8. LANDSCAPE AND VISUAL IMPACT 8.1 Introduction · 2008-04-07 · 8.5.1.12 The assessment of the...
Transcript of 8. LANDSCAPE AND VISUAL IMPACT 8.1 Introduction · 2008-04-07 · 8.5.1.12 The assessment of the...
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-1 January 2008
8. LANDSCAPE AND VISUAL IMPACT
8.1 Introduction
8.1.1.1 This section assesses the potential landscape and visual impacts arising from the
proposed upgrading works of the existing Pillar Point STW in accordance with the
criteria and guidelines as stated in Annexes 10 and 18 of the TM and EIAO.
Landscape and visual impacts of any above ground structures and work areas
associated with the project during both construction and operation stages within the
study area will be assessed. Key elements of the proposed works are described
below:-
� Modify and expand the existing aerated grit channel;
� Construct chemically enhanced primary treatment units;
� Construct sludge treatment units which include sludge dewatering facilities and
sludge holding facilities;
� Construct UV irradiation disinfection units;
� Modify and expand the existing septic waste reception facilities;
� Provide odour control facilities; and
� Modify and upgrade the existing ancillary facilities including administration
building, workshop, laboratory and landscaping works.
The dimensions of all the above-ground structures as listed above are:
Approximate dimensions of above-ground structures New structures for
upgraded PPSTW
(Figure 2.3 refers) Width (m) Length (m) Height (m)
New Transformer
Room 6 12 5
Extension of Air
Compressor House 5.5 5.5 4.8
New Aerated Grit
Channel 5.5 13 1.5
New Workshop, New
Admin. Building &
Lab and Control
Room
14 46 9
New Rapid Mixing
Tanks, New
Flocculation Tanks
and New
Sedimentation Tanks
85 95.5 2.5
New Odour Control
Plant I 24 27 7
New Low Lift and
Pumping Station 23.5 25 7
New Chemical
Building 18 45.5 8
Sludge Holding Tank
No. 1, 2, 3 29 38.2 17.5
New Odour Control
Plant II 16.5 27 7
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-2 January 2008
Approximate dimensions of above-ground structures New structures for
upgraded PPSTW
(Figure 2.3 refers) Width (m) Length (m) Height (m)
New Sludge
Dewatering Building 30 31 13.5
New Sludge / Septic Waste Reception Area
15.2 29.7 6
New Return Liquor
Pumping Station 6.2 6.7 0.5
New Sludge Pumping
Station 7 7 0.5
UV Spares Storage
Area 6 16 5
UV Spares Storage
Area 12 13 5
UV Switchgear and
Control Building 6 18 5
Transformer Bay 6 18 5
UV disinfection
Facility 35.3 39.4 0.5
Payment Flowmeter
Chamber 13.4 22.3 2
8.2 Project Overview 8.2.1.1 The scope of the work, construction methodologies and works sites and works areas
for expanding the sewage treatment capacity and upgrading of the existing Pillar
Point STW are described in detail, and illustrated with figures in Section 2. 8.3 Review of Planning and Development Control Framework 8.3.1.1 A review of the existing and planned development framework of the proposed works
and surrounding area are undertaken as input to the Landscape and Visual Impact
Assessment (LVIA). The aim is to identify any issues within the neighbouring
planned land uses, and therefore to identify potential VSRs, and to ensure a high
compatibility between the proposed project and the surroundings.
8.3.1.2 Reference is made to the draft Tuen Mun Outline Zoning Plan No. S/TM/23, and
Site Layout Plan of the Pillar Point Treatment Works from Drainage Services
Department (refer to Section 2). 8.3.1.3 The study area of the Pillar Point STW site falls within an area zoned as “Other
Specified Uses” (OU) annotated “Sewage Treatment Plant” on the draft Tuen Mun
Outline Zoning Plan No. S/TM/23. The upgrading works of the Pillar Point STW
are considered to be highly compatible with the surrounding. 8.4 Environmental Legislation and Standards 8.4.1.1 The methodology for undertaking the LVIA takes reference from Annexes 3, 10 and
18 of EIAO–TM, and in accordance with EIAO Guidance Note No. 8/2002.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-3 January 2008
8.4.1.2 Other landscape documents relevant for the preparation of the LVIA include:
• Government General Regulation 740 – restrictions on the preservation and
felling of trees in Hong Kong
• The Forests and Countryside Ordinance (Cap96) – prohibits felling, cutting,
burning or destroying of trees and growing plants in forests and plantations on
government land. Its subsidiary regulations prohibit the picking, felling or
possession of listed rare and protected plant species
• The Forestry Regulations – made under Section 3 of the Forests and Countryside
Ordinance (Cap. 96), defined the list of protected species in Hong Kong
• ETWBTC No. 2/2004 – sets out the government departmental responsibilities
for maintenance of vegetation and hard landscape features
• WBTC No. 3/2006 – Tree Preservation, which defines and outlines the
management and maintenance responsibilities for natural vegetation and
landscape works, and the authorities for tree preservation and felling
• WBTC No. 25/93 – Control of Visual Impact of slopes, outlines the design
principles recommended to be used in designing man-made slopes for Public
Works projects in order to reduce their adverse visual impact
• WBTC 17/2000 – Improvement to appearance of slopes, outlines the principles
and procedures recommended for all departments involved in new slope works
and maintenance of existing slopes for improving aesthetic and environmental
impact of slope works
• WBTC No. 7/2002 Tree planting in Public Works, affirms the advocated policy
on tree planting which adopts a flexible and balanced approach in the planning
and design of public works
• WBTC No. 29/2004 Registration of Old and Valuable Trees, and Guidelines for
their Preservation
• GEO publication No. 1/2000 ‘Technical Guidelines on landscape treatment and
Bio-engineering for Man-Made Slopes and Retaining Walls’
• Hong Kong Planning Standards and Guidelines Chapter 4, “Open Space”
• Hong Kong Planning Standards and Guidelines Chapter 10 “Conservation”
• Technical Reports of Landscape Value Mapping in Hong Kong by Planning
Department – establishes the essential landscape baseline information which
provides a systematic reference framework to facilitate landscape assessment.
• Environment Impact Assessment for Development of an EcoPark in Tuen Mun
Area 38 – Final EIA Report.
8.5 Assessment Methodology 8.5.1.1 The Project is a designated project (DP) under the EIAO and the methodology
adopted for the Project conforms to the requirements of the EIAO. The methodology
consists of the following tasks:
• Baseline study of landscape and visual resources
• Landscape impact assessment
• Visual impact assessment
• Recommendation on landscape and visual mitigation measures
• Identification of residual impacts
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-4 January 2008
Baseline Study of Landscape and Visual Resources
8.5.1.2 The study area for the landscape impact assessment shall include all areas within 500
meters from the Project. The study area for the visual impact assessment shall be
defined by the visual envelope of the Project. The defined visual envelope is shown
on Figure 8.4.1.
8.5.1.3 The baseline study identified and examined the existing landscape and visual
resources within the study area. An aerial photograph is used to show the overall
study area and labelled to indicate the Landscape Character Areas (LCAs), while
photographs would be given to demonstrate the Landscape Resources (LRs).
Landscape Resources (LRs) 8.5.1.4 Landscape Resources (LRs) considered the following elements:
• Natural and secondary woodland
• Amenity planting
• Scrubland and grassland
• Natural topography
• Significant planning designation, e.g. Country Park, Green Belt
• Heritage or cultural features
Landscape Character Area (LCA)
8.5.1.5 Field and desk surveys of topographical maps, information databases and
photographs would identify the landscape character (LCA) of the study area. The
character of the landscape is derived from its physical components related to its
visual amenity, cultural association and heritage value. Elements to be considered
include:
• Land use
• Public use of land
• Extent of vegetation
• Age of landscape
• Cultural, heritage and religious elements
• Scale and type of buildings
• Pattern of settlement
• Location and topography
• Extent of natural vs manmade
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-5 January 2008
8.5.1.6 The baseline study describes the LRs by identifying broadly homogenous Landscape
Character Areas (LCAs) of a similar character. The sensitivity of LR / LCAs are
rated low, medium or high. This is influenced by a number of factors including
whether the resources / character is common or rare, whether it is considered to be of
local, regional, national or global importance, whether there are any statutory
limitations / requirements relating to the resource/ character, the quality of the
resource / character, the maturity of the resource, and the ability of the resource /
character to accommodate change.
Visual Resources
Zone of Visual Influence/ Visual Envelope(ZVI)
8.5.1.7 Visual resources are considered as typical viewpoints, with location and direction of
views towards the proposed works. A Zone of Visual Influence/ Visual Envelope is
established which approximately defines the extent of visual influence of the
proposed works, and therefore, of the potential visual impacts. This is achieved by
site visit and desk-top study of topographic maps and photographs, and preparation
of cross-sections to determine visibility of the project from various locations.
Visually Sensitive Receivers (VSRs)
8.5.1.8 Visually Sensitive Receivers (VSRs) who would be present at typical viewpoints and
key views, and likely to be affected by the proposed works, are identified within the
visual envelope. VSRs are defined as individuals or groups of whom are sensitive to
changes in the visual environment. Residents, users of open space/recreational
facilities, road users (private and public transport users), schools, tourists and people
working within the visual envelope shall be considered as VSRs. 8.5.1.9 Each type of VSR is assigned with a number. Description of the view from each
VSR towards the proposed works in terms of location of VSRs, type of VSRs, and
direction of view towards the proposed works, are given and assigned in accordance
with the relative tolerance to change of the VSRs.
8.5.1.10 The sensitivity of VSRs are determined by considering:
• Value and quality of existing views, e.g. urban high-rise, natural hills, sea
view
• Presence and amenity of alternative views
• Type and estimated number of receiver population
Sensitivity Definition
High Important components of landscape of particularly distinctive
character susceptible to relatively small changes
Medium A landscape of moderately valued characteristics reasonably tolerant
of change
Low A relatively unimportant landscape, the nature of which is largely
tolerant to change
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-6 January 2008
• Duration or frequency of view
• Degree of visibility of the proposed project, e.g. no view, glimpse, partial
view, vista, open view, and panorama view)
8.5.1.11 Both present and future VSRs, i.e. from planned developments, would be
considered. The survey information shall be tabulated in a table and summarised in
the text. Drawings to show the location of VSRs and photographs showing typical
views would be included.
Assessment Methodology - Landscape Impacts 8.5.1.12 The assessment of the potential landscape impacts would result from:
• Identification of the source of impact, their magnitude, that would be
generated during construction and operation of the project; and
• Identification of principal impacts, primarily in consideration of the degree of
change to the baseline conditions.
8.5.1.13 The magnitude of change for landscape impact assessment would be determined by
the following factors:
• Compatibility of the project with the surrounding landscape
• Duration of impacts under construction and operation phases
• Scale of the impact
• Reversibility of change
8.5.1.14 The impacts are considered systematically as a product of the sensitivity of the
LCAs and the magnitude of change of the impacts to the landscape. The magnitude
of the change in the landscape is rated large, intermediate, small and negligible as
follows:
Magnitude of Change Definition
Large Notable permanent change in the landscape characteristics over
an extensive area ranging to very intensive changes over a more
limited area
Intermediate Moderate changes in a localised area
Small Virtually imperceptible change or temporary change
Negligible Virtually no changes in the area
8.5.1.15 The following factors are considered to the judgement of the overall landscape
impacts:
• The landscape character and its quality
• The sensitivity of the landscape in accommodating change
• Source, nature and magnitude of potential impacts
• Construction and operation phases impacts
• Degree of change caused by each of the impacts to the existing LCAs
• Significance of this change in the local and regional context and in relation to
other developments
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-7 January 2008
• Cumulative effects on the landscape of this and neighbouring projects
8.5.1.16 The overall impact likely to occur to LCAs, is derived from the magnitude of change
which the project would cause to the existing landscape and ability to tolerate the
change. A matrix shall be used to demonstrate the overall impact:
Sensitivity / Quality of the landscape
Low Medium High
Large Slight /
moderate
Moderate /
Substantial Substantial
Intermediate Slight /
Moderate Moderate
Moderate /
Substantial
Small Insubstantial /
Slight Slight / Moderate
Moderate /
slight Mag
nit
ude
of
Chan
ge
Negligible Insubstantial Insubstantial Insubstantial
8.5.1.17 Furthermore the impacts need to be identified as Adverse, Beneficial or Neutral,
which indicate the impact on the existing landscape context as follows:
8.5.1.18 The product of the LIA is termed the Significance Threshold, and shall be
considered as follows:
Identification of
the Landscape
Impact
Definition
Adverse An impact which will be detrimental to the existing landscape
context
Beneficial An impact which will improve the existing landscape context
Neutral An impact which will alter the existing landscape context but not to
improve or destroy it
Impacts
Substantial Adverse/beneficial impact where the proposal would cause significant
deterioration or improvement in existing landscape quality
Moderate Adverse/beneficial impact where the proposal would cause a noticeable
deterioration or improvement in existing landscape quality
Slight Adverse/beneficial impact where the proposal would cause a barely perceptible
deterioration or improvement in the existing landscape quality
Insubstantial No discernible change in the existing landscape quality
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-8 January 2008
Assessment Methodology - Visual Impacts
8.5.1.19 The baseline survey forms the basis of the visual impact assessment, and shall result
from:
• Identification of the source of visual impacts, their magnitude of change and
sensitivity of the receivers, that would be generated during construction and
operation of the project, and;
• Identification of principal visual impacts, primarily in consideration of the
degree of change to the baseline conditions
8.5.1.20 The magnitude of change for visual impact assessment would be determined by the
following factors:
• Compatibility of the proposed project with the surrounding landscape
• Duration of impacts during construction and operation stages
• Scale of impact and distance of the source of impact from the viewer
• Reversibility of impact
• Potential blockage of the view
8.5.1.21 The overall impact likely to occur to VSRs, is derived from the magnitude of change
which the project would cause to the existing visual context and its ability to tolerate
the change. A matrix shall be used to demonstrate the overall impact:
Sensitivity / Quality of the Visual Receivers
Low Medium High
Large Moderate Moderate /
Substantial
Substantial
Intermediate Slight / moderate Moderate Moderate /
Substantial
Small Slight Slight / Moderate Moderate
Mag
nit
ude
of
Chan
ge
Negligible Insubstantial Insubstantial Insubstantial
8.5.1.22 Furthermore the impacts need to be identified as Adverse, Benefit or Neutral, which
indicate the impact on the existing visual context as follows:
Identification of
the Visual Impact
Definition
Adverse An impact which will be detrimental to the existing views
Beneficial An impact which will improve the existing views
Neutral An impact which will alter the existing views but not to improve
or destroy it
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-9 January 2008
8.5.1.23 The product of the VIA is termed the Significance Threshold, and shall be
considered as follows:
Identification of Potential Landscape and Visual Impact Mitigation Measures
8.5.1.24 After assessing and identifying the landscape and visual impacts of the proposed
works which likely to occur and how significant these impacts would be,
recommendations would then be formulated to reduce or alleviate these impacts both
during the construction and operation stages. The agencies responsible for the
funding, implementation, management and maintenance of the mitigation measures
have been identified and their approval-in-principle will be sought.
Identification of Residual Impacts
8.5.1.25 This is a further assessment to establish residual impacts that persist after the
implementation of mitigation measures.
8.5.1.26 The principles for undertaking the residual impact assessment are similar to the
landscape and visual impact assessments. Significance threshold for the residual
impacts would be established to consider the impacts against the successfulness of
the recommended mitigation measures to alleviate such impacts.
Impacts
Substantial Adverse/beneficial impact where the proposal would cause significant
deterioration or improvement in existing views
Moderate Adverse/beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing views
Slight Adverse/beneficial impact where the proposal would cause a barely
perceptible deterioration or improvement in the existing views
insubstantial No discernible change in the existing views
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-10 January 2008
8.6 Baseline Study
Landscape Resources (LR)
8.6.1.1 Several landscape resources have been identified within the study area. These are
described below and mapped in Figure 8.2.1 and with photographic record in
Figure 8.2.2 & 8.2.3. The approximate locations of the tree groups within the study
boundary are indicated in Figure 8.9.2. Name of the LRs is listed and a description
of each LR is summarized as follows:
LR1 - Water Body LR2 - Stream Course
LR3 - Disturbed Hillside Plantation
LR4 - Scrubland/ Woodland Natural Terrain
LR5 - Roadside Planting
LR6 - Vegetation within existing DSD Sewage Treatment Works
LR7 - Vegetation within Industrial Area
LR8 - Golf Course
8.6.1.2 LRs findings from the baseline study are summarized in Table 8.1:
Table 8.1 Illustration of the Sensitivity of LRs in Study area
Id. No. Vegetation Feature Dominant Tree Species Function Sensitivity
LR 1 Water Body N.A. As habitat
purpose Low
LR 2
Stream course
(natural / artificial
channel)
N.A. As habitat
purpose Medium
LR 3 Disturbed hillside
plantation area Casuarina equisetifolia
As habitat
purpose Medium
LR 4 Scrubland/ Woodland
natural terrain
- Acacia confusa, Ficus microcarpa,
Sapium discolor, Sapium sebiferum,
Mallotus paniculatus, Litsea
glutinosa, Celtis sinensis, Sterculia
lanceolata, Casuarina equisetifolia,
Musa paradisiaca, Macaranga
tanarius, and other native tree
species, etc.
Public usage High
LR 5 Roadside planting Delonix regia, Cassia siamea Public usage medium
LR 6
Vegetation within
existing DSD sewage
treatment Works
343 no of exsting trees are recorded
in general height from 4m to 13m,
trunk diameter from 95mm to 300mm
and a spread from 2 to 13; they are
mainly Casuarina equisetifolia,
Hibiscus trifolia, Ficus elastica,
Leucaena leucocephala
Public usage medium
LR 7 Vegetation within
industrial area
Casuarina equisetifolia, Hibiscus
trifolia, Cassia siamea Public usage Medium
LR 8 Golf course N.A. Recreational
purpose Low
8.6.1.3 Apart from LR6, most the trees at other LRs are common species found with
approximately height from 4m to 13m, trunk diameter from 95 mm to 250 mm and
spread from 3 to 10. Amenity value of most of the existing trees is fair in average.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-11 January 2008
Landscape Character Area (LCA)
8.6.1.4 A baseline review has been undertaken of the landscape resources, landscape
character areas (LCA), zone of visual influence, and visual sensitive receivers. The
study area consists of five distinct LCA. The LCA are mapped in Figure 8.3.1 and
photographic record are illustrated in Figure 8.3.2. A description of each LCA is
provided as follows:
• LCA 1 – Transport Corridor Landscape Character Area, which represents
vehicular roads such as Lung Mun Road Highway.
• LCA 2 – Upland & Hillside Landscape Character Area, which represents all
hillside plantation area, including roadside amenity areas along Lung Mun
Road Highway. It also contains woodlands, scrubland and fresh water body,
which represent the major character of the area.
• LCA 3 – Inshore Water Landscape Character Area, which represents seawater
body and waterfront character such as breakwaters and seashore at the south of
the River Trade Terminal.
• LCA 4 – Institutional Landscape Character Area, which represents all
government institutions and public utilities such as existing Pillar Point STW,
EMSD Tuen Mun Vehicular Servicing Station, Harbor Hydraulics Laboratory,
Physical Model Lab Sub-station, Pillar Point Fire Station and WSD Tuen Mun
West Fresh Water Service Reservoir.
• LCA 5 – Industrial Urban Landscape Character Area, which represents all
industrial zone in the reclaimed area of Ho Fuk Street and Ho Yeung Street
such as River Trade Terminal & cargo handling area.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-12 January 2008
Visual Sensitive Receivers (VSRs)
8.6.1.5 Table 8.2 and Table 8.3 indicate the Sensitivity to Change and Magnitude of the Impacts in VSRs accordingly found within the ZVI’s
for the construction phase and operational phase. For ease of reference, each VSR is given an identity number, and mapped in Figure
8.4.1 and with photographic record in Figures 8.4.2 & 8.4.3. Table 8.2 summarises the characteristics of key views as seen in the
photomontages. All impacts are adverse unless otherwise stated.
Table 8.2 Identity of key Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
Id. No. Key Visual Sensitive
Receivers (VSRs) Type of VSRs
Number of
Individuals
(Many/ Medium/
Few/ Very Few)
Quality
of
Existing
View (Good/
Fair/
Poor)
Availability
of
Alternative
Views (Yes/ No)
Amenity of
Alternative
Views
(Good/Fair/
Poor)
Degree of
Visibility
(Full/
Partial/
Glimpse)
Frequency of View (Very
Frequent/
Frequent/
Occasional/
Rare)
Sensitivity to
Change
(Low,
Medium,
High)
OU1 River Trade Terminal &
Cargo Handling Area Occupational Many Fair Yes Fair
Full Occasional Low
OU2 River Trade Golf Course Recreational Many Fair Yes Fair Glimpse Rare Medium
OU3
Planned Development in
Tuen Mun Area 38 – Eco
Park and Waste Sorting
Facilities
Occupational Medium Fair Yes
Fair
Glimpse Rare Low
GIC1
EMSD Tuen Mun Vehicle
Servicing Station, Harbour
Hydraulics Laboratory and
Physical Model Lab Sub-
station
Occupational Medium Fair Yes
Fair
Partial Rare Low
GB1 Castle Peak Recreational Few Good Yes Fair Partial Rare Low
T1 Lung Mun Road Transportation Medium Fair Yes Fair partial Frequent Low
R = Residential; C = Commercial, GIC = Government/Institution/Community, O = Open space, OU = Others use; T = Transport related
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-13 January 2008
Table 8.3 Visual Sensitive Receivers (VSRs) and Their Magnitude of Impacts
Magnitude of Impacts
(Large/ Intermediate/ Small/
Negligible Id No. Key Visual Sensitive Receiver (VSR)
Blockage
of View
(Full/
Partial/
Glimpse
Viewing
Distance
(M)
Scale of
Development
(Large/
Medium/
Small)
Compatibility
(Good/ Fair/
Poor)
Reversibility
of Change
(Yes/ No) Construction Operation
OU1 River Trade Terminal & Cargo Handling
Area Partial 10 Large Good No Intermediate Intermediate
OU2 River Trade Golf Course Glimpse 150 Medium Good No Small Small
OU3
Planned Development in Tuen Mun Area
38 – Eco Park and Waste Sorting
Facilities
Glimpse 650 Small Good No
Negligible Negligible
GIC1
EMSD Tuen Mun Vehicle Servicing
Station, Harbour Hydraulics Laboratory
and Physical Model Lab Sub-station
Glimpse 25 Large Good No
Intermediate Intermediate
GB1 Castle Peak Glimpse 25 Large Good No Intermediate Intermediate
T1 Lung Mun Road Glimpse 10 Large Good No Small Small
R = Residential; C = Commercial, GIC = Government/Institution/Community, O = Open space, OU = Others use; T = Transport related
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-14 January 2008
8.7 Landscape Impact Assessment (LIA)
Sources of Landscape and Visual Impacts 8.7.1.1 The nature and extent of the sewage plant upgrading works, works areas and the
construction methodologies are described in detail in Section 2. For easy of
reference, the extent of works at ground level, including all contractors’ temporary
works area, are shown on all the plans illustrating landscape and visual impacts in
this section.
8.7.1.2 The sources of landscape and visual impacts in the construction phase will include:-
� construction works involving the removal of existing vegetation;
� construction of site access;
� excavation works for the sedimentation tank and sludge holding tank;
� stockpiling of excavated materials;
� haulage off-site of excavated materials
� stockpiling of construction materials;
� importation and storage of construction equipment and plant;
� contractor’s temporary works areas, including site accommodation and
parking area;
� construction of above ground features such as new administration building,
laboratory, and control room; and
� night lighting;
8.7.1.3 During the operation stage, potential landscape and visual impacts would be related
to the following visible above ground structures:
� new administration building, laboratory and control room (approximately 8m
height);
� chemical storage building and chemical dosing area (approximately 8m
height);
� low lift and returns pumping station / odour control units (approximately 7m
height);
� rapid mixing tanks, flocculation tanks and sedimentation tanks (approximately
2.5m height);
� UV disinfection facilities (approximately 0.5-5m height);
� sludge holding tanks (approximately 17.5m height);
� sludge dewatering building (approximately 13.5m height);
� septic waste reception area (approximately 6m height)
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-15 January 2008
Landscape Impact Assessment
Nature and Magnitude of Landscape Change Before Mitigation in Construction
Phase
8.7.1.4 The magnitude of the impacts, before implementation of mitigation measures, on the
landscape resources and LCA that would occur in the construction phase are
described below and tabulated in Table 8.4. Only those resources and character
areas that would be impacted are listed. All impacts are adverse unless otherwise
stated.
LR6-Vegetation within existing sewage treatment plant There would be a large change to the existing Pillar Point STW due to the excavation
works of the sedimentation tanks and associated structures, and site access. There are
a total approx. 343 trees within the Pillar Point STW. The approximate location of
the existing trees and the broadbrush tree survey results (including the general
species name) are shown in Figure 8.9.2. There would be impacts on approximately
90 numbers of trees, of which all have a high to low amenity value. The locations as
well as the assessment schedule for the 90 numbers of the affected trees are shown in
Figure 8.9.3. Those affected trees have a height from 4m to 13m, trunk diameter
from 95mm to 300mm and a spread from 2 to 13. Apart from the 18 numbers of
“Leucaena leucocephala”, which are proposed to be felled in accordance with
ETWB TCW No. 3/2006, all the affected trees are capable of transplanting, although
the largest trees would suffer some loss of form and amenity value during
transplanting process.
8.7.1.5 In addition to the above impacts on landscape resources, there would be moderate
magnitude of change on LCA4 due to excavation works within the existing STW,
temporary works areas, stockpiling of excavated materials, and associated impacts
on trees as described above.
8.7.1.6 There would be negligible magnitude of impact on all the remaining landscape
character areas.
Predication of Significance of Landscape Impacts
8.7.1.7 The potential significance of the landscape impacts during the construction and
operational phases, before and after mitigation, are provided in Table 8.4. The
landscape impacts for the construction and operational phases after mitigation are
mapped in Figures 8.5.1 to 8.5.4. This assessment follows the stated methodology
and assumes that the appropriate mitigation measures identified in previous section
would be implemented, and that the full effect of the soft landscape mitigation
measures would be realised after ten years. Photomontages of the proposed
development are illustrated in Figure 8.7.1 and Figure 8.7.2.
Operational Phase Landscape Impacts
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-16 January 2008
8.7.1.8 Residual landscape impacts on landscape resources in the operation phase are
mapped in Figure 8.5.2. Residual landscape impacts on LCA in the operational
phase are mapped in Figure 8.5.4.
8.7.1.9 All residual adverse landscape impacts in the operational phase of Day 1 will be of
insubstantial significance, with the exception of the impacts on existing vegetation
within the existing Pillar Point STW (LR7), where an adverse impact of slight
significance is anticipated due to the permanent alienation of existing planting area
and approx. 90 no. trees due to the upgrading of Pillar Point STW. After all
landscape mitigation measures are implemented and have matured over 10 years,
there would be no residual adverse landscape impacts of any significance in Year 10.
8.8 Visual Impact Assessment (VIA)
8.8.1.1 The potential sources of landscape and visual impacts are described above in
Sections 8.7.1.1-8.7.1.3.
Visual Impacts at Construction Stage before Mitigation
8.8.1.2 Workers on River Trade Terminal & Cargo Handling Area (OU1), EMSD lab sub-
station (GIC1) and leisure walkers (GB1) will receive moderate impact towards to
the proposed upgrading works as they are both really closed to Project.
8.8.1.3 Golf player (OU2) and Lung Mun Road (T1) will have intermittent views to the
construction works. As roadside vegetation screening off most of the Project
boundary; therefore visual impact is slight.
8.8.1.4 Workers and visitors in Eco Park (OU3) will have fairly distant views to the
proposed works which will be frequently screened by the containers from the River
Trade Terminal and topographic changes in vary locations. Therefore visual impact
is insubstantial before mitigation.
Residual Visual Impacts at Construction Stage after Mitigation
8.8.1.5 Residual visual impacts in the construction phase are mapped in Figures 8.5.1 &
8.5.3. Adverse impacts of significance during the construction phase which would be
experienced by the VSRs are listed below. This would be primarily because of the
cut & cover excavation, stockpiling of excavated materials; temporary works sites
and works area, temporary traffic diversions, the associated removal of trees, either
by felling or transplanting, and the obstruction of views arising from boarding.
8.8.1.6 Workers on River Trade Terminal & Cargo Handling Area (OU1) will still have
moderate residual impact as most of mitigation measures implementation can not all
comprehensively instated of disturbance of views towards to the proposed upgrading
works as they are both are directly or relatively close to Project.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-17 January 2008
8.8.1.7 The residual adverse visual impacts in construction stage on OU2, GIC1, GB1 and
T1 are slight after the implementation of visual mitigation measure. As most VSRs
will have intermittent views to the Project.
8.8.1.8 OU3 will have insubstantial adverse visual impact.
Visual Impacts at Operation Stage before Mitigation
8.8.1.9 The potential significance of the visual impacts during the operate phase, before and
after mitigation, are briefly described below, provided in detail in Table 8.5, and
illustrated in Figure 8.5.6. This assessment follows the methodology outlined in
Section 8.5 and assumes that the appropriate mitigation measures identified in Table
8.7 below would be implemented.
8.8.1.10 Workers on River Trade Terminal & Cargo Handling Area (OU1), EMSD lab sub-
station (GIC1) and leisure walkers (GB1) will receive moderate impact towards to
the proposed upgrading works as they are both really closed to Project.
8.8.1.11 Golf player (OU2) and Lung Mun Road (T1) will have intermittent views to the
construction works. As roadside vegetation screening off most of the Project
boundary; therefore visual impact is slight.
8.8.1.12 Workers and visitors in Eco Park (OU3) will have fairly distant views to the
proposed works which will be frequently screened by the containers from the River
Trade Terminal and topographic changes in vary locations. Therefore visual impact
is insubstantial before mitigation.
8.8.1.13 The adverse impacts on OU3 is insubstantial.
Residual Visual Impacts at Operation Stage after Mitigation
8.8.1.14 A residual visual impact in the operational phase is mapped in Figure 8.5.6 and was
demonstrated in photomontage view Figures 8.7.1 and 8.7.2.
8.8.1.15 Day 1 after the implementation of mitigation measures during operation there would
still be some slight negative visual impact on the VSRs on OU1 which are close to
the Project. 10 years after the implementation of mitigation measures during
operation, the residual impacts on all VSRs are insubstantial. Overall, it is
considered that the residual landscape and visual impacts of the proposed
development are considered as acceptable with mitigation measures during
construction and operation phase.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-18 January 2008
Table 8.4 Significance of landscape impacts in the construction and operation phases (Note: All impacts adverse unless otherwise
noted. Only those resources or character areas that are impacted are listed in the table – resources not impacted are not
listed. )
Part 1 – Physical Landscape Resources (Topography, Vegetation, Soil, Open Space, Special Features, etc) Magnitude of Change before
Mitigation
(Negligible, Small,
Intermediate, Large)
Impact significance
Threshold Before Mitigation
(Insubstantial, Slight,
Moderate, Substantial)
Residual Impact Significance Threshold
After Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Operation
Id. No. Landscape Resources (LR)
Sensitivity
to Change
(Low,
Medium,
High) Construction Operation Construction Operation
Recommended Mitigation
Measures*
Construction DAY 1 YEAR 10
LR1 Water Body High Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR2 Stream Course (natural artificial
channel) Medium Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR3 Disturbed Hillside Plantation Medium Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR4 Scrubland / Woodland Natural
Terrain High Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR5 Roadside Planting Medium Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR6 Vegetation within Existing DSD
Sewage Treatment Works Medium Intermediate Intermediate Moderate Moderate
CM1, CM2, CM5, CM6
OM1, OM2, OM3 Moderate Slight Insubstantial
LR7 Vegetation within Industrial Area Medium Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LR8 Golf Course Low Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
* Recommendation on landscape and visual mitigation measures are described in Section 8.9.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-19 January 2008
Part 2 – Landscape Character Areas Magnitude of Change
before Mitigation
(Negligible, Small,
Intermediate, Large)
Impact significance Threshold
Before Mitigation
(Insubstantial, Slight,
Moderate, Substantial)
Residual Impact Significance Threshold
After Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Operation
Id. No. Landscape Character Area (LCA)
Sensitivity to
Change
(Low,
Medium,
High) Construction Operation Construction Operation
Recommended
Mitigation
Measures*
Construction DAY 1 YEAR 10
LCA1 Transport Corridor Landscape Character Area Medium Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LCA2 Upland & Hillside Landscape Character Area High Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LCA3 Inshore Water Landscape Character Area Low Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
LCA4 Institutional Landscape Character Area Medium Negligible Negligible Insubstantial Insubstantial
CM1, CM2,
CM5, CM6
OM1, OM2,
OM3
Moderate Slight Insubstantial
LCA5 Industrial Urban Landscape Character Area Low Negligible Negligible Insubstantial Insubstantial N/A Insubstantial Insubstantial Insubstantial
* Recommendation on landscape and visual mitigation measures are described in Section 8.9.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-20 January 2008
Table 8.5 Significance of visual impacts in the construction and operational phases (Note: All impacts adverse unless otherwise
noted. Only those VSRs that are impacted are listed in the table – VSRs not impacted are not listed.)
Magnitude of Change in
View before Mitigation
(negligible, small,
intermediate, large)
Receptor Sensitivity
(Low, medium, High)
Impact significance
threshold before
mitigation
(insubstantial, slight,
moderate, substantial)
Residual Impact Significance
Threshold after Mitigation
(insubstantial, slight, moderate,
substantial)
Operation
VSR
Type
& ID
Key Visually Sensitive Receiver
(VSR)
Construction Operation Construction Operation Construction Operation
Recommended
Mitigation
Measures*
Construction DAY 1 YEAR 10
OU1 River Trade Terminal & Cargo Handling
Area Intermediate Intermediate Low Low Moderate Moderate
CM1, CM3, CM5, CM7, OM2, OM3
Moderate Slight Insubstantial
OU2 River Trade Golf Course Small Small Medium Medium Slight Slight CM1, CM3, CM5,
CM7, OM2, OM3 Slight Insubstantial Insubstantial
OU3 Planned Development in Tuen Mun Area
38 – Eco Park and Waste Sorting Facilities Negligible Negligible Low Low Insubstantial Insubstantial
CM1, CM3, CM5,
CM7, OM2, OM3 Insubstantial Insubstantial Insubstantial
GIC1
EMSD Tuen Mun Vehicle Servicing
Station, Harbour Hydraulics Laboratory
and Physical Model Lab Sub-station
Intermediate Intermediate Low Low Moderate Moderate CM1, CM3, CM5,
CM7, OM2, OM3 Slight Insubstantial Insubstantial
GB1 Castle Peak Intermediate Intermediate Low Low Moderate Moderate CM1, CM3, CM5,
CM7, OM2, OM3 Slight Insubstantial Insubstantial
T1 Lung Mun Road Small Small Low Low Slight Slight CM1, CM3, CM5,
CM7, OM2, OM3 Slight Insubstantial Insubstantial
R = Residential; C = Commerciall, GIC = Government/Institution/Community, O = Open space, OU = Others use; T = Transport related * Recommendation on landscape and visual mitigation measures are described in Section 8.9.
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-21 January 2008
8.9 Recommendation on Landscape and Visual Mitigation Measures
8.9.1.1 The proposed landscape and Visual mitigation measures in the construction and
operational phases are listed in Table 8.6 and Table 8.7 below, together with an
indication of Funding, Implementation, and Management and Maintenance agencies.
Table 8.6 Proposed Landscape and Visual Mitigation Measures in Construction
Phase
ID No. Nature / Type Landscape and Visual Mitigation Measure Implementation
Agent
Management
/
Maintenance
CM1 Design /
construction
Planning
Temporary Tree Nurseries
Temporary tree nurseries may be set up for the transplanted tree
and proposed trees at an early stage to allow small trees to grow
during the construction periods. By the time when planting area
becomes available, trees mature and increase in trunk & spread
size. They will require minimal pruning and suffer much less
damage during transplanting when comparing the travel distance
from an on-site nursery to an off-site nursery.
Besides, these trees may also be positioned as visual mitigation
during the construction period.
Potential site and locations should sought agreement with
relevant department in advance and avoid doubling
transplantation procedure.
Contractor Contractor
CM2 Design /
construction
Planning
No-intrusion Zone
To maximize protection to existing trees and ground vegetation,
construction contracts may designate “No-intrusion Zone” to
various areas within the site boundary with rigid and durable
fencing for each individual no-intrusion zone. The contractor
should close monitor and restrict the site working staff not to
enter the “no-intrusion zone”, even for non-direct construction
activities and storage of equipment.
Contractor Contractor
CM3 Design /
construction
Planning
Hoarding
Hoarding or boundary fencing for construction shall be
considered. It should be sensitively designed, subtle,
camouflaged and more ‘permeable’ so that they fit into the
existing environment when looking from outside.
Contractor Contractor
CM5 Site Practice Dust and Erosion Control for Exposed Soil
Excavation works and demolition of existing building blocks and
which will be highly visible form surrounding areas should be
well planned and with precautions to suppress dust. Exposed soil
shall be covered or ‘camouflaged’ and watered often. Areas that
are expected to be left with bare soil for a long period of time
after excavation shall be properly covered with suitable
protective fabric. Silt and erosion shall be controlled by ground
barriers around the slope cutting area.
Contractor Contractor
CM6 Site
Supervision
Existing Tree Record Inventory
All retained trees should be record photographically at the
commencement of the Contract, and carefully protected during
the construction period. Detailed tree protection specification
shall be allowed and included in the Contract Specification,
which specifying the tree protection requirement, submission
and approval system, and the tree monitoring system.
Contractor Contractor
CM7 Site Practice Construction Light
All security floodlights for construction sites shall be equipped
with adjustable shield, frosted diffusers and reflective covers,
and be carefully controlled to minimize light pollution and night-
time glare to nearby residences and GIC users. The Contractor
shall consider other security measures which shall minimize the
visual impacts.
Contractor Contractor
CM8 Design / Tree Transplanting Contractor Contractor
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-22 January 2008
ID No. Nature / Type Landscape and Visual Mitigation Measure Implementation
Agent
Management
/
Maintenance
construction
Planning
Apart from the 18 numbers of “Leucaena leucocephala”, which
are proposed to be felled in accordance with ETWB TCW No.
3/2006, all the affected trees shall be transplanted. Where
practicable, trees shall be directly transplanted to permanent on-
site locations. The location of the transplanted tree is shown in
Figure 8.9.1.
CM9 Design /
construction
Planning
Tree Compensation Ratio
The total number of compensatory trees planted in the project
area shall not be less than 1:1 ratios by new trees. Required
numbers and locations of compensatory trees shall be
determined and agreed with Government during the tree felling
application process under ETWCTC 3/2006.
Compensatory trees shall be at least heavy standard size to create
“immediate” greening effect.
81 numbers of “Cassia surattensis” will be provided as the
additional compensatory planting for loss of greenery in the area
due to removal of the affected trees. The location of the
additional compensatory planting is shown in Figure 8.9.1.
Contractor Contractor
CM10 Design /
construction
Planning
Re-use of Existing Soil and Advance formation of Planting Area
Existing topsoil shall be re-used where possible for new planting
areas within the project. Advance formation of planting area and
early implementation of the plating works can minimize adverse
impact on trees. The construction program shall consider using
the soil removed from one phase for backfilling another. Suitable
storage ground, gathering ground and mixing ground may be set
up on-site as necessary.
Contractor Contractor
Table 8.7 Proposed Landscape and Visual Mitigation Measures in Operation Phase ID No. Nature / Type Landscape and Visual Mitigation Measure Implementation
Agent
Management
/
Maintenance
OM1 Site
Supervisions
Establishment Period
12 month establishment period for the soft landscape works
will be allowed in the main contract. Most construction
contracts in Hong Kong require the Contractor to carry out
routine horticultural operations, including watering, pruning,
weeding, pest control, replacement of dead plants etc. to
ensure healthy establishment of new planting during a 12
month establishment period. This period also serves as a kind
of warranty / guarantee on the quality of the plants supplied
and installed by the Contractor. Monthly monitoring during
the first year of establishment period is recommended.
PPSTW
Operator
PPSTW
Operator
OM2 Design /
construction
Planning
Re-instatement of excavated Area
All excavated area and disturbed area for utilities diversion,
temporary road diversion, and pipeline woks will be
reinstated to former conditions, subject to applicable
Government Standards.
PPSTW
Operator
PPSTW
Operator
OM3 Design /
construction
Planning
Appearance and Greening for the proposed structures
Compatible design, construction materials and surface
finishes of the proposed structure should match with the
nearby existing external appearance of PPSTW buildings for
achieving visual uniformity. Finishing materials shall have
due consideration to form, basic color, color/tone variation,
micro- and macro-texture, and reflectivity/light absorbance to
avoid glare. Planting, such as turf, low groundcovers and
climbers, may also be planted on top of these elements to
provide greening and aesthetic effect.
PPSTW
Operator
PPSTW
Operator
Agreement No. CE 51/2002 (DS)
Upgrading of Pillar Point STW
- Investigation, Design and Construction Final EIA Report
Metcalf & Eddy Ltd. Page 8-23 January 2008
8.10 Conclusions
Summary of Predicated Residual Landscape and Visual Impacts in the
Construction Phase
8.10.1.1 Residual landscape impacts in the construction phase are listed in Table 8.4 and
mapped in Figures 8.5.1 and 8.5.3. Residual visual impacts in construction phase are
listed in Table 8.5 and mapped in Figure 8.5.5.
8.10.1.2 There are a total approx. 343 trees within the Pillar Point STW, the approximate
location of the existing trees and the broadbrush tree survey results (including the
general species name) are shown in Figure 8.9.2. Of these, 253 trees are proposed to
be retained, 90 trees will be affected. The species of all the affected trees are listed
in Figure 8.9.3 and none of them are classified as the Old and Valuable (OVT) trees.
Apart from the 18 numbers of “Leucaena leucocephala”, all the affected trees are
proposed to be transplanted. The 18 numbers of “Leucaena leucocephala” are
proposed to be felled in accordance with ETWB TCW No. 3/2006. There will be
mitigation through the transplanting of some existing trees and the planting of new
stock. Moreover, 81 numbers of “Cassia surattensis” will be provided as the
additional compensatory planting for loss of greenery in the area due to removal of
the affected trees. Locations of the transplanted trees (total 72 numbers) and
additional compensatory planting (total 81 numbers) are shown in Figure 8.9.1.
8.10.1.3 There is expected to be moderate impacts on the existing institutional areas (LCA4)
during construction to the landscape character of the Government utilities area.
8.10.1.4 Workers on River Trade Terminal & Cargo Handling Area (OU1) would have
moderate adverse visual impact during construction phase. Impact would be lessen
as slight in operational stage when landscape and visual mitigation measures are
fully implemented. The visual impact would be insubstantial significance as most of
the tree planting would provide proper screening effect in maturity of 10 years.
Summary of Predicated Residual Landscape and Visual Impacts in the
Operational Phase
8.10.1.5 Day 1 after the implementation of mitigation measures during operation there would
still be some slight negative visual impact on the VSRs close to the Project on OU1.
10 years after the implementation of mitigation measures during operation, the
residual impacts on all VSRs are insubstantial.
8.10.1.6 After the proposed mitigation measures have been implemented and the proposed
tree planting has matured over 10 years, all residual adverse landscape and visual
impacts in operational phase will be of insubstantial significance.