The role of this appendix is to provide a somewhat more formalized
methodology for the calculation offlexible budget variances.
FLEXIBLE BUDGET EXPENSE VARIANCES
The first step in flexible budgeting is to establish the flexible budget for
the actual output level. That is, we must determine what we would have
expected to spend if we had known in advance the output level that
would actually occur. Because of variable costs, we would have
budgeted more resources if we knew service levels would be higher andless resources if we knew they were going to be lower. For example,
consider an excerpt from the variance report for the Millbridge High
School for August.23
Town of Millbridge High School August Variance Report
Actual
Budget
Variance
Books
$120,000
$100,000
$20,000 U
The actual spending was $120,000. The budgeted cost was $100,000.
Suppose that the budget assumed that there would be 2,000 students,
but 2,100 students enrolled. Assuming that the purchase of textbooks
would be expected to vary in direct proportion with enrolled students,
-
7/21/2019 78588E Appendix 8A
2/13
the budget called for planned spending of $50 per student (i.e., $50
2,000 students = $100,000).
For 2,100 students at $50 per student, $105,000 would have been
budgeted for supplies. This is the flexible budget. It is the amount the
school would have expected to spend had the actual number of students
been known. The original budget was $100,000. The flexible budget,
which adjusts for the actual volume, is $105,000. The actual amount
spent was $120,000:
The difference between the original budget and the actual amount spent
is the total variance. This is still $20,000 unfavorable. The $5,000
-
7/21/2019 78588E Appendix 8A
3/13
difference between the original budget and the flexible budget is the
volume variance. This volume variance is unfavorable because the
flexible budget requires more spending than was expected in the
original budget. The increased number of students may be considered to
be good or bad, depending on the attitudes of the people in the town.Regardless, from a variance reporting standpoint, the convention is to
consider increased spending to be unfavorable. Managers should guard
themselves from assuming that unfavorable variances are always bad
events.
The difference between the flexible budget and the actual amount spent
is referred to as the flexible budget variance. It simply represents all
other causes, aside from the volume variance. In this case the flexible
budget variance is $15,000. It is unfavorable, since actual spending was
$15,000 more than the flexible budget, which is the expected spending
for the actual number of students enrolled. If the flexible budget
variance and volume variance are combined, we get the total variance
for the line-item. Note that if one of these variances was favorable and
the other was unfavorable, they would offset each other, like positive
and negative numbers.
23Note that in preparation for the new school year, Millbridge orders most of its
books during August of each year. There are many other lines in the variance
report, but we will focus on just the line-item for textbooks.
FLEXIBLE BUDGET NOTATION
At this point in the analysis, we do not know much about the flexible
budget variance. It is a combination of the price and quantity variance.
We need to be able to calculate each of these two variances. To do this
we will introduce some notation. The letterAis used to refer to an
actual amount. The letterBis used to refer to a budgeted amount. The
letter Pstands for a price or rate, and the letter Qstands for a quantity.The letter iis used to stand for an input and the letter oto stand for an
output or workload.Inputsare resources consumed. These can be labor
hours, or units of supplies, or any other resource the organization pays
for. Outputsare a measure of the volume of goods or service being
produced. These can be the number of students or the number of meals
-
7/21/2019 78588E Appendix 8A
4/13
or the number of patients.
The notation is combined to form six key variables. Pistands for the
price of the input, such as $20 per textbook. Qostands for the total
quantity of output, such as the number of students.Qi
stands for thequantity of input needed to produce one unit of output. For example, we
might expect that each year the school will buy, on average, 2.5
textbooks per pupil. The letterBin front of other letters indicates a
budgeted amount. The letterAin front of other letters indicates an
actual result. The definitions of the notation can be formalized as
follows:
BPi:
budgeted price per unit of input
BQi:
budgeted quantity of input for each unit of output
BQo:
budgeted quantity of output
APi:
actual price paid per unit of input
AQi:
actual quantity of input for each unit of output produced
AQo:
actual quantity of output
Suppose that for the Town of Millbridge High School, these six items
had the following values:
BPi:
-
7/21/2019 78588E Appendix 8A
5/13
$20 per textbook
BQi:
2.5 textbooks per student
BQo:
2,000 students
APi:
$22 per textbook
AQi:
2.5974 textbooks per student
AQo:
2,100 students
To calculate the price, quantity, and volume variances, it is necessary to
get these six pieces of information. The three budgeted items are
generally available from the data that were used in making the originalbudget. The three actual pieces of information should be available in
most organizations. School systems will know the actual number of
students, the AQo. Also, if you buy books, you should have a record of
how many books were purchased and how much was paid for them.
The actual price paid for each book is not needed. If we know how
many books we purchased and how much we paid in total for books, we
can divide the total cost for books by the number of books to find the
average price paid per book, the APi. Similarly, we do not need to
know how many books we acquired for each student. If we know how
many books we actually purchased and how many students we actually
had, we can divide to find the actual number of books purchased per
student, on average, the AQi.
The first step in these data is to calculate the original budget in terms of
-
7/21/2019 78588E Appendix 8A
6/13
the notation. The original budget is simply the expected number of new
books per student, multiplied by the expected cost per book, multiplied
by the expected number of students. Using our notation, this can be
shown as follows:
Original Budget
BQi BPi BQo
2.5 $20 2,000
$100,000
That is, BQi, the budgeted quantity of input per unit of output, is 2.5
new books per student; BPi, the budgeted price per book is $20; andBQo, the budgeted quantity of students, is 2,000. The total budgeted
amount for textbooks is $100,000.
The next step is to find the flexible budget. Recall that the flexible
budget is the amount that one would have expected to spend if the
actual number of enrolled students had been known in advance.
Therefore, leave the BQi at the budgeted 2.5 books per student, and
leave the BPi at the budgeted $20 per book. The only change is from a
BQo of 2,000 students to a new AQo of 2,100 students. The flexiblebudget can be calculated as follows:
Flexible Budget
BQi BPi AQo
2.5 $20 2,100
$105,000
The difference between the original budget and the flexible budget is
caused by a difference in the number of students. Other than that, the
calculations are the same. The originally budgeted amount of $100,000
can be compared with the flexible budget amount of $105,000 to
determine the volume variance of $5,000 U. Since the number of
students is higher than expected, cost will be higher than expected. This
-
7/21/2019 78588E Appendix 8A
7/13
will give rise to an unfavorable variance. The comparison between the
original budget and the flexible budget can be shown as follows:
We can also calculate the flexible budget variance that we found earlier,
by comparing the flexible budget to the actual spending. The actual
amount spent is simply the product of the number of books purchased
per student, the cost per book, and the number of students, as follows:
Actual
AQi APi AQo
2.5974 $22 2,100
$120,000
Note that to calculate the actual cost, the actual number of books per
student, the actual price per book, and the actual number of students isused. Also note that the actual number of books per student is based on
the actual number of books acquired in total, divided by the actual
number of students. The difference between the flexible budget and the
actual amount spent was earlier described as the flexible budget
variance:
-
7/21/2019 78588E Appendix 8A
8/13
The volume variance and the flexible budget variance add up to the
total variance for the line-item, as shown earlier. Using our notation,
that would appear as follows:
To this point, we have the same information as we had before we
started using notation. Now, however, we can go further by determining
the price and quantity variances. In order to determine these variances,
-
7/21/2019 78588E Appendix 8A
9/13
it is necessary to derive a subcategory. This subcategory is simply a
device to allow for separation of the flexible budget variance into two
pieces: the price variance and the quantity variance. The subcategory is
defined as the actual quantity of input per unit of output, multiplied by
the budgeted price of the input, times the actual output level. In terms ofthe notation, the subcategory can be calculated as follows:
Subcategory
AQi BPi AQo
2.5974 $20 2,100
$109,091
If the subcategory calculation is compared with the actual costs, the
price variance can be determined as follows:
Note that the actual and subcategory calculations both use the AQi and
the AQo. The only difference between the two calculations is that theactual uses the APi whereas the subcategory uses the BPi. Since the
price is the only element that differs, it must be responsible for the
$10,909 difference between the two calculations. This $10,909 variance
is because books cost $22 on average, instead of $20 as expected.
To determine the quantity variance, it is only necessary to compare the
-
7/21/2019 78588E Appendix 8A
10/13
subcategory with the flexible budget:
In comparing the subcategory and the flexible budget calculations, we
note that both use the BPi and the AQo. However, the subcategory uses
AQi, whereas the flexible budget uses BQi. So, the $4,091 difference
that is observed is the result of the fact that the number of books
purchased per pupil, on average, differed from the expected number.
Thus, we have a quantity difference. Note that this quantity difference
has nothing to do with the number of students but rather with the
number of books per student.24
Reviewing the price and quantity variances, we can look at how they
together comprise the flexible budget variance:
-
7/21/2019 78588E Appendix 8A
11/13
Notice that adding the price variance of $10,909 U and the quantity
variance of $4,091 U results in the flexible budget variance. Recall that
the flexible budget variance and the volume variance add up to the total
variance. Figure 8-A-1shows that the three individual variances
price, quantity, and volumeadd up to the total variance for the line-
item.
FIGURE 8-A-1 Flexible Budget Variance
Analysis Model
-
7/21/2019 78588E Appendix 8A
12/13
24
In this example we have constructed a subcategory that uses the actual quantity ofinputs per unit of output and the budgeted price of inputs. This is an arbitrary
convention. We could have instead used the budgeted quantity of inputs per unit of
output and the actual price of inputs. We would still generate a price and quantity
variance if this switch was made. However, there is an interaction effect of price
and quantity, and the answers may vary slightly if the alternative approach is used.
Recall that without flexible budget variance analysis, the total variance
for the line-item would be the only piece of information available for
analysis. There was an unfavorable variance of $20,000. Without
additional information, this variance might be attributed to the increasein the number of students. Using Figure 8-A-1, it is possible to
determine that of this total variance, $5,000 was caused by the increase
in the number of students. However, $4,091 was caused by an increase
in the number of books per student, and $10,909 was caused by either
an increase in book prices or perhaps a movement to acquiring
different, more expensive books than had been planned. We would
certainly want to investigate both the quantity and price variances to
determine more specifically why they occurred and whether any
remedial action is necessary to avoid cost overruns in the future.
In considering Figure 8-A-1, note that this calculation would need to be
done for each line-item for each department. Although that might seem
to be a large task in large organizations, it is readily converted to a
simple computer spreadsheet program. Thus, the major effort required
to calculate price, quantity, and volume variances is to input into the
-
7/21/2019 78588E Appendix 8A
13/13
computer the six basic pieces of information needed for each line-item
(i.e., BQi, BPi, BQo, AQi, APi, and AQo).
It is also important to realize that the price, quantity, and volume
variances are merely components of the total variance for any line-item.
In Figure 8-A-1, the total variance is $20,000. Note that if we compare
the actual amount spent, $120,000, with the original budget of $100,000
in that figure, the difference is the $20,000 total variance. As we try to
understand why that total amount was incurred, the variance has been
divided into components. Note that the price variance of $10,909, plus
the quantity variance of $4,091 plus the volume variance of $5,000 add
up to the total variance.
It sometimes is not obvious whether a variance is favorable or
unfavorable. Looking at Figure 8-A-1, an easy rule of thumb is that as
one moves from the right side toward the left. larger numbers on the left
indicate unfavorable variances. If the flexible budget amount is larger
than the originally budgeted amount, the volume variance is
unfavorable. If the subcategory is greater than the flexible budget, the
quantity variance is unfavorable. This is true because as one moves
from the original budget toward the left, movement is toward the actual
result. If the actual result is larger than the original budget, then more
was spent than budgeted. Such higher spending indicates an
unfavorable variance.
(Financial Management for Public, Health, and Not-for-Profit
Organizations, 3rd Edition. Pearson Learning Solutions 14).