FP6 Informativno tijelo za BiH (National Information Point for FP6 BiH)
8 April 2003 Annex III of the model contract Networks of Excellence Training session for FP6...
-
Upload
alyssa-brady -
Category
Documents
-
view
212 -
download
0
Transcript of 8 April 2003 Annex III of the model contract Networks of Excellence Training session for FP6...
8 April 2003
Annex III of the model
contract
Networks of ExcellenceTraining session for FP6 National Contact Points,
Brussels, 8 April 2003Colette Renier, RTD-B2
2
The determination of the grant for integration
Various elements
number of researchers
number of doctoral students
converting table
specificity of the research field
3
The number of researchers
In the proposal, indication by the participants of the number of researchers who:
have their PhD or 4 years experience in research
make part of the participants’ research capacities in the topic of the network
are employee of one of the participants or
work under one participant’s management authority in the frame of a formal agreement between this participant and their normal employer
8 April 2003
The number of doctoral students
In the proposal, indication of the number of doctoral students who:
are enrolled in a recognised course run by one of the participants
have less than 4 years experience
are involved in the network’s research activities
researchers and doctoral students are auditable at the time of the call’s deadline
8 April 2003
The converting table
50 researchers € 1 million/year
100 researchers € 2 million/year
150 researchers € 3 million/year
250 researchers € 4 million/year
500 researchers € 5 million/year
1000 researchers and + € 6 million/year
Doctoral students
€ 4,000/year/head within the limits of 10 % of the result
of the application of the converting table
8 April 2003
Calculation of the grant
Number of researchers
X amount per head (converting table or less if requested by participants)
X number of years
----------------------------
subtotal 1
+Number of doctoral students
X € 4,000
X number of years
----------------------------
subtotal 2 (maximum 10 % of subtotal 1)
7
Payment of the grant for integration
Rhythmas negotiated between Commission and
participantsspecified in Annex I of the contract
Conditions satisfactory results of the annual review and demonstration of no-profit through the grant:
eligible costs incurred for implementing the JPA at least = EC contribution
at the end of the period: costs incurred for JPA > EC contribution
8
Competitive calls
When? as defined in Annex I of the contract
How? Publicity : journals (1 international, 3
national), Internet, specialist press, NCPs
According to instructions and guidance by the Commission
Information of the Commission (call + content) at least 90 days before publication
9
Selection of new
partnersHow? On basis of the evaluation criteria applied for
the project by the Commission With the assistance of at least 2 external
independent experts
Notification to the Commissionproposed new partner(s)means of publicationnames and affiliations of experts
Commission reactionmay object within six weeks of the receipt
10
Updating the joint programme of activities (1)
Which update?
The detailed joint programme of activities for the next 18 months period and/or
The outline joint programme of activities for the whole remaining period
Commission reaction
evaluation, if appropriate with the assistance of external experts
no comment within 90 days = approval
11
Updating the joint programme of activities (2)
Possible casesunconditional approval (i.e. absence of
Commission reaction within 90 days) continuation
“conditional” rejection completion of the work, additional work re-submission of the reports/deliverables
“conditional” approvalre-negotiation of the work to be performed during the next period (possible suspension)
unconditional rejection termination of the contract
12
Annual review
When?After having received the reports and the
proposed JPA update
What is assessed?Progress of the networkProspects for achieving the overall objectives
(durable integration)
Which follow up?Results and possible Commission
recommendations communicated to the consortium
if necessary submission of a revised JPA
13
Failure of the annual review
Exampleno satisfactory progress towards durable
integration
Follow up
Two options: termination of the contract by the
Commission (red flag) the consortium is offered the choice(yellow
flag)
termination continuation
14
Continuation after failure of the annual review
Consequence
continuation of the action but without any contribution from the Commission
Follow up
arrangement of a review at the end of the year:
if successful: payment of the contribution for both previous periodsif failure: termination of the contract