© BIS 2006 B U R E A U O F I N D I A N S T A N D A R D S MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG NEW DELHI 110002 IS : 7272 (Part I) - 1974 (Reaffirmed 2005) Edition 1.1 (1979-02) Price Group 3 Indian Standard RECOMMENDATION FOR LABOUR OUTPUT CONSTANTS FOR BUILDING WORK PART I NORTH ZONE (Incorporating Amendment No. 1) UDC 69.008 : 331.024 (545)

description

analysis

Transcript of 7272_1

  • BIS 2006

    B U R E A U O F I N D I A N S T A N D A R D SMANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG

    NEW DELHI 110002

    IS : 7272 (Part I) - 1974(Reaffirmed 2005)

    Edition 1.1(1979-02)

    Price Group 3

    Indian StandardRECOMMENDATION FOR LABOUR OUTPUT

    CONSTANTS FOR BUILDING WORK

    PART I NORTH ZONE

    (Incorporating Amendment No. 1)

    UDC 69.008 : 331.024 (545)

  • IS : 7272 (Part I) - 1974

    BIS 2006

    BUREAU OF INDIAN STANDARDS

    This publication is protected under the Indian Copyright Act (XIV of 1957) andreproduction in whole or in part by any means except with written permission of thepublisher shall be deemed to be an infringement of copyright under the said Act.

    Indian StandardRECOMMENDATION FOR LABOUR OUTPUT

    CONSTANTS FOR BUILDING WORKPART I NORTH ZONE

    Planning and Organization at Site Sectional Committee, BDC 29

    Chairman RepresentingSHRI O. MUTHACHEN Central Public Works Department, New Delhi

    MembersSHRI D. N. CHOPRA Institution of Engineers (India), CalcuttaSHRI M. N. DASTUR M. N. Dastur & Co (P) Ltd, CalcuttaSHRI P. P. DHARWADHKAR National Buildings Construction Corporation Ltd,

    New DelhiDIRECTOR GENERAL Directorate General of Factory Advice Service and

    Labour Institute, BombayEXECUTIVE DIRECTOR National Productivity Council, New DelhiSHRI HARCHARAN SINGH DUGAL Uttam Singh Dugal & Co Pvt Ltd, New Delhi

    SHRI S. G. ATHAVALE ( Alternate )SHRI I. C. GUPTA Punjab PWD (B & R), ChandigarhJOINT DIRECTOR (CIV ENGG) Ministry of Railways (Railway Board)SHRI K. M. KANTAWALA Gujarat PWD (B & R), Ahmedabad

    SHRI M. D. PATEL ( Alternate )SHRI J. S. KOHLI Institution of Work Study, New DelhiSHRI G. C. MATHUR National Buildings Organization, New Delhi

    SHRI V. G. HEGDE ( Alternate )SHRI A. S. PATIL Indian Institute of Architects, BombayMANAGING DIRECTOR Oriental Building & Furnishing Co (P) Ltd, New

    DelhiSHRI T. S. MURTHY National Projects Construction Corporation Ltd, New

    DelhiSHRI K. N. TANEJA ( Alternate )

    SHRI B. K. PANTHAKY Hindustan Construction Co Ltd, BombaySHRI N. T. PATEL N. T. Patel & Co, Madras

    SHRI S. N. PATEL( Alternate )SHRI Y. G. PATEL Builders Association of India, BombaySHRI K. G. SALVI Hindustan Housing Factory, New Delhi

    SHRI G. K. MEHTA ( Alternate )SHRI J. S. SHARMA Central Building Research Institute (CSIR), Roorkee

    SHRI S. P. SINGH ( Alternate )SHRI M. B. SILGARDO Hindustan Steel Ltd, Ranchi

    SHRI R. G. JOG ( Alternate )

    ( Continued on page 2 )

  • IS : 7272 (Part I) - 1974

    2

    ( Continued from page 1 )

    Members RepresentingSHRI S. R. SIVASWAMY Gammon India Limited, BombayBRIG H. S. SOBTI Engineer-in-Chiefs Branch, Army Headquarters

    BRIG B. L. KAPOOR ( Alternate )SUPERINTENDING SURVEYOR OF

    WORKS IICentral Public Works Department

    SHRI D. AJITHA SIMHA, Director General, ISI ( Ex-officio Member )Director (Civ Engg)

    Secretary

    SHRI S. P. MAGGU

    Assistant Director (Civ Engg), ISI

    Output Standards for Building Industry Subcommittee, BDC 29 : 4Convener

    SHRI H. C. RAMANNA In personal capacity ( 21, XI Main Road Malleswaram,Bangalore 3 )

    MembersSHRI B. V. APTE Builders Association of India, Bombay

    SHRI K. K. MADHOK ( Alternate )SHRI D. R. BAHL Institution of Surveyor, New DelhiSHRI P. P. DHARWADAKAR National Buildings Construction Corporation, New

    DelhiSHRI MUNISH GUPTA MES Builders Association of India, Delhi

    SHRI T. C. GOYALA ( Alternate )SHRI S. K. KOGEKAR National Buildings Organizations, New Delhi

    SHRI M. R. RAO ( Alternate )SHRI O. P. KUMAR, SSW Engineer-in-Chiefs Branch (Ministry of Defence)

    SHRI R. S. MURTHY, SSW ( Alternate )SHRI T. R. MEHANDRU The Association of Consulting Engineers (India), New

    DelhiSHRI S. RAMACHANDRAN National Projects Construction Corporation Ltd, New

    DelhiSHRI S. K. MOORTHY ( Alternate )

    SHRI T. S. NARAYANA RAO In personal capacity ( 93, Aruna East Road,Basavangudi, Bangalore 14 )

    SHRI K. G. SALVI Delhi Productivity Council, New DelhiSHRI J. S. SHARMA Central Building Research Institute (CSIR), Roorkee

    SHRI S. P. SINGH ( Alternate )SURVEYOR OF WORKS I (NDZ) Central Public Works Department

  • IS : 7272 (Part I) - 1974

    3

    Indian StandardRECOMMENDATION FOR LABOUR OUTPUT

    CONSTANTS FOR BUILDING WORKPART I NORTH ZONE

    0. F O R E W O R D0.1 This Indian Standard (Part I) was adopted by the IndianStandards Institution on 15 March 1974, after the draft finalized bythe Planning and Organization at Site Sectional Committee had beenapproved by the Civil Engineering Division Council.0.2 Schedule of rates form the basis for preparing the detailed estimatesfor works. These are also very useful in considering the reasonableness ofthe tenders received from the contractors and for pricing the alterations,additions, omission and substitutions in a contract. It is, therefore,necessary that the schedule of rates should be prepared correctly and bebased on rationally stipulated material and labour constants.0.3 At present different departments at a place are having their ownschedule of rates. A comparison of the labour and material constantsused for different items of work in these schedules of rates hasindicated that there is a good variation in them and due to whichdifferent rates exist in various departments for the same items of workin the same locality. This standard is being issued in order torationalize the labour output constants for different building works.0.4 The labour constants have been arrived at by the Central BuildingResearch Institute, Roorkee by taking actual observations, using workmeasurement techniques, on the construction sites at Delhi and Roorkee.Different types of building works up to 10 m height of CPWD, MES andother organizations were included where the workers from neighbouringstates were working. Sufficient number of observations to ensure aconfidence limit of 95 percent and an accuracy of 5 percent were taken.The relaxation allowance for the time required for rest to overcomephysical fatigue and working condition allowance has been taken as perthe standardized values given for Indian conditions by the Ministry ofLabour, Employment and Rehabilitation, Government of India. Otherallowances, such as organizations, incidental holdups, ineffective timearising out of preparatory work and additional weightage for small sizeworks have been arrived at by the activity sampling studies and mutualagreement at the committee meetings by the members representing theconstruction departments and the builders association.

  • IS : 7272 (Part I) - 1974

    4

    0.5 This edition 1.1 incorporates Amendment No. 1 (February 1979).Side bar indicates modification of the text as the result ofincorporation of the amendment.0.6 For the purpose of deciding whether a particular requirement ofthis standard is complied with, the final value, observed or calculated,expressing the result of a test or analysis, shall be rounded off inaccordance with IS : 2-1960*. The number of significant placesretained in the rounded off value should be the same as that of thespecified value in this standard.

    1. SCOPE

    1.1 This standard (Part I) covers the recommended labour outputconstants for general items of building work for north zone whichcomprises of the following areas:

    Punjab, Haryana, Delhi, Uttar Pradesh and Rajasthan.1.1.1 The labour constants for other zones would be covered separatelyin other parts of the standard.

    2. LABOUR OUTPUT CONSTANTS2.1 The recommended labour output constants for general items ofbuilding work are given in Table 1.

    *Rules for rounding off numerical values ( revised ).

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDED CONSTANT IN DAYS (8 WORKING HOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)

    i) Excavation and Earth Worksa) Excavation over areas (Hard/

    dense soil), depth up to 1.5 mand removal (up to one metrefrom edge)

    m3 Mate Mazdoor

    0.060.62

    b) Excavation in trenches (Soft/loose soil) for foundations notexceeding 1.5 m in width andfor shafts, wells, cesspits andthe like, not exceeding 10 m2

    on plan, depth up to 1.5 mand removal (up to one metreaway from edge)

    m3 Mate Mazdoor

    0.050.50

    ( Continued )

  • IS : 7272 (Part I) - 1974

    5

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)c) Extra over item (a) for an addi-

    tional depth of 1.5 m to 3 mm3 Mate

    Mazdoor0.010.11

    d) Extra over item (b) for an addi-tional depth of 1.5 m to 3 m

    m3 MateMazdoor

    0.010.08

    e) Extra over items (a) and (b) forevery additional lead of 25 mbeyond one metre up to 250 mand deposit to a level of 1.5 m

    m3 MateMazdoor

    0.010.12

    f) Returning, filling andramming of excavated earth inlayers not exceeding 20 cm indepth, watering, well rammingand levelling lead up to 25 m

    m3 MateMazdoorBhisti

    0.020.220.02

    ii) Concretea) Mixing by hand at banker, ce-

    ment concrete (with 40 mmgraded coarse aggregate)

    m3 MazdoorBhisti

    1.00.1

    Lead of con-crete mix fromthe place ofmix to place ofdeposit ofconcrete isassumed up to30 metreswhere noto t h e r w i s ementioned

    b) Mixing by hand at banker,lime concrete (with 40 mmgraded brick ballast)

    m3 MazdoorBhistiBullock withdriver

    1.60.200.15

    c) Mixing by machine (mixer)at banker, cement concrete(with 20 mm graded coarseaggregate)

    m3 MazdoorBhistiMixer operatorMixer

    0.500.100.070.07

    d) Unreinforced concrete infoundations including mixing,pouring, consolidating andcuring for depths up to 3 m(with 40 mm and below coarseaggregate)1) Hand m i x e d cement

    concretem3 Mason

    MazdoorBhisti

    0.102.130.70

    ( Continued )

  • IS : 7272 (Part I) - 1974

    6

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)2) Mixer mixed cement

    concretem3 Mason

    MazdoorBhistiMixer operatorMixerVibrator

    0.101.630.700.070.070.07

    2) Hand mixed lime concrete m3 MasonMazdoorBhistiBullock withdriver

    0.102.650.800.15

    e) Unreinforced concrete underfloors including mixing,pouring, consolidating andcuring for depths up to 3 m(with 40 mm and below coarseaggregate)1) Hand m i x e d cement

    concretem3 Mason

    MazdoorBhisti

    0.172.330.80

    2) Mixer m i x e d cementconcrete

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.171.830.800.070.070.07

    3) Hand mixed lime concrete m3 MasonMazdoorBhistiBullock withdriver

    0.172.850.800.15

    f) Reinforced cement concretein situ in foundations,footings, bases for columns,etc excluding form work andreinforcement

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.172.000.900.070.070.07

    The constantsfor items (f) to(m) includemixing, pour-ing, consoli-dating andcuring. Thisdoes not in-clude fairfinish( Continued )

  • IS : 7272 (Part I) - 1974

    7

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)g) Reinforced cement concrete in

    situ in suspended floors/roofsexcluding from w o r k, andreinforcement

    m3 Mason Mazdoor BhistiMixer operator MixerVibrator

    0.242.500.900.070.070.07

    h) Reinforced cement concrete insitu in CHAJJAS up to 15 cmin thickness excluding formwork and reinforcement

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.303.500.900.100.100.10

    j) Reinforced cement concrete insitu in beams excluding formwork and reinforcement

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.203.000.900.070.070.07

    k) Reinforced cement concrete in

    situ in columns, pillars inground floor excluding formwork and reinforcement

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.233.500.900.100.100.10

    m) Reinforced cement concrete in

    situ in stairs excluding formwork and reinforcement

    m3 MasonMazdoorBhistiMixer operatorMixerVibrator

    0.304.300.900.070.070.07

    iii) Mortars

    a) Mixing by hand, cementmortar of any mix/proportions

    m3 MazdoorBhisti

    0.750.07

    Labour re-quired will beapproximatelys a m e fordifferent mixproportions

    ( Continued )

  • IS : 7272 (Part I) - 1974

    8

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)

    b) Mixing by hand, cement-limemortar:

    Cement: Lime: Sand of anyproportions

    m3 MazdoorBhistiBullock withdriver

    1.330.100.33

    iv) Brick work (Straight Walls)

    a) Brick work in walls exceedingone brick thick, in cement/lime mortar

    m3 Mason Mazdoor Bhisti

    0.941.800.20

    i) The con-stants in-clude la-bour in-volved inscaffolding

    b) Brick work in walls, one brickthick, in cement/lime mortar

    m2 Mason Mazdoor Bhisti

    0.250.400.10

    ii) The cons-tants couldbe adoptedfor brickwork withany mix ormortar

    c) Half brick walls (with or with-out hoop iron reinforcement)in cement mortar

    m2 Mason Mazdoor Bhisti

    0.120.200.07

    iii) L a b o u rfor mix-ing mor-tar will beextra

    d) Tile work in super-structurein cement mortar

    m3 Mason Mazdoor Bhisti

    1.801.800.20

    v) Formwork (with wooden planks)

    a) Fabrication and erection withall supports, struts, braces,etc, and dressing with oil ascleaning of formwork:1) Rectangular column and

    wallsm2 Carpenter

    Mazdoor0.250.20

    2) Suspended floors/roofs m2 Carpenter Mazdoor

    0.230.20

    3) Sides and soffits of beams m2 Carpenter Mazdoor

    0.300.20

    ( Continued )

  • IS : 7272 (Part I) - 1974

    9

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)vi) Reinforcement

    Bar reinforcement includingcutting to length, hooked ends,cranking or bending, hoistingand placing in any position,binding with binding wire andholding firmly so as not to bedisturbed while placing andramming of concrete

    Quintal Bar-bender Mazdoor

    1.001.00

    vii) Plastering and Pointinga) 15 mm thick cement plaster to

    ceiling including mixing ofmortar

    m2 Mason Mazdoor Bhisti

    0.080.100.10

    Labour constantsfor Bhisti includes

    labour for curing.

    b) 15 mm thick cement plaster onbrick walls (exterior) includ-ing mixing of mortar

    m2 Mason Mazdoor Bhisti

    0.060.100.10

    c) 15 mm thick cement plaster onbrick walls (exterior). Underlayer 10 mm cement sandplaster and top layer 5 mm,cement : Marble powder : stonegrit, including mixing

    m2 Mason Mazdoor Bhisti

    0.150.150.15

    d) 15 mm thick cement plaster onbrick walls (interior) includingmixing mortar

    m2 Mason Mazdoor Bhisti

    0.080.100.10

    e) Struck pointing to brick workin cement mortar includingmixing mortar

    m2 Mason Mazdoor Bhisti

    0.080.100.10

    f) Tuck pointing to random rub-ble masonry in cement mortarincluding mixing mortar

    m2 Mason Mazdoor Bhisti

    0.100.150.10

    viii) Paving and Floor Finisha) Laying of PCC 40 mm thick in

    alternate bays with side formsand templates and finishedsmooth

    m2 Mason Mazdoor Bhisti

    0.080.120.10

    Labour for mixing

    concrete for items (a) to (e) will be extra.

    Labour constants for

    Bhisti includes

    labour for curing.

    ( Continued )

  • IS : 7272 (Part I) - 1974

    10

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)b) Laying of PCC 25 mm thick in

    alternate bays with side formsand templates and finishedsmooth

    m2 Mason Mazdoor Bhisti

    0.070.100.10

    Labour for mixing

    concrete for items (a) to (e) will be extra.

    Labour constantsfor Bhisti includes

    labour for curing.

    c) Laying of 40 mm thick in situterrazo flooring, under layer30 mm thick cement concreteand top layer of 10 mm thickmarble chips laid in cementwith dividing strips of glass,metal or asbestos to form baysincluding cutting, grindingand polishing:1) Laying m2 Mason

    Mazdoor Bhisti

    0.220.220.10

    2) Cutting, g r i n d i n g andpolishing

    m2 Mazdoor Machine

    0.500.40

    d) Laying of 20 mm thick in situterrazo skirting/dado under-layer 13 mm thick cementplaster and top layer 7 mmthick marble chips laid incement including rounding ofjunctions with floor cutting,grinding and polishing:1) Laying m2 Mason

    Mazdoor Bhisti

    0.300.300.10

    2) Cutting, g r i n d i n g andpolishing

    m2 Mazdoor 0.70

    e) Precast terrazo tile flooring 20mm thick laid over 10 mmthick cement mortar:1) Laying m3 Mason

    Mazdoor Bhisti

    0.120.200.10

    2) Cutting, g r i n d i n g andpolishing

    m2 Mazdoor Machine

    0.500.40

    ( Continued )

  • IS : 7272 (Part I) - 1974

    11

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)ix) Damp-proof Course

    a) Laying damp-proof course 40mm thick cement concrete in-cluding formwork and fairfinishing to edges and mixing

    m2 Mason Mazdoor Bhisti

    0.100.100.01

    Labour constants for

    Bhisti includes

    labour for curing.

    b) Laying damp-proof course 20mm thick in cement mortarintegral water-proofing com-pound including mixing

    m2 Mason Mazdoor Bhisti

    0.100.100.01

    x) Joinerya) Door and window CHOKHATS

    coniferous and teak woodwrought and rebated

    m2 Carpenter Mazdoor

    20.002.00

    b) Panelled/glazed joinery inconiferous and teak wood 30 to40 mm thick framed withpanels or space left out for glassor fixing of mesh wire (with ten-noned joints)

    m2 CarpenterMazdoor

    0.900.10

    c) Fixing of readymade shuttersto frames including fixing offittings

    m2 CarpenterMazdoor

    0.250.25

    xi) GlazingFixing glass panes on steel orwood work bedded with putty

    m2 Glazier Mazdoor

    0.200.01

    xii) Painting and PolishingFrench polishing complete in-cluding a coat of wood filler onnew work

    m2 Polisher 0.35

    xiii) White Washing and Colour Washing (for Walls and Flat Ceilings)a) White washing with lime 3

    coats on new surfacem2 Washer

    Mazdoor0.020.01

    Items (a) to (e) do not include

    labour for erection of scaffolding

    and dismantling

    the same.

    b) Two coats of colour wash overan undercoat of white wash onnew work

    m2 Washer Mazdoor

    0.030.01

    ( Continued )

  • IS : 7272 (Part I) - 1974

    12

    TABLE 1 RECOMMENDED LABOUR OUTPUT CONSTANTS FORBUILDING WORK Contd

    SL NO.

    DESCRIPTION OF WORK UNIT LABOUR RECOMMENDEDCONSTANT IN

    DAYS (8WORKINGHOURS)

    REMARKS

    (1) (2) (3) (4) (5) (6)c) Distempering with dry distem-

    per 3 coats on new surfaceincluding a priming coat ofwhiting

    m2 Painter Mazdoor

    0.080.04

    Items (a) to (e) do not include

    labour for erection of scaffolding

    and dismantling

    the same.

    d) Cement based paint 2 or morecoats on new work (for eachcoat)

    m2 Painter Mazdoor Bhisti

    0.150.010.10

    e) Cement wash one coat on newwork

    m2 Washer 0.02

    xiv) Terraced Roofinga) 10 cm thick (average) mud

    PHUSKA of clay mixed withBHUSA at 8 kg per m3 of clayon roofs laid to slope andconsolidated

    m2 Mason Mazdoor Bhisti

    0.010.200.01

    b) 10 mm thick mud plaster andGOBRI leeping with mudGOBRI mortar over mudPHUSKA

    m2 Mazdoor 0.01

    c) One layer of tile brick laid overGOBRI leeping and groutedwith cement mortar includingmixing and finished neat

    m2 Mason Mazdoor Bhisti

    0.120.150.10

    d) Lime concrete terracing com-prising of lime, surkhi, brickballast 20 mm and downaverage consolidated thickness10 cm, finished with gur andbelgiri treatment complete:1) Laying m2 Mason

    Mazdoor Bhisti

    0.100.300.05

    2) Beating and finishing m2 Mazdoor Bhisti

    0.070.10

  • Bureau of Indian StandardsBIS is a statutory institution established under the Bureau of Indian Standards Act, 1986 to promoteharmonious development of the activities of standardization, marking and quality certification ofgoods and attending to connected matters in the country.

    CopyrightBIS has the copyright of all its publications. No part of these publications may be reproduced in anyform without the prior permission in writing of BIS. This does not preclude the free use, in the courseof implementing the standard, of necessary details, such as symbols and sizes, type or gradedesignations. Enquiries relating to copyright be addressed to the Director (Publications), BIS.

    Review of Indian StandardsAmendments are issued to standards as the need arises on the basis of comments. Standards are alsoreviewed periodically; a standard along with amendments is reaffirmed when such review indicatesthat no changes are needed; if the review indicates that changes are needed, it is taken up forrevision. Users of Indian Standards should ascertain that they are in possession of the latestamendments or edition by referring to the latest issue of BIS Catalogue and Standards : MonthlyAdditions.This Indian Standard has been developed by Technical Committee : BDC 29

    Amendments Issued Since Publication

    Amend No. Date of IssueAmd. No. 1 February 1979

    BUREAU OF INDIAN STANDARDSHeadquarters:

    Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002.Telephones: 323 01 31, 323 33 75, 323 94 02

    Telegrams: Manaksanstha(Common to all offices)

    Regional Offices: Telephone

    Central : Manak Bhavan, 9 Bahadur Shah Zafar MargNEW DELHI 110002

    323 76 17323 38 41

    Eastern : 1/14 C. I. T. Scheme VII M, V. I. P. Road, KankurgachiKOLKATA 700054

    337 84 99, 337 85 61337 86 26, 337 91 20

    Northern : SCO 335-336, Sector 34-A, CHANDIGARH 160022 60 38 4360 20 25

    Southern : C. I. T. Campus, IV Cross Road, CHENNAI 600113 235 02 16, 235 04 42235 15 19, 235 23 15

    Western : Manakalaya, E9 MIDC, Marol, Andheri (East)MUMBAI 400093

    832 92 95, 832 78 58832 78 91, 832 78 92

    Branches : AHMEDABAD. BANGALORE. BHOPAL. BHUBANESHWAR. COIMBATORE.FARIDABAD. GHAZIABAD. GUWAHATI. HYDERABAD. JAIPUR. KANPUR. LUCKNOW.NAGPUR. NALAGARH. PATNA. PUNE. RAJKOT. THIRUVANANTHAPURAM.VISHAKHAPATNAM

    Title Page0. Foreword1. Scope2. Labour Output ConstantsTable 1