Profile

Established in 1931 Phoenix is based in central London.

We specialise in the complete installation of Mechanical & Electrical to all work sectors including quality office developments, commercial and public buildings, data centers, retail, health, education, leisure,

hotels, residential and pharmaceuticals.

The company has an extensive client base including financial institutions, insurance companies, the legal and accountancy sectors and major pharmaceutical companies. Our clients include prominent

main and management contractors.

Our experience ranges from projects with a value in excess of £50M to £1M. Our special works division undertakes projects up to the

value of £1M.

Phoenix Mechanical was introduced in 2008 to form a stronger team and provide a fully coordinated and integrated service solution. We offer an M&E design & build management facility along with

design and development, installation of MV / LV distribution systems, shell & core, CAT A & B fit-out, HV cabling and switchgear, lighting control, BMS, Public Health, water treatment and commissioning,

At Phoenix we believe that the way to promote our business is

through the development of good working relationships with our clients. We aim to provide a high quality installation in an efficient,

friendly manner on time and to budget.

Phoenix ME

A better way to do business

New Year New Phoenix

After 83 years of successful trading as Phoenix Electrical Company Limited we have decided to rename the company to reflect that we

now undertake the full range of engineering services within the Construction sector. Our Mechanical capability has been developed to enable us to offer a competitive and proficient Mechanical and

Electrical combined service offer to meet our customers requirements. We feel that this requires us to market and identify

our services differently and to clearly communicate what our business does and where we see our future. We are therefore

pleased to announce a change of company name to

Phoenix ME Limited

Phoenix ME

A better way to do business

Management Staff

phoenix me

a better way to do business

Managing Director Lee Compton

Director Dave Cunningham

Director Stewart Crane

Operations Director Terry Perkins

Operations Director Adam Cecil

Operations Director Mike Viney

Project Director Sean O’Connor

Health, Safety & QA John King

Company Secretary Nigel Swanson

Director Colin Mint

Brett Cowlbeck Contracts Services

Manager Special Works

Project Director Simon Collingbourne

Claire Walker Procurement

Manager

Rita Gobin Estimating Manager

Tony Deacon CAD Manager

Danielle Browne Customer Relations

Turnover

Phoenix ME

A better way to do business

2011 - £44M

Mechanical £8M Electrical £36M

2012 - £52M

Mechanical £14.2M Electrical £31M

Construction £6.8M

2013 - £62M

Mechanical £16M Electrical £45M

Construction £1M

Project Profiles

Phoenix ME

A better way to do business

Phoenix have been appointed to carry out the services fit out for Arcadia’s

head office at Oxford Street. Works consist of Electrical , Mechanical and

Public Health services which includes ownership of BMS, Fire Alarm and

Sprinkler installations. The building is located above a live shopping centre

which occupies Levels grd – 1st with Arcadia’s demise consist of Part

basement level, grd floor receptions, levels 2-6 and roof. Arcadia currently

have staff occupying levels 3-5 whilst the fit out of the basement, core 1 (

grd – 6th floor), 2nd floor, 6th floor and roof are fitted out with new services

and Plant which consist of the following :

Generator works, LV Distribution, Lighting, LV Power, Uninterruptable

Power Supply, Earthing/bonding, Fire Alarm including disabled facilities,

Lighting Protection, Leak detection & Trac Heating, BMS, Rainwater,

Drainage, Gas, Domestic Services, General office supply & extract

ventilation, Fire rated Smoke extract ventilation from the shopping centre,

Toilet Extract, Kitchen Ventilation, Natural gas, LTHW, VRF System, DX

Split systems, AHU’s, Packaged Plant rooms, Sprinklers and Dry Risers.

Phoenix are the lead co-ordinator on the project and are responsible for

producing fully working coordinated drawings for all the above services ,

including new riser works which pass both through the shopping centre and

occupied Arcadia floors. As well as co-ordinating old plant with new in both

the roof and basement areas.

Phoenix are also working very closely with ISG, Arcadia and the Plaza

Shopping Centre teams to ensure the existing occupants are not affected

by any installation works, Major Plant shutdowns and the migration of old

services to new.

On completion of the above the Arcadia occupants on Level 5 will move to

Levels 2 & 6 to allow the strip out and fit out works to commence on level 5

with the process repeating for the remaining floors, this is a live project and

runs until July 2015.

phoenix me

a better way to do business

Arcadia

Client – Arcadia Group Main Contractor - ISG

Architect – Sheppard Robson Consultant – TB&A

Programme Duration – Sept 13 – Present Value – £10.6M Area – 12,542M2

phoenix me

a better way to do business

Phoenix were appointed by Double Negative (Europe’s largest visual effects company) to carry out the Mechanical & Electrical

fit out for there new London offices over five floors.

This project was CatB, providing Double Negative with new design studios, two bespoke purpose build cinemas, ten black out

screening rooms complete with remote on air indication, general offices, refreshment hubs and reception area complete with café

and seating, along with an illuminated pictorial work history.

At the heart of the business is a basement level main machine room (MCR). Cooling to the MCR is provided by the means of 48 chilled

water racks, supplied by three new chillers at roof level.

Many areas required a high end finish, such as specialised lighting to the Oscar award cabinet. Reception and cinemas required in-depth interfacing from mechanical plant, lighting and ceiling to

provide the desired finish. Throughout the fit-out there is a proportion of exposed

services.

Double Negative

Client – Double Negative Main Contractor – BW Interiors

Architect – MCM Consultant – Medland Metropolis

Quantity Surveyor – CBRE Programme Duration - 24 Weeks

(June 2012 – November 2012)

Value – £3.2M Area – 8000M²

phoenix me

a better way to do business

Phoenix have been appointed to carry out the Cat B Fit-Out

for Amazon’s new London head office. Works consisted of the

electrical, mechanical and public health services over 11 floors,

with additional plant space on the roof and basement levels.

All co-ordination drawings were produced on site and approval

given via workshops with the professional team.

Services consisted of extension to the LV system, new dedicated

UPS system and CRAC units serving MDF & IDF rooms, high and

low level power track installation serving fan coils with LTHW heater

batteries, fully addressable Simmtronic lighting control system and

specialist feature lighting.

Installation of new Advanced Air fan coil units served by new chilled

water installation, and the relocation of existing FCU’s, new supply

air and extract air system. Installation of public health tea points on

all levels west and east sides.

Flushing and commissioning was via a temporary floor mounted

pumps. All electrical testing and commissioning was

undertaken by Phoenix JIB approved operatives.

Tribble

Client – Amazon Main Contractor – BW Interiors

Architect – AI Architects Consultant – YES Engineering

Quantity Surveyor – Cushman & Wakefield Programme Duration –

2013 – Present Value – £7M

Area – 3700M²

60 Holborn Viaduct, EC1

phoenix me

a better way to do business

Phoenix have been appointed to carry out the Cat A&B Fit-Out

for Jardine Lloyd Thompson’s new London head office. Works

consisted of the electrical, mechanical and public health

services over 10 floors, with additional plant space on the roof

and basement levels.

All co-ordination drawings were produced on site and approval

given via workshops with the professional team.

Services consisted of extension to the LV system, new

dedicated UPS systems serving SER & MER rooms, high and

low level power track installation serving fan coils with electric

heater batteries, fully addressable DALI lighting control system

and specialist feature lighting.

Installation of 602 ability Matrix fan coil units served by new

chilled water installation, new supply and extract system.

Installation of public health showers, tea points and a fully

workable kitchens on various levels

Flushing and commissioning was via a temporary floor. Mounted

pumps over seen by Chesterfield prior to installation. All

electrical testing and commissioning was undertaken by

Phoenix JIB approved operatives.

JLT St Botolphs

Client – JLT Main Contractor – ISG

Architect – M Moser Associates Consultant – Grontmij

Quantity Surveyor – Capita Symonds Programme Duration - 36 Weeks

(November 2012 – July 2013)

Value – £10M Area – 27,000M2

Phoenix were appointed by ISG to carry out the Mechanical,

Electrical and Public Health Cat ‘A’ installation on levels Grd, 1,

2, 3, 5, 7, 8 & 9 and Cat ‘B’ fit out works on levels Grd, 1, 7, 9

and basement levels within the Walbrook.

The Cat ‘A’ works comprised off fully co-ordinated services

installation comprising off approx. 200 Diffusion FCUs a floor

with associated BMS controls and power supplying conditioned

air to the office space. FCUs were fed via a dedicated CHW

system that was integrated to the landlord system. Installation of

new DBs and associated tap off, h/l modular wiring power and

Simmtronic lighting control system

The Cat ‘B’ works comprised off installation off a dedicated AC

system to the on floor SERs, post room , and executive shower

room. Modifications to the Cat ‘A’ service to accommodate the

new meeting rooms, executive meeting rooms, executive offices,

tea points, WCs and pantry. A new kitchen ventilation system

providing conditioned air to the kitchen located on level 7 via an

AHU located within the ceiling void and extract fan at roof level.

Electrical installation comprising of fully co-ordinated under

power track installation, power supplies to SERs, desk top fit out,

specialist lighting to all executive areas and main receptions

New WCs, tea points, pantry and kitchen were provided

throughout consisting of all new DWS & PH and dedicated

extract ventilation system

phoenix me

a better way to do business

Walbrook

Fit-Out

Client Minerva & AJG Gallagher's

Main Contractor - ISG Architect

Fosters & partners Scott Brownrigg

Morey Smith Consultant

Cat A Gronmij Cat B HPF

Programme Duration Oct 2012 - Present

Value – £4.2M

phoenix me

a better way to do business

Phoenix were appointed as the principal contractor,

responsible for the full Design and Build and the Construction

of a 7 storey building which was located between two existing

buildings. The new building housed new Generators, MV and

LV switch panels and associated services. New Chillers were

added to the roof on one of the existing buildings which

required full structural strengthening.

Two floors in the existing building were stripped out and fully

fitted out as Data Halls.

The other ten floors in the building were occupied and all

existing services were maintained throughout the project. A

new incoming MV supply substation

was built under the DLR and new bulk fuel tanks were

housed in an external compound.

Within the data halls we installed new PDU’s, Cooling

CRACs, fire protection, water mist, new UPS system

were installed in new rooms and ventilation and

humidification systems were added in addition to the new

power and lighting systems. A full BMS/PMS and EMS

were installed to control the Generators and Power

management.

Harbour Exchange Data Centre

Client – Telecity Main Contractor – Phoenix

Architect – NWA Consultant – Houseman Henderson Quantity Surveyor – Davis Langdon Programme Duration - 44 Weeks

(January 2012 – November 2012)

Value – £18M Area – 8000M²

Phoenix ME

A better way to do business

Endorsements

Quadrant 3 Project

Technical Services Manager Sir Robert McAlpine

“100% well lead from the Project Director, Project

Manager and all site staff”

“Attitude excellent from the project manager through to all the team”

“Project completed early and within

budget / costs allocated”

The Walbrook Project

Technical Services Manager ISG

“Your complete team including your

subcontractors showed full commitment from start to finish, I was very pleased”

Double Negative Project

Project Director BW Interiors

“Bought competitively & quick.

Final account good”

“Director always keen to come to site and assist. Honest approach from the Project

Manager and all the Phoenix team”

Project Skype

Construction Director

ISG

“Phoenix consistently delivered an excellent product on time /on budget and to the highest

quality”

Project Salford

Project Manager Mace

“Pro-active attitude throughout”

“Good overall performance from the Phoenix Team and I look forward to

working with Phoenix again”

Phoenix ME