access roads

    Availability of construction materials in close proximity to a site can reduce the cost of construction. Also, the

    access roads to access the project, head race canal, penstock and other structures locations are necessary. If

    they are already present, the construction cost and the environmental effects due to new roads construction

    can be reduced. Hence, the detailed land survey shall be carried out to pick the road network in the project

    area or to plan the new road network to be used during construction.

    3.1 Planning of Bulathwatha SHP project - weir and intake

    The project approval conditions of Forest Department of Sri Lanka being the project approval body had the following

    conditions with respect to weir construction.

    (a) Maximum height of the weir had been restricted to 1.17 m.

    (b) The environmental flow had been decided as 780 liters per second.

    (c) The silt deposit behind the weir had to be flushed out weekly.

    As the weir height had been restricted to 1.17 m and the river width was 20.6 m , the 100 year flood flow was not a

    serious issue in this case. The flood water rise due to 100 year flood flow was about 2.85 m above the weir top. The

    100 year flood water level change due to weir construction was estimated as 1.2 m. As the weir height was very short

    & continuous minimum environmental flow release was 780 l/s, a considerable negative impact was not created due to

    construction of the weir.

    As the weir height was restricted to 1.17 m, the sedimentation behind the weir can significantly reduce the water flow

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    4/9

    WAC-IC 2014

    Page 4/9

    in to the intake. Considering the operational aspects and the environmental aspects, two silt removal gates of 1m x 0.6

    m were provided to the weir. One gate was located near the intake and the other gate was located at the mid of the

    river to remove the silt frequently. Normally, only a single silt removal gate is provided at the mid of the weir in most of

    the projects of similar capacity.

    A 10 m wide side intake with a flow depth of 0.9 m was designed to abstract the designed flow in to the head race

    canal. A small drop weir was constructed in front of the intake opening to prevent sediment flow in to the intake. Theminimum flow pipe was located along the small weir to take the bed material with the continuous minimum flow

    release.

    3.2 Head race canal planning

    The project approval conditions of Forest Department had the following conditions with respect to canal construction.

    (a). Tree cutting should be minimum

    (b). Slope stability must be ensured by engineering designs

    (c). Over passes should be provided at every 50 m for terrestrial animals over the canal

    The total head race canal length was 1620 m. Initial 300 m of the head race canal was in the forest department

    reservation. It had very old rare types of trees like Kubuk (Terminalia arjuna). The second section of the head race

    canal (960 m) was in agricultural lands of individual village farmers. The third section of the head race canal (360 m)

    was again in forest department reservation.

    The first step in the design of the head race canal was commenced with preparation of detailed contour survey of the

    project land area. All the trees to be preserved in the canal trace were marked in the detailed survey plan. The head

    race canal alignment was selected using the detailed contour plans of the head race trace avoiding the large trees as

    much as possible.

    In meeting the condition (c) as given above, it was decided to construct a box canal through the initial 300 m section

    of the forest lands and to back fill over the canal and to reinstate the ground to the original condition to provide

    unhindered pass over the canal for the terrestrial animals. After reinstating the excavated ground over the canal, the

    slope stability issues were also automatically resolved. The box canal was provided with inspection manholes at 100

    m to inspect the canal during periodic maintenance.

    Photo. 1.0 - Concrete box canal constructed in first section of head race canal

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    5/9

    WAC-IC 2014

    Page 5/9

    The second section of the head race canal (960 m) and the De-sand tank were through farm lands of the villagers.

    Out of 960 m, 300 m was through the paddy field and the balance section was through the cultivated farm lands. The

    design of the head race canal in this section had two main challenges other than the approval conditions. They are,

    (a) 11 m high aquaduct of 60 m long required to be constructed over a valley. (b) There had been no land acquired to

    construct a spillway from the Forebay to the river. The forebay tank spills over when the turbine shuts down, and it is

    necessary to have a spillway from the forebay to the river to send the spill water. Although a decision was taken to

    acquire the lands for the forebay spill way, it was not possible to acquire additional lands than approved area from theForest department.

    Hence, to address these issues, the following three options were considered for the head race canal in the second

    section between the De-sand tank and the forebay tank.

    (a) A concrete open canal from the forebay tank with sufficient free board to bring water back to the De- sand

    tank when the turbines shut down;

    (b) A concrete box canal as a pressure conduit with surge tank, instead of a forebay;

    (c) A buried Glass fiber Reinforced Plastic (GRP) pipes as the head race pipe with surge tank, instead of

    forebay.

    The three options were ranked as follows considering environmental considerations, cost and the construction time.

    The cost of the GRP pipe construction was higher than concrete canal, but selection of best alternative did not

    consider the construction cost alone. The environmental considerations also were taken in to account and selection

    was made accordingly.

    Factors Concrete Open canal Concrete box canal GRP pipes

    No Restrictions onmovement to Villagers &Terrestrial animals

    1 2 3

    Safety to terrestrial animals 1 3 3

    Slope stability 1 2 3

    Excavation volume 2 2 1

    Removal of trees 1 2 3

    Construction cost 2 2 1Constructability over thevalley

    1 2 3

    Water tightness 2 1 3

    Durability 2 2 3

    Construction time 2 1 3

    Damage proneness if notburied

    2 3 1

    Head loss 2 2 3

    Maintenance 1 2 3

    18 26 33

    Key : 1- Poor , 2- Good, 3- Very Good

    Out of the three options, GRP pipe construction obtained highest rank, and hence considered as the best environment

    friendly option in Bulathwatha SHP project. So, the construction of second section of the head race canal used GRP

    pipes as the construction material.

    The construction of GRP pipes in Bulathwatha project was easy and a good construction progress was achieved as,

    a) The diameter of the head race pipes were 1.6 m, 1,4 m and 1.3 m;

    b) The technical assistance and solutions for pipe installation was given by HOBAS, Austrian GRP pipe

    manufacturer;

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    6/9

    WAC-IC 2014

    Page 6/9

    c) There were no steep slopes in the head race pipe trace other than four valleys which require open above

    ground pipe laying;

    d) The rock blasting was minimal . Excavation was not a problem as excavator could use;

    e) As the head race pipe trace was close to village road, pipe transportation to the head race trace was

    easy.

    Photo.2.0 Photo. 3.0

    Photo.2.0 - GRP pipe in a deep cut

    Photo.3.0 - GRP pipe as a siphon across a valley instead of a 11 m high aqueduct (pipe diameter 1.6 m)

    3.3 Selection of a Surge tank instead of a Forebay

    Having a Forebay tank with a spill way is usually the head pond arrangement at the upper end of the penstock. The

    forebay tank stores water, serves as the intake to the penstock and caters the sudden water demand of the turbine.

    But, a forebay tank is not constructed to store, when a operating turbine shut down. Hence, the water entering theforebay starts to spill over the forebay tank walls during a turbine shutdown. To prevent damage to the ground at the

    forebay, the spill water shall be directed safely to a river or to a natural stream using a spill way.

    The land required for the spill way of Bulathwatha SHP project was approximately 2000 m2 at the shortest route. The

    shortest forebay spill way route was through the forest department lands. The land necessary for the spill way at the

    forebay had not been acquired from the forest department at the land acquisition stage. Possibility of the location of a

    spill way between De-sand tank and the upper end of the penstock was investigated and found as not feasible due to

    land acquisition difficulties, environmental considerations and higher construction cost.

    As an alternative to the forebay tank which requires a spill way, a surge tank was considered as a feasible option in

    Bulathwatha SHP project. A surge tank is a circular, tall structure. The height of the surge tank is selected such that

    water will not spill over its top wall during turbine shut down and to have a sufficient volume of water required forsudden turbine opening .Correctly designed surge tank can handle the water demand of the turbines and the

    oscillations of the water surface within the surge tank without any spill. Therefore, the negative environmental effects

    like removal of trees, excavation for the spill way construction, blasting of rocks, erosion and threat to the lives of

    terrestrial animals and people could be avoided. In Bualthwatha SHP project, it was possible to avoid negative

    environmental impacts due to forebay spillway by selection of a surge tank as an alternative to forebay cum spillway

    solution.

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    7/9

    WAC-

    3.4

    At th

    strea

    to th

    the t

    and

    the e

    4.

    Ope

    (a).

    (b).

    IC 2014

    Selection

    e power ho

    m side to th

    water pool

    ail race direc

    he water po

    nvironment.

    Oper

    ations and m

    anagement

    anagement

    f power h

    se location,

    tail race exi

    after power g

    tion were pla

    l. The align

    Photo. 5.0

    tions

    aintenance o

    & maintenan

    & maintenan

    Photo. 4

    ouse & tai

    there is a n

    point in the

    eneration. T

    nned accord

    ent of the tai

    . Natural Water

    f the h

    f a SHPs ca

    ce of civil str

    ce of electro-

    .0 - 17 m high

    l race alig

    tural water

    original desi

    is condition

    ingly. Also, t

    l race was d

    pond at the tail

    dro po

    be divided i

    ctures & hyd

    mechanical

    urge tank (Und

    nment

    pool (Photo.

    n. The Fore

    was taken in

    ere were fe

    signed avoid

    race & one of Pr

    er proj

    to two cate

    ro- mechani

    quipment lik

    r construction)

    .0). The wa

    t departmen

    to account a

    huge trees

    ing the huge

    otected huge tr

    ect

    ories.

    al elements l

    turbines, ge

    er pool is si

    t requested t

    nd the powe

    (Kubuk) bet

    trees and wi

    e at the tail rac

    ike gates an

    nerators, co

    tuated abou

    o direct the

    house orien

    een the po

    th minimum

    trashracks

    trol systems

    15 m up

    ater back

    tation and

    er house

    amage to

    etc.

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    8/9

    WAC-IC 2014

    Page 8/9

    An SHP with an open head race canal , forebay tank, spill way at forebay, steel penstock etc. needs the following

    personnel to manage & maintain the structures ( Table -01). The necessary management and resources are given in

    the table.

    But, Bulathwatha SHP project is having GRP pipes instead of concrete open canal, surge tank instead of forebay

    tank and no spill way hence, no significant maintenance requirements ( Table -02) . Also, the penstock was

    constructed using GRP pipes. Hence, the selected structural arrangement minimizes negative environmental effects

    and saves the maintenance cost during the project life time.The two tables below compare the management of thestructures during operation phase of the project.

    Table -01 Management of structures (Head race canal / Forebay / Spillway)

    Structure Management Resources necessary

    Head race canal Road along the HR canal,

    safety fences, over crossings,

    weeding

    Drainage structures, side slopes

    1 person on regular basis,

    periodic maintenance funds

    Forebay tank Trash removal, trash rack, silt

    removal

    2 persons on regular basis.

    Spill way Erosion of the structures due to

    high velocity

    Periodic maintenance funds

    Penstock Painting, adjustment of

    expansion joints

    Periodic maintenance funds

    Table -02 Management of structures (Buried head race pipes/ Surge tank)

    Structure Management Resources necessary

    Head race pipe ( GRP) buried No maintenance Nil

    Surge tank No management Nil

    Spill way No spill way & No management Nil

    Penstock ( GRP) buried No maintenance Nil

    5. Conclusion

    Factors to be considered in selection of structures of a hydro power project which had to be constructed in

    environmentally sensitive area in line with the project approval conditions were discussed in the paper. The

    awareness of the project approval agency and their projects approval conditions by the stakeholders as well as design

    engineers can ensure minimum negative impacts to the environment. The logical selection process of structures

    based on engineering, environmental and operation & maintenance aspects at the design phase of a project ensure a

    viable power project. This aspect was elaborated using the examples drawn from Bulathwatha SHP where alternative

  • 8/10/2019 A Case on Planning and Operation of a Small Hydro Power Project With Minimum Negative Effects to the Environ

    9/9

    WAC-IC 2014

    Page 9/9

    structural forms were used instead of traditional head race canals and forebay tanks. The possibility of achieving

    savings on maintenance costs through adopting environment-friendly structural solutions was also highlighted. It is

    expected that the concepts discussed in the paper would be beneficial to design engineers and developers of Small

    Hydropower Schemes to be developed in environmentally sensitive areas.

    6. References1. Bulathwatha small hydropower project approval letter by Forest Department, Sri Lanka

    2. Standards/Manuals/Guidelines for small hydropower development Alternate hydro energy center, Indian

    Institute of Technology, Roorkee

    3. AWWA-M45-Fiberglass Pipe Design

    4. HOBAS pipe laying instructions (http://www.hobas.com)