Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
1
James E. Kenyon, P.S. ODOT District 3
Jim has an Associate Degree in Civil Engineering and has been a licensed Professional Surveyor in the State of Ohio since 1983 with considerable experience in Boundary surveying, Right of Way surveying and plans, Geodetic and GPS surveying.
Jim started with ODOT in 1988 as the Survey Operations Manager for District 3, has been the Acting Real Estate Administrator on two occasions throughout his career and functions as the R/W Manager responsible for Consultant R/W Plan reviews, District R/W Plan preparation and the District Right of Way Plan records in addition to directing the District 3 Survey Operations.
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
2
Field Survey for R/W Plans
Field Survey for Right of Way Plans• Survey Manager Database (SMD) file • Survey Feature Code List for data collection• Topographic items• Existing Utilities
Ohio Utility Protection Service (OUPS)Oil and Gas Producers Underground Protection Services (OGPUPS) Subsurface Utility Engineering (SUE)
• Property Monumentation• Right of Way Monumentation
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
3
http://www.dot.state.oh.us/Divisions/ProdMgt/Production/CADD/Pages/GEOPAKDownloads.aspx
Survey Manager Database (SMD) file
Survey Feature Code Lists
Trimble Data Collector Code List
Survey Preferences
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
4
http://www.dot.state.oh.us/Divisions/ProdMgt/Production/CA
DD/Pages/GPKManual.aspx
ODOT GEOPAK Survey Training Guide
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
5
Survey Feature Code List Mapping Codes / Linking Codes Location on objects to take field measurements Indicates use in DTM List can be uploaded to Data Collectors
Trimble Data Collector (.ddf file)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
6
Survey Feature Code List
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
7
Plan the Field Survey Work Notice Sent to Property Owners
ORC 163.03 Right of Entry See: http://codes.ohio.gov/orc/163.03 “…. not less than forty-eight hours nor more than thirty days prior to the date
of such entry.”
OUPS call – document ticket number Control Provided By ODOT
Datum & Project Adjustment Factor
Mapping Provided By ODOT Existing Plans Provided By ODOT Review Right of Way Attachment & Scope with Field
Crew Provide the Field Crew with a Digital Camera
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
8
Topographic Items Section 3108.5
Structures Drives Drive Pipes
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
9
Underground Items Wells, Septic Tanks &
Leach Systems Have Field Crew Talk to
Property Owners
Underground Tanks , Sprinkler Systems , Field Tiles
Signs Fences Trees
Encroaching
Prop R/W
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
10
Existing Utilities Section 153.64 ORC
Requires Underground Utilities To Be On Plans
Ohio Utility Protection Service (OUPS) Make the Call ( 800 - 362 – 2764 ) Get Reference Number
Not All “Utilities” covered by OUPS
Oil & Gas Companies ( 800) – 925 – 0988
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
11
Subsurface Utility Engineering (SUE)
Check Scope 4 Levels of Detail Level A – Expose & 3D Positions –
Requires Survey Control Points Level B – Field Marking - 2D Level C – Added to Plan from Record Data Level D – Gather Existing Available Records
Locate Service Lines Shut Off Valves Meters
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
12
Right of Way Monumentation
Centerline Monumentation Monument Assemblies
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
13
Right of Way Monumentation
Centerline Monumentation Centerline Reference
Swing Tie References
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
14
Right of Way Monumentation Right of Way Monuments
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
15
Right of Way Monumentation• OLD MAPS REPORTS
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
16
Property Monuments Right of Way Plans are
Boundary Surveys OAC 4733-37-05-C-4
Minimum Standards “there shall be a statement
describing the material, size, position and condition of every monument found and/or set.”
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
17
Search for the Record Monuments
Have field crews describe monuments found
SIZE TYPE / MATERIAL CAP STAMPING CONDITION
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
18
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
19
Boundary Resolution
Original Government land lines and monuments Intent of Government Surveys Know the Local Standards & Surveying Customs
Existing Boundary Monuments Standard Surveying Rules of Evidence Apply Called for in Deeds & Survey Plats Use data from Record Survey Plats
Does the Monument represent the Corner?
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
Boundary Resolution
Survey Monuments should be given considerable weight
Ignoring Survey Monuments Causes Chaos and Problems
Hierarchy of Monuments Uncalled for Monuments
Record of Survey Compatible with Deed Accepted by Owners – Talk to Owners
20
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
Boundary Resolution
Intent Calls - “along the” and “to” “Centerline”
What does it really mean?
Occupation Lines Overlap Areas and Deed Conflicts Reference / Offset Pins Existing Right of Way Monuments
21
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
22
Monumentation
• O.R.C. 5519.05… monument the right of way line of the property acquired. … provide for the preservation of all cornerstones and landmarks set within the limits of the highway to be improved. … furnish adequate protection ….
• O.A.C. Chapter 4733-37-03 (Minimum Standards)… each corner of the property and each control station will be physically monumented.
• C/L Monument/Assembly, Reference Monument, Right of Way Monuments and Project Horizontal / Vertical Control.
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
23
Setting ODOT Monuments• ODOT Monument Setting Policy
– Revised August 20, 2007 – See http://www.dot.state.oh.us/prod/ROW/Manual/ROWUpdates.asp– R/W Plan Designer to Set R/W Monuments After Acquisition As
Directed by District– Payment by R/W Plan
– Contractor to Construct Monument Assembly Box With Pin (no cap)– Payment by Project Pay Item 604
– Contractor to Set / Construct All Reference Monuments– Payment by Project Pay Item 604
– Contractor to Reset All R/W Monuments After Construction– Set by or under the Supervision of a Licensed Ohio Surveyor– Payment by Project Pay Item 604
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
Monumentation
• Centerline Monument Assembly– Set on the centerline of right of way in pavement– Includes a Monument Box with a Lid– 1” Dia. x 36” Long Steel Rod
• Set by or under the Supervision of a Licensed Ohio Surveyor– Centerline Monument– Set on the centerline of right of way in non paved areas– Same construction as Reference Monument– ¾” Dia. x 42” Long Steel Rod in 8” Dia. Cast in Place
Concrete with a Min. 3” Dia. Aluminum Cap– Cap Marked “C/L MON.” plus PS Number
24
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
25
Standard
Construction
Drawing RM-1.1
Rev. 7-18-08
Monument
Assembly
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
26
• Reference Monument– Set on or off centerline of
right of way in non paved areas
– ¾” x 42” Steel Rod in 8” Cast in Place Concrete with a Min. 3” Aluminum Cap
– Cap Marked “REF. MON.” plus PS Number
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
Monumentation
• Right of Way Monument– Set on Right of Way – ¾” Dia. x 30” Long Steel Rod – with a Min. 1-1/2” Dia. Aluminum Cap x 1-7/8” tall
(recommend a dissimilar metal insulator)– Cap Marked “ODOT R/W” plus “PS Number”
• Surveyor Name and / or Company Name may ALSO be added
27
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
Monumentation
28
• Right of Way Monument
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
29
Michael J. Ware, P.S.O.D.O.T. Central Office
• Graduated from Ohio State University in 1998• Worked in the private sector for 12 years, performing
boundary and topographic surveys, subdivision plan development, and right-of-way plan development for O.D.O.T. and LPA projects.
• Joined O.D.O.T. in September 2006
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
30
Base Map Preparation• Most commonly used Base Map types:
• Existing topography mapping-• Base Existing (BE) – Existing ground survey• Base Aerial (BA) – Aerial mapping• Base Combined (BC) – Combined aerial and ground
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
31
Base Map Preparation
• Most commonly used Base Map types (cont.)• Proposed design elements-
• Proposed roadway (BP) – most common• On some projects-
• Proposed drainage (BD)• Proposed walls (BW)• Utilities (BU)
• Right-of-Way elements-• Right-of-Way base map (BR)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
32
Base Map Preparation
• Base Existing Drawing (BE)• All topographic items within 100’ of proposed R/W lines
need to be located and identified• All buildings and fences located within the project limits and
those to be effected by the project• All above ground utility items, and underground utilities
located by OUPS or other locator service. Also private utilities, including septic systems and leach fields (extents), water supply wells, sprinkler systems, landscape lighting, and invisible fence.
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
33
Base Map Preparation
• Base Existing Drawing (BE)• All waterways & drainage structures• All field drives, alleys, roads and railroads within the project
limits• All trees, shrubs, flowerbeds, etc. (Varies by project)• All roadway signs, and private signs (Including ADC permit
number if present)• If it’s on the site, locate it and show it.• Take photos of the site for future use.
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
34
Base Map Existing (BE)Was anything missed?
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
35
Base Map Existing (BE)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
36
Base Map Existing (BE)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
37
Base Map Preparation
• Base Aerial Drawing (BA)• All visible topographic items• Provided by Aerial Engineering, or outside consultant• Usually provided for planning purposes, on larger
projects• Lacks detail and accuracy needed for design work
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
38
Base Aerial (BA)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
39
Base Map Preparation
• Base Combined Drawing (BC)• Combination of features from aerial and ground
surveys• Aerial portion for wider coverage• Ground survey portion fills in details
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
40
Base Map Preparation
• Base Proposed Drawing (BP) All proposed roadways and driveways All proposed drainage structures and ditches
(May be in separate files) Construction limits Any proposed items that will effect the Right of
Way location Centerline construction baseline and stationing
(sometimes)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
41
Base Proposed Drawing (BP)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
42
Base Proposed Drawing (BP)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
43
Base Map Preparation
• Base Right of Way Drawing (BR) Prior listed Reference Files (BE & BP) Centerline of Right of Way and stationing marks for
all roads located within the project limits, including bearings, distances and curve information
Try to avoid dual Centerlines (Construction Centerline & R/W Centerline), dual centerlines should be the exception not the rule
Can lead to confusion on right-of-way and construction plans
Be sure the relationship between the centerlines is clearly shown on the centerline plat
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
44
Base Map Preparation
• Base Right of Way Drawing (BR) Existing and proposed Right of Way Lines Original Government land lines and monuments used to
establish them. Showing direct ties to the CL of R/W. Property lines, easement lines, and monuments used to
establish them Civil boundaries and monuments used to establish them Ownership information Land use information Note any areas of concern with overlaps, gaps and occupation
problems
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
45
Base Right of Way (BR)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
46
Base Right of Way (BR)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
47
Base Right of Way (BR)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
48
Field Review by R/W Plan Designer
• Should be performed at the Preliminary R/W Submission, Final R/W Submission and at the Right of Way Tracings Submission (within 15 days of the Tracings Submission)
• Accuracy of Base Map (Relates directly to plan quality) Confirm all topography, structures, fences, drives, trees, and
the disposition of these items. Confirm above ground and below ground utilities Confirm OUPS and SUE's utility information Confirm sanitary sewer, septic tanks, septic system, leach
fields, private water supply wells, sprinkler systems, invisible fences (as possible)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
49
Field Review by R/W Plan Designer
Confirm all Advertising and Device Controlled signs and the Permit Plate No. (if present)
Confirm all field related items listed from the prior Base Right of Way Map Preparation
• Also need to check and confirm property ownerships within 15 days of submitting R/W tracings
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
50
Field Review by R/W Plan Designer
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
51
GEOPAK Standards
• ODOT CADD Manual Pages 49-63 contains GEOPAK guidelines (COGO element and file naming conventions
• http://www.dot.state.oh.us/cadd/CaddManual/2007-01-19CADDManual.pdf
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
52
GEOPAK Standards
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
53
GEOPAK Standards
• COGO points named per standards
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
54
GEOPAK Standards
• Right of Way sheet files in proper directory
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
55
GEOPAK Standards
• GEOPAK Files Only one GPK file per project All cogo related information (Points, Chains, Parcels etc.)
to be stored in the GPK file GPK file is a required deliverable. It is recommended that an output file for each alignment
be saved
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
56
‘Cutting’ R/W Sheets• Create .dgn file for first plan sheet (use proper filename and seed file)• Using ODOT_files.exe makes this easier
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
57
‘Cutting’ R/W Sheets• Open file and attach all needed references (BE, BP, BR, etc)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
58
‘Cutting’ R/W Sheets• Open file and attach all needed references (BE, BP, BR, etc)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
59
‘Cutting’ R/W Sheets
• Place border cell at proper plan scale (if ODOT_files.exe utility was used, this should be in the file already)
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
60
‘Cutting’ R/W Sheets• Fill in sheet title and headers, place cells and other drafting items
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
61
‘Cutting’ R/W Sheets• Place a closed shape on a Scratch level
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
62
‘Cutting’ R/W Sheets• Place a closed shape on a Scratch level
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
63
‘Cutting’ R/W Sheets• Select reference files and use the closed element to clip
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
64
‘Cutting’ R/W Sheets• Sheet file with references clipped and shape level turned off
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
65
‘Cutting’ R/W Sheets• Copy file in directory, or perform ‘save as’ in Microstation
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
66
‘Cutting’ R/W Sheets• In each file, ‘select all’ and move along the alignment
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
67
‘Cutting’ R/W Sheets• In each file, ‘select all’ and move along the alignment
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
68
‘Cutting’ R/W Sheets• Manipulate the shape to enclose the desired area
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
69
‘Cutting’ R/W Sheets• Plan sheet with shape level turned off
Ohio Depar t ment of Tr anspor t at ion – R/W P l an Devel opment
70
‘Cutting’ R/W Sheets
• Attach all needed references (BE, BP, BR, etc)
• Place fence or closed smartline to define boundary (smartline can be edited later)
• Clip Boundary
• For Questions contact :
Eric Thomas (614) 752-6403
Mike Ware (614) 466-5228