660MW Generator

download 660MW Generator

of 87

Transcript of 660MW Generator

  • 7/28/2019 660MW Generator

    1/87

  • 7/28/2019 660MW Generator

    2/87

    -FAQCP

    Page 2 of 87

    600MW

    -FAQCPGenerator Field Assembly Quality Control Points

    S.O:

    User name &Generator No..

    Installation Company:

    Supervision Company

    T F AService start time

    Completion Date:

    Note: The FAQCP contains generator manufacturers for TFA to record the installation process

    which not only improve installation quality but also a important task for our TFA.In order to

    provide you high quality service. We advice Installation representative, Supervision

    representative and power plant representative witness the installation process and accomplish

    the FAQCP record job. This book interpretation of SHANGHAI GENERATOR WORKS all.

  • 7/28/2019 660MW Generator

    3/87

    -FAQCP

    Page 3 of 87

    600MW

    Catalogue

    ....................................................................................................................................................... 6

    Part 1 Open-case inspection ............................................................................................................................... 6

    ................................................................................................................ 7

    Part 2 key point of generators installation ................................................................................................................. 11

    ..................................................................................................................................................... 15

    Part 3 Generator body .................................................................................................................................................... 15

    1. Seating plates and stator emplacement .................................................................. 15

    2. (Temperature measuring element check ) ............................................................................ 15

    3. (Test the insulation water manifold pipe)......................................................................... 16

    4. (Check the three phases' main insulation of generator)........................................ 16

    5. (Terminal box installation) ................................................................................................... 17

    6. (Rotor check ) .............................................................................................................................. 17

    6.1 (Check the elasticity & non-cylindrical degrees of rotor ) ................. 17

    6.2 (Rotor airtight test) ................................................................................................. 19

    6.3 (Rotor electric test) ................................................................................................ 19

    7. (Check the seal bearing and seal bearing seat) ......................................... 207.1 (Check the sealed bearing) ..................................................................................... 20

    7.2 (Check the seal bearing) ............................................................................................. 22

    7.3 pre-installation(Seal bearing fitting clearance) .......................................... 26

    8. (Stator coil water circuit pump pressure test) ................................................................. 27

    9. flexible connector within terminal box ...................... 28

    (Hand-lapped insulation surface of end winding & potential relocation tests) ...................................................... 28

    10. ..................................................................................... 29

    Check stator main lead terminalsneutral enclosure& lead bushing adapter............................................... 29

    11. (Preinstall & check stator bracket) ........................................................................................ 30

    11.1 ................................................................................................... 30

    (Check the combination surface gap between Level face divides in and Vertical joint surface) ................... 30

    11.2 (Bracket oil leakage test).............................................................................................. 32

    11.3 (Check the insulation of bearing seat) ..................................................................... 33

    12. (Check of contact surface between bearing and bearing seat ) ....................................... 33

    12.1 600MW (For 600MW tilling pad bearing) ....................................................... 33

    12.2 660MW (For 660MW elliptical bearing) ......................................... 33

    13. ........................................................................................................................ 34

    (Water pump pressure test of cooler and installation of encloser) ......................................................................... 34

    14. CG (The gap between Stator and rotor the size of CG) ................................. 3515. (Check rotor interturn fault monitoring) ......................................................... 36

    16. ............................................................................................................ 38

  • 7/28/2019 660MW Generator

    4/87

    -FAQCP

    Page 4 of 87

    600MW

    (Check swaying& run out of shaft and coupling face of rotor on EE & TE) ...................................................... 38

    17. (Install blower shroud and stationary blades) ............................................. 39

    18. (Install the air tight mount and check the insulate ) ............................................ 40

    18.1 600MW (double rings for 600MW generator) ........................................................ 4018.2 660MW (single ring for 660MW generator) .............................................................. 43

    19.(Check injection of sealant) .............................................................................................. 45

    20. (Measure the gap between bearing and rotor shaft ) ............................................... 45

    20.1 600MW ............................................................. 45

    Gap between Upper half tilling pad bearing and shaft (For the bearing of 660MW ultra-critical generator) 45

    20.2 660MW .................................................................................................... 45

    Elliptical BearingFor the bearing of 660MW ultra-critical generator.................................................... 45

    21. 600MW .......................................................................................................... 46

    Floating oil ring inspection (for 600MW generator) ............................................................................................. 46

    22. 660MW .................................................................................. 47

    Gap between deflector oil ring and shaft(for 660MW ultra-critical generator) ..................................................... 47

    23. ................................................................................................................................ 48

    (Check related gap between top half bearing and top dowel) ................................................................................ 48

    23.1 600MW (600MW supercritical) .......................................................................................... 48

    23.2 660MW (660MW ultra-critical generator) .................................................................. 48

    24. (check of double insulation leads) .................................................................................. 49

    24.1 600MW ................................................................................................ 49

    Check of double insulation leads (for 660 MW)............................................................................................ 49

    24.2 660MW ............................................................................. 50Wire of Turbine side Potential measurements(for 660MW ultra supercritical) ............................................ 50

    25. (The related gap between end shield and rotor shaft) ................................................. 50

    25.1 600MW (600MW supercritical).................................................................................................. 51

    25.2 660MW (660MW ultra-critical) .......................................................................................... 51

    26. (Check & Assembly of cooler) ........................................................................................... 52

    27 Before twice grouting (Alignment of Turbine and Generator. In

    cold state.) .................................................................................................................................................... 52

    28.(installation & inspection of ladder shims) ................................................................... 53

    29. .......................................................................................................... 54

    (Centering & Butt joint of Turbine and Generator) ............................................................................................... 54

    30.(Generator foundation bolt installation & inspection) .......................................... 55

    31 Before twice grouting .................................... 56

    (Alignment of slip ring axis(exciter) and generator rotor) ..................................................................................... 56

    31.1 (Slip Ring Axis) ........................................................................................................................ 56

    31.2 (exciter) ..................................................................................................................................... 56

    32 .......................................................................... 57

    (Slip ring axis (Exciter) and generator rotor connect coupling (after twice alignment)) ....................................... 57

    33. (Swing test of slip ring axis (exciter)) ............................................................. 58

    34. ........................................................................................................................ 59(Bearing installation of Slip ring axis (Exciter)).................................................................................................... 59

    34.1 (slip ring axis) ............................................................................................................................ 59

  • 7/28/2019 660MW Generator

    5/87

    -FAQCP

    Page 5 of 87

    600MW

    34.2 (exciter) ..................................................................................................................................... 60

    35. Installation of brush holders.................................................................................................... 60

    36. (water circuit pump pressure test of exciter)......................................................... 61

    37. (Installation of exciter grounding detection device) ................................................. 6238. (Electrical test of exciter) .................................................................................................. 62

    39. (Stator winding DC test) ................................................................................................. 63

    40. (Stator winding AC test) ......................................................................................................... 64

    41.Take carefully inspection before Generator wind test .............................. 64

    42. (Wind pressure test) ................................................................................................................ 67

    ................................................................................................................................................. 67

    Part 4 Oil Water & Hydrogen system ................................................................................................................ 67

    1. (hydrogen system)............................................................................................................................ 67

    2. (oil system) .................................................................................................................................... 68

    3. (water system) ................................................................................................................................ 68

    4. (Site commissioning of the equipments manufacturers confirmation) ......... 70

    5. specification of prevent seal oil into frame ..................................... 71

    6. --........................................................................................................................... 73

    Water system assembly installationinstallation of water pipes .......................................................................... 73

    7. ................................................................................................................. 80

    Attachments ofspecification of prevent seal oil into frame ........................................................................... 80

  • 7/28/2019 660MW Generator

    6/87

    -FAQCP

    Page 6 of 87

    600MW

    Part 1 Open-case inspection

    1. Check the packaging without damage, if the damaged boxes be found, it must be reported to the

    company.

    2. Check parts look no obvious bump against injury appearance, deformation, rust, according to the

    actual situation reflected (recommended photos form).

    3. Reflects the number of parts according to the number in the packing list.

    4After open the important assembly parts case, must keep the parts inside storehouse. Requirements

    of storage according to packaging.

    (Signature by four parties: )

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)

  • 7/28/2019 660MW Generator

    7/87

    -FAQCP

    Page 7 of 87

    600MW

  • 7/28/2019 660MW Generator

    8/87

    -FAQCP

    Page 8 of 87

    600MW

  • 7/28/2019 660MW Generator

    9/87

    -FAQCP

    Page 9 of 87

    600MW

  • 7/28/2019 660MW Generator

    10/87

  • 7/28/2019 660MW Generator

    11/87

    -FAQCP

    Page 11 of 87

    600MW

    Part 2 key point of generators installation

    f

    Installation of Stator fame & seating plant

    check thermometric elements

    Test the insulation water manifold flange

    Test the main insulation of the generator

    Install terminal box

    check rotor Water pressure test of stator coil

    Install Hand-lapped insulation of end

    winding connectors & flexible connector

    check the size of Gland seal ring and gland

    seat bracket

    Preinstall & check stator bracket

    check contact surface between bearing and

    bearing seat

  • 7/28/2019 660MW Generator

    12/87

    -FAQCP

    Page 12 of 87

    600MW

    Water pressure test of

    stators cooler

    Electric test of rotor

    Install stators cooler Adjust detector of rotor winding

    shorted turns

    Generator Rotor Thread

    check swaying& run out of shaft and

    coupling face

    Adjust generators magnetize center

    Check gap between blower shroud and stationary

    blades

    Installation of bearing gland seal & oil seal

    check the gap between bearing shaft and bearing

    check the related gap between bearing and float oil

    ring

  • 7/28/2019 660MW Generator

    13/87

    -FAQCP

    Page 13 of 87

    600MW

    Check related gap between upper half bearing

    and top dowel

    Installation of double insulation leads

    Second Centering of Turbine and

    Generator

    Twice grouting of generator

    foundation

    Centering & Butt joint of Turbine and

    Generator

    Centering of exciter and Generator

    Twice grouting of slip ring axis

    exciter foundation

    Exciter (slip ring axis) and generators

    rotor connect coupling

    Swaying test

  • 7/28/2019 660MW Generator

    14/87

  • 7/28/2019 660MW Generator

    15/87

    -FAQCP

    Page 15 of 87

    600MW

    Part 3 Generator body

    1. Seating plates and stator emplacement

    Requirements: Check whether the seating plates have wrong holes or not. Avoid wrong holes

    when emplace the stator frame foot on seating plates. Exact data requires

    according to installation guide & drawings.

    (On-site inspection)

    Attached photos

    (Without exception within the visible parts of the stator

    and the foreign body)

    (Photo:inside the stator,end)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)

    2. (Temperature measuring element check )

    250V 1

    Requirements: After the stator placed check all the DC resistance and AC resistance of all the

    temperature sensor on the terminal row .Use the millimeter and 250V mugger,

    Insulation resistance 1M.

    (On-site inspection)

    Attached the test report)

    Signature by four parties

    (Power plant Representative)

  • 7/28/2019 660MW Generator

    16/87

    -FAQCP

    Page 16 of 87

    600MW

    (Installation Company)

    (Supervision Company)

    TFA

    date

    3. (Test the insulation water manifold pipe)500V 10

    2500V 69#70#

    71# 30K

    Requirements: Use 500V megger , check the insulation of water manifold pipe, resistance 10

    M( not post-cooling water).

    Use 2500V special water megger, test the insulation of water manifold flange to

    the ground.Requirements:No.069(Primary water pipe at T.E. ),No.070(Primary

    water pipe at E.E.)No.071Water pipe at main lead box,after three points

    parallel connection, the insulation 30K(post-cooling water).

    (On-site inspection)

    ) Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    4. (Check the three phases' main insulation of generator)

    After the stator emplacement, open the transportation cover, and then check the three phases'

    main insulation of generator.

    ABC 2500V 1000 M1min

    R60s/ R15s1.3; R600s/ R60s2

    Requirements: Stator winding ABC use 2500V meggerrequire1000 M, Absorptions

    R60s/ R15s1.3; Polarization index R600s/ R60s2.

    (On-site inspection)

    (M)

    Insulation resistances

    Absorptions

    Polarization indexR15s R60s R600s R60s/ R15s R600s/ R60s

  • 7/28/2019 660MW Generator

    17/87

    -FAQCP

    Page 17 of 87

    600MW

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    5. (Terminal box installation) 0.05mm

    6

    Requirements: The bolts which connect stator and terminal box should installed tighten as

    required, check joint surface clearance requirements 0.05mm. Inject sealant

    after checked. Torque all bolts be tightened by drawing.Pay more attention to the

    six main leads during terminal box installation

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    6. (Rotor check )6.1 (Check the elasticity & non-cylindrical degrees of rotor )

    A BC

    A phase to B phase C phase&

    ground

    B AC B phase to A phase C phase&

    ground

    C AC

    C phase to A phase C phase&

    ground

  • 7/28/2019 660MW Generator

    18/87

    -FAQCP

    Page 18 of 87

    600MW

    (T.E.) (Unit)mm

    No.

    Measure

    position

    Measure items

    Design

    value

    Tolerance

    On-site

    measure

    value

    1 D1

    (Rotor journal diameter)

    500

    -0.063

    2 D2 500

    3 D3 500

    4 D4 500

    5 D5 500

    6 D6 500

    7

    (elasticity degree of rotor)0.03

    8

    (Non-cylindrical degrees of rotor) 0.03

    E.E. (Unit)mm

    No.

    Measure

    position

    Measure items

    Design

    value

    Tolerance

    On-site

    measure

    value

    1 D1 500

    2 D2 500

  • 7/28/2019 660MW Generator

    19/87

    -FAQCP

    Page 19 of 87

    600MW

    3 D3

    (Rotor journal diameter)

    500

    -0.0634 D4 500

    5 D5 500

    6 D6 500

    7

    (elasticity degree of rotor)

    0.03

    8

    (Non-cylindrical degrees of rotor)

    0.03

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    6.2(Rotor airtight test) 1.4MPa 2 0.02MPa/h 10

    -5ml/s

    Requirements1.4 MPa air test for 2 hours. ExpectationsLeakage 0.02MPa/h or halogenseveral leak detection 10-5ml/s no alarm for qualified.

    (On-site inspection)

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    6.3(Rotor electric test)a. 20 500V 10

    2510M

    b. GBT1029c.

  • 7/28/2019 660MW Generator

    20/87

    -FAQCP

    Page 20 of 87

    600MW

    Requirementsa.Rotor insulation resistance: Rotor winding in the cold state (room temperature

    is 20 ). Use the 500V megger to test. 10 minutes of insulation

    resistance10M when the temperature is 25

    b. Rotor DC resistance: use a bridge to measure the resistance. Resistance

    tolerance according to "Factory test reports, test method according to

    GBT1029 requirements with GB

    c. The rotor with AC impedance: Test purpose to detect generator rotor winding

    turn-to-turn without static and dynamic short-circuit fault.

    Data Reference to "Factory test report".

    (On-site inspection)

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    7. (Check the seal bearing and seal bearing seat)

    Note: The following items should be checked after the cases opened.

    7.1 (Check the sealed bearing)aa.Check the level points face dislocation of the sealed bearings

    0.025mm Requirementsthe junction plane dislocation and surface gap(The junction plane axial and

    tangential dislocation 0.025mm)

  • 7/28/2019 660MW Generator

    21/87

    -FAQCP

    Page 21 of 87

    600MW

    UW

    The level points face dislocation of the sealed bearings and slots of bearings U&W

    (Unit)mm

    b(Gland seat's slot width)(Unit)mm

    (Manufactory

    Record)(Install Record)

    EE

    TE

    EE

    TE

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)TFA

    U

    LEFT

    RIGHT

    TE

    EE

    W

    LEFT

    RIGHT

    TE

    EE

  • 7/28/2019 660MW Generator

    22/87

    -FAQCP

    Page 22 of 87

    600MW

    date

    7.2(Check theseal bearing)aa. Seal bearing thickness (seal bearing on Hydrogen side, seal bearing on air side after assembly)

    0.05mm

    RequirementsAfter unpackingseal bearing, do the following checks before apart Thickness

    change requirement 0.05mm.

    (Unit)mm

    Manufactory

    Record

    PositionA B C D E A1 B1 C1 D1 E1

    thickness

    TE

    EE

    (InstallationRecord)

    thickness

    TE

    EE

    b ()

  • 7/28/2019 660MW Generator

    23/87

    -FAQCP

    Page 23 of 87

    600MW

    Seal bearing inside diameter (seal bearing on Hydrogen side, Gland seal bearing on air side after

    assembly)

    0.02mm

    Requirements: Check diameter of seal bearing immediately after unpacking and before bolts on

    half surface are not dismantled yet. max change 0.02mm.

    (Unit)mm

    PositionA-A1 B-B1 C-C1 D-D1 E-E1

    (MR)

    T.E.

    E.E.

    (IR)

    T.E.

    E.E.

    c ()Misalignment and clearance check seal bearing on air side after assembly

    0.025mm

    Requirements: tolerance 0.025 mm

    Note: After unpackingseal bearing, do the following check before apart.

  • 7/28/2019 660MW Generator

    24/87

  • 7/28/2019 660MW Generator

    25/87

  • 7/28/2019 660MW Generator

    26/87

    -FAQCP

    Page 26 of 87

    600MW

    TFA

    date

    7.3 pre-installation(Seal bearing fitting clearance)

    Requirements: Put Seal bearing on rotor for pre-installation, sealing seat and sealing bearing for

    pre-instillation.

    a double rings600MW 600MW supercritical Measure Position

    mm

    Design Value

    mmActual Measure

    T.E. E.E.

    Radial

    gaps

    13

    0.23~0.2814

    15

    16

    Axial gaps

    9

    0.306~0.38510

    11

    12

    b single ring660MW 660MW ultra-critical

  • 7/28/2019 660MW Generator

    27/87

    -FAQCP

    Page 27 of 87

    600MW

    Measure Positionmm

    Design Value

    mmActual Measure

    T.E. E.E.

    Radial

    gaps

    13

    0.34~0.3614

    15

    16

    Axial gaps

    9

    0.21~0.2410

    11

    12

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    8. (Stator coil water circuit pump pressure test) 0.75MPa 8

    63# 68#

    RequirementsAfter the install flexible connector and insulation water pipe.Stator coil water pump

    pressure test. 0.75Mpa for 8 hours, no leakage. The water in the coil must be

    blown to dry immediately when the test finished, and the three-phase main

    insulation be retested.No.63 THRU No.68 on the board need our engineer to

    install, and then checked by Power plant Representative.

    Water requirements of pure water

    (On-site inspection)

    Attached test reports

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

  • 7/28/2019 660MW Generator

    28/87

    -FAQCP

    Page 28 of 87

    600MW

    9. flexible connector within terminal box(Hand-lapped insulation surface of end winding & potential relocation tests)

    3

    RequirementsAll the bolts involved these installed parts need to tighten according to the

    drawing.Make sure to meet the following three conditions before hand-insulation

    aStator water pump pressure test is qualified

    bStators temperature units inspection is qualified

    cStators three phases insulations inspection is qualified

    After the hand-insulation the test of potential relocation test should be done by user.

    The method of Potential relocation of hand insulation test can be divided into positive connect and

    reverse connect:

    a 100

    KV v

    20KV 1000

    a. Positive connects: wrap the aluminum foil outside the hand insulation of the end of the stator

    winding. The DC high voltage is connected with the tested stator windings. Rated voltage is set for

    the step-up generator. And an insulation bar of 100 M is pu t on the aluminum foil. Then the

    to-ground voltage of each foil packet is measured by the digital voltmeter.

    Requirements:

    Rated voltage of the generator (KV) 20KV

  • 7/28/2019 660MW Generator

    29/87

    -FAQCP

    Page 29 of 87

    600MW

    Potential relocation allowed (V) 1000V

    b20KV 30

    b. reverse connect: In each tin foil with high Voltage20KV, Winding end through uA meter

    grounded, read mA meter values, Qualification requirements: lto 30uA.

    Voltage

    (leakage of the winding ends)

    1 2 3 4 5 6

    (On-site inspection)

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFAdate

    10.Check stator main lead terminalsneutral enclosure&lead bushing adapter

    M30 40mm

    6.5mm

    Requirments:Involved in this part of the installation torque of all bolts must be tightened

    according todrawing and

    stop gasket

    must do the insurance. Screw for pegging

    CT should be screwed in lead box about 40mm and tightened by nuts. Neutral

    enclosure should be only one grouded.Min of 6.5mm electrical clearance should be

    maintained between metal parts of bus and metal studs.

  • 7/28/2019 660MW Generator

    30/87

    -FAQCP

    Page 30 of 87

    600MW

    (On-site inspection)

    (Signature by four parties: )

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)

    11. (Preinstall & check stator bracket)11.1

    (Check the combination surface gap between Level face divides in and Vertical joint

    surface)

    0.05mm

    Requirements: check the contact areas with a thin ruler,which are between the up-down

    bearing bracket and stator,the up-bearing bracket and down-bearing bracket.the

    thin ruler of 0.05mm should not be allow to be slipped in.

  • 7/28/2019 660MW Generator

    31/87

    -FAQCP

    Page 31 of 87

    600MW

    Level face divides in

    Vertical joint surface

    1. T.E. level face divides in (Unit)mmPosition

    Item

    Tolerance

    maxOn-site measure value

  • 7/28/2019 660MW Generator

    32/87

    -FAQCP

    Page 32 of 87

    600MW

    A1~A26

    Measurement of bracket level

    face divides in

    0.05

    2. T.E. vertical joint surface (Unit)mm

    Position

    Item

    Tolerance

    max

    On-site measure value

    1~14

    Measurement of bracket vertical

    joint surface

    0.05

    3. E.E. level face divides in (Unit)mm

    Position

    Item

    Tolerance

    max

    On-site measure value

    A1~A26 Measurement of bracket level

    face divides in

    0.05

    4. E.E. vertical joint surface (Unit)mm

    Position

    Item

    Tolerance

    max

    On-site measure value

    1~14

    Measurement of bracket vertical

    joint surface

    0.05

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    11.2 (Bracket oil leakage test)

    Requirements: set the bracket vertical then check the bearing return oil chamber, sealing oil,

    floating oil into the tubing on into the lubricating oil check each weld seams

    cover whether there is oil leakage.

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

  • 7/28/2019 660MW Generator

    33/87

  • 7/28/2019 660MW Generator

    34/87

    -FAQCP

    Page 34 of 87

    600MW

    Requirements

    a 75%

    100 0.02mm

    0.1mm 50-60mm 100mm

    Check the contact surface between sphere surface of bearing and bearing seat carefully,

    make sure that contact areas 75% and the contact points should uniform distribution.

    Oil feed hole should sealed 100%.Use feeler gauge to check the gap between bearing

    and bearing seat , make sure that the contact surface around oil groove is required which

    means feeler gauge can only put in 0,02mm in depth max. Use 0.01mm feeler gauge to

    check the gap between bearing and bearing seat, the depth is 50-60mm, max 100mm.

    b

    Bearing color penetrant test

    c 4 8

    Scratch bottom half bearing at 4 and 8 oclock positions for transition scrape, according

    drawing of Bearing.

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    13. (Water pump pressure test of cooler and installation of encloser)

  • 7/28/2019 660MW Generator

    35/87

    -FAQCP

    Page 35 of 87

    600MW

    0.8MPa 2

    RequirementsHydrogen water cooler must take water pump pressure test at 0.8Mpa 2 hours

    separately. Make sure that no leakage of water or change of Pressure gauge. Pay

    more attention to the different from EE and TE cooler encloser during installation:

    EE side cooler encloser have two more internal arc pipes than TE side. Involved

    in this part of the installation torque of all bolts must be tightened according to

    drawing and stop gasket must do the insurance.

    (On-site inspection)

    Attached the test report

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    14. CG(The gap between Stator and rotor the size of CG)

    (Unit):mm

    Measure

    point Position Drawing demand

    MR

    IR

  • 7/28/2019 660MW Generator

    36/87

    -FAQCP

    Page 36 of 87

    600MW

    Signature by four parties(Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date15. (Check rotor interturn fault monitoring)

    90

    Requirements: After the Generator Rotor Thread in, rotor interturn fault monitoring must be

    Vertical to Rotor

    From T.E. to E.E.

    up

    0.76mm

    gap with the pointthe difference

    0.76mm on

    average

    down

    left

    right

    From E.E. to T.E.

    up

    0.76mm

    gap with the point

    the difference

    0.76mm on

    average

    down

    left

    right

    From

    Stator TE end side to the TE

    rotor coupling surface(CG

    size)

  • 7/28/2019 660MW Generator

    37/87

    -FAQCP

    Page 37 of 87

    600MW

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    90

  • 7/28/2019 660MW Generator

    38/87

    -FAQCP

    Page 38 of 87

    600MW

    TFA

    date

    16. (Check swaying& run out of shaft and coupling face of rotor on EE & TE)

    0.03mm 0.02mm

    Requirements: swaying 0.03Run out of shaft and coupling face 0.02mm

    T.E. (Unit)mm

    E.E.

    (Unit)mm

    No.

    Measure

    position

    A B A-B C

    1 1-5

    2 2-6

    3 3-7

    4 4-8

    5 5-1

    6 6-2

    7 7-3

    8 8-4

    swaying Run out of shaft and

    coupling face

    No.

    Measure

    position

    A B A-B C

    1 1-5

    2 2-6

    3 3-7

    4 4-8

  • 7/28/2019 660MW Generator

    39/87

    -FAQCP

    Page 39 of 87

    600MW

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    17. (Install blower shroud and stationary blades)

    Requirements: Involved in this part of the installation torque of all bolts must be tightened

    according to drawing and stop gasket must do the insurance.

    T.E. (Unit)mm

    No.

    Measure

    position

    Design Value

    MR

    IR

    1 A 2.29~2.44

    2 B 2.29~2.44

    5 5-1

    6 6-2

    7 7-3

    8 8-4

    swaying Run out of shaft and

    coupling face

  • 7/28/2019 660MW Generator

    40/87

    -FAQCP

    Page 40 of 87

    600MW

    3 C 1.85~2

    4 D 1.85~2

    E.E.

    No.

    Measure

    position

    Design Value

    MR

    IR

    1 A 2.29~2.44

    2 B 2.29~2.44

    3 C 1.85~2

    4 D 1.85~2

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    18. (Install the air tight mount and check the insulate )

    Requirements: Involved in this part of the installation torque of all bolts must be tightened

    according to drawing and stop gasket must do the insurance.

    18.1 600MW(double rings for 600MW generator)18.1.1

    (The gap between oil block of bottom half of gland seal bracket and shaft)

  • 7/28/2019 660MW Generator

    41/87

    -FAQCP

    Page 41 of 87

    600MW

    Measure position

    mm

    Design value

    mm

    Installation record

    TE(down)

    0.102~0.152

    TE(left)

    0.7~0.807

    TE(right)

    0.7~0.807

    EE(down)

    0.102~0.152

    EE(left)

    0.7~0.807

    EE(right)

    0.7~0.807

    18.1.2 ( Check the insulation between bracket and bottom half of gland seal bracket)

    No.

    Items

    Design

    Value

    On-site value

    1

    Insulation Between E.E. Bracket

    and Bottom Half of Seal Bracket

    1M

    2

    Insulation Between T.E. Bracket

    and Bottom Half of Seal Bracket

    1M

    3

    Insulation Between E.E. Bracket

    and Buffer Ring

    1M

    18.1.3 (The gap around airtight bearing)

    (The radial gap between airtight bearing and shaft)

    mm

    Design Value

    mm

    IR

    T.E. 0.23~0.28

    E.E. 0.23~0.28

    The axial gap between mount and airtight bearing

    mm

    Design Value

    mm

    IR

    T.E. 0.306~0.385

    E.E. 0.306~0.385

    0.1mm

  • 7/28/2019 660MW Generator

    42/87

    -FAQCP

    Page 42 of 87

    600MW

    Note: The difference between seal ring brackets EE&TE. Seal ring bracket could be moved easily

    if the installation is ok. Insulating sleeve bolts which to fasten the Seal ring bracket must be

    0.1mm lower than the surface of middle ring.

    18.1.4(The gap between oil block of top half of gland seal bracket and shaft)

    Measure position

    mm

    Design Value

    mm

    IR

    T.E. Up

    1.289~1.462

    T.E. Down

    0.102~0.152

    T.E. Left

    0.7~0.807

    T.E. Right

    0.7~0.807

    E.E. Up

    1.289~1.462

    E.E. Down

    0.102~0.152

    E.E. Left

    0.7~0.807

    E.E. Right

    0.7~0.807

    18.1.5 (Check insulation between stator bracket and gland sealbracket)

    No.

    Item

    Design Value

    On-site Measure

    Value

    1

    Insulation Between

    E.E.Bracket and Seal Bracket

    1M

    2

    Insulation Between

    T.E.Bracket and Seal Bracket

    1M

    Signature by four parties(Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFAdate

  • 7/28/2019 660MW Generator

    43/87

  • 7/28/2019 660MW Generator

    44/87

    -FAQCP

    Page 44 of 87

    600MW

    18.2.2 (Insulation between bracket and inside oil deflection)

    No.

    Item

    Design Value

    Actual Measure1

    Insulation Between

    E.E.Bracket and Inside Oil

    Deflection

    1M

    2

    Insulation Between

    T.E.Bracket and Inside Oil

    Deflection

    1M

    18.2.3(The gap around airtight bearing)Radial gaps

    mm

    Design Value

    mm

    IR

    T.E. 0.34~0.36

    E.E. 0.34~0.36

    Axial gaps

    mm

    Design Value

    mm

    IR

    T.E. 0.21~0.24

    E.E. 0.21~0.24

    0.1mm

    Note: The difference between seal ring brackets EE&TE. Seal ring bracket could be moved easily

    if the installation is ok. Insulating sleeve bolts which to fasten the Seal ring bracket must

    be 0.1mm lower than the surface of middle ring.

    18.2.4 (Check insulation between stator bracket and gland sealbracket)

    No.

    Item

    Design Value

    Actual Measure

    1

    Insulation Between

    E.E.Bracket and Seal Bracket

    1M

    2

    Insulation Between

    T.E.Bracket and Seal Bracket

    1M

  • 7/28/2019 660MW Generator

    45/87

  • 7/28/2019 660MW Generator

    46/87

    -FAQCP

    Page 46 of 87

    600MW

    No.

    Items

    (mm)

    Design Value

    (mm)

    Measure Value

    1

    Gap between bearing and

    shaft(T.E.Left)

    1~1.04

    2

    Gap between bearing and

    shaft(T.E.Right)

    1~1.04

    3

    Gap between bearing and

    shaft(T.E.Top)

    0.6~0.735

    4

    Gap between bearing andshaft(E.E.Left)

    1~1.04

    5

    Gap between bearing and

    shaft(E.E.Right)

    1~1.04

    6

    Gap between bearing and

    shaft(E.E.Top)

    0.6~0.735

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    21. 600MWFloating oil ring inspection (for 600MW generator)

    0.25-0.5mm.

  • 7/28/2019 660MW Generator

    47/87

    -FAQCP

    Page 47 of 87

    600MW

    Requirement: Gaps between 0.25-0.5mm.

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    22.660MWGap between deflector oil ring and shaft(for 660MW ultra-critical generator)

    Measure Item

    (mm)

    Design Value

    (mm)

    Measure Value

    T.E.

    (mm)

    Measure Value

    E.E.

    Gap between Deflector

    oil ring and shaft

    top

    0.3-0.44

    bottom

    0.10

    left

    0.2-0.27

    right

    0.2-0.27

  • 7/28/2019 660MW Generator

    48/87

    -FAQCP

    Page 48 of 87

    600MW

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    23. (Check related gap between top half bearing and top dowel)

    Requirements: Involved in this part of the installation torque of all bolts must be tightened

    according to drawing and stop gasket must do the insurance.

    23.1 600MW(600MW supercritical)

    (Related gap)0.127~0.381mm

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    23.2 660MW(660MW ultra-critical generator)

  • 7/28/2019 660MW Generator

    49/87

    -FAQCP

    Page 49 of 87

    600MW

    (Related gap)0.3~0.4mm

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    24. (check of double insulation leads)24.1 600MW

    Check of double insulation leads (for 660 MW)

    250V

    Requirement: all stop gaskets must do the insurance.Assembly the parts according to drawings,

    then check each insulation test point, by using the 250V mega meter.

    (No. & corresponding leading single wires)

    (Design value)

    (Measured value)

    1

    buffer ring

    1M

    2

    bearing key

    1M

    3

    bearing stop dowel(combined from twoorigins)

    1M

  • 7/28/2019 660MW Generator

    50/87

    -FAQCP

    Page 50 of 87

    600MW

    4 insulated

    bearing seat(buffer pad left hand side)

    1M

    5 insulated

    bearing seat(buffer pad right hand side)

    1 M

    6

    bearing oil seal

    1 M

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    24.2660MWWire of Turbine side Potential measurements(for 660MW ultra supercritical)

    250V

    Requirement: All stop gaskets must do the insurance. Assembly the parts according to drawings,

    then check each insulation test point, by using the 250V mega meter.

    No

    Design

    Actual Measure

    T.E.

    Actual Measure

    E.E.

    1

    Insulation between seal bracket

    and ground

    1 M

    2

    Insulation between bearing and

    bearing bracket

    1 M

    3

    Insulation between bearing and

    bearing bracket

    1 M

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date25. (The related gap between end shield and rotor shaft)

  • 7/28/2019 660MW Generator

    51/87

    -FAQCP

    Page 51 of 87

    600MW

    25.1 600MW(600MW supercritical)

    (Measure position)

    mm

    (Design value)

    mm

    (Install record)

    (ET top) 1.29-1.46

    (ET bottom) 0.10-0.15

    (ET left) 0.7-0.8

    (ET right) 0.7-0.8

    (EE top) 1.29-1.46

    (EE bottom) 0.10-0.15

    (EE left) 0.7-0.8(EE right) 0.7-0.8

    25.2 660MW(660MW ultra-critical)

    (Measure position)

    mm

    (Design value)

    mm

    (Install record)

    (ET top) 0.65-0.73

    (ET bottom) 0.10-0.15

    (ET left) 0.375-0.44(ET right) 0.375-0.44

    (EE top) 0.65-0.73

    (EE bottom) 0.10-0.15

    (EE left) 0.375-0.44

    (EE right) 0.375-0.44

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

  • 7/28/2019 660MW Generator

    52/87

    -FAQCP

    Page 52 of 87

    600MW

    TFA

    date

    26. (Check & Assembly of cooler)

    Requirements:Appropriate grinding according to the manufacturer records. Involved in this part

    of the installation torque of all bolts must be tightened according to drawing and stop

    gasket must do the insurance.

    1

    4 2

    3

    cooler

    1 2 3 4

    T.E.left

    T.E.right

    E.E.left

    E.E.right

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    27 Before twice grouting(Alignment of Turbine and Generator. In cold state.)

    (According to shafting drawings offered by Turbine company)

    Note: Only use flat shims for aiming the center before twice grouting. No using ladder

    shims.

    (cooler)

    Positioning block

  • 7/28/2019 660MW Generator

    53/87

  • 7/28/2019 660MW Generator

    54/87

    -FAQCP

    Page 54 of 87

    600MW

    A1~A4B1~B4C1~C4D1~D4,E1~E4

    Note:When installing,record the thickness of each shim A1~A4B1~B4C1~C4D1~D4,E1~E4

    according to the drawings under.Fill in the the corresponding box.

    On-site inspection:

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    29.(Centering & Butt joint of Turbine and Generator)

    According to shafting drawings offered by Turbine company.

    10 1

    Note: Check the rotors insulation resistance against ground before connect coupling.Expected value 10M1M

  • 7/28/2019 660MW Generator

    55/87

  • 7/28/2019 660MW Generator

    56/87

    -FAQCP

    Page 56 of 87

    600MW

    On-site inspection:

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    31 Before twice grouting(Alignment of slip ring axis(exciter) and generator rotor)

    31.1 (Slip Ring Axis)

    Item

    mm

    Design Value

    IR

    concentricity0.05

    under shed0.06~0.08

    parallelism

    0.12

    Bearing seat's vertical

    alignment to rotor

    0.127

    swaying0.05

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    31.2 (exciter)

  • 7/28/2019 660MW Generator

    57/87

    -FAQCP

    Page 57 of 87

    600MW

    Item

    mm

    Design Value

    IR

    concentricity

    0.05

    under shed0.100.125

    parallelism0.078

    Bearing seat's vertical

    alignment to rotor 0.127

    swaying0.05

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    32(Slip ring axis (Exciter) and generator rotor connect coupling (after twice alignment))

    On-site inspection

    ( Attached The Report)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

  • 7/28/2019 660MW Generator

    58/87

    -FAQCP

    Page 58 of 87

    600MW

    33. (Swing test of slip ring axis (exciter))1660~1930NM0.05

    1795 135 1660 1930

    Requirements: Bolt torque 1660~1930NM, swaying 0.05.The purpose of using the different

    torques to fix the bolt in order to adjust the sway within requirement tolerance.

    PS: In order to adjust swaying tolerance the torque within 135 NM.Which means after the

    adjustMIN torque 1660 NMMAX torque 1930 NM.

    Signature by four parties

    (Power plant Representative)

    Measure position

    A

    A meter

    B

    B meter

    A-B

    A-B

    C

    C meter

    1----5

    2----6

    3----7

    4----85----1

    6----2

    7----3

    8----4

    1----5

    =A-Bmax-(A-B)min/2=

    Coupling face out of=A-Bmax-(A-B)min/2=

    Circular run out

  • 7/28/2019 660MW Generator

    59/87

    -FAQCP

    Page 59 of 87

    600MW

    (Installation Company)

    (Supervision Company)

    TFA

    date

    34. (Bearing installation of Slip ring axis (Exciter))

    34.1(slip ring axis)

    Requirements: Involved in this part of the installation torque of all bolts must be tightened

    according to drawing and stop gasket must do the insurance. check whetherfloat oil ring could be moved smoothly after installation.Gaps reqirements

    according to table below.

    Measure items

    mm

    Design value

    mm

    Actual value

    Gap between half upper

    bearing bracket and shaft

    0.20~0.25

    Interference fitness between

    first half bearing and

    bearing seat

    0~0.05

    0.10mm0.05mmunitmm

    Requirements :Gaps between slip ring axis and Oil Deflection:bottom gap requirement

    0.01mm,left and right gap requirement0.05mm

    No

    Measure position

    Measure items

    Actual value

  • 7/28/2019 660MW Generator

    60/87

  • 7/28/2019 660MW Generator

    61/87

    -FAQCP

    Page 61 of 87

    600MW

    requirements: Involved in this part of the installation torque of all bolts must be tightened

    stop gasket must do the insurance. The distance between the bottom of

    the brush holder and the surface of collecting-ring is no more than

    5mm,which is shown on the drawing, other parts of the brush holderexcept carbon brush can not contact with the surface of collecting-ring.

    Details according to drawings.

    (Measured value)(Signature by four parties)

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)

    36. (water circuit pump pressure test of exciter) 0.8Mpa 2

    RequirementsKeep the pressure at 0.8Mpa in 2 hours and the check value of Pressure gauge is

    stable. No leakage of the exciter cooler.

    (On-site inspection)Attached the test report

  • 7/28/2019 660MW Generator

    62/87

    -FAQCP

    Page 62 of 87

    600MW

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    37. (Installation of exciter grounding detection device) 3mm 1.5~2.3mm

    5.125.2390

    RequirementsDistance between Steel Spring washer and Solenoid is 3mm,distance between

    carbon brushs copper piece and rotor shaft is 1.5~2.3mm(after the carbon

    brushs copper was bending by force ).pay a attention to the elasticity of carbon

    brushs copper piece At the install stage. Grounding carbon brushs drawing NO.

    5.125.2390

    (On-site inspection)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    38. (Electrical test of exciter)1. 500V 10 2510M

    Exciters rotor coil Electrical test, use the megger at 500V for 10Min, and the insulation

    resistance 10M at the temperature of 25.

    2.

    The test should be done before exciter rotor connected with generator.

    a) (DC resistance)

    Measure the Armature winding of main exciter, exciter winding and stator winding resistance

    of Pilot exciter at the cold state.

    b) (Insulation resistance)

    1000V

  • 7/28/2019 660MW Generator

    63/87

  • 7/28/2019 660MW Generator

    64/87

  • 7/28/2019 660MW Generator

    65/87

    -FAQCP

    Page 65 of 87

    600MW

    Take overall cleanliness inspection before generator sealing. Owner shall fill the inspection form to

    our company.

    1

    On-site inspection record (0ffered by power plant)

    2

    Take photos of key parts (etc)

    Stator ends & Inside terminal box (include circuit ring)

    3

    2011T01

    To From C/c Date2011-3-14Corp Page1Fax Or Ret No021-.64633745Tel Subject

    1

    2

    3

  • 7/28/2019 660MW Generator

    66/87

    -FAQCP

    Page 66 of 87

    600MW

    021-64633745 021-64620738

    ---029To From Shanghai generator worksC/c DateCorp Page1Fax Or Ret No021-64633745Tel SubjectStrengthen the control of generator cleanliness

    Power Plant

    Thank you for using our generator equipment,

    We would be delighted to serve you.Recently one of our customers didnt take strict control of cleanliness duringinstallation, which leads to great damage to the generator. During accidentinspection we found metal remains inside terminal box. In view of this situation, weremind all customers which are under installing and running take great attention tothis issuer

    1. Installation process, half year and one year Maintenance must be strictlyaccording to rules, and supervision to strengthen self-control.2. make sure there are no metal remains or other debris in the stator and terminal3. Cleanliness inspection should take under strict regualtations.All parties should

    take part in the inspection and signature for recognition .

    Please reply when received

    Thanks & Regards!Power plant: signature: date:

    Ret No 021-64633745 or 021-64620738 Receiver Hai Bing Zhang or Feng Wei Thanks

  • 7/28/2019 660MW Generator

    67/87

    -FAQCP

    Page 67 of 87

    600MW

    42. (Wind pressure test)

    RequirementsThe test should operate after the Stator winding AC/DC test. Make sure that all

    the pipes which connected the generator are finished.Gland oil system is run.

    0.31MPa 24h,

    1.7m/24h

    Requirements: Use the dry and clean Compressed air. Use pressure gauge which pressure level

    is 0.31MPa. Test time 24h. If the air leakage not greater than 1.7m / 24h then the

    test is qualified.

    (On-site inspection)

    Attached the test report)

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    Part 4 Oil Water & Hydrogen system

    1. (hydrogen system)1) 7 3

    2 1

    2)

    Note 1Hydrogen leakage system includes 7 detector devices. Three of seven located at shell

    of three main lead enclosed bus. Two of seven located at shell of center point

    enclosed bus, Remains on each side of EE and TE Lubricating oil pipes.

    2Pay attention to the hydrogen system pipes; check if the hydrogen pipes lowest points

  • 7/28/2019 660MW Generator

    68/87

    -FAQCP

    Page 68 of 87

    600MW

    have drain pipes or leakage detector device. Make sure that all the pipes connected

    with leakage detector devices are installation with decline, and the horizontal pipe

    must be downward-sloping. Recorded all the details

    (On-site inspection)

    ( 7 attached photos take photoes for seven detector points)

    (Signature by four parties)

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)

    2. (oil system)1

    2

    3 27-49

    4

    5

    Note1Install oil system pipes correctly. Make sure that the pipes connected hydrogen

    side turn oil tank is downward-sloping Check to make sure2Oil flushing is

    according to regulation. The quality of Seal Oil must be do the rigorous testing

    before it run into the bearings3pay more attention to the temperature of seal oil the

    temperature arrange from 27to 494Before seal oil system put into use, open

    the bracket of hydrogen oil tank for inspection. Check the Hydrogen return oil tank

    cleanliness and the float valves is work smoothly. 5Install the defoaming tank

    alarm system and put into operation as soon as possible,.

    (On-site inspection)

    (Signature by four parties)

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    (date)3. (water system)

  • 7/28/2019 660MW Generator

    69/87

  • 7/28/2019 660MW Generator

    70/87

    -FAQCP

    Page 70 of 87

    600MW

    attach water & oil quality test reports.

    Signature by four parties

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    date

    4.(Site commissioning of the equipments manufacturers confirmation)

    The device name

    Equipments are

    adjust completed or

    not

    factory

    representatives

    power plant

    date

    Hydrogenoilwater system

    Radiofrequency apparatus

    Hydrogen gas dryers

    Thermal insulation device

    Leaking hydrogen monitor

    Humidity Monitor

    Hydrogen purity meter

    Hydrogen cycling fan

    Excitation systems

    Exciting transformer

    Leakage protector

  • 7/28/2019 660MW Generator

    71/87

  • 7/28/2019 660MW Generator

    72/87

  • 7/28/2019 660MW Generator

    73/87

    -FAQCP

    Page 73 of 87

    600MW

    Seal oil temperature (keep oil temperature) , Advice power plant

    owner to adjust temperature of generator operation oil as low as possible which

    according to the condition of vibration of generator.

    2.

    Check liquid leakage detection device have oil leakage phenomenon. If find there

    much oil leakage phenomenon, must ask power plant owner stop operation and find

    result.

    (on-site inspection)______________________________

    (Signature by four parties)

    (Power plant Representative)

    (Installation Company)

    (Supervision Company)

    TFA

    6. --Water system assembly installationinstallation of water pipes

    a. X Z

    0.302.375 3.902.0166

    38x3 1.5

    X Z 5

    4

    a. Inspections whether the stator cooling water pipes which connect stator main lead terminals

    (position X) and bottom of TE side of water manifold pipe (position Z) are installed according to

    the drawing of turbine generator flange interface 0.302.375 and stator cooling water system

  • 7/28/2019 660MW Generator

    74/87

    -FAQCP

    Page 74 of 87

    600MW

    3.902.0166.(the diameter ofoutlet cooling water pipers connects terminal box must be 38x3, the

    diameter of the elbow 1.5 diameter of straight pipe. The lengths of the pipes which connect

    position X to position Z must be 5m and the use of elbow must be 4 pics)

    b.

    Operating parameters of stator cooling water

    55 m3/h

    Rated flow of Stator winding cooling water55 m3/h

    44 m3/h80%

    Low alarm of Stator winding cooling water44 m3/h80% of rated flow

    38.5 m3/h70%

    Low-low alarm of Low alarm of Stator winding cooling water(protection of without

    water ) 38.5 m3/h70%of rated flow

    DCS (attached photos of DCS )

    c

    Exhaust the air inside the Stator winding before run the generator

    To prevent parallel rings gas blocking, take measures to exhaust the air inside the Stator

    winding system during stator winding system flooding water. The Details according to the manual

    book of stator cooling water system operation reference to second section of chapter one.

    Strict accordance with the requirements of manual book only in that way can prevent the gas

    blocking. All the measures you take to prevent the gas blocking which according to the

    manual book not only used for run a new generator but also for either generator which have

    let the cooling water in to the stator winding should take the measures to exhaust the air

  • 7/28/2019 660MW Generator

    75/87

  • 7/28/2019 660MW Generator

    76/87

    -FAQCP

    Page 76 of 87

    600MW

  • 7/28/2019 660MW Generator

    77/87

    -FAQCP

    Page 77 of 87

    600MW

  • 7/28/2019 660MW Generator

    78/87

    -FAQCP

    Page 78 of 87

    600MW

  • 7/28/2019 660MW Generator

    79/87

    -FAQCP

    Page 79 of 87

    600MW

  • 7/28/2019 660MW Generator

    80/87

    -FAQCP

    Page 80 of 87

    600MW

    7. Attachments ofspecification of prevent seal oil into frame

  • 7/28/2019 660MW Generator

    81/87

    -FAQCP

    Page 81 of 87

    600MW

  • 7/28/2019 660MW Generator

    82/87

    -FAQCP

    Page 82 of 87

    600MW

  • 7/28/2019 660MW Generator

    83/87

  • 7/28/2019 660MW Generator

    84/87

  • 7/28/2019 660MW Generator

    85/87

  • 7/28/2019 660MW Generator

    86/87

    -FAQCP

    Page 86 of 87

    600MW

  • 7/28/2019 660MW Generator

    87/87

    -FAQCP

    600MW