98730405-PWHT

103
1 HEAT TREATMENT OF PRESSURE VESSELS 

description

PWHT

Transcript of 98730405-PWHT

  • 1

    HEAT TREATMENT OF

    PRESSURE VESSELS

  • 2

    WHAT IS HEAT TREATMENT?

    MATERIALS TREATED BY APPLICATION OF HEAT - NORMALLY DONE IN SOLID STATE

    HEATING BY VARIOUS SOURCES

    PARAMETERS

    RATE OF HEATING

    SOAKING TEMP.

    SOAKING TIME

    COOLING RATE

    COOLING MEDIA

  • 3

    WHY HT REQUIRED ?

    TO ENHANCE PROPERTIES

    Strength

    Toughness

    Hardness TO BRING THE PROPERIES SUITABLE FOR FABRICATION

    CARRIED OUT IN FABRICATION INDUSTRIES

    STEEL PLANTS

    FOUNDRY

    FORGING SHOPS

  • 4

    MATERIALS HEAT TREATED

    METALS & ALLOYS

    SINGLE PHASE

    MULTIPHASE

    ALLOYS

    Single Phase : Copper Nickel

    Multiphase : Steels

    METALS (Single phase )

    Titanium

  • 5

    HEAT TREATEMENT

    CRITERIA

    COLD WORKED to NORMAL All materials

    UNEQUILIBRIUM PHASES to

    EQUILIBRIUM Stainless Steels ,Maraging Steels

    STRESSED to UNSTRESED All Materials

  • 6

    MATERIALS HEAT TREATED

    CS

    C-Mn , C-Mo , Cr-Mo , Cr-Mo-V, Ni -Steels

    Stainless Steels

    Non Ferrous Materials

  • 7

    TYPES OF HEAT TREATMENT

    NORMALIZING

    ANNEALING

    STRESS RELIEVING

    SOLUTION ANNEALING

    HARDENING

    TEMPERING

    AGEING

  • 8

    IRON CARBON DIAGRAM

  • 9

    NORMALIZING The steel is heated to 40 C above the upper

    critical temperature followed by cooling in the

    still air.

    To achieve

    Uniform structure

    Change in Mechanical properties,

    UTS & YS

    Hardness

    Impact properties

    To refine the grains

  • 10

    ANNEALING

    Steel is heated 10 to 50C above the upper critical temperature and held for the desired length of time followed by very slow cooling within the furnace

    To achieve:

    Softness & better ductility

    Stresses free material Stress generated due to mechanical working / previous HT

    Uniform property through out the material

  • 11

    SOLUTION ANNEALING

    Austenitic Stainless steels is heated to above

    1050C and held for the desired time followed by

    cooling to room temperature within few minutes

    by quenching / blowing the air.

    Solution annealing is done on stainless steel and

    non ferrous alloys to achieve following:

    To soften the material

    To remove carbide precipitation formed at grain

    boundaries during manufacturing process

    To improve Corrosion Resistance

  • 12

    AGEING

    The Material is heated to a certain temperature,

    and held for the desired time; followed by

    quenching or cooling in air

    Ageing is done on materials susceptible for ageing characteristics : Maraging Steels

    Normally increases strength

    Improve Toughness

  • 13

    AGEING

    Maraging Steels

    M250

    Temperature : 485 C

    Normally 3 Hrs 15 mts

    Heating Rate : 200 C per hr per inch thick

    Cooling Rate : Cool in Air / Quench in water

  • 14

    STRESS RELIEVING

    The steel is heated to a temperature below or close to the lower critical temperature with a specific rate of heating. It is held at the temperature for a desired length of time, followed by cooling with a specific rate up to certain temperature.

    There is no change in grain structure.

    Stress relieving is done Fabricated Components of CS & LAS:

    To reduce Internal Stresses

    To soften the steel partially

    To soften HAZ

  • 15

    STRESS RELIEVING

    C-Mn , C-Mo , Cr-Mo (< 2% Cr)

    C - Mn Steels , C - Mo Steels, Cr-Mo Steels

    SA 515Gr 70 , SA204GrA, SA387GR11CL1

    Temperature : 593 C Min

    Normally 600 - 640 C, 650-690 C

    Time : 15 minutes min

    Time : 1 hr / inch thick

    Heating Rate : 200 C per hr per inch thick

    Cooling Rate : 260 C per hr per inch thick

  • 16

    Cr-Mo Steels

    Cr - Mo Steels (Cr >2%) SA 335P22 ,SA335P5

    Temperature : 676 C Min

    Normally 680 - 700 C 2.25Cr

    704 - 720 C 5 Cr

    Time : 15 mts min

    Time : 1 hr / inch thick

    Heating Rate : 200 C per hr per inch thick

    Cooling Rate : 260 C per hr per inch thick

    STRESS RELIEVING

  • 17

    Ni -Steels

    Nickel Steels : 1,2,3% Ni SA 203 GrA ,D

    Temperature : 593 C Min

    Normally 600 - 640 C,

    Time : 60 mts min

    Time : 1 hr / inch thick

    Heating Rate : 200 C per hr per inch thick

    Cooling Rate : 260 C per hr per inch thick

    STRESS RELIEVING

  • 18

    Steels enhanced by Heat Treatments

    Q&T Steels :

    9.5% Ni Steels , SA 517 Gr E

    Temperature : 538 C Typ

    Normally < 600 C

    Time : Minimum 15 minutes to 2 Hr

    Time : 1 hr / inch thick

    Heating Rate : 200 C per hr per inch thick

    Cooling Rate : 260 C per hr per inch thick

    STRESS RELIEVING

  • 19

    LAYOUT OF A TYPICAL

    FURNACE

    (Electrical or Gas fired )

    RECORDER P.I.D.

    FURNACE

    JOB

    COMPENSATING

    CABLE

    THERMOCOUPLE

  • 20

    THERMOCOUPLES

    PRINCIPLE OF A THERMOCOUPLE

    THERMOCOUPLE MATERIAL

    TYPES OF THERMOCOUPLE BEING

    USED IN HZW

  • 21

    PRINCIPLE OF THERMOCOUPLE

    The basic principle of thermoelectric

    thermometry is that a thermocouple develops

    an emf which is a function of the difference in

    temperature of its measuring junction &

    reference junction. If the temperature of

    reference junction is known, the temperature

    of the measuring junction can be determined

    by measuring the emf generated in the circuit.

  • 22

    THERMOCOUPLE MATERIAL

    REQUIREMENT 1. High coefficient of thermal emf.

    2. Continuously increasing relation of emf to temperature over

    a long range.

    3. Freedom from phase changes or other phenomenon giving

    rise to discontinuity in temperature emf relationships.

    4. Resistance to oxidation, corrosion and contamination.

    5. Homogeneity and reproducibility to fit an establish

    temperature & emf relationship.

    SPEED OF RESPONSE MAY BE IMPROVED AND

    RADIATION & CONDUCTION ERRORS MAY BE REDUCED

    BY THE USE OF SMALL DIAMETER THERMOCOUPLES.

  • 23

    TYPES OF THERMOCOUPLE

    BEING USED IN HZW

    K type :

    Material : Chromel + Alumel

    Nickel based ( 10 %Cr ) + ( 2 % Al )

    Properties : Non-Magnetic + Magnetic

    In this type of thermocouple, the wires are

    joined at one end only to form a point-type

    temperature sensor. Instrumentation converts

    the millivolt signal to related temperature.

  • 24

    TYPES OF THERMOCOUPLE

    BEING USED IN HZW contd... K type :

    Dia : 2.5 mm 0. 7 mm

    Insulation Bare(ceramic) Refractory

    coated

    Attachment Mech Capacitor

    Usability Reusable Disposable

    Location PIT F/c except PIT F/c

    Color - Red & Yellow

  • 25

    recorder

    pid

    Compensating

    cable

    Thermocouple

    wire

    Welded

    junction

    CONSTRUCTION OF A

    K TYPE THERMOCOUPLE

    Accuracy : 0.75%

  • 26

    S TYPE THERMOCOUPLE

    S TYPE THERMOCOUPLE ARE THE STANDARD THERMOCOUPLES.

    IT IS USED FOR CALIBRATING K Type THERMOCOUPLES.

    MATERIAL OF CONSTRUCTION 90% PLATINUM + 10% RHODIUM

    PLATINUM

    OXIDATION RESISTANCE , SO MORE LIFE .

    Accuracy : 0.25 %

  • 27

    ISSUE METHODOLOGY For DISPOSAL TYPE

    Users will send their requirement of thermocouple

    through Consumable slip ( mentioning HTR No ) to

    QA

    QA shall issue the same .

    QA shall issue identification sticker duly attached

    Users shall ensure availability of identification sticker

    on unused wire .

  • 28

    COMPENSATING CABLE

    COMPENSATING CABLE IS DEFINED AS A PAIR OF WIRES

    HAVING SUCH EMF TEMPERATURE CHARACTERISTICS

    RELATED TO THE THERMOCOUPLE WITH WHICH THE

    WIRES ARE INTENDED TO BE USED, THAT WHEN

    PROPERLY CONNECTED TO THERMOCOUPLE THE

    EFFECTIVE REFERENCE JUNCTION IS IN EFFECT

    TRANSFERRED TO THE OTHER END OF THE WIRES.

    MATERIAL ==> +ve COPPER ( white )

    -ve COPPER NICKEL (blue ) for K TYPE .

  • 29

    P.I.D. PID = PROPORTIONAL INTEGRAL DERIVATIVE

    PID FUNCTIONS BOTH AS PROGRAMMER AND CONTROLLER PID CONTROLLER CAN BE ZONE WISE

    PROGRAMME IS MADE IN SEGMENTS AS PER

    DIFFERENT STAGES OF HEAT TREATMENT

    DIGITAL DISPLAY IS AVAILABLE FOR PROGRAMME

    TEMPERATURE AND FURNACE TEMEPERATURE

    TYPICAL OR REPETITIVE HEAT TREATMENT CYCLE

    CAN BE STORED IN PID(PROGRAMMER)

  • 30

    RECORDER TYPES OF RECORDER PAPERLESS -- WITH COLOUR DISPLAY SCREEN ,HARD DISC AND FLOPPY DRIVE.

    NOT USED IN HZW.

    WITH PAPER -- CURRENTLY BEING USED IN HZW.

    24 CHANNEL -- CURRENTLY BEING USED IN PFS( CHINO MAKE-- model no.I003 /Graph ET 001).

    12 CHANNEL -- CURRENTLY BEING USED IN MFS1 AND HFS1 ( CHINO MAKE -- model no. EH100 / Graph ET 201).

    COMPENSATING CABLES ARE CONNECTED BEHIND THE RECORDER SCREEN IN

    CHANNELS.

    X-AXIS IS FOR TEMPERATURE (RANGE = 0 TO 1200C) THE SCALE ON X-AXIS IS NON-LINEAR.

    Y-AXIS IS FOR GRAPH SPEED.

    VARIOUS SPEED OF GRAPHS ARE 12.5, 25, 50, 100 MM / HOUR GENERALLY KEEP 25 MM / HOUR.

  • 31

    GRAPH PAPER

    GRAPH PAPERS ARE USED FOR PLOTTING THE FURNACE TEMPERATURE VIA THERMOCOUPLE.

    THEY ARE FITTED ON THE RECORDER.

    GRAPH PAPER RECOMMENDED ON RECORDER ONLY TO BE USED

    GRAPH PAPER FOR MFS1 AND HFS1 FURNACE ==> ET 201 CHINO MAKE, JAPAN

    GRAPH PAPER FOR PFS FURNACE

    ==> ET 001 CHINO MAKE, JAPAN

    THE LENGTH OF ONE BUNDLE OF GRAPH PAPER IS GENERALLY 2000 MM.

    DOTTING TYPE RECORDER INK (CHINO MAKE, JAPAN)

    IS USED IN RECORDER FOR PLOTTING OF GRAPH.

    USUALLY , 6 COLOURS ARE FILLED FOR PLOTTING.

  • 32

    STANDARD OPERATING

    PROCEDURE FOR HFS-1

    FURNACE

  • 33

    1650

    3575

    14300.

    3575 3575 3575

    ( ZONE-1 ) ( ZONE-3 ) ( ZONE-5 ) ( ZONE-7 )

    ( ZONE-2 ) ( ZONE-4 ) ( ZONE-6 ) ( ZONE-8 )

    1640 1650

    7900

    (BOGIE

    WIDTH

    )

    BURNER

    HFS-I FURNACE SKETCH

  • 34

    7900 BOGGIE WIDTH

    8700

    1050

    9500

    9000

    1195

    1. PROJECT NO:

    2. SECTION NO :

    3. CHARGE NO :

    4. H. T. REQ. NO :

    BURNER

    HFS-I FURNACE SKETCH

  • 35

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    1. Receive the job as per HT request.

    2. Receive heat treatment request duly approved by metallurgy engineer.

    3. Ensure that Insp. Clearance is available prior

    to loading for job.

    4. Load the supporting arrangement as per the attached annexure -3

    5. Ensure the spider arrangement as per attached annexure - 5

    6. Fix the thermocouples at locations shown in furnace charge.

    7. Check the entire job as per check list (annex.-I).

  • 36

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    9. Move the bogie inside the furnace

    10. Pass the thermocouples through ports and

    connect it with compensating cables

    11. Set the program as per heat treatment request.

    Secure it and then run it in fast mode as check.

    Bring it back to the initial segment and hold.

    12. Insert heat treatment chart in recorder and adjust

    the speed of the graph.

    13. Clear inspection of job and get the signature of

    inspector on graph paper for firing the furnace.

    14. Check LPG level, pressure and temperature in the

    storage tanks and note down in logbook.

  • 37

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    15. Switch on the power supply

    16. Close the bogie door

    17. Follow the procedure for startup of furnace in zone-I

    18. Start the blower from the field push button station

    provided

    19. Give power supply to the ignition panel

    20 When the system healthy contact comes from the

    instrument panel, the lamp for the system healthy

    signal is on. This indicates that the combustion air

    pressure and gas pressure are within the specified

    limits

    21. Now the firing on the cycle can start.

  • 38

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    22. Open the pilot and main gas valves

    23. Press start cycle button on doing so the cycle starts

    and purging start indicator lamp is on.

    24. After 3 minutes ( time adjusted through timer ) the

    purging is completed and ignition start lamp is ON

    At the same time the purging start lamp gets OFF.

    25. After 10 seconds the ignition start lamp gets OFF

    By this time the pilot burner should have been fired

    and the pilot flame is established.

    26. Flame healthy signal LED gets on which is provided

    on the flame sensor relay. This can be viewed through

    the glass window provided in the ignition panel.

  • 39

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    27. Due to certain length of pipe between the burner and

    solenoid valves, which may contain air, the burner

    may not light up in the first attempt. In that case,

    repeat the above mentioned procedure.

    28. Once the main flame is established, the control is

    passed on to the temperature controller.

    29. For startup of furnace in other zones, follow the same

    steps no 16 to 27 mentioned above.

    30. After all zones are started, start recording time and

    temperature from recorder every 30 minutes in the

    logbook.

    31. Conduct spot checks for heat treatment every 4hours

    and fill the spot check format.

  • 40

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

    32. Monitor the heat treatment process and graph till

    the completion to ensure that it is as per program

    and heat treatment request.

    33. After heat treatment cycle is completed, shut off

    all LPG supply valves and let furnace run with

    blowers on for 15 minutes.

    34. Open the bogie door. Disconnect thermocouples

    from compensating cable.

    35. Submit the graph and duly filled spot check formats

    to inspection for approval of heat treatment.

  • 41

    36. Retrieve the thermocouples from the ports and the

    bogie out of the furnace.

    37. Allow the job to reach room temperature.

    38. Remove the thermocouples from the job carefully

    without damaging the junction of thermocouples and

    without making impression on parent material of job.

    39. Unload the job from the bogie and move the bogie

    inside the furnace.

    40. Close the furnace. Shut off the main power supply.

    STANDARD OPERATING PROCEDURE FOR HFS-1

    FURNACE

  • 42

    STANDARD OPERATING

    PROCEDURE FOR PFS

    FURNACE

  • 43

    125T Bogie hearth furnace -- PFS

  • 44

    BOGGIE WIDTH

    4100

    2650

    5600

    10

    50

    12

    35

    14

    60

    5

    50

    0

    BURMER

    PFS FURNACE SKETCH

  • 45

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

    1. Receive the job as per HT request.

    2. Receive heat treatment request duly approved by

    metallurgy engineer.

    3. Ensure that Insp. clearance is available prior to

    loading for job.

    4. Load the job on the bogie as per the heat treatment

    furnace request.

    5. Ensure the supporting arrangement as per the

    attached annexure-I.

    6. Ensure the spider arrangement as per annexure- II.

    7. Fix the thermocouples at locations shown in furnace

    charge.

  • 46

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

    8. Check the entire job as per check list attached as

    annexure-III

    9. Move the bogie inside the furnace.

    10. Pass the thermocouples through ports and

    connect it with compensating cables.

    11. Insert heat treatment chart in recorder and adjust

    the speed of the graph.

    12. Clear inspection of job and get the signature

    of inspector on graph paper for firing the furnace.

    13. Check LPG level, pressure and temperature in

    the storage tanks and note down in logbook.

  • 47

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

    14. Switch on the power supply.

    15. Close the bogie door.

    16. Switch on ID blower first and then the air blower

    and maintain pressure at about 800mm WG by

    slowly opening the suction valve.

    17. Ensure that pressure of LPG from yard to inlet

    of pressure regulator is always less than 20psi

    (1.5kg/CM2).

    18. Open the inlet valve to the regulator and open

    the outlet valve.

    19. If pressure exceeds 1600 mm WG , isolate the

    pressure by lifting the handle of safety shut off

    valve.

  • 48

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

    20. Immediately start lighting the pilot burners and adjust

    the flame with the air valve .

    21. Open the isolating valve for pressure gauge and

    adjust the pressure regulator by turning the screw

    provided in the stem so that the pressure is

    maintained at about 1000mm WG.

    22. Light up alternate main burners and adjust the flame

    lengths uniformly.

    23. Lock the doors by pneumatic locking.

    24. After all zones start, record time and temperature

    from recorder every 30 minutes in the logbook.

  • 49

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

    25. Conduct spot checks for heat treatment every

    4 hours and fill the spot check format. Monitor the

    heat treatment process and graph per heat

    treatment request.

    26. After the heat treatment cycle is completed, shut off

    all LPG valves and let furnace run with blowers on

    for 15 minutes.

    27. Open the bogie door. Disconnect thermocouples

    from compensating cables.

    28. Submit the graph and duly filled spot check formats

    to inspection for approval of heat treatment.

  • 50

    29. Retrieve the thermocouples from the ports and move

    the bogie out of the furnace.

    30. Allow the job to reach room temperature.

    31. Remove the thermocouples from job carefully and

    without marking impression on parent material of

    job.

    32. Unload the job from bogie and move the bogie inside

    the furnace.

    33. Close the furnace. Shut off the power supply.

    STANDARD OPERATING PROCEDURE FOR PFS

    FURNACE

  • 51

    STANDARD OPERATING

    PROCEDURE FOR PIT

    FURNACE IN MFS-I

  • 52 B

    LO

    WE

    R

    3700 1

    /D O

    F B

    AF

    FL

    E

    4150 ( R

    EF

    RA

    CT

    OR

    Y I/S

    )

    4961 1000

    250 125

    1380

    4020

    TROLLEY

    STRUCTURE

    CERAMIC

    BLANKET

    ROOF

    BAFFLE

    HEATING

    ELEMENT CERMIC FIBER

    SLABER BLOCK

    INSULATING

    CASTABLE

    FIRE BRICK

    OUTER

    SHELL

    CERMIC

    BLANKET

    GROUND LEVEL

    PIT FURNACE SKETCH

  • 53

    STANDARD OPERATING PROCEDURE

    FOR PIT FURNACE

    1. Receive heat treatment request duly authorized

    by metallurgy engineer.

    2. Receive the job for heat treatment with

    inspection clearance.

    3. Put the job either on support or on heat

    treatment fixture inside the furnace.

    4. Ensure that equal clearance is available on all

    sides between job and baffle.

    5. Ensure that the furnace is calibrated.

    6. Connect thermocouples with compensating

    cable to PID.

  • 54

    7. Set the program in the programmer as per heat

    treatment request.

    8. Take a trial run of program to ensure the accuracy.

    9. Calibrate all 5 PIDs prior to starting the furnace.

    10. Insert the graph inside the recorder and take the

    signature of inspector on the graph paper.

    11. Close the furnace door.

    12. Start the furnace by giving power supply ON

    STANDARD OPERATING PROCEDURE

    FOR PIT FURNACE

  • 55

    13. Start recording the time and temperature in the

    logbook every 30 minutes.

    14. Ensure that the cycle is functioning as per program.

    15. After the heat treatment is over, open the furnace

    cover.

    16. If the job calls for water quenching, lift the job and

    dip it in quench tank.

    17. It the job calls for air cooling in still air, lift the job

    and put it outside on supports in open air.

    STANDARD OPERATING PROCEDURE

    FOR PIT FURNACE

  • 56

    18. It the job doesnt call for anything above, allow the

    job to cool down in furnace.

    19. Keep the job outside after removing from furnace.

    20. Submit the heat treatment graph to inspection for

    approval of heat treatment cycle.

    21. Close the furnace cover after the furnace is cooled

    down to room temperature.

    STANDARD OPERATING PROCEDURE

    FOR PIT FURNACE

  • 57

    PROCEDURE FOR EMPTY FURNACE

    CALIBRATION

    Calibration of PIDS ( indicator & controller )

    1. Connect the millivolt source to the temperature

    indicator or controller by a compensating cable.

    Care should be taken to clean the wires and

    terminals thoroughly before connections are

    made.

    2. The millivolt output for various temperature

    ranging from 00C to 1000

    0C in steps of 50

    0C is fed

    to the indicator / controller.

    3. After the millivolt value / temperature reading

    displayed is steady, the reading of

    indicator/controller shall be noted.

  • 58

    PROCEDURE FOR EMPTY FURNACE

    CALIBRATION

    Calibration of recorder

    1. Connect the millivolt source to the recorder by a

    compensating cable. Care should be taken to

    clean the wires and terminals thoroughly before

    the connections are made.

    4. If the error in the indicated readings is more than

    the specified accuracy ( +/- 10C ), then correction

    to be carried out for the indicator / controller and

    points 1 to 4 shall be repeated till the specified

    accuracy is obtained is obtained.

  • 59

    PROCEDURE FOR EMPTY FURNACE

    CALIBRATION

    2. The millivolt output for various temperature

    ranging from 400 C to 10000C is fed to the

    recorder and is allowed to plot on a graph.

    3. The graph thus obtained is reviewed for time

    and temperature values. These values should

    meet the accuracy requirements.

    4. If there is error in the values plotted on the

    graph, then correction to be carried out for

    the recorder and points 1 to 4 shall be

    repeated till the specified accuracy is

    obtained.

  • 60

    PROCEDURE FOR EMPTY FURNACE

    CALIBRATION

    EQUIPMENT REQUIRED ACCURACY

    1. 20 Nos. big K-type thermocouples +/- 0.25%

    2. 10 Nos. small K-type thermocouples +/- 0.25%

    3. Millivolt source (wahl unit )

    ( 1 micro volt at 1000 micro volts )

    4. Heat treatment fixture.

    5. Temperature indicators (PID) +/- 10C

    6. Recorder +/- on temperature scale.

    +/- minutes on time scale.

  • 61

    PIT FURNACE CALIBRATION PROCEDURE

    1. Ensure that the PIDs are calibrated as mentioned above.

    2. Ensure that the recorder is calibrated as mentioned

    above.

    3. Ensure that all the thermocouples used are calibrated.

    4. Ensure that the thermocouples are attached to the heat

    treatment fixture as shown in sketch-I.

    5. Place the heat treatment fixture inside the furnace with

    thermocouples in position.

    6. Close the furnace lid. Start the furnace and the recorder.

  • 62

    7. Set the temperature of controller to 4000C.

    8. After reaching the set temperature, it is allowed to

    stabilize for half an hour.

    9. Measure and record the temperature indicated by

    each of the 20 thermocouples. The temperature is to

    be read through WAHL UNIT.

    10. Three sets of readings are to be taken for each

    thermocouples at an interval of 10 minutes.

    11. Also record the readings indicated by each of the

    thermocouples at an interval of 10 minutes.

    PIT FURNACE CALIBRATION PROCEDURE

  • 63

    PIT FURNACE CALIBRATION PROCEDURE

    12. The temperature is then raised in steps of 50 C up to

    10000C. ( I. e. 400

    0C, 450

    0C, .., 950

    0C, 1000

    0C. ) The

    measured temperature is stabilized for 30 minutes.

    PID reading are also to be recorded along with this.

    13. The allowed temperature variation with respect to the

    set temperature is +/- 50C up to 800

    0C and +/- 10

    0C

    above 8000C.

    14. This is allowed to plot on the graph and thus

    obtained for time and temperature values.

    15. Calibration of furnace is valid for 1 year.

  • 64

    STANDARD OPERATING

    PRACTICES FOR LOCAL

    STRESS RELIEVING

  • 65

    LOCAL STRESS RELIEVING

    WHY Local SR to be done only when furnace SR not feasible

    When only certain components to be PWHT

    HOW Can be done by Electrical / Gas / diesel / Induction etc..

    DETAILS ON ENSURING PWHT TEMP. IN WELDMENT AREA

    Soaking band(SB) = Widest weld width x+ t or 2 inches whichever is less from edge of weld

    Heating band width (HB)

    Induction stress level

    Through thickness criteria

    SB + 4 rt where r = Inside radius, t = thickness

    Insulation band width (IB)

    Axial gradient

    HB + 4 rt

  • 66

    LSR -BAND WIDTH

    Weld width X + lesser of 1T or 2

    X

    t

    Soak band

    Insulation band

    Heating band

  • 67

    LOCAL STRESS RELIEVING SET UP

    1. Provide multitonne roller on one end of vessel during

    LSR of circular seam when job is horizontal.

    2. If both ends are open during LSR, provide insulation

    from inside. If not possible , prevent airflow so that

    temperature on inside surface do not drop down.

    3. Spider/prop shall be provided in such a way that upper

    portion of spider / prop is not welded with inside

    surface to allow contraction/expansion of shell surface.

    4. Spider/prop shall be between 200- 500mm from heating

    zone.

    5. Temporary attachments, provided for holding insulation,

    shall be within soak band only.

    6. Minimum two thermocouples shall be provided from

    inside, when accessible.

  • 68

    LOCAL STRESS RELIEVING

    No Welding at top

    Multitonne roller

    200 to 500mm from heating band

    LSR of C/S

    SB+HB+IB

    Spider or

    prop

  • 69

    GOOD ENGG. PRACTICES

    FOR FURNACE CHARGES

    & L S R

  • 70

    SUPPORTING ARRANGEMENTS

    1. Minimum distance between wall of furnace and the

    job shall be 600mm.

    2. Minimum distance between floor of the furnace

    and lower most part of the job shall be 300mm.

    3. The distance between the flame of burner and

    saddle support shall be 600mm.

    4. Minimum 90 degree saddle to be used, however

    120 degree saddle is desirable.

  • 71

    600mm

    900

    600mm

    SUPPORTING ARRANGEMENTS

    450mm

    5. Saddle shall be arranged in such away that open

    end of the vessel is maximum 450mm from saddle

    support.

    6. Saddle shall be located as close to spiders

    (temporarily arranged to control deformation) as

    possible.

    burner

    300mm(point no:2)

  • 72

    SUPPORTING ARRANGEMENTS

    7. Spiders shall be provided as per annexure-5

    8 Saddle supports shall be selected as per annexure.-3

    9. Spiders or vertical prop shall be provided at open

    ends, center and below man way/nozzles above 24

    10. Avoid gap between saddle support and job surface

  • 73

    Zero gap

    Supporting

    arrangement

    SUPPORTING ARRANGEMENTS

    11. Locking/clamping of job, restricting the movement

    (axial/lateral) during heat treatment shall be avoided.

    12. All long nozzles projecting outside job surface shall

    be supported.

  • 74

    13. Checklist shall be prepared and attached with HT

    request before furnace is fired as per Ann-1

    14. Spot check report shall be filled by supervisor as per

    Annexure-2 during job is being heat treated.

    15. Moonplate support and welding inside surface

    prior to release for Heat treatment as per

    Annexure-4

    16. General idea about thermocouple locations and its

    attachments is as per Annexure-6

    SUPPORTING ARRANGEMENTS

  • 75

    GENERAL

    1. Blocking the flame of the burner is not desirable

    2. Burner shall have blue flame and not yellow

    3. Flame shall not directly impinge on job

    4. All burners shall be fired at a time

    5. Keep all job nozzles open during heat treatment

    6. Above 24 nozzles / manways shall be located

    towards bottom

  • 76

    GENERAL

    Temp. support

    Furnace floor

    Gasket machined surface

    7. Deoxidization agent shall be applied on all

    machined and gasket faces

    8. Gasket / machined face of loose assemblies

    shall not be touching any object.

  • 77

    THERMOCOUPLES

    1. All the thermocouples shall be

    tagged with aluminum sheet

    and identification hard punched

    on it.

    (For PIT furnace only)

    2. Minimum two thermocouples to

    be attached for any charge.

  • 78

    3. Minimum 8 thermocouples to be used for a charge in

    HFS- I furnace if the job occupies all 8 zones

    4. Maximum distance between two thermocouples for a

    sample job is as shown in annexure- 6

    5. PTC shall have separate thermocouple

    THERMOCOUPLES

  • 79

    1. Use only TAU-90 capacitor Discharge Welding

    machine for thermocouple connection

    2. Use WPS:999-154 R0 for attachment of

    thermocouple for cs/alloy steel material

    3. Only trained person by welding engineering shall

    attach thermocouple

    4. A list of qualified person shall be by Welding

    Eng.

    THERMOCOUPLES

    ATTACHMENTS

  • 80

    5. Clean surface prior to attachment. 6. Two wire of thermocouple shall be attached one after another.

    7. Gap between two wire of a thermocouple shall be

    max. 3.0mm 8. Only calibrated thermocouple shall be used. Calibration shall be by QA. 9. After PWHT, thermocouple area shall be ground and DP shall be carried out.

    THERMOCOUPLES

    ATTACHMENTS

  • 81

    THERMOCOUPLES

    ATTACHMENT UNIT

  • 82

    SPECIAL NOTE

    IF THE TEMPERATURE OF HEAT TREATMENT

    EXCEEEDS 650-DEGREE CENTIGRADE, THE

    MATERIAL AND SIZE OF SPIDERS AND SUPPORTS

    TO BE DECIDED BY PLANNING AND APPROVED BY

    DESIGN.

  • 83

    CODE EXTRACTS

    FURNACE PWHT

    L S R

  • 84

    REQUIREMENT OF HEAT TREATMENT

    AS PER ASME-SEC VIII Div.-1

    SERVICE CONDITION (UW-2)

    MATERIAL (UG-85, UW-40,UCS-56,UAT-80,UHA-32,UNF-79)

    THICKNESS (UG-85, UW-40,UCS-56,UAT-80,UHA-32,UNF-79)

    LOW TEMERATURE

    OPERATION (UCS-68)

    COLD WORKING (UG-79)

    CUSTOMER SPEC.

  • 85

    CODE EXTRACT FOR HEAT TREATMENT ( 1 ) The soak band shall contain the weld, heat

    affected zone and a portion of base metal adjacent to the

    weld being heat treated. The minimum width of this

    volume is the widest width of weld plus 1T or 2 inches,

    whichever is less, on each side or end of the weld. The

    term T is the nominal thickness. ( 2 ) The operation of postweld heat treatment shall be

    performed either by heating the vessel as a whole in an

    enclosed furnace or heating the vessel in more than one

    heat in a furnace, provided the overlap of the heated

    sections of the vessel is at least 5 feet ( 1.5m). When this

    procedure is used, the portion outside of the furnace

    shall be shielded so that the temperature gradient is not

    harmful. The cross section where the vessel projects

    from the furnace shall not intersect a nozzle or other

    structural discontinuity.

  • 86

    CODE EXTRACT FOR HEAT TREATMENT

    ( 3 ) When the vessel is required to be postweld heat

    treated, and it is not practicable to postweld heat treat the

    completed vessel as a whole or in two or more heats; any

    circumferential joints not provisionally heat treated may be

    thereafter locally postweld heat treated by heating such

    joints by any appropriate means that will assure the

    required uniformity.

    ( 4 ) While carrying out local postweld heat treatment,

    the soak band shall extend around the full circumference.

    The portion outside the soak band shall be protected so

    that the temperature gradient is not harmful.

    ( 5 ) Heating a circumferential band containing nozzles

    or other welded attachments in such a manner that the

    entire band shall be brought up uniformly to the required

    temperature and held for the specified time.

  • 87

    CODE EXTRACT FOR HEAT TREATMENT

    ( 6 ) Where more than one pressure vessel or more

    pressure vessel part are postweld heat treated in one

    furnace charge, thermocouples shall be placed on

    vessels at the bottom, center, and top of the charge or in

    other zones of possible temperature variation so that the

    temperature indicated shall be true temperature for all

    vessels or parts in those zones.

    ( 7 ) Postweld heat treatment, When required, shall be

    done before the hydrostatic test and after any welded

    repairs. A preliminary hydrostatic test to reveal leaks

    prior to PWHT is permissible.

    ( 8 ) For pressure vessels or parts of pressure vessels

    being post weld heat treated in a furnace charge, it is the

    greatest weld thickness in any vessel or vessel part

    which has not previously been postweld heat treated.

  • 88

    CODE EXTRACT FOR HEAT TREATMENT

    ( 8 contd...) The nominal thickness is the total depth of

    the weld exclusive of any permitted weld

    reinforcement.

    For groove weld, the nominal thickness is the

    depth of the groove.

    For fillet welds, the nominal thickness is the

    throat dimension.

    If a fillet weld is used in conjunction of groove

    weld, the nominal thickness is the depth of the

    groove or the throat dimension, Whichever is

    greater.

    For stud welds, the nominal thickness shall be the

    diameter of the stud.

    ( 9 ) For P1 material ( carbon steel), minimum holding temperature during postweld heat treatment shall

    be 1100 Deg. F ( 593 Deg.c).

  • 89

    CODE EXTRACT FOR HEAT TREATMENT

    P. NO. HOLDING TEMP. NOM.THICKNESS

    SOAKING PERIOD

    1 ( CARBONSTEEL) & 3(LOW ALLOYSTEEL)

    1100 DEG. F(593C)

    UPTO 2 1 HR. PER INCH. ,HOWEVER 15 MINUTESMINIMUM

    OVER 2TO 5

    2 HOURS , PLUS 15 MIN.FOR EACH ADDITIONALINCH ABOVE 2

    OVER 5 2 HOURS , PLUS 15 MIN.FOR EACH ADDITIONALINCH ABOVE 2

    * POST WELD HEAT TREATMENT IS MANDATORY ON P-NO.3 GR. NO. 3MATERIAL IN ALL THICKNESSES.

  • 90

    ( 10 ) Postweld heat treatment is mandatory in

    Following conditions :

    For welded joints over 1. 5 nominal thickness.

    For welded joints over 1.25 nom. Thickness

    through 1.5 nom. Thickness, unless preheat is

    applied at a min. Temperature of 200F ( 94c )

    during welding.

    Vessels or parts of vessels constructed of base

    material with corrosion resistant integral or weld

    metal overlay cladding or applied corrosion

    resistant lining material shall be postweld heat

    treated when the base material is required to be

    postweld heat treated. In applying this rule, the

    determining thickness shall be the total thickness

    of base material.

    When the PWHT is a service requirement.

    CODE EXTRACT FOR HEAT TREATMENT

  • 91

    SERVICE CONDITION

    LETHAL SERVICE PWHT IS MANDATORY

    EXEMPTIONS ARE FEW

    CODE EXTRACT FOR HEAT TREATMENT

  • 92

    CODE EXTRACT FOR HEAT TREATMENT

    ( 11 ) Postweld heat treatment is not mandatory for carbon steel jobs (P1 material ) in Following conditions (UG2):

    If groove welds is not over in size or fillet weld with a throat thickness of or less used for attaching non pressure parts to pressure parts provided preheat to a minimum temperature of 200F is applied when the thickness of pressure Part exceeds 1.25. If studs are welded to pressure parts provided preheat to a minimum temperature of 200F is applied when the thickness of the pressure parts exceeds 1.25. for corrosion resistant weld metal overlay cladding or for welds attaching corrosion resistant applied lining provided preheat to a minimum temperature of 200f is maintained during application of the first layer when the thickness of the pressure part exceeds 1.25.

  • 93

    CODE EXTRACT FOR HEAT TREATMENT

    The temperature of furnace shall not exceed 800F

    ( 4270C) at the time when the vessel or part is placed in it.

    Above 8000F( 427

    0C), the rate of heating shall not be more

    than 4000F Per hour (200

    0C/Hour) divided by the maximum

    metal thickness of the shell or head plate in inches, but in no

    case more than 4000F Per hour( 222

    0C Per hour ).

    During the heating period, There shall not be a greater

    variation in temperature throughout the portion of the vessel

    being heat treated than 2500F( 139

    0C) within any 15 feet (

    4.6m) interval of length.

  • 94

    CODE EXTRACT FOR HEAT TREATMENT

    During the holding period, there shall not be a

    greater difference than 1500f ( 83

    0c) between the highest and

    the lowest temperature the portion of the vessel being heated

    During the heating & holding periods, the furnace

    atmosphere shall be so controlled as to avoid excessive

    oxidation of the surface of the vessel. The furnace shall be of

    such design as to prevent direct heat impingement of the

    flame on the vessel.

    Above 8000F ( 427

    0C), The rate of cooling shall not be

    more than 5000F Per hour (278

    0C/Hour) divided by the

    maximum metal thickness of the shell or head plate in inches,

    but in no case more than 5000F Per hour ( 278

    0C Per hour).

  • 95

    when it is impractical to postweld heat treat at the

    temperature specified in table mentioned in Sr.. No. 9, It is

    permissible to carry out the post weld heat treatments at

    lower temperatures for longer periods of time as shown in

    table below :

    CODE EXTRACT FOR HEAT TREATMENT

    DECREASE IN TEMP. BELOW

    MIN. SPECIFIEDTEMPERATURE IN F

    MINIMUM HOLDING

    TIME AT DECREASEDTEMPERATURE (NOTE 1)

    NOTES

    50 (10C) 2 HOURS ----

    100(38C) 4 HOURS ----

    150(68C) 10 HOURS 2

    200(94C) 20 HOURS 2

    NOTES :1. MINIMUM HOLDING TIME FOR 1 THICKNESS OR LESS ; ADD 15 MINUTES PER INCH OF

    THICKNESS FOR THICKNESS GREATER THAN 1.2. THESE LOWER POSTWELD HEAT TREATMENT TEMPERATURES PERMITTED ONLY FOR P-

    NO.1 GROUP NO. 1 AND 2 MATERIALS.

  • 96

  • 97

  • 98

  • 99

  • 100

    SELECTION OF SPIDERS AT OPEN ENDS FOR HEAT TREATMENT

    10000 10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    9500

    9000

    8500

    8000

    7500

    7000 ISMB 250

    6500 ISMB 250 BOX SEC ISMB 250

    6000

    5500

    5000

    4500

    4000

    3500 ISMB 150

    3000

    2500

    2000 ISMB 125 ISMB 150

    1500

    1000

    500 ISMB 125 ISMB 150

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    DATA FOR ABOVE CHANNELS:

    WEB HT FLG WD FLG THK WEB THK

    SH

    EL

    L D

    IAM

    ET

    ER

    WT/ MTR.(KG)

    13

    SHELL THICKNESS

    ISMB 125 75

    ISMB 250

    14.9

    37.3

    SHELL THICKNESS

    ISMC 250

    DESIGNATION

    30.4

    125

    150

    250

    250

    ISMB 150 80

    125

    80

    7.6

    7.6

    12.5

    14.1

    4.4

    4.8

    6.9

    7.1

    Annexure-5

  • 101

  • 102

    HT REQUEST

  • 103

    HT CHARGE