999779002 Method statement Doka form-ties for special … · The Formwork Experts 06/2006 999779002...
Transcript of 999779002 Method statement Doka form-ties for special … · The Formwork Experts 06/2006 999779002...
The Formwork Experts
06/2006
GB999779002
User informationMethod statement
Doka form-ties for special requirements
9779
-203
-03
3999779002 - 06/2006
Contents Page
User information Doka form-ties for special requirements Introduction
The Formwork Experts
General instructions for compliant utilisation............................................4Elementary safety warnings ........................................................................5Preliminary remarks .....................................................................................6
Form-tie system 15.0....................................................................................8
Design variants - Form-tie system 15.0 ......................................................9Water-stop connector 15.0.........................................................................10Fibre-concrete tube 22mm.........................................................................12Water stop G 15.0 .......................................................................................16Water stop 15.0...........................................................................................18Distance piece 20, 25, and 30cm ...............................................................20Plastic tube 22mm ......................................................................................21Expendable tie-rod with Anchor cones 15.0.............................................22
Form-tie system 20.0..................................................................................24
Design variants – Form-tie system 20.0....................................................25Water stop 20.0...........................................................................................26Fibre-concrete tube for Form-tie system 20.0 ..........................................28Plastic tube 26mm ......................................................................................29Expendable tie-rod with Anchor cones 20.0.............................................30
General remarks .........................................................................................32
Bibliography and literature........................................................................32
Component overview.................................................................................33
The Formwork Experts4 999779002 - 06/2006
Introduction User information Doka form-ties for special requirements
General instructions for compliant utilisation● This User Information booklet (Method State-
ment) is aimed at everyone who will be working with the Doka product or system it describes. It contains information on how to set up this sys-tem, and on correct, compliant utilisation thereof.
● Doka products are ONLY to be used in accord-ance with the Doka User Information booklets or other technical documentation provided by Doka.
● The functional/technical instructions, safety warnings and loading data must all be strictly observed and complied with. Failure to comply with this requirement may cause accidents, injury and damage.
● If any deviation from these instructions is con-templated, or any application which goes beyond those described here, revised static calculations must be produced for checking. The customer shall provide supplementary assembly instructions, and Doka's prior con-sent shall be required.
● The customer is to ensure that the User Infor-mation booklet (Method Statement) provided by Doka is available to all users and that they have been made aware of it and can easily access it.
● Always observe all industrial safety regulations and other safety rules applying to the applica-tion and utilisation of our products in the coun-try and/or region in which you are operating.
● Many of the illustrations in this booklet show the situation during formwork assembly and are therefore not always complete from the safety point of view.
● All materials must be inspected by the cus-tomer before use to ensure that they are in per-fect condition. Any components that are dam-aged, deformed, or weakened due to wear, cor-rosion or rot, must not be used.
● Only original Doka components may be used as spare parts.
● It could be dangerous to combine our form-work systems with those of other manufactur-ers. If you intend to combine different systems, please contact Doka for advice first.
● All persons working with the product described herein must be familiar with the contents of this manual and with all the safety instructions it contains.
● Persons who are incapable of reading and understanding this booklet, or who can do so only with difficulty, must be instructed and trained by the customer.
● The customer must ensure that this product is erected and dismantled, reset and generally used for its intended purpose under the direc-tion and supervision of suitably skilled persons with the authority to issue instructions.
User information Doka form-ties for special requirements Introduction
5999779002 - 06/2006 The Formwork Experts
Elementary safety warnings
Symbols usedThe following symbols are used in this booklet:
MiscellaneousWe reserve the right to make alterations in the inter-ests of technical progress.Unless otherwise stated, all dimensions are given in cm.
● Doka products and systems must be set up in such a way that all loads acting upon them are safely transferred!
● The stability of all components and units must be ensured during all phases of the construc-tion work!
● Provide safe workplaces for those using the formwork (e.g. for when it is being erected/dis-mantled, modified or repositioned etc). It must be possible to get to and from these workplaces via safe access routes!
● Do not exceed the permitted fresh-concrete pressures. Excessively high pouring rates lead to formwork overload, cause greater deflection and risk causing breakage.
● Do not strike the formwork until the concrete has reached sufficient strength and the person in charge has given the order for the formwork to be struck!
● When stripping the gang-form, never use the crane to break concrete cohesion. Use suitable tools such as timber wedges or a special pry-bar.
● When striking the formwork, do not endanger the stability of any part of the structure, or of any scaffolding, platforms or formwork that is still in place!
● Observe all regulations applying to the hand-ling of formwork and scaffolding. In addition, the Doka slinging means must be used - this is a mandatory requirement.
● Remove any loose parts or fix them in place so that they cannot fall off!
● All components must be stored safely, follow-ing all the special Doka instructions given in the relevant sections of this User Information book-let!
● Further safety instructions may be found in each of the sections of this booklet!
● The faulty utilisations shown in the various sections of this booklet are only a selection of examples taken from our many years' experi-ence in the field.
Important note
Failure to observe this may lead to malfunction or damage.
Caution / warning / danger
Failure to observe this may lead to material damage, and to injury to health which may range up to the severe or even life-threatening.
Instruction
This symbol indicates that actions need to be taken by the user.
Sight-check
Indicates that you need to do a sight-check to make sure that necessary actions have been carried out.
Tip
Points out useful practical tips.
☞
The Formwork Experts6 999779002 - 06/2006
Introduction User information Doka form-ties for special requirements
Preliminary remarksTo pour walls, it is necessary to have wall-ties with sufficient load-bearing capacity.
In general, a distinction is made between:● wall-ties where no special requirements are
made – these only need sustain the pressure of the fresh concrete – and
● wall-ties for special requirements that are ful-filled by additional measures aimed at making the tie-points e.g.:- water-impermeable- fire-resistant- sound-insulating- gas-impermeable- radiation-proof
This manual offers ideas and suggested solutions for form-tie points that need to meet one or more of the requirements stated above.
General remarks:
● Choosing a suitable formwork system with a widely spaced form-tie pattern is one way of reducing the number of expensive wall-ties that are needed. This will, of course, depend upon the circumstances and requirements applying on each site.
● If the main sealing function is intended to be in the middle of the wall (in the same way as with joint-sealing tape), this has the advantage that the form-tie point is watertight from the moment the formwork is stripped.
● Sealing measures that are carried out on the out-side only, e.g. by bonding, call for extremely skilled, painstaking work.
● Tie-holes with small conical openings are more pleasing to the eye (fair-faced concrete) and eas-ier to close off.
● In order to ensure that the wall-tie fulfils the requirements made of it, the points below must be followed, regardless of which design variant is selected:- the wall-tie must be precisely defined in the
tendering documents- the relevant regulations and Standards must
be observed- the manufacturer's installation instructions
must be followed- the personnel involved must be sufficiently
skilled
Water-impermeable concrete, and the wall-ties used in it
Concrete with high water-penetration resistance (watertight concrete without any extra sealing lay-ers), has been in use for many years now. When it comes to manufacturing and casting water-tight concrete, there is plenty of good, detailed liter-ature with references to DIN regulations etc. Water-tight form-ties, on the other hand, do not receive anything like as much attention in the pertinent Standards.
● Recent investigations have shown that the depth of water penetration into watertight concrete is only approx. 7 cm Source: "Feuchtetransport durch Bauteile aus Beton" (Moisture transmission through concrete structural components) in "Beton- und Stahlbe-tonbau" (Concrete and reinforced concrete con-struction), 4 1999
a ... up to approx. 7 cm (capillary region)b ... approx. 8 cm (drying-out region)d ... Wall thickness
"Water-impermeable" means that more water vaporises from the side facing away from the water pressure than penetrates into the side which is exposed to it.
9779-219-01
a
d
b
User information Doka form-ties for special requirements Introduction
7999779002 - 06/2006 The Formwork Experts
Form-tie points for special "dry" applicationsThe sealing techniques for fireproofing, acoustic insulation, radiation protection etc. are mostly sim-ilar to those for creating water-impermeable form-tie points, and use the same components.
Fitting the wall-tie
The properties set out in the test report can only be attained if the following conditions are met:● only undamaged and clean components are used● the components are only fitted by trained, skilled
personnel● all the relevant installation instructions are fol-
lowed
Concrete and concrete placementIn order for concrete structures to be cast in such a way that they fulfil architectural specifications, properly prepared wall-ties have to be combined with careful placing of the concrete.
● the concrete must be defined in accordance with the requirements- bid description to EN 206-1:2000
● attention must be paid to the quality of concrete placement- vibration, weathering, concrete-placement
method etc.
Minimum wall thicknesses
The wall thickness will be determined by the func-tion that the structure will have to fulfil.
The following practical site-related factors may necessitate a larger wall thickness:● the type of reinforcement● the concrete-placement method (be careful
regarding drop heights and de-mixing)● the type of compaction (internal or external
vibrators)In practice, the wall thickness will already have been decided. If the thickness stipulated is not ideal, then a suitable approach will need to be taken to tackling this situation.
Wall thickness required for placing the concrete by drop-pipe in accordance with the regulations
Example:a ... Drop-pipe diameter 15 cmb ... min. 20 cmd ... Wall thickness min. 30 cm
(Source: Lohmeyer / Ebeling "Weisse Wannen - ein-fach und sicher" - "Monolithic concrete tanks made easy".).
Tender documentsIt is on the basis of the tender documents that the most suitable design variant will be chosen ("suita-ble", that is, in terms of the use to which the struc-ture will later be put). All the variants outlined must make clear what additional work / costs will be involved, and the care that will need to be taken. It is advisable to give detailed descriptions of sizes, materials, fitting instructions and problem points. Also, there are several different design variants, as outlined in the following sections.
☞ ● Do not unscrew form-ties prematurely (in "green", i.e. new, concrete) or with violent hammer-blows. This would break the adhesion between the tie-rods and the concrete in which they are embedded, and might mean that the form-tie point is no longer watertight.
A Drop-pipe
B Reinforcement
C Formwork
D Concrete
9779-206-01
a
d
b
A
B
C
D
8 999779002 - 06/2006
User information Doka form-ties for special requirements
The Formwork Experts
Form-tie system 15.0
User information Doka form-ties for special requirements Form-tie system 15.0
9999779002 - 06/2006 The Formwork Experts
Design variants - Form-tie system 15.0Overview of the products used in the Doka Form-tie system 15.0, and their areas of application.
Note:
For special applications, such as in tunnels, please contact the "Tunnels" Expertise Centre.
Water-impermeable
Fire-resistant
Sound-insulating
Gas-impermeable
Radiation-proof
Water-stop connector 15.0
Fibre-concrete tube 22mm
Water stop G 15.0
Water stop 15.0 or
Water stop S 15.0 (sulphate-
resistant)
Page 10 Page 12 Page 16 Page 18
Fibre-concrete tube 22mm Water stop G 15.0
Water stop 15.0 orWater stop S 15.0
(sulphate-resistant)
Page 12 Page 16 Page 18
Distance piece
Expendable Tie-rod 15.0
with 2 anchor cones
Page 20 Page 22
Fibre-concrete tube 22mm Water stop G 15.0
Water stop 15.0 orWater stop S 15.0
(sulphate-resistant)
Page 12 Page 16 Page 18
Distance piece Plastic tube 22mm
Expendable Tie-rod 15.0
with 2 anchor cones
Page 20 Page 21 Page 22
Fibre-concrete tube 22mm Water stop G 15.0
Water stop 15.0 orWater stop S 15.0
(sulphate-resistant)
Page 12 Page 16 Page 18
Fibre-concrete tube 22mm
Water stop G 15.0
Water stop 15.0 or
Water stop S 15.0 (sulphate-
resistant)
Expendable Tie-rod 15.0
with 2 anchor cones
Page 12 Page 16 Page 18 Page 22
The Formwork Experts10 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Water-stop connector 15.0
Can be mounted in walls with a thickness of 20 cm and above.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable
Preparing the form-tie pointVarious types of wall-tie can be prepared using the Water-stop connector.
General instructions for sealing the form-tie
point
In its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
Variant 1With plastic tubes and conesIn this variant, the tie-rods can be re-used.
Form-tie point enclosed by formwork
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 20 cmb ... depends on wall thickness
Fixed dimensions:c ... 7.4 cmd ... 1 cm
Closing off the form-tie point
➤ Either remove the Universal cone 26mm or leave it in place.
➤ If desired, close off the form-tie point with a Plug 26mm (K) .
➤ Always screw in components until they fully engage.
➤ Use 2 Spanners for tie-rods to tighten the tie-rods so firmly that they cannot be dis-lodged when the form-tie assembly is being fitted or reinforcement is being placed.
➤ Never weld or heat tie-rods - risk of frac-ture!
A Water-stop connector 15.0
B Plastic tube 26 mm
C Universal cone 26 mm
D Tie-rod 15.0mm (length as dictated by formwork)
E Super-plate 15.0
F Formwork
9779-215-01
A
B
C
BC
9779-210-01
F
A DCB E
9779-210-02
c
a
b bd d
9779-210-03
K
User information Doka form-ties for special requirements Form-tie system 15.0
11999779002 - 06/2006 The Formwork Experts
Variant 2Anchor cone 15.0 on one sideCan be mounted in walls with a thickness of 30 cm and above.The Anchor cone enables the "Water-stop connec-tor plus tie-rod" assembly to be positioned and fixed on one side of the formwork even before the reinforcement is placed.The tie-rod on the cone-side remains in the con-crete. The Anchor cone can be used either on both sides or on one side only.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchor cone 15.0:● Reversible ratchet 1/2"● Box nut 24
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 30 cmb ... form-tie length 11.6 cm where wall thickness is 30 cmc ... 7.3 cm where wall thickness is 30 cm
Fixed dimensions:d ... 6 cme ... 4.1 cmf ... 1 cm
Closing off the form-tie point
● For details on closing off the openings on the Anchor-cone side see the section headed "Water stop G 15.0 33cm".
● For details on closing off the opposite side, see the previous Variant.
A Water-stop connector 15.0
B Plastic tube 26 mm
C Universal cone 26 mm
D Anchor cone 15.0
E Tie-rod 15.0mm (length as dictated by formwork)
F Super-plate 15.0
G Formwork
9779-216-01
A
B
C
E
D
9779-209-03G
A ED B C F
b fe cd
a
9779-209-04
The Formwork Experts12 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Fibre-concrete tube 22mm
Can be mounted in walls with a thickness of 8 cm and above.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable● fire-resistant● sound-insulating● gas-impermeable● for civil defence structures (radiation-proof)Proofs provided by Frank GmbH & Co. KG, Ger-many.
Ready-cut lengths available from Doka:
Preparing the form-tie point
Form-tie point enclosed by formwork
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 8 cmb ... cut-to-size length of the fibre-concrete tube 22mm
Fixed dimensions:c ... 1 cm
A Fibre-concrete tube 22mm
B Universal cone 22mm
C Fibre-concrete plug 22mm
Item name For wall thicknessFibre-concrete tube 22mm 0.18m 20 cmFibre-concrete tube 22mm 0.23m 25 cmFibre-concrete tube 22mm 0.28m 30 cmFibre-concrete tube 22mm 0.38m 40 cm
Fibre-concrete tube 22mm 1.25m For cutting to any length
9779-205-01
AC
B
☞ ● Always use fibre-concrete tubes of the same length – otherwise the formwork cannot be closed cleanly, and laitance may penetrate into the Universal cones, making it difficult to remove them.
● Keep fibre-concrete tubes well away from release-agent. Also, do not wear release-agent-smeared gloves when fitting them. Otherwise, the in-situ concrete will not bind sufficiently tightly to the tubes.
● Thoroughly moisten the fibre-concrete tubes before pouring.
● Time any interruptions to placement cor-rectly.
A Fibre-concrete tube 22mm
B Universal cone 22mm
C Tie-rod 15.0
D Super-plate 15.0
E Formwork
Longer cones are also commercially availa-ble. These cones can be cut to size for e.g. sloping walls.
9779-224-04
E
A B CD
9779-224-05
b
a
c c
9779-218-01
User information Doka form-ties for special requirements Form-tie system 15.0
13999779002 - 06/2006 The Formwork Experts
Methods of preparing the form-tie point in walls up to 40 cm thick
Normal closure –
fire-resistant to F30
● One Fibre-concrete plug 22mm is glued in on either side.
Watertight closure –
fire-resistant to F30 - F180
● Two Fibre-concrete plugs 22mm are glued in on either side.
Soundproof closure
● Several Fibre-concrete plugs 22mm are glued in, together filling 4/5 of the length of the fibre-con-crete tube.
● Glue in the plugs with REPOXAL two-component glue.
Gas-tight and radiation-proof closure
● Several Fibre-concrete plugs 22mm are glued in, filling the entire length of the fibre-concrete tube
Wall-thicknesses over 40 cm
● From 40 to 60 cm – with a coupling in the middle
● Over 60 cm – with a steel tube in the middle
Note:
Suitable products for preparing special ties in walls that are more than 40 cm thick may be obtained from e.g. Frank GmbH & Co. KG, Germany.
Minimum wall thicknesses for vari-ous fire-resistance classes
Reinforced concrete walls cast in normal concrete to DIN 4102-4: 1994-03
Fire-walls cast in normal concrete
☞ The version used on F90 fire-walls corre-sponds to the watertight type of closure with 2 plugs on either side.Also, completely grout the remaining cavity with FRANK special mortar 3/25.
9779-200-01
9779-200-02
9779-200-03
9779-200-03
Fire-resistance classMinimum wall thickness
Non-load-bearing Load-bearingF30 80 mm 120 mmF60 90 mm 130 mmF90 100 mm 140 mm
F120 120 mm 160 mmF180 150 mm 210 mm
Fire-resistance class
Minimum wall thickness
Non-rein-forced
ReinforcedNon-load-
bearingLoad-bear-
ingF90 200 mm 120 mm 140 mm
9779-204-01
9779-204-02
The Formwork Experts14 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Closing off the form-tie point
Cleaning the centre-hole
➤ e.g. with a round brush or a drill bit. The fibre-concrete tubes should be as dry as possible; any water must be removed.
Mixing the REPOXAL two-component glue
➤ Completely empty the contents of the hardener pot into the can of REPOXAL glue. Thoroughly mix the hardener and the glue to make a com-pletely homogeneous mass.
Sealing the tubes with plugs
➤ Always start fitting the plugs on the side of the wall exposed to water pressure.
➤ Dip the first plug into the glue and briefly rotate it in the glue so that its entire circumference is wet-ted. Now push in the plug with the tamping tool until the top of the plug is approx. 5 mm inside the fibre-concrete tube.
➤ Then insert the second plug, after dipping it into the glue in the same way. Push it in until it is flush with the end of the tube, then spread the rest of the glue.
Correctly closed-off form-tie point
Wrong:
➤ Now these plugs should be left for several hours so that the glue can harden before the end of the tube facing away from the water-pressure is closed off with plugs in the same way.If you do not leave sufficient time for the glue to set, the air being compressed inside the tube may push out or loosen the plugs at the first end of the tube.
☞ The important job of plugging and sealing the form-tie point should only be entrusted to reliable and experienced workers or sub-contractors.
If the plugs will not fit into the tube because cement paste has run into the opening and dried, this can be drilled out with a Widia drill bit. Specially short drill bits with exactly calibrated diameters are available for this job.
Wherever possible, wear gloves when fit-ting the plugs.Any glue that gets onto your hands can be cleaned off with spirit or thinner. After this, wash your hands thoroughly with water and soap.
9779-202-02
☞ If a hydrostatic pressure test is intended, this should be performed with only the two plugs on the water-pressure side inserted – i.e. before the plugs on the other side have been fitted. After the plugs have been inserted on the water-pressure side, the glue must be allowed to set. The waiting time is highly temperature-dependent. For the structure temperatures given below, it will be as follows:● 20°C – approx. 10 days● 10°C – approx. 24 days● 5°C – approx. 40 days
After the end of this waiting time, the tank or vessel (for example) can be filled.Once any pressure test has been carried out, the end of the tube facing away from the water-pressure can be closed off with two plugs as described above.
9779-202-03
9779-202-04
9779-202-05
User information Doka form-ties for special requirements Form-tie system 15.0
15999779002 - 06/2006 The Formwork Experts
REPOXAL two-component glue
Area of utilisation
REPOXAL two-component glue is used for plugging fibre-concrete tubes.
Product description
Owing to its chemical composition, REPOXAL two-component glue reacts with the REPOXAL hard-ener. This chemical reaction results in a hard, watertight, chemical-resistant adhesive.
Pot life
The ready-mixed adhesive remains workable for max. 4 hours at 20°C.
Setting time
At temperatures of 20°C, the glued plugs can be subjected to gentle loading after 48 hours, and to normal loading after 96 hours.Higher temperatures shorten the pot-life and the reaction times, while lower temperatures prolong them.At temperatures below +5°C, no chemical reaction takes place and the glue cannot set. For this reason, do not attempt to use the glue at temperatures below +5°C.The temperatures given here always refer to the temperature of the building component.
Yield
For 1000 plugs, each 2 cm long, the following quan-tities of REPOXAL two-component glue will be con-sumed:● ø 22 mm - approx. 3 kg● ø 27 mm - approx. 4 kg● ø 32 mm - approx. 5 kg● ø 40 mm - approx. 7 kg
Resistance
REPOXAL two-component glue is resistant to tap water, seawater, waste water in sewage treatment plants and water containing ozone or chlorine used in swimming pools.In addition, loading tests have been carried out with a wide variety of agents, to which REPOXAL two-component glue has been proven resistant.
The Formwork Experts16 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Water stop G 15.0
Can be mounted in walls with a thickness of 25 cm and above.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable● fire-resistant to F90● sound-insulating● gas-impermeable● radiation-proof
Preparing the form-tie pointThe Water stop G 15.0 is an economical way of pre-paring form-tie points that will meet the above requirements.The anchor cones, tie-rods and super-plates can be re-used over and over again. The Water stop G remains embedded in the concrete. The form-tie can be ordered in various different lengths, as necessitated by the thickness of the wall. Can be ordered under Art.n° 580100000.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchor cone 15.0:● Reversible ratchet 1/2"● Box nut 24
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 25 cmb ... form-tie length 13 cm where wall thickness is 25 cmUp to a tie-rod length of 40 cm, the plate of the Water stop G 15.0 33cm must be positioned in the middle of the rod.Where the tie-rod is between 40 cm and 150 cm long, the plate must be positioned at a fixed distance of 20 cm from the end of the tie-rod.(Varying lengths - b - can be ordered under Art.n° 580100000).
Fixed dimensions:c ... 6 cm
A Water stop G 15.0
B Anchor cone 15.0
➤ Always screw in components until they fully engage.
➤ Never weld or heat tie-rods - risk of frac-ture!
9779-213-01 A
BB
A Water stop G 15.0
B Anchor cone 15.0
C Tie-rod 15.0mm (length as dictated by formwork)
D Super-plate 15.0
E Formwork
9779-207-01
E
A CB D
9779-207-02
b
a
c c
User information Doka form-ties for special requirements Form-tie system 15.0
17999779002 - 06/2006 The Formwork Experts
Closing off the form-tie pointIn its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
Example with fibre concrete plug
We recommend the following materials for gluing in the plugs:● Commercially available cement mortar, e.g.
repair and renovation mortar, watertight exterior grouting compound etc.Pay attention to the colour of the concrete here!
● Tile bonding cement (is mostly dark) in cases where the colour of the concrete is unimportant.
➤ Evenly distribute the mortar mixture in the coni-cal opening and then slowly press the Fibre con-crete plug 54mm (K) into the opening while gen-tly turning it. (Using a piece of wood makes it easier to fit the plug on the right plane).
Grout level with the rest of the surface
➤ Fill the remaining space (L) with mortar and grout it smoothly.
☞ If it is still necessary to close off the form-tie point, for rust protection reasons (tie-rod), we recommend gluing in a fibre-concrete plug.The job of closing off the form-tie point should only be carried out by reliable skilled workers or competent subcontractors.
9779-212-01
K
9779-212-01
K
L
The Formwork Experts18 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Water stop 15.0
Can be mounted in walls with a thickness of 33 cm and above.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable● fire-resistant to F90● sound-insulating● gas-impermeable● radiation-proof
In addition to these properties, the Water stop S 15.0 is also sulphate-resistant.
Preparing the form-tie pointThe Water stop 15.0 consists of a tie-rod with a fibre-concrete disc glued onto the middle of the rod.The anchor cones, tie-rods and super-plates can be re-used over and over again. The Water stop 15.0 remains embedded in the concrete. The form-tie can be ordered in various different lengths, as necessitated by the thickness of the wall. Can be ordered under Art.n° 580100000.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchor cone 15.0:● Reversible ratchet 1/2"● Box nut 24
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 33 cmb ... form-tie length 21 cm where wall thickness is 33 cmFor form-tie length of up to 150 cm. Above this: on request.(Varying lengths - b - can be ordered under Art.n° 580100000).
Fixed dimensions:c ... 6 cm
A Water stop 15.0
B Anchor cone 15.0
➤ Always screw in components until they fully engage.
➤ Never weld or heat tie-rods - risk of frac-ture!
9779-214-01A
BB
A Water stop 15.0
B Anchor cone 15.0
C Tie-rod 15.0mm (length as dictated by formwork)
D Super-plate 15.0
E Formwork
9779-208-01
E
A CB D
9779-208-02
b
a
c c
User information Doka form-ties for special requirements Form-tie system 15.0
19999779002 - 06/2006 The Formwork Experts
Closing off the form-tie pointIn its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
Example with fibre concrete plug
We recommend the following materials for gluing in the plugs:● Commercially available cement mortar, e.g.
repair and renovation mortar, watertight exterior grouting compound etc.Pay attention to the colour of the concrete here!
● Tile bonding cement (is mostly dark) in cases where the colour of the concrete is unimportant.
➤ Evenly distribute the mortar mixture in the coni-cal opening and then slowly press the Fibre con-crete plug 54mm (K) into the opening while gen-tly turning it. (Using a piece of wood makes it easier to fit the plug on the right plane).
Grout level with the rest of the surface
➤ Fill the remaining space (L) with mortar and grout it smoothly.
☞ If it is still necessary to close off the form-tie point, for rust protection reasons (tie-rod), we recommend gluing in a fibre-concrete plug.The job of closing off the form-tie point should only be carried out by reliable skilled workers or competent subcontractors.
9779-212-01
K
9779-212-01
K
L
The Formwork Experts20 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Distance piece 20, 25, and 30cm
for wall thicknesses of 20, 25 and 30 cm.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● fire-resistant to F90● sound-insulating
Preparing the form-tie pointThe tie-rods and super-plates can be re-used over and over again. The distance piece remains embed-ded in the concrete.
Form-tie point enclosed by formwork
Formwork stripped from around form-tie point
Fixed dimensions:a ... wall thickness 20, 25 and 30 cm
Closing off the form-tie point➤ Close off the distance piece with the plugs (K)
supplied with each distance piece unit.
A Distance piece with integral plugs
A Distance piece
B Tie-rod 15.0
C Super-plate 15.0
D Formwork
9779-223-01
D
A BC
9779-223-02
a
9779-223-03
K
User information Doka form-ties for special requirements Form-tie system 15.0
21999779002 - 06/2006 The Formwork Experts
Plastic tube 22mm
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● sound-insulating
Preparing the form-tie point➤ Cut a length of Plastic tube 22mm to the desired
length, and insert a Universal cone 22mm into either end of the tube.
The tie-rods and super-plates can be re-used over and over again. The plastic tube remains embedded in the concrete.
Form-tie point enclosed by formwork
Formwork stripped from around form-tie point
Variable dimensions:a ... wall thicknessb ... cut-to-size length of the plastic tube
Fixed dimensions:c ... 1 cm
Closing off the form-tie point➤ Either remove the Universal cone 22mm or leave
it in place.➤ If desired, close off the form-tie point with a Plug
22mm (K) .
A Plastic tube 22mm
B Universal cone 22mm
C Plug 22mm
9779-222-01
AC
B
A Plastic tube 22mm
B Universal cone 22mm
C Tie-rod 15.0mm (length as dictated by formwork)
D Super-plate 15.0
E Formwork
9779-224-01
E
A CB D
9779-224-02
b
a
c c
9779-224-03
K
The Formwork Experts22 999779002 - 06/2006
Form-tie system 15.0 User information Doka form-ties for special requirements
Expendable tie-rod with Anchor cones 15.0
Can be mounted in walls with a thickness of 25 cm and above.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● fire-resistant to F90● sound-insulating● radiation-proof
Preparing the form-tie pointThe anchor cones and super-plates can be re-used over and over again. The Tie-rod 15.0 remains embedded in the concrete.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchor cone 15.0:● Reversible ratchet 1/2"● Box nut 24
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 25 cm where the form-tie has a bond length of 27 mm in the concreteb ... form-tie length 13 cm where wall thickness is 25 cm
Fixed dimensions:c ... 6 cm
A Tie-rod 15.0
B Anchor cone 15.0
➤ Always screw in components until they fully engage.
➤ Never weld or heat tie-rods - risk of frac-ture!
9779-213-02
A
BB
A Tie-rod 15.0
B Anchor cone 15.0
C Tie-rod 15.0 (length as dictated by formwork)
D Super-plate 15.0
E Formwork
9779-207-03
E
A CB D
9779-207-04
b
a
c c
User information Doka form-ties for special requirements Form-tie system 15.0
23999779002 - 06/2006 The Formwork Experts
Closing off the form-tie pointIn its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
Example with fibre concrete plug
We recommend the following materials for gluing in the plugs:● Commercially available cement mortar, e.g.
repair and renovation mortar, watertight exterior grouting compound etc.Pay attention to the colour of the concrete here!
● Tile bonding cement (is mostly dark) in cases where the colour of the concrete is unimportant.
➤ Evenly distribute the mortar mixture in the coni-cal opening and then slowly press the Fibre con-crete plug 54mm (K) into the opening while gen-tly turning it. (Using a piece of wood makes it easier to fit the plug on the right plane).
Grout level with the rest of the surface
➤ Fill the remaining space (L) with mortar and grout it smoothly.
☞ If it is still necessary to close off the form-tie point, for rust protection reasons (tie-rod), we recommend gluing in a fibre-concrete plug.The job of closing off the form-tie point should only be carried out by reliable skilled workers or competent subcontractors.
9779-212-01
K
9779-212-01
K
L
24 999779002 - 06/2006
User information Doka form-ties for special requirements
The Formwork Experts
Form-tie system 20.0
User information Doka form-ties for special requirements Form-tie system 20.0
25999779002 - 06/2006 The Formwork Experts
Design variants – Form-tie system 20.0Overview of the products used in the Doka Form-tie system 20.0, and their areas of application.
Note:
For special applications, such as in tunnels, please contact the "Tunnels" Expertise Centre.
Water-impermeable
Fire-resistant
Sound-insulating
Gas-impermeable
Radiation-proof
Water stop 20.0 Fibre-concrete tube for Form-tie system 20.0
Page 26 Page 28
Water stop 20.0
Fibre-concrete tube for
Form-tie system 20.0
Expendable Tie-rod 20.0
with 2 anchoring cones
Page 26 Page 28 Page 30
Water stop 20.0 Fibre-concrete tube for Form-tie system 20.0
Page 26 Page 28
Plastic tube 26mm
Expendable Tie-rod 20.0
with 2 anchoring cones
Page 29 Page 30
Water stop 20.0 Fibre-concrete tube for Form-tie system 20.0
Page 26 Page 28
Water stop 20.0
Fibre-concrete tube for
Form-tie system 20.0
Expendable Tie-rod 20.0
with 2 anchoring cones
Page 26 Page 28 Page 30
The Formwork Experts26 999779002 - 06/2006
Form-tie system 20.0 User information Doka form-ties for special requirements
Water stop 20.0
Can be mounted in walls with a thickness of 42 cm and above.
Note:
It is also possible to use the She-bolt 20.0 instead of the Anchoring cone 20.0.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable● fire-resistant to F90● sound-insulating● gas-impermeable● radiation-proof
Preparing the form-tie pointThe Water stop 20.0 consists of a tie-rod with a fibre-concrete disc glued onto the middle of the rod.The anchoring cones, tie-rods and super-plates can be re-used over and over again. The Water stop 20.0 remains embedded in the concrete. The form-tie can be ordered in various different lengths, as necessitated by the thickness of the wall. Can be ordered under Art.n° 580100000.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchoring cone:● Cone spanner 20.0
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 25 cmb ... form-tie length 25.6 cm where wall thickness is 42 cmFor form-tie length of up to 150 cm. Above this: on request.(Varying lengths - b - can be ordered under Art.n° 580100000).
Fixed dimensions:c ...8.2 cm
A Water stop 20.0
B Anchoring cone 20.0 + Sealing sleeve 20.0
➤ Always screw in components until they fully engage.
➤ Never weld or heat tie-rods - risk of frac-ture!
9779-217-01A
BB
A Water stop 20.0
B Anchoring cone 20.0 + Sealing sleeve 20.0
C Tie-rod 20.0mm (length as dictated by formwork)
D Super-plate 20.0
E Formwork
9779-211-01
E
A CB D
9779-211-02
b
a
c c
User information Doka form-ties for special requirements Form-tie system 20.0
27999779002 - 06/2006 The Formwork Experts
Closing off the form-tie point
In its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
➤ Remove the sealing sleeve (J) .
Example with fibre concrete plug
We recommend the following materials for gluing in the plugs:● Commercially available cement mortar, e.g.
repair and renovation mortar, watertight exterior grouting compound etc.Pay attention to the colour of the concrete here!
● Tile bonding cement (is mostly dark) in cases where the colour of the concrete is unimportant.
➤ Evenly distribute the mortar mixture in the coni-cal opening and then slowly press the Fibre con-crete plug 45mm (M) into the opening while gen-tly turning it. (Using a piece of wood makes it easier to fit the plug on the right plane).
Grout level with the rest of the surface
➤ Fill the remaining space (L) with mortar and grout it smoothly.
☞ If it is still necessary to close off the form-tie point, for rust protection reasons (tie-rod), we recommend gluing in a fibre-concrete plug.The job of closing off the form-tie point should only be carried out by reliable skilled workers or subcontractors.
9779-217-02
J
9779-217-03
M
9779-217-03
M
L
The Formwork Experts28 999779002 - 06/2006
Form-tie system 20.0 User information Doka form-ties for special requirements
Fibre-concrete tube for Form-tie system 20.0
Not in the Doka sales range. Can be obtained from e.g. Frank GmbH & Co. KG, Germany.Allow for delivery times.
Matching tubes, cones and fibre-concrete plugs for the Form-tie system 20.0 can be obtained from e.g. Frank GmbH & Co. KG, Germany.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● water-impermeable● fire-resistant● sound-insulating● gas-impermeable● for civil defence structures (radiation-proof)Proofs provided by Frank GmbH & Co. KG, Ger-many.
Preparing the form-tie pointThe form-tie point is prepared here in the same way as with the Form-tie system 15.0 using the Fibre-concrete tube 22mm.
A Fibre-concrete tube d27 ("Frank" product name)
B Cone d27 ("Frank" product name)
C Stopper d27 ("Frank" product name)
9779-205-01
AC
B
User information Doka form-ties for special requirements Form-tie system 20.0
29999779002 - 06/2006 The Formwork Experts
Plastic tube 26mm
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● sound-insulating
Preparing the form-tie point➤ Cut a length of Plastic tube 26mm to the desired
length, and insert Universal cones 26mm into both ends of the tube.
The tie-rods and super-plates can be re-used over and over again. The plastic tube remains embedded in the concrete.
Form-tie point enclosed by formwork
Formwork stripped from around form-tie point
Variable dimensions:a ... wall thicknessb ... cut-to-size length of the plastic tube
Fixed dimensions:c ... 1 cm
Closing off the form-tie point➤ Either remove the Universal cone 26mm or leave
it in place.➤ If desired, close off the form-tie point with a Plug
26mm (K) .
A Plastic tube 26mm
B Universal cone 26mm
C Plug 26mm
9779-227-01
AC
B
A Plastic tube 26mm
B Universal cone 26mm
C Tie-rod 20.0mm (length as dictated by formwork)
D Super-plate 20.0
E Formwork
9779-228-01
E
A CB D
9779-228-02
b
a
c c
9779-228-03
K
The Formwork Experts30 999779002 - 06/2006
Form-tie system 20.0 User information Doka form-ties for special requirements
Expendable tie-rod with Anchor cones 20.0
Can be mounted in walls with a thickness of 35 cm and above.
Note:
It is also possible to use the She-bolt 20.0 instead of the Anchoring cone 20.0.
Is suitable for preparing wall-ties that meet the fol-lowing requirements:● fire-resistant to F90● sound-insulating● radiation-proof
Preparing the form-tie pointThe anchoring cones and super-plates can be re-used over and over again. The Tie-rod 20.0 remains embedded in the concrete.
Form-tie point enclosed by formwork
Tools needed for unscrewing the Anchoring cone:● Cone spanner 20.0
Formwork stripped from around form-tie point
Variable dimensions:a ... minimum wall thickness 35 cmb ... depends on wall thickness
Fixed dimensions:c ... 8.2 cm
A Tie-rod 20.0
B Anchoring cone 20.0 + Sealing sleeve 20.0
➤ Always screw in components until they fully engage.
➤ Never weld or heat tie-rods - risk of frac-ture!
9779-217-04
A
BB
A Tie-rod 20.0
B Anchoring cone 20.0 + Sealing sleeve 20.0
C Tie-rod 20.0mm (length as dictated by formwork)
D Super-plate 20.0
E Formwork
9779-211-03
E
A CB D
9779-211-04
b
a
c c
User information Doka form-ties for special requirements Form-tie system 20.0
31999779002 - 06/2006 The Formwork Experts
Closing off the form-tie pointIn its technical bulletin entitled "Fair-faced con-crete", the DBV (German Concrete Association) rec-ommends leaving cone indentations as they are. This is because attempts to grout them level with the rest of the surface normally produce unsatisfac-tory results (colour differences, grouted areas have unclean edges).
➤ Remove the sealing sleeve (J) .
Example with fibre concrete plug
We recommend the following materials for gluing in the plugs:● Commercially available cement mortar, e.g.
repair and renovation mortar, watertight exterior grouting compound etc.Pay attention to the colour of the concrete here!
● Tile bonding cement (is mostly dark) in cases where the colour of the concrete is unimportant.
➤ Evenly distribute the mortar mixture in the coni-cal opening and then slowly press the Fibre con-crete plug 45mm (M) into the opening while gen-tly turning it. (Using a piece of wood makes it easier to fit the plug on the right plane).
Grout level with the rest of the surface
➤ Fill the remaining space (L) with mortar and grout it smoothly.
☞ If it is still necessary to close off the form-tie point, for rust protection reasons (tie-rod), we recommend gluing in a fibre-concrete plug.The job of closing off the form-tie point should only be carried out by reliable skilled workers or subcontractors.
9779-217-02
J
9779-217-03
M
9779-217-03
M
L
32 999779002 - 06/2006
User information Doka form-ties for special requirements
The Formwork Experts
General remarks
Bibliography and literature● Prof. K. Simons / Dipl.-Ing. P. Kolbe, "Verfahren-
stechnik im Ortbetonbau"("A process-engineer-ing approach to cast-in-place building construc-tion"), 1987.
● Werner Nehls, "Wasserundurchlässige Scha-lungsanker" ("Water-impermeable form-ties"), Document n° 32825 from the archives of publish-ers GRIN Verlag
● Lohmeyer / Ebeling, "Weisse Wannen - einfach und sicher" ("Monolithic concrete tanks made easy"), published by Verlag Bau+Technik, Düs-seldorf 2004.
● Gottfried C.O. Lohmeyer, Dipl.-Ing. "Schäden an Flachdächern und Wannen aus wasserundurch-lässigem Beton" ("Damage to flat roofs and tanks cast in water-impermeable concrete", published by Fraunhofer IRB-Verlag 2001, 3rd Edition.
● "Feuchtetransport durch Bauteile aus Beton" ("Moisture transmission through concrete struc-tural components") in "Beton- und Stahlbeton-bau" (Concrete and reinforced concrete construc-tion, 4 1999)
● Report n° 21 0791568 MPA Dortmund, Sept. 1986. Applicant: Reuß GmbH, Sprockhövel.
● German Reinforced-Concrete Committee (DAStb). "Wasserundurchlässige Bauwerke" ("Water-impermeable structures"), Edition 2003 – 11,
● DBV technical bulletin "Wasserundurchlässige Baukörper aus Beton" ("Water-impermeable building members made of concrete"), DBV (Ger-man Concrete Association), Aug. 1999.
● DIN 18216 "Formwork ties; requirements, testing, use".
● DIN 1045 "Concrete, reinforced and prestressed concrete structures".
● DIN 4102 and ÖNORM B 3800 "Fire behaviour of building materials and building components".
● DIN EN ISO 717-1 "Acoustics - Rating of sound insulation in buildings and of building elements".
Article n°[kg] Article n°[kg]
33999779002 - 06/2006
User information Doka form-ties for special requirements
The Formwork Experts
Component overview
Doka System Components
Form tie system 15.0
Tie rod 15.0mm galvanized 0.50m 0.72 581821000Tie rod 15.0mm galvanized 0.75m 1.1 581822000Tie rod 15.0mm galvanized 1.00m 1.4 581823000Tie rod 15.0mm galvanized 1.25m 1.8 581826000Tie rod 15.0mm galvanized 1.50m 2.2 581827000Tie rod 15.0mm galvanized 1.75m 2.5 581828000Tie rod 15.0mm galvanized 2.00m 2.9 581829000Tie rod 15.0mm galvanized .....m 1.4 581824000Tie rod 15.0mm non-treated 0.50m 0.73 581870000Tie rod 15.0mm non-treated 0.75m 1.1 581871000Tie rod 15.0mm non-treated 1.00m 1.4 581874000Tie rod 15.0mm non-treated 1.25m 1.8 581886000Tie rod 15.0mm non-treated 1.50m 2.1 581876000Tie rod 15.0mm non-treated 1.75m 2.5 581887000Tie rod 15.0mm non-treated 2.00m 2.9 581875000Tie rod 15.0mm non-treated 2.50m 3.6 581877000Tie rod 15.0mm non-treated 3.00m 4.3 581878000Tie rod 15.0mm non-treated 3.50m 5.0 581888000Tie rod 15.0mm non-treated 4.00m 5.7 581879000Tie rod 15.0mm non-treated 5.00m 7.2 581880000Tie rod 15.0mm non-treated 6.00m 8.6 581881000Tie rod 15.0mm non-treated 7.50m 10.7 581882000Tie rod 15.0mm non-treated .....m 1.4 581873000Ankerstab 15,0mm
Super plate 15.0 0.91 581966000Superplatte 15,0
Water stop connector 15.0 0.52 581914000Wasserstop 15,0
Water stop 15.0 33cm 1.3 581817000Water stop S 15.0 33cm 1.2 581819000Wassersperre 15,0
Water stop G 15.0 33cm 1.0 581818000Wassersperre G 15,0 33cm
Fibre concrete plug 54mm 0.16 581955000Faserbetonstopfen 54mm
Concrete cone 52mm 0.19 581939000Betonkonus 52mm
Anchor cone 15.0 0.46 581967000Spannkonus 15,0
Plastic tube 22mm 2.50m 0.45 581951000Kunststoffrohr 22mm 2,50m
Universal cone 22mm 0.005 581995000Universal-Konus 22mm
Plug 22mm 0.003 581953000Verschlussstopfen 22mm
Distance piece 20cm 0.05 581907000Distance piece 25cm 0.09 581908000Distance piece 30cm 0.10 581909000Distanzhalter
Fibre concrete tube 22mm 0.18m 0.28 581904000Packed in units of 90 Fibre concrete tube 22mm 0.23m 0.36 581905000Packed in units of 70 Fibre concrete tube 22mm 0.28m 0.44 581906000Packed in units of 60 Fibre concrete tube 22mm 0.38m 0.61 581903000Packed in units of 60 Fibre concrete tube 22mm 1.25m 2.1 581991000Faserbetonrohr 22mm
Fibre concrete plug 22mm 0.02 581992000Verschlussstöpsel 22mm
Perm. capacity with safety factor of 1.6: 120 kNPerm. capacity to DIN 18216: 90 kNBreaking load: 195 kNNever weld or heat tie-rods - risk of fracture!
GalvanisedHeight: 6 cmDiameter: 12 cmWidth-across: 27 mmPacked in units of 20 Perm. capacity with safety factor of 1.6: 120 kNPerm. capacity to DIN 18216: 90 kNBreaking load: > rod breaking load (> 195 kN)
Non-treatedLength: 12 cmFollow the fitting instructions!
Non-treatedLength: 33 cmDiameter: 7 cmWeight without tie rodFollow the fitting instructions!Never weld or heat tie-rods - risk of fracture!Varying lengths can be ordered un-der Art.n° 580100000.
Non-treatedLength: 33 cmWidth: 12 cmHeight: 12 cmWeight without tie rodFollow the fitting instructions!Never weld or heat tie-rods - risk of fracture!Varying lengths can be ordered un-der Art.n° 580100000.
Grey
Grey
YellowLength: 11 cmDiameter: 6 cmPacked in units of 25 Perm. capacity with safety factor of 1.6: 120 kNPerm. capacity to DIN 18216: 90 kNBreaking load: > rod breaking load (> 195 kN)
GreyDiameter: 4 cmPacked in units of 500
GreyPacked in units of 1000
GreyFollow the fitting instructions!
Packed in units of 1000 Follow the fitting instructions!
Article n°[kg] Article n°[kg]
34 999779002 - 06/2006
Component overview User information Doka form-ties for special requirements
The Formwork Experts
REPOXAL two component adhesive 1.2 581993000REPOXAL-Zweikomponenten Kleber
Tie rod wrench 15.0/20.0 1.9 580594000Ankerstabschlüssel 15,0/20,0
Reversible ratchet 1/2" 0.73 580580000Umschaltknarre 1/2"
Box nut 24 0.12 580584000Stecknuss 24
Form tie system 20.0
Tie rod 20.0mm galvanized 0.50m 1.3 581411000Tie rod 20.0mm galvanized 0.75m 1.9 581417000Tie rod 20.0mm galvanized 1.00m 2.5 581412000Tie rod 20.0mm galvanized 1.25m 3.2 581418000Tie rod 20.0mm galvanized 1.50m 3.8 581413000Tie rod 20.0mm galvanized 2.00m 5.0 581414000Tie rod 20.0mm galvanized .....m 2.5 581410000Tie rod 20.0mm non-treated 0.50m 1.3 581405000Tie rod 20.0mm non-treated 0.75m 1.9 581416000Tie rod 20.0mm non-treated 1.00m 2.5 581406000Tie rod 20.0mm non-treated 1.50m 3.8 581407000Tie rod 20.0mm non-treated 2.00m 5.0 581408000Tie rod 20.0mm non-treated .....m 2.5 581403000Ankerstab 20,0mm
Super plate 20.0 B 2.0 581424000Superplatte 20,0 B
Water stop 20.0 33cm 1.7 581426000Wassersperre 20,0 33cm
Anchoring cone 20.0 1.0 581437000Ankerkonus 20,0
Sealing sleeve 20.0 0.03 581441000Dichtungshülse 20,0
Fibre concrete plug 45mm 0.10 581438000Faserbetonstopfen 45mm
Concrete cone 52mm 0.19 581939000Betonkonus 52mm
Plastic tube 26mm 2.00m 1.2 581463000Kunststoffrohr 26mm 2,00m
Universal cone 26mm 0.008 581464000Universal-Konus 26mm
Plug 26mm 0.006 581465000Verschlussstopfen 26mm
Cone spanner 20.0 3.5 581471000Konusschlüssel 20,0
Sufficient for 350 plugs for fibre con-crete tube 22mm.
GalvanisedLength: 37 cmDiameter: 8 cm
GalvanisedLength: 30 cm
Perm. capacity with safety factor of 1.6: 220 kNPerm. capacity to DIN 18216: 150 kNBreaking load: 354 kNNever weld or heat tie-rods - risk of fracture!
GalvanisedHeight: 7 cmDiameter: 14 cmWidth-across: 34 mmPacked in units of 10 Perm. capacity with safety factor of 1.6: 220 kNPerm. capacity to DIN 18216: 150 kNBreaking load: > rod breaking load (> 354 kN)
Non-treatedLength: 33 cmDiameter: 8 cmWeight without tie rodFollow the fitting instructions!Never weld or heat tie-rods - risk of fracture!Varying lengths can be ordered un-der Art.n° 580100000.
GalvanisedLength: 15 cmDiameter: 5 cmPacked in units of 30 Tool: Key for positioning cone 20.0
GreyLength: 16 cmDiameter: 5 cmPacked in units of 400
Grey
Grey
GreyDiameter: 5 cm
Grey
GalvanisedLength: 57 cm