    Sl. Description Unit Quantity Rate Amount

    No. Rs. Rs.

    1. a) Towers with accessories MT 15 0.80 12.000

    b) Bolts & Nuts including spring washers MT 0.75 0.80 0.600

    2. Foundation materials LS KM 0.65 0.650

    3. Earthing materials SETS 3 0.02 0.060

    4. PANTHER ACSR Conductor KM 6.1 1.37 8.357

    5. Insulators LS KM 1.30 1.300

    6. Hardware & Accessories for conductor LS KM 0.60 0.600

    7. High tensile galvanised steel wire 7/3.15mm KM 1.01 0.20 0.202

    8. Hardware & Accessories for steel wire LS KM 0.03 0.030

    Total Material Cost : 23.799

    9. Spares @ 3% 0.71

    10. Surveys, Lands & rights, tree/crop 2.50 2.50

    compensation, works to be executed

    as per PTCC approval etc.

    11. Erection charges 3.00 3.00

    Add work contract tax @ 4% 0.12

    SUB-TOTAL 30.13

    Price escalation @ 10% 3.01

    33.15

    Contingencies @ 3% 0.99

    34.14

    Establishment charges andOther overhead charges @ 10.75% 3.67

    37.81

    TOTAL 37.81

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    COST DATE FOR ERECTION OF 132 KV DC LINE WITH PANTHER ACSR CONDUCTOR

    (DATA FOR 1 KM)

    OR SAY Rs.38.00 LAKHS

  • 7/25/2019 87057182-Cost-Data-132-kV

    2/13

    S.No Description Units Qty Unit

    Rate.

    Total

    Amount

    1 Fibre Optic Cable of ADSS type with

    DWSM, 24 Fibre capacity & following

    Accessories

    kMs.

    23 1.17 26.91

    i) Suspension Clamp sets.

    ii) Tension Clamp sets

    iii) 4R Stock bridge Vibration dampers

    2 Splice boxes (OFC-OFC) Nos. 15 0.036 0.54

    3 Splice boxes (OFC-OFAC) Nos. 3 0.036 0.108

    4 Fibre distribution panels for termination of

    fibres of 24 Fibre capacity. (Nos.)

    Nos.

    2 0.15 0.3

    5 Fibre approach cable of 24 Fibre capacity kMs. 3 0.50 1.50

    6 OLTE, MUX equipments

    6.1 Two directional PDH type OLTE equipment

    with capacity of 8 Mbps in each direction

    with 1+1 protection at optical level and hot

    stand by power supply system, primary

    Multiplexer, Digital Distribution Frame,

    Engineering Order Wire Telephone.

    Nos.

    2 5 10

    9.2 Three directional PDH type OLTE

    equipment with capacity of 8 Mbps in each

    direction with 1+1 protection at optical level

    and hot stand by power supply system,

    Primary Multiplexer, Digital Cross Connect,

    Digital Distribution Frame, Engineering

    order wire Telephone.

    Nos.

    1 10.5

    6.2 Main Distribution Frame (MDF) with Krone

    tag block & tool for 100 terminations of

    Voice & Data Circuits.

    Nos.

    5 0.03 0.15

    6.3 Spares for OLTE equipment of 8 Mbps

    capacity suitable accessories.

    Nos.

    1 6.4

    COST ESTIMATE FOR PROVIDING OFCEQUIPMENT FOR 132 kV SUB-STATION

  • 7/25/2019 87057182-Cost-Data-132-kV

    3/13

    9.5 Network Management System comprising

    of Personnal Computer (P IV, 2.8 + GHz,

    120 GB HDD, 10/100 Mbps, ETH Card,

    1.44 MB FDD with Serial Ports-4 Nos, USB

    Ports-4 Nos, Optical Mouse, Optical

    keyboard etc., Computer Table, Computer

    Chair, Inkjet Printer and Software for

    configuration. All necessary Software (OS,

    Antivirus, Drivers, Printer etc.) with License

    version shall be supplied in the form CD

    also.

    Nos.

    1 3.49

    7 EPAXs (16 / 16) Nos. 2 2.00 4.00

    8 EPB Telephones Nos. 25 0.02 0.50

    9 48V / 50A Float Cum Boost Charger (1+1) Nos.

    1 1.70 1.70

    10 48V / 250AH SMF VRLA Battery set Nos. 1 1.50 1.50

    11 1.5 ton Split AC Units along with

    Stabilizers

    Nos.

    2 0.03 0.06

    12 6 Pair Telephone Cable kMs. 0.5 0.50 0.25

    13 1 Pair Telephone Cable kMs. 0.5 0.20 0.10

    14 16 Sq.mm Battery Cable kMs. 0.5 1.30 0.65

    A) Sub total 48.27

    B) Excise Duty @ 14.42% 6.960

    C) Sub total 55.23

    D) CST @ 2% on C 1.10

    E) Sub total 56.33

    F) Errection and Commissioning @ 6% 3.38

    GRAND TOTAL (Rs. In Lakhs) 59.71

    Note:

    Sd/-

    Chief Engineer / Telecom

    or SAY Rs. 60.00 Lakhs

    1. If PLCC is established, only two communication channels can be made available.

  • 7/25/2019 87057182-Cost-Data-132-kV

    4/13

    Sl. Description Unit Quantity Rate Amount

    No. (Rs.Lakhs) (Rs.Lakhs)1. a) Towers with accessories MT 15 0.80 12.00

    b) Bolts & Nuts MT 0.75 0.80 0.60

    2. Foundation materials LS LS 0.65 0.65

    3. Earthing materials SETS 3 0.02 0.06

    4. PANTHER ACSR Conductor KM 3.05 1.37 4.18

    5. Insulators LS LS 1.30 1.30

    6. Hardware & Accessories for conductor LS LS 0.60 0.60

    7. High tensile galvanised steel wire 7/3.15mm KM 1.01 0.20 0.20

    8. Hardware & Accessories for earthwire LS LS 0.03 0.03

    Total Material Cost 19.62

    9. Spares @ 3% 0.59

    10. Surveys, Lands & rights, tree/crop LS LS 2.50 2.50

    compensation, works to be executed

    as per PTCC approval etc.

    11. Erection charges LS LS 3.00 3.00

    12. Work Contract Tax 0.12

    SUB-TOTAL 25.83

    Price escalation @ 10% 2.5828.41

    Add 3% towards contingencies 0.85

    29.26

    Establishment charges and 3.15

    Other overhead charges @ 10.75%

    TOTAL 32.41

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    COST DATA FOR ERECTION OF 132 KV DC/SC LINE (DATA FOR 1 KM)

    or say Rs.33.00 lakhs

  • 7/25/2019 87057182-Cost-Data-132-kV

    5/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs. lakhs) (Rs. lakhs)

    1 50 MVA Transformers Nos. 2 400.000 800.000

    2 132 kV Breakers Nos. 4 11.000 44.000

    3 33 kV Breakers Nos. 6 3.200 19.200

    4. 132 kV Current Transformers Nos. 12 0.900 10.800

    5. 33 kV Current Transformers Nos. 18 0.250 4.500

    6. 132 kV Potential Transformers. Nos. 3 0.940 2.820

    7 33 kV Potential Transformers. Nos. 3 0.140 0.420

    8. 132 kV CVTs. Nos. 4 2.600 10.400

    9. 132 kV Lightining Arrestors Nos. 12 0.370 4.440

    10. 33 kV Lightining Arrestors Nos. 21 0.050 1.050

    11. 132 kV Isolators Nos. 7 1.330 9.310

    12. 33 kV Isolators Nos. 12 0.310 3.720

    13. 33 kV Twin Feeder control & Relay Panels Nos. 2 1.370 2.740

    14. 132 kV Feeder control & Relay Panels No. 2 5.400 10.800

    15. Transformer HV&LV Control Panels Nos. 2 7.130 14.260

    16. LTAC Panels No. 1 1.120 1.12017. Battery set No. 1 2.770 2.770

    18. Station Transformer No. 1 1.100 1.100

    19. Control & Power Cables KM 20 0.500 10.000

    20. Structures MT 40 0.800 32.000

    21. Bolts & Nuts MT 2.5 0.800 2.000

    22. 33 kV 5 MVAR Shunt Capacitor Banks Sets 0 9.890 0.000

    23. Control House LS LS 40.000 40.000

    24. Bus bar Jumpers, insulators, LS LS 5.000 5.000

    25 Earth connectors clamps & connectors etc., LS LS 7.500 7.500

    25. Foundations for Structures & Trs. LS LS 52.000 52.000

    26. Fire Protection Equipment LS LS 3.000 3.000

    27. Land & Rights, levelling etc., LS LS 20.000 20.00028. Roads & Bridges LS LS 21.000 21.000

    29. Enclosers & Sidings LS LS 15.000 15.000

    30. Office & Stores LS LS 2.000 2.000

    31. Sanitary System LS LS 2.000 2.000

    32. Water System LS LS 2.000 2.000

    33. Electricty System LS LS 2.000 2.000

    34. Cable Laying System LS LS 8.000 8.000

    35. General Substation equipment LS LS 2.500 2.500

    36 Diesel Generator set LS LS 4.000 4.000

    SUB - TOTAL 1173.450

    Spares @ 3% 29.624Transport & Insurance @ 4% 39.498

    Erection charges @ 6% 59.247

    1301.819

    Price escalation @10% 130.182

    1432.000

    Contingencies @ 3% 42.960

    1474.960

    Establishment and overhead 158.558

    charges @ 10.75%

    TOTAL 1633.519

    COST DATA FOR ERECTION OF 132/33 kV SUBSTATION WITH 2x50 MVA POWER

    TRANSFORMERS WITH 2NOs.132KV INCOMING AND 4NOs. 33KV OUTGOING

    FEEDERS(LILO)

    OR SAY Rs. 1638.00 LAKHS

  • 7/25/2019 87057182-Cost-Data-132-kV

    6/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs. lakhs) (Rs. lakhs)

    1 21.50 MVA Power Transformer Nos. 1 230.00 230.00

    16 MVA 37.500 37.500

    2 132 kV Breakers Nos. 3 11.00 33.00

    3 33 kV Breakers Nos. 6 3.20 19.204. 132 kV Current Transformers Nos. 9 0.90 8.10

    5. 33 kV Current Transformers Nos. 18 0.25 4.50

    6. 132 kV Potential Transformers. Nos. 3 0.94 2.82

    7 33 kV Potential Transformers. Nos. 3 0.14 0.42

    8. 132 kV CVTs. Nos. 2 2.60 5.20

    9. 132 kV Lightining Arrestors Nos. 9 0.37 3.33

    10. 33 kV Lightining Arrestors Nos. 21 0.05 1.05

    11. 132 kV Isolators Nos. 5 1.33 6.65

    12. 33 kV Isolators Nos. 12 0.32 3.84

    13. 33 kV Twin Feeder control & Relay Panels Nos. 2 1.37 2.74

    14. 132 kV Feeder control & Relay Panels No. 1 5.40 5.40

    15. Transformer HV&LV Control Panels Nos. 2 9.00 18.00

    16. LTAC Panels No. 1 1.12 1.12

    17. Battery set No. 1 2.37 2.37

    18. Station Transformer No. 1 1.10 1.10

    19. Control & Power Cables KM 15 0.50 7.50

    20. Structures MT 50 0.80 40.00

    21. Bolts & Nuts MT 2.5 0.80 2.00

    22. 33 kV 5 MVAR Shunt Capacitor Banks Sets 0 9.89 0.00

    23. Control House LS LS 40.00 40.00

    24. Bus bar Jumpers, insulators, LS LS 5.00 5.00

    25 Earthing system LS LS 7.50 7.50

    26. Foundations for Structures & Trs. LS LS 52.00 52.00

    27. Fire Protection Equipment LS LS 3.00 3.00

    28. Land & Rights, levelling etc., LS LS 20.00 20.00

    29. Roads & Bridges LS LS 21.00 21.00

    30. Enclosers & Sidings LS LS 15.00 15.0031. Sanitary System LS LS 2.00 2.00

    32. Water System LS LS 2.00 2.00

    33. Electricty System LS LS 2.00 2.00

    34. Cable Laying System LS LS 8.00 8.00

    35.

    General Substation equipment including Air

    coolers,water coolers,PC with Printer etc LS LS 2.50 2.50

    36 Diesel generator set LS LS 4.00 4.00

    SUB - TOTAL 619.84

    Spares @ 3% 11.59

    Transport & Insurance @ 4% 15.45

    Erection charges @ 6% 23.18

    670.06

    Price escalation @ 10% 67.01737.07

    Contingencies @ 3% 22.11

    759.18

    Establishment & overhead charges @ 10.75% 81.61

    TOTAL 840.79

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    COST DATA FOR ERECTION 132/33 kV SUBSTATION WITH 2 X 50 MVA POWER TRANSFORMERS

    (RADIAL)

    or say Rs.841.00 Lakhs

  • 7/25/2019 87057182-Cost-Data-132-kV

    7/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs. lakhs) (Rs. lakhs)

    1 16 MVA Transformers No. 1 125.00 125.00

    2 132 kV Breakers Nos. 2 11.00 22.00

    3 33 kV Breakers Nos. 5 3.20 16.00

    4. 132 kV Current Transformers Nos. 6 0.90 5.40

    5. 33 kV Current Transformers Nos. 15 0.25 3.75

    6. 132 kV Potential Transformers. Nos. 3 0.94 2.82

    7 33 kV Potential Transformers. Nos. 3 0.14 0.42

    8. 132 kV CVTs. Nos. 2 2.60 5.20

    9. 132 kV Lightining Arrestors Nos. 6 0.37 2.22

    10. 33 kV Lightining Arrestors Nos. 15 0.05 0.75

    11. 132 kV Isolators Nos. 4 1.33 5.32

    12. 33 kV Isolators Nos. 11 0.32 3.52

    13.33 kV Twin Feeder control & RelayPanels No. 2 1.37 2.74

    14. 132 kV Feeder control & Relay Panels No. 1 5.40 5.40

    15. Transformer HV&LV Control Panels No. 1 9.00 9.00

    16. LTAC Panels No. 1 1.12 1.12

    17. Battery set No. 1 2.37 2.37

    18. Station Transformer No. 1 1.10 1.10

    19. Control & Power Cables KM 15 0.50 7.50

    20. Structures MT 30 0.60 18.00

    21. Bolts & Nuts MT 2 0.60 1.20

    240.83

    COST DATA FOR ERECTION 132/33 kV SUBSTATION WITH 1 X 16 MVA POWER

    TRANSFORMER (RADIAL)

  • 7/25/2019 87057182-Cost-Data-132-kV

    8/13

    22. 33 kV 5 MVAR Shunt Capacitor Banks Sets 0 9.89 0.00

    23. Control House LS LS 25.00 25.00

    24. LS LS 5.00 5.00

    25. Foundations for Structures & Trs. LS LS 15.00 15.00

    26. Fire Protection Equipment LS LS 1.00 1.00

    27. Land & Rights, levelling etc., LS LS 20.00 20.00

    28. Roads & Bridges LS LS 10.00 10.00

    29. Enclosers & Sidings LS LS 15.00 15.00

    30. Office & Stores LS LS 2.00 2.00

    31. Sanitary System LS LS 2.00 2.00

    32. Water System LS LS 2.00 2.00

    33. Electricty System LS LS 2.00 2.00

    34. Cable Laying System LS LS 8.00 8.00

    35. General Substation equipment LS LS 6.50 6.50

    SUB - TOTAL 354.33

    Spares @ 3% 6.42

    Transport & Insurance @ 4% 8.57

    Erection charges @ 6% 12.85

    382.17

    Price escalation @ 10% 38.22

    420.38

    Contingencies @ 3% 12.61

    433.00

    Establishment & overhead

    charges @ 10.75% 46.55

    TOTAL 479.54

    Bus bar Jumpers, insulators, earthconnectors clamps & connectors etc.,

    or say Rs.480.00 lakhs

  • 7/25/2019 87057182-Cost-Data-132-kV

    9/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs. lakhs) (Rs. lakhs)

    1 16MVA Transformer(released) No. 1 37.50 37.50

    2 132 kV Breakers Nos. 3 11.00 33.00

    3 33 kV Breakers Nos. 5 3.20 16.00

    4. 132 kV Current Transformers Nos. 9 0.90 8.10

    5. 33 kV Current Transformers Nos. 12 0.25 3.00

    6. 132 kV Potential Transformers. Nos. 3 0.94 2.82

    7 33 kV Potential Transformers. Nos. 3 0.14 0.42

    8. 132 kV CVTs. Nos. 2 2.60 5.20

    9. 132 kV Lightining Arrestors Nos. 9 0.37 3.33

    10. 33 kV Lightining Arrestors Nos. 18 0.05 0.90

    11. 132 kV Isolators Nos. 6 1.33 7.98

    12. 33 kV Isolators Nos. 11 0.32 3.52

    13. 33 kV Twin Feeder control & Relay Panels No. 2 1.37 2.74

    14. 132 kV Feeder control & Relay Panels No. 2 5.40 10.80

    15. Transformer HV&LV Control Panels No. 1 9.00 9.00

    16. LTAC Panels No. 1 1.12 1.12

    17. Battery set No. 1 2.37 2.37

    18. Station Transformer No. 1 1.10 1.10

    19. Control & Power Cables KM 10 0.50 5.00

    20. Structures MT 40 0.60 24.00

    21. Bolts & Nuts MT 2 0.60 1.20

    179.10

    COST DATA FOR ERECTION 132/33 kV SUBSTATION WITH 1 X 16 MVA POWER

    TRANSFORMER

  • 7/25/2019 87057182-Cost-Data-132-kV

    10/13

    22. 33 kV 5 MVAR Shunt Capacitor Banks Sets 0 9.89 0.00

    23. Control House LS LS 25.00 25.00

    24. LS LS 5.00 5.00

    25. Foundations for Structures & Trs. LS LS 15.00 15.00

    26. Fire Protection Equipment LS LS 1.00 1.00

    27. Land & Rights, levelling etc., LS LS 20.00 20.00

    28. Roads & Bridges LS LS 10.00 10.00

    29. Enclosers & Sidings LS LS 15.00 15.00

    30. Office & Stores LS LS 2.00 2.00

    31. Sanitary System LS LS 2.00 2.00

    32. Water System LS LS 2.00 2.00

    33. Electricty System LS LS 2.00 2.00

    34. Cable Laying System LS LS 8.00 8.00

    35. General Substation equipment LS LS 6.50 6.50

    SUB - TOTAL 292.60

    Spares @ 3% 5.37

    Transport & Insurance @ 4% 7.16

    Erection charges @ 6% 10.75

    315.88

    Price escalation @10% 31.59

    347.47

    Contingencies @ 3% 10.42

    357.90

    Establishment & overhead

    charges @ 10.75% 38.47

    TOTAL 396.37

    Bus bar Jumpers, insulators, earth

    connectors clamps & connectors etc.,

  • 7/25/2019 87057182-Cost-Data-132-kV

    11/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs.) (Rs.)

    A. PLCC EQUIPMENT

    1. PLCC TERMINAL (TWIN CHANNEL) Nos. 2 3.60 7.20

    2. Protection Couplers

    3. VFT

    4.a) EPAX Nos. 1 3.20 3.20

    3. EPB Phones Nos. 25 0.01 0.25

    4. 48 V / 150 AH Battery Nos. 1 0.80 0.80

    5. 48 V / 35 A Charger Nos. 1 1.10 1.10

    6. Digital Multimeter Nos. 1 0.30 0.30

    7. A/C Units 1.5 ton capacity Nos. 2 0.35 0.70

    8. Wave Traps (630A/0.2 m H) Nos. 2 0.90 1.80

    9. Copuling Units (P/P) Nos. 1 0.80 0.80

    10. Co-axial cable Nos. 1 0.80 0.80

    11. 6 Pair telephone cable KM 0.5 0.20 0.10

    12. 1 Pair telephone cable with connectors KM 0.6 0.08 0.05

    13. 16 Sq. mm battery cable KM 0.1 0.80 0.08

    Spares for item 1-4 @ 3% 0.45

    SUB-TOTAL (A) 17.63

    B. VSAT EQUIPMENT

    1.TDMA/FTDMA VSAT equipment with all accessories

    i. 1.2 M Antenna with IFL cable & Termination Nos. 1 0.15 0.15

    ii. Nos. 1 1.50 1.50

    iii. -48 V Inverter Nos. 1 0.05 0.05

    Spares @ 3% 0.051

    SUB-TOTAL (B) 1.751

    SUB-TOTAL (A+B) 19.379

    Insurance, Transport & CST @ 8% 1.550

    20.93

    2.09

    23.02

    Contingencies @3% 0.91

    23.93

    Establishment & Other overhead charges @ 10.75% 2.57

    TOTAL 26.50

    Recurring Charges per annum

    a Bandwidth usage charges

    i. 1 No. voice circuit (4.8 kbps) kbps 4500 0.216ii. Metering data transmission (2kbps) kbps 4500 0.09

    b i. DOT charges @ 10% on (a) 0.031

    ii. WPC charges @ 3.5% on (a) 0.011

    iii. Annual Maintenance & Repair 0.06

    0.408

    Price Escalation 10% 2.650

    GRAND TOTAL 29.563

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    2 Watt VSAT RF Terminal with LNA, SSPA and down

    convertor and VSAT base band equipment with one

    Ethernet port, two serial one 2 W voice port, cables

    and connectors

    Erection & Commission charges for A&B including

    provision of earthing system for VSAT 10%

    COST DATA FOR PLCC ON THE 132 kV LINE WITH NEW SUB-STATION (PER LINK)

    or SAY Rs.30.00 lakhs

  • 7/25/2019 87057182-Cost-Data-132-kV

    12/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs.) (Rs.)

    1. 9.1 M PSCC Pole Each 12 1408 1689

    2. 1.53 M Cross Arm (Channel) Each 10 413 413

    3. Top Clamp with cleat Each 10 135 135

    4. Back clamp Each 10 51 51

    5. Stay Sets Each 6 510 306

    6. Bracing Set with double cross arm Set 1 4050 405

    7. 100 Sq.mm AAA Conductor KM 3.06 33576 10274

    8. 33 kV Pin-insulator with Pin Each 27 303 818

    9. Strain insulator with pin Set 12 1029 1234

    10. Concreting of Pole, Stay sets & Base Concreting LS LS 15400 1540

    11. LS LS 2500 250

    TOTAL COST OF MATERIAL 17116

    3% Storage & handling charges on items (1) to (9) 459

    3% Contingencies on Materials 513

    Labour 2235

    Transport 409

    10% Estt. & Gen. Charges on material 1711

    TOTAL 22445

    Price Escalation @ 10% 2244

    GRAND TOTAL 24690

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    REC Construction standard No.M11/1979(R-1989) Cost data per KM of 33 kV line with

    100 Sq.mm AAA Conductor over 9.1 Mts. PSCC Poles at 105 Mts. Span 75 KG per Sq.Mt. Wind

    pressure, working load 280 KGs.

    Misc. items like coil earthing, pipe earthing, danger-boards

    or SAY Rs.2.50 Lakhs

  • 7/25/2019 87057182-Cost-Data-132-kV

    13/13

    Sl. Item Unit Quantity Rate Amount

    No. (Rs. lakhs) (Rs. lakhs)

    1 132 kV Breakers No. 1 11.000 11.000

    2 132 kV Current Transformers Nos. 3 0.900 2.700

    3 132 kV CVTs Nos. 2 2.600 5.200

    4 132 kV Feeder control & Relay Panels No. 1 5.400 5.400

    5 132 kV Isolators Nos. 2 1.330 2.660

    6 132 kV Lightining Arrestors Nos. 3 0.370 1.110

    7 Cables KM 5 0.500 2.500

    8 Structures (Galvanised) MT 11 0.800 8.800

    9 Bolts & Nuts MT 0.55 0.800 0.440

    10.Bus bar Jumpers, insulators, earth connectors

    clamps & connectors etc,LS LS 2.500 2.500

    11 Foundations for Structures LS LS 3.500 3.500

    12 Fire Protection Equipment LS LS 0.200 0.200

    13 Land Levelling etc. LS LS 0.500 0.500

    14 Roads & Bridges LS LS 0.000 0.000

    15 Enclosures & Sidings LS LS 0.000 0.000

    16 Water System LS LS 0.200 0.200

    17 Cable Laying System LS LS 0.700 0.700

    SUB - TOTAL 47.410

    Spares @ 3% 1.194

    Transport & Insurance @ 4% 1.592

    Erectior charges @ 6% 2.389

    52.585

    Price escalation @10% 5.259

    57.844

    Contingencies @ 3% 1.735

    59.579

    Establishment and overhead charges @ 10.75% 6.405

    GRAND TOTAL 65.984

    OR SAY Rs.66.00 LAKHS

    \\vboxsrv\conversion_tmp\scratch8926\[90249299.xls.ms_office.xls]2x50 (LILO)

    COST DATA FOR ERECTION OF 132 kV BAY EXTENSION (1 No. BAY)