The New Age of FOUNDATION fieldbus™Commissioning
Application of New Tools and Techniques to Conventional Commissioning Practices
1
Copyright © 2006-2009 BusCorp Inc.
Description of Project
2
Copyright © 2006-2009 BusCorp Inc.
Some Motivations For Change
3
Copyright © 2006-2009 BusCorp Inc.
Some Motivations For Change
4
Copyright © 2006-2009 BusCorp Inc.
Problem Statement
Commissioning Capital Projects:• Timely• Efficiently
The Goal:• Seeking Potential Early Reward• On-time Startup• Safety of Personnel
5
Copyright © 2006-2009 BusCorp Inc.
Conventional Practice
Device Pre-Configuration by Vendor• Pre-set:
• PD_TAG• Device Class• Node Address
6
Copyright © 2006-2009 BusCorp Inc.
Conventional Practice
Physical Layer Testing• Digital Multi-Meter• Portable Oscilloscope • Hand-Held Fieldbus Testers
8 MemoryLocations 16 Memory
Locations
7
Copyright © 2006-2009 BusCorp Inc.
Conventional Practice
Fieldbus ParameterConfiguration
• Resource Block• Transducer Block• Function Blocks
8
Copyright © 2006-2007 BusCorp Inc. Copyright © 2006-2009 BusCorp Inc. 9
Praxis Solution
1. Pre-configure Devices at Site
2. Use Integrated Physical Layer Testing
• Hardware
• Software
3. Remote Configuration of Device Parameters
Copyright © 2006-2009 BusCorp Inc.
Implementation
Pre-Configure Devices at Site Prior to Commissioning
• Align Devices with Database:• PD_Tag, • Device Class• Node Address
• No Site Power Available• “Go-Bag” includes portable power,
power conditioner, configuration software on laptop
10
Copyright © 2006-2009 BusCorp Inc.
Implementation
Use Integrated Software/Hardware Diagnostics for Physical Layer Testing
11
Copyright © 2006-2009 BusCorp Inc.
Implementation
12
Copyright © 2006-2009 BusCorp Inc.
Implementation
Configure Device Parameters Remotely During Commissioning
13
Copyright © 2006-2007 BusCorp Inc. Copyright © 2006-2009 BusCorp Inc. 14
Summary
Copyright © 2006-2009 BusCorp Inc.
Summary
Devices Pre-Configured• Accelerated Testing of Physical Layer
15
Copyright © 2006-2009 BusCorp Inc.
Summary
Data collection in safe (and comfortable) location eliminating:
• Pinch-points – swinging cabinet doors
• Stooping in panels with hand-held tools
• Live circuits – electrical hazards
• Close-quarters – other workers in proximity
16
Copyright © 2006-2009 BusCorp Inc.
Summary
Device Parameters Configured Remotely Using Asset Management Tools (PRM)
17