610 – 10TH AVENUE VANCOUVER, B.C. · VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER,...
Transcript of 610 – 10TH AVENUE VANCOUVER, B.C. · VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER,...
Reference: 30-1044
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
BCCA CYCLOTRON ADDITION
VANCOUVER CANCER CENTRE 610 – 10TH AVENUE VANCOUVER, B.C.
OPERATING & MAINTENANCE MANUAL
FOR
MECHANICAL SYSTEMS
MECHANICAL CONSULTANT - MECHANICAL CONTRACTOR -
Stantec Consulting Ltd. 1100 – 111 Dunsmuir Street Vancouver, B.C. V6B 6A3 Phone: (604) 696-8000 Fax: (604) 696-8100 Keith Plumbing & Heating Co. Ltd. 1 – 40 Gostick Place North Vancouver, B.C. V7M 3G2 Phone: (604) 980-4891 Fax: (604) 980-4756
PREPARED BY - Western Mechanical Services (1977) Ltd. 8576 Fraser Street Vancouver, BC, V5X 3Y3 Phone: (604) 324- 1434 Fax: (604) 324 -8263
DATE PREPARED - NOVEMBER 2009
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
TABLE OF CONTENTS
TAB SECTION
1.1 Mechanical Drawing Schedule
1.2 Description of Systems
1.3 Operating Division
1.4 Maintenance and Lubrication Division
1.5 Equipment Supplier and Contractor Schedule
2.0 Guarantees, Certificates and Reports
2.1 Valve Tag List
2.3 Chemical Cleaning and Treatment
3.0 Equipment Shop Drawings and Maintenance Data
1. Air Handling Unit
2. Steam Humidifier
3. Steam Separator
4. Fans
5. Louvres
6. Fire Dampers
7. Grilles, Registers & Diffusers
8. Single Duct Terminal Unit
9. Circulating Pumps
10. Unit Heater
11. Force Flow Cabinet Heater
12. Air Cooled Scroll Chiller
13. Plumbing Fixtures & Trim
14. Acid Neutralizer
15. Drains
16. Storm Pumps
17. Medical Gas
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
TABLE OF CONTENTS
TAB SECTION
18. Vibration Isolation
19. Fire Protection
20. Hydronic System Feeder
4.0 Balancing Report
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
1.5 EQUIPMENT SUPPLIERS AND CONTRACTOR SCHEDULE
EQUIPMENT MAKE SUPPLIER / CONTRACTOR
Air Handling Unit Air Cooled Scroll Chiller York Custom
HVAC Systems & Solutions Ltd. 2085 Brigantine Drive Coquitlam, B.C. V3K 7B8 Phone: (604) 777-0266 Fax: (604) 777-0268
Steam Humidifier Pure
HVAC Systems & Solutions Ltd. 2085 Brigantine Drive Coquitlam, B.C. V3K 7B8 Phone: (604) 777-0266 Fax: (604) 777-0268
Steam Separator Armstrong
Preston Phipps Inc. #214 – 4259 Canada Way Burnaby, B.C. V5G 1H1 Phone: (778) 328-9888 Fax: (778) 328-9889
Fans Greenheck
E.H. Price Limited 8038 Glenwood Drive Burnaby, B.C. V3N 5E9 Phone: (604) 777-1712 Fax: (604) 777-1713
Louvres,Fire Dampers Ruskin
Progressive Air Products Ltd. 1200 Cliveden Avenue Delta, B.C. V3M 6G4 Phone: (604) 516-6007 Fax: (604) 516-6009
Grilles, Registers & Diffusers Single Duct Terminal Units Titus
Progressive Air Products Ltd. 1200 Cliveden Avenue Delta, B.C. V3M 6G4 Phone: (604) 516-6007 Fax: (604) 516-6009
Circulating Pumps Armstrong
Universal Supply Co. Ltd. 2835 E. 12th Avenue Vancouver, B.C. V5M 4P9 Phone: (604) 253-4000 Fax: (604) 253-4003
Unit Heater,Force Flow Heater Rosemex
HVAC Systems & Solutions Ltd. 2085 Brigantine Drive Coquitlam, B.C. V3K 7B8 Phone: (604) 777-0266 Fax: (604) 777-0268
Plumbing Fixtures & Trim
Drains
A/Standard,Sloan,Bemis,Toto Delta,McGuire,Zurn,Fiat Haws,Guardian,Franke
Wolseley Mechanical Group 5950 Kingsland Drive Burnaby, B.C. V5B 4W7 Phone: (604) 205-2900 Fax: (604) 294-5685
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
1.5 EQUIPMENT SUPPLIERS AND CONTRACTOR SCHEDULE
EQUIPMENT MAKE SUPPLIER / CONTRACTOR
Acid Neutralizer SMS
Wolseley Mechanical Group 5950 Kingsland Drive Burnaby, B.C. V5B 4W7 Phone: (604) 205-2900 Fax: (604) 294-5685
Storm Pumps Myers
E.P. Engineered Pump Systems Ltd. 1635 Industrial Avenue Port Coquitlam, B.C. V3C 6M9 Phone: (604) 552-7900 Fax: (604) 552-7901
Medical Gas Peerless
Peerless Engineering Sales Ltd. 4015 East First Avenue Burnaby, B.C. V5C 3W5 Phone: (604) 659-4100 Fax: (604) 659-4122
Vibration Isolation Mason
Vibra-Sonic Control 4004 Gravely Street Burnaby, B.C. V5C 3T6 Phone: (604) 294-9495 Fax: (604) 294-8033
Fire Protection Viking
Viking Fire Protection 7885 North Fraser Way Unit 140 Burnaby, B.C. V5J 5M7 Phone: (604) 324-7122 Fax: (604) 324-8260
Hydronic System Feeder Axiom
Axiom Industries Ltd. 2615 Wentz Avenue Saskatoon, SK S7K 5J1 Phone: (306) 651-1815 Fax: (306) 242-3373
Balancing & Testing -
K.D. Engineering Co. Ltd 239 – East 6th Avenue Vancouver, B.C. V5T 1J7 Phone: (604) 872-8651 Fax: (604) 872-8653
Operating & Maintenance Manuals Commissioning -
Western Mechanical Services (1977) Ltd. 8576 Fraser Street Vancouver, B.C. V5X 3Y3 Phone: (604) 324-1434 Fax: (604) 324-8263
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
1.1 MECHANICAL DRAWING SCHEDULE
DWG # TITLE
M-001 SITE PLAN, DRAWING LIST & HVAC LEGEND
M-101 EXISTING PET SCAN & MRI EQUIP. RELOCATION PLAN – ROOF
PLAN
M-102 EXISTING PET SCAN EQUIP. RELOCATION PLAN – MAIN FLOOR
M-201 HVAC – DUCTWORK PLAN – MAIN FLOOR PLAN
M-202 HVAC – PIPING PLAN – MAIN FLOOR PLAN
M-203 HVAC – SENSOR & PRESSURIZATION – MAIN FLOOR PLAN
M-204 HVAC – AIRFLOW QUANTITIES – MAIN FLOOR PLAN
M-301 HVAC – EQUIPMENT – MECHANICAL ROOM PLAN
M-302 HVAC – PIPING – MECHANICAL ROOM PLAN
M-401 STEAM & CONDENSATE RETURN PLAN – INTEGRATION TO
EXISTING FACILITY.
M-402 STEAM & CONDENSATE RETURN PLAN – INTEGRATION TO
EXISTING FACILITY.
M-501 HVAC – ROOF PLAN
M-601 HEATING & COOLING SCHEMATIC – BUILDING LOAD
M-602 STEAM & CONDENSATE RETURN SCHEMATIC
M-603 EXHAUST CONCEPTUAL FLOW SCHEMATIC
M-604 PROCESS COOLING LOAD SCHEMATIC
M-701 MECHANICAL SCHEDULES
M-702 MECHANICAL SCHEDULES
M-703 MECHANICAL SCHEDULES
M-704 MECHANICAL SCHEDULES
M-705 MECHANICAL SCHEDULES
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
1.1 MECHANICAL DRAWING SCHEDULE
DWG # TITLE
M-801 MECHANICAL DETAILS
M-802 MECHANICAL DETAILS
M-803 MECHANICAL DETAILS
M-804 MECHANICAL DETAILS
BCCA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE – 610 – 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone – (604) 324-1434, Fax – (604) 324-8263
1.1 PLUMBING DRAWING SCHEDULE
DWG # TITLE
P-001 SITE PLAN, DRAWING LIST & PLUMBING LEGEND
P-101 PLUMBING – FOUNDATION PLAN
P-102 PLUMBING – MAIN FLOOR PLAN
P-103 PLUMBING – MECHANICAL ROOM
P-104 FIRE PROTECTION – MAIN FLOOR PLAN
P-105 FIRE PROTECTION – MECHANICAL ROOM
P-106 EXISTING SERVICES
P-107 EXISTING SERVICES
P-201 PLUMBING/ FIRE PROTECTION DETAILS
P-202 PLUMBING/FIRE PROTECTION DETAILS
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
1
1.2 DESCRIPTION OF SYSTEMS This section covers descriptions of the mechanical equipment and systems at the BCCAA Cyclotron Vancouver Cancer Centre
Addition building in Vancouver, British Columbia.
The following mechanical equipment and systems are described:
Heating Ventilating and Air Conditioning Systems
AHU-01 Cyclotron and Support Area
AHU-02 Production Area and Research Development Area
AHU-03 PET Scan and General Purpose Area
AHU-04 Existing PET Scan
Chilled Water Plant - Existing Centrifugal Packaged Water Chiller CH-01 and New air-Cooled Scroll Type
Packaged Water Chiller CH-02
HVAC Chilled Water Piping System
Process Chilled Water Piping System
Heat Exchangers HEX-01 and HEX-02 and Hot Water Heating System
Steam and Condensate Piping Systems and Condensate Return Unit CRU-01
General Exhaust Ventilation Systems Nuclear Facility Class II Areas
General Exhaust Ventilation Systems Other Areas
Fume Hood Exhaust Systems
Hot Cells Exhaust Ventilation Systems
Hi Plume Dilution Fans EF-02A, EF-02B and EF-02C
Automatic Temperature Control System
Disclaimer: The information contained herein is intended to provide general guidelines only to the building operators and maintainers and an overview to the building operators and maintainers so they may start with a general understanding of the system components and that new O & M staff may study to develop a basic understanding of the major mechanical systems. The descriptions of the mechanical systems are written by technical writers who did not design, install or provide any equipment for the mechanical systems installed in this project. The descriptions represent our best understanding and these have been reviewed by the engineering firms that carried out the mechanical system design. The selection of material provided by the mechanical subcontractor to us is determined by the mechanical consultants. Western Mechanical Services is responsible to describe the systems based on the contract documents at the time of construction, unless clarification and contract adjustments have been made and updated information provided before the guidelines are completed. Contact lists of the suppliers, subtrades and system designers are provided in Section 1-5 so that any additional information required may be obtained from the actual companies involved during the design and construction phase. We recommend that building operators and maintainers contact these suppliers before finalizing operating and maintenance programs for their equipment and systems to ensure that they will obtain optimum performance and efficiency.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
2
Plumbing and Drainage Systems
Domestic Cold Water Potable and Non Potable Water Systems
Domestic Hot Water Piping System
Storm Drainage System and Storm Sump Pumps
Sanitary Drainage System and Sanitary Sump Pumps
Fire Protection System
For additional information regarding individual items of equipment, refer to Section 3.0: Equipment Shop Drawings and Maintenance Data.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
3
AHU-01 Cyclotron and Support Area
Air Handling Unit AHU-01 is a packaged heating ventilating and mechanical cooling unit that is located in the Mechanical
Room. The unit delivers 100 % outdoor air supply through a low velocity variable air volume (VAV) supply duct system to
the supply air diffusers in the Cyclotron and Support Areas.
A. Outdoor air is drawn into the system through an Outdoor Air Intake Louvre above the roof level.
B. The outdoor air is conveyed from the louvre to the intake of the air handling unit through an acoustically lined Air Intake Plenum (air chamber) that also serves Air Handling Units AHU-02 and AHU-03.
C. A set of Motorized Outdoor Air Dampers is provided at the inlet to the air handling unit to isolate the unit from
AHU-02 and AHU-03 and to prevent uncontrolled outdoor air from entering the building when the unit is shut
down.
D. As the outdoor air enters the unit it passes through a bank of 2-inch thick MERV 7 pleated type Prefilters that
remove dirt and dust from the airstream.
E. The air next passes through a bank of 12-inch thick MERV-13 rigid type Air Filters that remove fine dirt and dust
from the air stream.
F. A Hydronic (Hot Water Glycol Solution) Heating Coil is used to heat the air passing through the unit when
heating is required.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
4
G. Propylene glycol solution heating fluid is conveyed from the main hydronic heating piping system to and from the
heating coil through the Hydronic Heating Supply and Return Piping.
H. A Coil Circulating Pump P-AHU-1 circulates heating fluid through the heating coil.
I. A Control Valve on the hydronic heating fluid supply piping controls the amount of heating output for the coil by
modulating the temperature of the fluid supplied to the coil.
J. A Chilled water glycol solution cooling coil cools the air when mechanical cooling is required.
K. The chilled water is conveyed from the main chilled water piping system to and from the cooling coil through the
Chilled water glycol solution supply and Return Piping.
L. A Control Valve on the chilled water glycol solution supply piping controls the cooling output of the coil by
modulating the flow of chilled water through the coil.
M. The belt-driven centrifugal Supply Air Fan draws the air through the air handling unit components and delivers the
air through the supply air ductwork to the Cyclotron and Support Areas.
N. The fan speed for the supply air fan is modulated electronically by a Variable Frequency Drive.
O. The supply air is conveyed from the air handling unit to the branch supply ducts by the Main Supply Air Duct. P. The air is conveyed from the main supply duct to the supply air outlets by the Branch Supply Ducts. There are a
total of three branch supply ducts; one serves the north end of the Cyclotron Vault, one serves the Equipment Room
105 and one serves the corridor.
Q. Each of the branch supply ducts is provided with one or more fast-acting Venturi type Variable Air Volume (VAV) Supply Air Terminal Boxes, each with a motorized damper that controls the amount of air delivered to each zone
between a minimum and a maximum air volume.
R. A Hydronic Reheat Coil tempers the air when required to maintain the space temperature in each zone when
heating is required.
S. A modulating Control Valve on the heating supply piping connection to each reheat coil controls the space
temperature by controlling the flow of glycol heating fluid through each coil.
T. The air is delivered into each zone through Supply Air Diffusers located in the ceiling.
Control of AHU-01 Cyclotron and Support Area Air Handling Unit
The air handling system operates continually (24 / 7).
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
5
AHU-02 Production Area and Research Development Area
Air Handling Unit AHU-02 is a packaged heating ventilating and mechanical cooling unit that is located in the Mechanical
Room. The unit delivers 100 % outdoor air supply through a low velocity variable air volume (VAV) supply duct system to
the supply air diffusers in the Production Area and Research Development Area.
A. Outdoor air is drawn into the system through an Outdoor Air Intake Louvre above the roof level.
B. The outdoor air is conveyed from the louvre to the intake of the air handling unit through an acoustically lined Air Intake Plenum (air chamber) that also serves Air Handling Units AHU-01 and AHU-03.
C. A set of Motorized Outdoor Air Dampers is provided at the inlet to the air handling unit to isolate the unit from
AHU-01 and AHU-03 and to prevent uncontrolled outdoor air from entering the building when the unit is shut
down.
D. As the outdoor air enters the unit it passes through a bank of 2-inch thick MERV 7 pleated type Prefilters that
remove dirt and dust from the airstream.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
6
E. The air next passes through a bank of 12-inch thick MERV-13 rigid type Air Filters that remove fine dirt and dust
from the air stream.
F. A Hydronic (Hot Water Glycol Solution) Heating Coil is used to heat the air passing through the unit when
heating is required.
G. Glycol solution hydronic heating Supply and Return Piping conveys the heating fluid to and from the heating coil.
H. A Control Valve on the hydronic glycol solution piping modulates to control the flow of glycol heating solution
circulating through heating coil.
I. A Steam Injection Humidifier is provided in the air handling unit between the heating and cooling coils to
maintain the relative humidity in the supply air at a setpoint level.
J. A Chilled water glycol solution cooling coil cools the air when mechanical cooling is required.
K. Chilled water glycol solution supply and Return Piping conveys chilled water to and from the cooling coil.
L. A Control Valve on the chilled water piping modulates to control the flow of chilled water circulating through the
cooling coil.
M. The belt-driven centrifugal Supply Air Fan draws the air through the air handling unit components and delivers the
air through the supply air ductwork to the Production and Research Development Areas.
N. The fan speed for the supply air fan is modulated electronically by a Variable Frequency Drive.
O. The air leaving the supply fan passes through a Discharge Diffuser that evens the air velocity from side to side and
from top to bottom.
P. The air passes through a bank of HEPA Air Filters that trap smaller pollutants and particles and remove them from
the airstream.
Q. The supply air is conveyed from the air handling unit to the branch supply ducts by the Main Supply Air Plenum (air chamber).
R. The air is conveyed from the main supply duct to the supply air outlets by the Branch Supply Ducts. There are a
total of five branch supply ducts; one serves the south end of the Cyclotron Vault and the (future) Theodorico Area,
one serves the Production Cyclotron Control Area, one serves the Anteroom, one serves the Production Office 107
and one serves the FDG Packaging Area 106.
S. Each of the branch supply ducts is provided with one or more fast-acting Venturi type Variable Air Volume (VAV) Supply Air Terminal Boxes, each with a motorized damper that controls the amount of air delivered to each zone
between a minimum and a maximum air volume.
T. A Hydronic Reheat Coil tempers the air when required to maintain the space temperature in each zone when
heating is required.
U. A modulating Control Valve on the heating supply piping connection to each reheat coil controls the space
temperature by controlling the flow of glycol heating fluid through each coil.
V. The air is delivered into each zone through Supply Air Diffusers located in the ceiling.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
7
Control of AHU-02 Production Area and Research Development Area
The air handling system operates continually (24 / 7).
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
AHU-03 PET Scan and General Purpose Area Air Handling Unit AHU-03 is a packaged heating ventilating and mechanical cooling unit that is located in the Mechanical
Room. The unit delivers 100 % outdoor air supply through a low velocity variable air volume (VAV) supply duct system to
the supply air diffusers in the PET Scan and General Purpose Areas.
A. Outdoor air is drawn into the system through an Outdoor Air Intake Louvre above the roof level.
B. The outdoor air is conveyed from the louvre to the intake of the air handling unit through an acoustically lined Air Intake Plenum (air chamber) that also serves Air Handling Units AHU-01 and AHU-02.
C. A set of Motorized Outdoor Air Dampers is provided at the inlet to the air handling unit to isolate the unit from
AHU-01 and AHU-02 and to prevent uncontrolled outdoor air from entering the building when the unit is shut
down.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
8
D. As the outdoor air enters the unit it passes through a bank of 2-inch thick MERV 7 pleated type Prefilters that
remove dirt and dust from the airstream.
E. The air next passes through a bank of 12-inch thick MERV-13 rigid type Air Filters that remove fine dirt and dust
from the air stream.
F. A Hydronic (Hot Water Glycol Solution) Heating Coil is used to heat the air passing through the unit when
heating is required.
G. Glycol solution hydronic heating Supply and Return Piping conveys the heating fluid to and from the heating coil.
H. A Control Valve on the hydronic glycol solution piping modulates to control the flow of glycol heating solution
circulating through heating coil.
I. A Coil Circulating Pump P-AHU-2 circulates heating fluid through the heating coil.
J. A Steam Injection Humidifier is provided in the air handling unit between the heating and cooling coils to
maintain the relative humidity in the supply air at a setpoint level.
K. A Chilled water glycol solution cooling coil cools the air when mechanical cooling is required.
L. Chilled water glycol solution supply and Return Piping conveys chilled water to and from the cooling coil.
M. A Control Valve on the chilled water piping modulates to control the flow of chilled water circulating through the
cooling coil.
N. The belt-driven centrifugal Supply Air Fan draws the air through the air handling unit components and delivers the
air through the supply air ductwork to the Production and Research Development Areas.
O. The fan speed for the supply air fan is modulated electronically by a Variable Frequency Drive.
P. The supply air is conveyed from the air handling unit to the main branch supply ducts by the Main Supply Air Duct.
Q. The supply air is conveyed from the main supply air duct to the branch supply ducts by two Main Branch Supply Air Ducts. The First Main Branch Supply Duct serves the General Purpose Areas.
R. The Second Main Branch Supply Duct serves the PET Scan Areas.
S. The main supply air duct serving the PET Scan Area has a Steam Injection Humidifier that is used to maintain the
relative humidity in the PET Scan areas at a setpoint R.H.
T. The air is conveyed from the General Purpose main supply duct to the supply air outlets by four Branch Supply Ducts. One serves the Analyst Room; one serves the Hot Waiting Sedation and the Hot Waiting area; one serves the
U. The air is conveyed from the PET Scan main supply duct to the supply air outlets by three Branch Supply Ducts.
One serves the PET Scan Room 122, one serves the Control Room and one serves the Equipment Mechanical
Room.
V. Each of the branch supply ducts is provided with one or more standard Variable Air Volume (VAV) Supply Air Terminal Boxes, each with a motorized damper that controls the amount of air delivered to each zone between a
minimum and a maximum air volume.
W. A Hydronic Reheat Coil tempers the air when required to maintain the space temperature in each zone when
heating is required.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
9
X. A modulating Control Valve on the heating supply piping connection to each reheat coil controls the space
temperature by controlling the flow of glycol heating fluid through each coil.
Y. The air is delivered into each zone through Supply Air Diffusers located in the ceiling.
Control of AHU-03 PET Scan and General Purpose Area
The air handling system operates continually (24 / 7).
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
AHU-04 Existing PET Scan
Air Handling Unit AHU-04 is an existing packaged heating ventilating and mechanical cooling unit, located in the existing
building. The unit delivers 100 % outdoor air supply through a low velocity variable air volume (VAV) supply duct system
to the supply air diffusers in the existing PET Scan Areas.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
10
Chilled Water Plant - Existing Centrifugal Packaged Water Chiller CH-01 and New Air Cooled Scroll Type Packaged Water Chiller CH-02 and Primary Chilled Water Piping
The chilled water plant consists of the existing centrifugal packaged water chiller and the new scroll type water chiller. The
existing chiller CH-01, with a cooling capacity of 125 Tons refrigeration is located on the Penthouse Roof and the new chiller
CH-02, with a cooling capacity of 60 Tons refrigeration is located on the lower roof. Both chillers use Refrigerant
HCFC-22.
Chilled water is required for the chilled water cooling coils in the four air handling units AHU-01 through AHU-04 (three
new units and one existing unit) and also for the process cooling equipment. A 30 % propylene glycol (antifreeze) solution is
circulated through the chilled water equipment.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
11
A two-pipe supply / return secondary chilled water piping system circulates chilled water solution through the HVAC chilled
water cooling coils for air handling units AHU-01 through AHU-04 .
A. The New 60 Ton Air-Cooled Scroll Chiller is connected in parallel with the existing packaged water chiller so that
either chiller or both chillers may be operated at any time as required satisfying the demand for cooling. The
components for the new chiller include hermetic scroll type refrigeration compressors, brazed plate stainless steel
evaporator, outdoor air-cooled condenser heat exchangers, condenser fans and microprocessor control centre all
enclosed in a galvanized steel cabinet. The chilled water is used for the chilled water cooling coils in the air
handling units or for the process chilling equipment.
B. The Existing 125 Ton Packaged Water Chiller connected in parallel with the new chiller produces chilled water
that is used for the chilled water cooling coils in the air handling units or for the process chilling equipment.
C. Primary Chilled Water Circulating Pumps PCHW-01 and PCHW-02 (one designated as duty pump and the other as
standby) circulate chilled water solution through the packaged water chillers and the primary circuit piping loop.
D. The speed for each of the pump motors is modulated electronically by a Variable Frequency Drive.
E. A two-position Control Valve is provided on the chilled water return piping connection to each chiller so that either
chiller may be isolated form the chilled water piping system when the chiller is idle. Control Valve CH-01CV is
located on the primary chilled water return piping to Chiller CH-01 and Control Valve CH-02CV is located on the
primary chilled water return piping to Chiller CH-02.
F. A Chilled Water Storage Tank ST-01 is provided on the primary chilled water piping circuit to provide some
storage of chilled water in the primary piping.
G. A Chemical Pot Feeder is provided on the primary chilled water piping to make provision for adding chemical
treatment to the chilled water to maintain water quality (e.g. to prevent corrosion of piping and equipment).
H. A Sidestream Filter is provided to remove impurities from the chilled water solution.
I. A Glycol Makeup Station with pressure reducing valve is connected into the piping system to make provision for
adding glycol solution to replace any that is lost from the piping system through leakage or drainage.
J. An Expansion Tank ET-02 is connected into the piping system to make provision for normal thermal expansion
and contraction of the chilled water solution contained inside the closed piping system as its temperature changes.
K. An Air Separator is provided on the primary chilled water piping connection to the secondary circuits to separate
air entrapped in the chilled water solution so that it may be removed through an air vent to reduce the likelihood of
corrosion of piping or equipment.
L. The Secondary Chilled Water Supply Piping connects into the primary chilled water circuit. The secondary
chilled water supply piping conveys chilled water solution from the primary chilled water piping connection to the
chilled water cooling coils in the air handling units.
M. The HVAC Chilled Water Circulating Pumps PCHW-03 or PCHW-04 (duty / standby) draw chilled water
solution from the primary chilled water piping circuit and circulate it to the four chilled water cooling coils.
N. Branch Chilled Water Supply& Return Lines convey chilled water from the HVAC main chilled water supply
piping through the individual chilled water cooling coils in Air Handling Units AHU-01 through AHU-04.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
12
O. A modulating Control Valve is provided on the branch chilled water supply piping to each air handling unit cooling
coil to control the amount of cooling provided by each unit.
P. A Pressure Relief Control Valve is provided to bypass chilled water solution directly from the supply piping to the
return pumping during times when there is very low demand for cooling and the control valves for all the cooling
coils is closed. The bypass control valve ensures that there is always at least a minimum amount of water flowing
through the active secondary circulating pump.
Q. The Main HVAC Chilled Water Return Piping conveys the chilled water returning form the coils back to the
primary chilled water return piping circuit.
R. Chilled water from the process chilled equipment is conveyed from the process chilled water equipment to the main
chilled water piping circuit through the Process Main Chilled Water Return Piping.
S. Chilled water from the main chilled water supply piping circuit is conveyed to the process chilled water equipment
through the Process Main Chilled Water Supply Piping.
T. The flow of chilled water into the process chilled water piping system is controlled by a Domestic Cold Water Supply Control Valve that is installed on a domestic cold water makeup line. There is a drain pressure valve
installed on a drain line that drains out an equivalent amount of water from the process equipment chilled water
piping. For information regarding the domestic cold water refer to the description regarding the process chilled
water piping system.
U. During an emergency chilled water shortage, the Supply Mixing Valve modulates open to accept a portion of the
process chilled water supply from the domestic cold water backup system.
V. In case the supply mixing valve modulates to the full open position then the Primary Chilled Water Supply Isolation Control Valve opens to isolate the process chilled water supply piping from the primary chilled water
supply piping system.
W. During an emergency chilled water shortage, the Return Mixing Valve modulates open to allow a portion of the
process chilled water return water to be discharged to drain.
X. In case the return mixing valve modulates to the full open position then the Primary Chilled Water Return Isolation Control Valve opens to isolate the process chilled water return piping from the primary chilled water
return piping system.
Y. A two position Three Way Control Valve is installed on the chilled water supply piping from each chiller to alleviate
chilled water temperature fluctuations during the periods when either chiller is off. Control Valve CH-01-CV serves
Chiller CH-01 and Control Valve CH-02-CV serves Chiller CH-02.
Z. A temperature sensor installed in the chilled water supp0ly line from each chiller monitors the chilled water
temperature as an input signal for controlling the two three-way control valves (see previous item) to allow flow
through the inactive chiller when the water temperature rises above a setpoint.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
13
Control of Chilled Water Plant - Existing Centrifugal Packaged Water Chiller CH-01 and New Air Cooled Packaged Water Chiller CH-02 and Primary Chilled Water Piping For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
14
Secondary Chilled Water Piping for Process Systems
A two-pipe supply / return secondary chilled water piping system circulates chilled water solution through the Process chilled
water equipment.
A. The Secondary Process Chilled Water Supply Piping connects into the primary chilled water circuit. The
secondary chilled water supply piping conveys chilled water solution from the primary chilled water piping
connection to the process chilled water cooling equipment.
B. During an emergency chilled water shortage, the Return Mixing Valve modulates open to allow a portion of the
process chilled water return water to be discharged to drain.
C. During an emergency chilled water shortage, the Supply Mixing Valve modulates open to accept a portion of the
process chilled water supply from the domestic cold water backup system.
D. The Process Chilled Water Circulating Pumps PCHW-05 or PCHW-06 (duty / standby) draw chilled water
solution from the primary chilled water piping circuit and circulate it to the process chilled water cooling equipment.
E. The motor speeds for the duty chilled water circulating pump is modulated electronically by a Variable Frequency Drive.
F. A Branch Chilled Water Supply Line conveys chilled water from the process main chilled water supply piping to
the individual items of chilled water cooling equipment, including the Cyclotron heat exchanger, the new PET Scan
PET chiller and WCS chiller, the existing PET Scan chillers and the existing MRI chiller.
G. A modulating Control Valve is provided on the branch chilled water supply piping to individual chiller or heat
exchanger on the secondary piping circuit to control the amount of cooling provided.
H. The Cyclotron Heat Exchanger cools the chilled water equipment serving the cyclotron.
I. The Existing PET Scan Heat Exchanger cools the existing chilled water equipment serving the PET Gantry
J. The Existing CT Gantry Heat Exchanger cools the existing chilled water equipment serving the CT Gantry
K. The New PET Scan Heat Exchanger cools the new chilled water equipment serving the PET Gantry
L. The New CT Gantry Heat Exchanger cools the new chilled water equipment serving the CT Gantry
M. The MRI Heat Exchanger cools the chilled water equipment serving the MRI equipment
N. The branch chilled water supply piping serving the existing MRI chiller has two Secondary Chilled Water Circulating Pumps (duty / standby) PCHW-07 and PCHW-08 that circulate chilled water through the heat
exchanger.
O. A Pressure Bypass Control Valve FCV-03 is provided to bypass chilled water solution directly from the supply
piping to the return pumping during times when there is very low demand for process cooling and the control valves
for all the process equipment are closed. The bypass control valve ensures that there is always at least a minimum
amount of water flowing through the active secondary circulating pump.
P. The Branch Chilled Water Return Piping Connections to the process cooling equipment convey the return water
from each item to the main process chilled water return piping.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
15
Q. The Main Process Chilled Water Return Piping conveys the chilled water returning from the process equipment
back to the primary chilled water return piping circuit.
R. In case the supply mixing valve modulates to the full open position then the Primary Chilled Water Supply Isolation Control Valve opens to isolate the process chilled water supply piping from the primary chilled water
supply piping system.
S. In case the return mixing valve modulates to the full open position then the Primary Chilled Water Return Isolation Control Valve opens to isolate the process chilled water return piping from the primary chilled water
return piping system.
T. A Backup Domestic Cold Water Supply Line provides an alternative emergency source of cooling water in case of
chilled water system breakdown.
U. The flow of chilled water into the process chilled water piping system is controlled by a Domestic Cold Water Supply Control Valve. There is a drain pressure valve installed on a drain line that drains out an equivalent amount
of water from the process equipment chilled water piping. For information regarding the domestic cold water refer
to the description regarding the process chilled water piping system.
V. The Backup Domestic Cold Water Drain Line conveys process cooling water out of the piping system to a gravity
drain connection to enable domestic cold water to flow through (on a one time basis) through the process cooling
heat exchanges during times when the backup domestic cold water system is being used.
W. The Backup Domestic Cold Water Drain Pressure Valve controls the pressure of the drain piping so that the
domestic water will flow through the cooling heat exchanges during emergency periods when DCW is needed.
Control of Secondary Chilled Water Piping for Process Systems
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
16
Heat Exchangers HEX-01 and HEX-02 and Hot Water Heating System
Two low pressure steam to hot water (glycol solution) Heat Exchangers HEX-01 and HEX-02 located in the Mechanical
Room transfer heat from the steam distribution system to the hot water heating piping system. Heating hot water is used
for the heating coils in the air handling units, for the reheat coils in the supply air ductwork and for the hot water heating
equipment including unit heaters and force flow heaters in the building addition.
A. Heating water (30 % propylene glycol solution) is conveyed from the hot water heating coils in the three air new
handling units AHU-01, AHU-02 and AHU-03 to the primary hot water heating return piping through the Secondary Hot Water Heating Return Piping.
B. Heating water (30 % propylene glycol solution) is conveyed from the secondary hot water heating return piping and
from the hot water reheat coils at the VAV terminal boxes, from the unit heaters and the force flow heaters to the
steam to hot water heat exchangers through the Primary Hot Water Heating Return Piping.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
17
C. Two shell and tube type steam to hot water Heat Exchangers HEX-01 and HEX-02 transfer heat from the 15 psig
steam to the heating water (30 % glycol solution).
D. A Control Valve is provided on the return heating water piping connection to each heat exchanger to isolate each
heat exchanger when required, e.g. when either one is idle or is being serviced. HEX-01CV serves heat exchanger
HEX-01 and HEX-02CV serves heat exchanger HEX-02.
E. The Primary Hot Water (30 % propylene glycol solution) Supply Piping conveys the heated water from the heat
exchanger to the reheat coils, unit heaters, force flow heaters and the secondary piping supply piping to the heating
coils in the air handling units.
F. An Air Separator is provided on the primary chilled water piping connection to the secondary circuits to separate
air entrapped in the chilled water solution so that it may be removed through an air vent to reduce the likelihood of
corrosion of piping or equipment.
G. The Primary Hot Water Heating Circulation Pumps PHW-01 and PHW-02 (primary / standby) circulate
heating water from the heat exchangers out through the primary hot water heating circuit, the force flow heaters and
unit heaters and back to the heat exchangers.
H. The motor speed for each primary heating circulating pump is modulated electronically by a Variable Frequency Drive.
I. Unit Heaters, each with a supply fan and a hot water heating coil provide heating for Mechanical Rooms.
J. Cabinet Unit Heaters, each with a hot water heating coil, a centrifugal supply fan and air grille mounted on a
cabinet provide heating for entrance lobbies.
K. Reheat Coils located in the branch supply ducts at the variable air volume terminal boxes provide controlled heat to
each thermal zone.
L. The amount of heating provided by each reheat coil is modulated by a Control Valve on the hot water heating
supply piping.
M. A Pressure Bypass Control Valve FCV-01 is provided to bypass hot water glycol solution directly from the supply
piping to the return pumping during times when there is very low demand for heating and the control valves for all
the equipment are closed. The bypass control valve ensures that there is always at least a minimum amount of water
flowing through the active primary circulating pump.
N. The Hydronic Heating Coil in Air Handling Unit AHU-01 heats the air passing through the air handling unit when
heating is required as glycol heating fluid is circulated through the tubes in the coil. Air Handling Units AHU-02
and AHU-03 each have a hydronic heating coil that operates in a similar manner.
O. A Coil Circulating Pump is provided on the hot water heating supply piping to each hot water heating coil in the
three new air handling units to circulate glycol heating solution through the coil when heating is required. Coil
Pump P-AHU-1 serves Air Handling Unit AHU-01 heating coil. Pump P-AHU-2 serves Air Handling Unit
AHU-02 heating coil. Pump P-AHU-3 serves Air Handling Unit AHU-03 heating coil.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
18
P. A Three-Way Mixing Control Valve is provided on the supply hot water piping connection to each heating coil.
The modulating three way mixing valves blend water returning from each coil with new heating water from the heat
exchanger to control the amount of heat provided by the coil in each air handling unit. Control Valve AHU1-HCV
serves the heating coil in air handling unit AHU-01. Control Valve AHU2-HCV serves the heating coil in air
handling unit AHU-02. Control Valve AHU3-HCV serves the heating coil in air handling unit AHU-03.
Q. A Heating Fluid (30 % glycol-water solution) Makeup Piping Connection introduces glycol fluid into the piping
system to replace any that is lost through leakage or drainage.
R. A Pressure Reducing Station with pressure reducing valve introduces new heating fluid into the piping system
when any is lost and the pressure inside the piping starts to decrease.
S. An Expansion Tank is used to compensate for the thermal expansion and contraction of the heating fluid inside the
piping system as its temperature changes under different operating conditions.
Control of Heat Exchangers HEX-01 and HEX-02 and Hot Water Heating System
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
19
Steam and Condensate Piping Systems and Condensate Return Unit CRU-01
Steam at a pressure of 150 psi (1034 kPa) is conveyed from the existing steam piping in the existing Mechanical Room
to the new steam equipment in the building addition through a new Steam Main. The steam pressure is reduced to a
pressure of 15 psi (103.4 kPa) at a pressure reducing station consisting of two pressure reducing valves. The new steam
equipment includes the two heat exchangers HEX-01 and HEX-02 and the steam humidifiers associated with Air
Handling Units AHU-02 and AHU-03. Condensate is returned from the new steam equipment to the existing
condensate return system by a new Condensate Return Unit CRU-1 with two condensate return pumps
A. A new Steam Main conveys steam at 150 psi from the existing steam main in the existing Mechanical Room to the
new Mechanical Room.
B. A Steam Pressure Reducing Station with two pressure reducing valves PRV-1 and PRV-2 in the new Mechanical
Room reduce the steam pressure from 150 psi to 15 psi. A normally closed bypass valve is provided on the steam
pressure reducing station so that the steam flow may be manually controlled in case of failure of the pressure
reducing station.
C. A Pressure Relief Valve is provided on the new 15 psi steam main to automatically relieve pressure in the steam
main in case it builds up above a safe pressure limit. The steam relief line is piped to discharge the steam to
outdoors above the roof level.
D. A Branch Steam Supply Line Connection conveys 15 psi steam from the new main steam piping to each item of
equipment including the three humidifiers for AHU-02 and AHU-03, and the two steam to heating water heat
exchangers HEX-01 and HEX-02.
E. The Steam to Heating Hot Water Heat Exchangers HEX-01 & HEX-02 transfer heat from the steam system to
the 30 % glycol (antifreeze) solution used for the hydronic heating system.
F. Three Steam Humidifiers HUM -AHU2A & AHU-2B serving Air Handling Unit AHU-2 and Humidifier HUM-
AHU-3 serving Air Handling Unit AHU-3 are used to humidify the air passing through the two air handling units
when humidification is required. Domestic cold water is piped to the humidifier through a solenoid valve that closes
when the humidifiers are not required and open when humidification is needed. The water entering the humidifier is
vaporized into steam by a steam to water heat exchanger. The steam is injected into the airstream.
G. Condensed steam from each humidifier is collected and discharged through a drain line that terminates with an air
gap to a sanitary drain line. The condensate is cooled before it is discharged into the drainage system as it passes
through a Condensate Cooler that blends domestic cold water with the hot condensate to cool it to a suitable
temperature before it enters the drainage piping.
H. A Steam Control Valve is provided on the steam piping connection to each item of equipment to control the flow
of steam to the required amount.
I. As the steam transfers its heat in the steam equipment it condenses to a liquid state. The condensate draining from
each piece of steam operated equipment flows through a Steam Trap that allows the liquid condensate to flow
freely through the condensate piping but prevents steam from entering.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
20
J. The condensate lines are sloped downward in the direction of flow so that the condensate flows by gravity. The
condensate lines connect together into a single main condensate line that discharges the condensate into the
Condensate Return Unit CRU-1, located in the Mechanical Room on Level 2. The condensate return unit consists
of a condensate return tank that contains and stores condensate and a duplex pump set with float valves. When the
level of condensate in the tank reaches a setpoint level the duty condensate pump is energized and pumps the
condensate out of the tank until the level is pumped down to a lower setpoint level.
K. The condensate is conveyed from CRU-1 to the main condensate return piping through a Pumped Discharge Condensate Line.
L. The Main Condensate Return Line conveys the condensate out of the building.
M. A Steam Separator is provided on the main condensate line from CRU-1 to separate out any steam in the
condensate piping before it is transferred to the main condensate return piping.
N. The steam leaving the steam separator is piped to a Thermostatic Steam Trap that separates condensate and returns
it to CRU-1, while the steam is relieved from the piping system.
Control of Steam and Condensate Piping Systems and Condensate Return Unit CRU-01
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
21
Fume Hood and General Exhaust Ventilation Systems Nuclear Facility Class II Areas
The Laboratory Areas are provided with Variable Air Volume (VAV) Fume Hoods.
The air from each exhaust hood is drawn through a stainless steel laboratory exhaust system to a set of three high plume
dilution exhaust fans located on the roof.
General Exhaust Air from the Laboratory Areas is drawn through exhaust air registers located in the ceiling.
The air leaving each fume hood passes through a pressure independent Venturi type Variable Air Volume (VAV)
Exhaust Air Valve that modulates open or closed to maintain the airflow at a variable air flow set point. The intent is to
maintain a set air velocity at the face of each hood regardless of the sash position. As the sash position is adjusted open
the air flow setpoint is increased to maintain the same setpoint for air velocity and as the sash height is adjusted
downward the air volume set point is decreased.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
22
The air passing through the VAV exhaust air valves serving each ceiling exhaust register or group of exhaust registers in
a particular area general exhaust passes through a pressure independent Venturi type Variable Air Volume (VAV)
Exhaust Air Valve that modulates open or closed to control the total airflow differential between total supply and total
exhaust so as to maintain a specific positive or negative building pressure in one area relative to an adjacent area.
The position of the motorized dampers on the intake plenum (air chamber) for the exhaust fans is varied to maintain a
relatively constant static pressure in the exhaust ductwork.
The amount of makeup and ventilation air supplied into each lab area is modulated to maintain a set differential between
supply and exhaust air volumes so that the positive or negative building pressurization in each area relative to the
adjoining areas does not vary.
A. Nuclear Facility Class II Laboratory Fume Hoods are provided in the Cyclotron Room, Research and
Development Hot Lab, Research Clean Rooms and other rooms and for the Pass Troughs.
B. Each fume hood is provided with a VAV Fume Hood Monitor and Variable Position Sash Sensor that sends a
signal to the fume hood monitor.
C. Each fume hood is connected by a stainless steel welded Laboratory Branch Exhaust Duct through an exhaust air
valve to the main laboratory exhaust ductwork and plenum.
D. The air flow through each fume hood and branch exhaust duct is controlled by a fast acting, pressure independent
VAV Venturi type Laboratory Exhaust Air Valve to maintain a constant air velocity at the face of each fume hood
regardless of the sash position to ensure that air flows from the room into the fume hood and out through the exhaust
ductwork and never reverses from the fume hood back into the occupied areas.
E. Supplementary exhaust air is drawn from Laboratory Areas through Exhaust Air Registers located in the ceiling.
F. The flow of exhaust air through the branch exhaust duct serving a specific area is controlled by an Exhaust Air
Terminal Box with motorized damper that varies the flow between a minimum and maximum air flow.
G. The air flow through each general branch exhaust duct is controlled by a fast acting, pressure independent VAV
Venturi type Laboratory Exhaust Air Valve to maintain the building pressurization in each area relative to
adjacent areas at a desired positive or negative set point.
H. Air is exhausted from the Hot Cells with activated carbon filters.
I. Under normal operating conditions when the radioactivity level of the exhaust air is within a safe limit, the exhaust
air leaving the hot cells is conveyed to the main exhaust air ductwork through a stainless steel Welded Exhaust Duct.
J. A fast reacting pressure independent Laboratory Exhaust Air Valve with motorized damper modulates the air flow
from the hot cells between a minimum and maximum amount.
K. An alternate path for the air leaving the hot cells is available to use during times when the radioactivity level as
sensed by the process instrumentation exceeds a safe limit. During times when the radiation levels are excessive the
air leaving the hot cells is directed through a stainless steel Welded Exhaust Duct to the decay maze.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
23
L. The Decay Maze is an underground concrete air chamber where the exhaust air slowly is drawn back and forth until
its radioactivity level has reduced.
M. Bubble tight Motorized Dampers are provided on the exhaust air duct leading to the decay maze. The dampers are
normally closed and they open up when the decay maze is required.
N. During times when the decay maze is active the flow of exhaust air is controlled by an Exhaust Air Valve.
O. The main exhaust duct, the individual fume hood branch exhaust ducts and the main general exhaust duct from the
non nuclear areas all connect into a Stainless Steel Exhaust Plenum (air chamber) located at the north side of the
Mechanical Equipment Penthouse.
P. Air leaving the exhaust plenum enters a Concrete Trench that runs outside of the north side of the Mechanical
Equipment Penthouse. The concrete trench is lined with Styrofoam board insulation.
Q. The Main Exhaust Duct Riser conveys the air leaving the concrete trench up to the fume exhaust fans on the roof.
The duct riser is located inside a shaft and is externally insulated with aluminium jacket.
R. The concrete trench conveys the exhaust air from the stainless steel exhaust plenum to the Fume Exhaust System on
the roof. The fume exhaust system consists of three high plume dilution type Laboratory Exhaust Fans EF-02A, EF-02B and EF-02C mounted on top of a common Laboratory Bypass Exhaust Air Plenum with two openings,
each with an air intake hood and Motorized Dilution Air Intake Damper CD-02-AB &CD-02-CB that control the
flow of dilution air into the suction side of the three Laboratory Exhaust Fans. As the total airflow from the fume
hoods decreases (e.g. when most of the VAV exhaust dampers are at or near their minimum air flow setting) then
more dilution air is drawn into the total exhaust air flow.
S. The three exhaust fans discharge the air upwards at high velocity through Discharge Cones that increase the
velocity of the air as it leaves the exhaust system to discharge the air as high as possible.
T. A Motorized Intake Damper is provided on the air intake to each fan so that each fan may be isolated from the
other fans when it is idle. Any combination of exhaust fans may operate at any time.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
24
PET Scan and General Exhaust Ventilation Systems Other (Non Nuclear) Lab Areas
The Other (Non Nuclear) Lab Areas including PET Scan and other areas are provided with ventilation and cooling
supply air with Variable Air Volume (VAV) Supply Air Valves that modulate the air flow according to the need for
outdoor air ventilation for the occupants and for cooling. The VAV air valves control the flow of supply air between a
minimum and maximum amount based on thermal requirements
These areas including PET Scan and other areas are provided with Variable Air Volume (VAV) Fume Hoods. General
Exhaust Air from the Non Nuclear Laboratory Areas is drawn through exhaust air registers located in the ceiling.
The air from each group of exhaust grilles in the ceiling of a thermal zone is drawn through Class A sealed galvanized
ductwork that connects into the main stainless steel Laboratory Exhaust Ductwork system that serves the nuclear areas
and the high plume exhaust fans.
The air leaving each fume hood is also drawn through Class A sealed galvanized ductwork that connects into the
stainless steel Laboratory Exhaust Ductwork system and the high plume exhaust fans
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
25
The air passing through the VAV exhaust air valves serving each ceiling exhaust register or group of exhaust registers in
a particular area general exhaust passes through a pressure independent Venturi type Variable Air Volume (VAV)
Exhaust Air Valve that modulates open or closed to control the total airflow differential between total supply and total
exhaust so as to maintain a specific positive or negative building pressure in one area relative to an adjacent area.
A. Air is drawn from the Non Nuclear Areas through Exhaust Air Grilles located in the ceiling.
B. The exhaust air from each specific area is conveyed from the exhaust grilles to a standard exhaust air valve through
a galvanized and sealed Class A Branch Exhaust Duct. C. The flow of exhaust air through each branch exhaust duct is regulated by an Exhaust Air Pressure Independent
Terminal Box that modulates between a minimum and maximum setting.
D. Each branch exhaust duct connects into the welded stainless steel Laboratory Exhaust Ductwork that conveys all
of the exhaust air from the Nuclear and Non Nuclear Areas to the high plume exhaust fans EF-02A, EF-02B and EF-
02C. E. The air supplied to the PET Scan and General Purpose Areas in each specific area (thermal zone) is controlled by a
standard Supply Air Pressure Independent Terminal Box that modulates between a minimum and maximum
setting.
F. The supply air is conveyed from each terminal box to the room through a Branch Supply Air Duct. G. The air is supplied into the non nuclear areas through Supply Air Diffusers located in the ceiling.
Control of Fume Hood and General Exhaust Ventilation Systems Nuclear Facility Class II Areas and PET Scan Areas
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
Automatic Control System
A system of electric / electronic Direct Digital (DDC) Controls has been installed to monitor and control the building
mechanical systems for space temperature comfort and energy conservation.
For all temperature control information refer to separate operation and maintenance manual provided by the temperature
control supplier for this project.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
26
PLUMBING AND DRAINAGE SYSTEMS Domestic Water System and Non Potable Domestic Water Systems
The Domestic Water System consists of Domestic Cold Water (DCW) and Domestic Hot Water (DHW) supply piping and
Domestic Hot Water Recirculation (DHWR) and a non potable water DCW piping supply system.
A new 100-mm potable DCW main for the plumbing fixtures and equipment in the new addition has been connected into the
existing DCW main waster service in the Level One existing Mechanical Room, downstream from the existing pressure reducing
valve and downstream from the existing Reduced Pressure Backflow Preventer.
Non potable water is supplied to some of the fume hoods in the addition. The new non potable water piping distribution system is
connected into the existing non potable water system.
A new 100-mm DCW line for emergency cooling is tied into the chilled water piping to be used in case the water chiller system
fails. When the DCW emergency backup system is in use, the water flowing through the chilled water piping system is drained
out to a 100-mm hub drain located in the new Mechanical Room. Reduced pressure backflow assemblies are provided on the
drain lines to prevent backflow of water into the potable DCW system and to control the pressure leaving the DCW piping system
into the drain. For further information refer to the previous description for the chilled water piping system.
A branch DCW line is provided with its own reduced pressure backflow assembly for the irrigation system. A control valve is
provided on the main irrigation water supply line to automatically control the flow of water to the irrigation system based on a
schedule.
Isolation valves are provided in the ceiling on the branch lines that connect into the main DCW line for the new addition. The
isolation valves make it possible to service the DCW piping and equipment in one area of the building without closing off the flow
of water to other parts.
The potable and non potable DCW water lines branch throughout the building, supplying water to the plumbing fixtures and
equipment. Stops (isolating valves) are provided for servicing individual fixtures.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
27
Domestic Hot Water System
The Domestic Hot Water (DHW) piping system is connected into the existing DHW piping distribution system in the
existing building. A new 50-mm DHW piping connection has been made to serve the plumbing fixtures and equipment in
the new addition that required hot water.
Storm Drainage System
The Storm Drainage System serves the roof drains that collect and transfer rainwater. Roof drains have been provided to prevent
water from building up on the roof. The roof drains are connected to vertical Rainwater Leaders (RWL)down and connect to underground horizontal gravity storm drain lines that run underground and discharge into a storm sump
located outside the northwest corner of the building addition. There is a duplex storm sump pump that discharges any storm
water through a pumped discharge line that connects to the 150-mm main storm drain line that conveys the storm water to the
municipal storm sewer system. .
The footi
PVC drain tile. The footing drains connect into a 6-inch solid storm drain lines that runs underground and discharge into the
storm sump.
Cleanouts are provided at regular intervals so that the drain lines may be kept free.
Storm Sump Pump Controls
A packaged control panel contains the electrical and control components that automatically start and stop the storm pumps when
they are required. A controller with four float switches in waterproof float bulbs is wired to start the lead pump when the water
float
switch setting, the lag pump cuts in. If the level reaches a maximum level, an alarm signal goes to the control panel. The pumps
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
DESCRIPTION OF SYSTEMS
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
28
Sanitary Drainage
The Sanitary Drainage System serves all the plumbing fixtures and floor drains. Vent lines, piped through the roof allow the
vent gases to exhaust to atmosphere unobstructed and enable free flow through the sanitary drain lines. The sanitary drain
connections from floor drains, lavatories, sinks and other plumbing fixtures are each provided with a trap. Each trap has a U-bend
or P-bend that fills with water each time the fixture is used. The water in the trap provides a seal to prevent unwanted gases from
the sanitary drain lines from coming out through the plumbing fixtures into the occupied areas. Trap seal primers are provided for
the floor drains to automatically fill them with water periodically to ensure that they do not dry out.
Each plumbing fixture is connected to a sanitary drain line that runs in the ceiling of the floor below the fixture or under the floor
slab. The sanitary drain lines are sloped downward towards the main 100-mm sanitary drain line for the building addition that
runs underground and discharge into a sanitary sump located outside the northwest corner of the building addition adjacent to
the storm sump. There is a duplex sanitary sump pump that discharges sanitary effluent through a pumped discharge line that
connects to the 150-mm main sanitary drain line that connects to the municipal sanitary sewer system. .
FIRE PROTECTION SYSTEM
The existing light hazard, Wet Sprinkler System that provides fire protection for the entire building has been extended to
serve the new sprinkler equipment installed in the new building. A 150-mm fire sprinkler main has been connected into the
existing fire protection piping system in the ceiling space of the existing part of the building. The 150-mm sprinkler main is piped
to the new Mechanical Room where there are two sprinkler zone stations, one for the wet sprinkler zones and the other for the pre-
action sprinkler zones.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
1
1.3 OPERATING DIVISION
This section provides operation instructions for the major items of the mechanical equipment and systems that were installed
under this contract. The following items are included:
Air Handling Units
Filters
Troubleshooting Procedures
Mechanical Equipment Starting Procedures
For additional information regarding individual items of equipment, refer to Section 3.0: Equipment Shop Drawings and Maintenance Data. For additional information on the operation of equipment, refer to Section 1.2 Description of Systems.
Disclaimer Section 1.3 The manual is intended to provide general guidelines only for reference by the building operators and maintainers. The responsibility for retaining knowledgeable operating and maintaining personnel to operate and maintain the mechanical equipment and systems rests with the Owner. It is up to the operating and maintenance staff to determine the optimum temperature control system set points to maintain building conditions at comfort levels suitable for the actual occupants of the building and to achieve the most efficient energy performance based on their experience and on guidance from the building Owner, who sets policies regarding safety, energy efficiency and building comfort.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
2
Air Handling Units
The air handling unit supply air fans may be electrically isolated by using the local disconnect switches. When changing the
filters or servicing any components inside the unit, de-energize the air handling unit fans for safety and limit the possibility of
damaging the equipment.
Ventilation: Outdoor air for ventilation is very important for building pressurization and for good air quality in the building.
If some of the occupied rooms become noticeably stuffy during times when the building is occupied, check to ensure that the
supply fans are operating, that the motorized outdoor air dampers are open and that there is flow of air to the supply air
diffusers.
Control Settings: The DDC system controls the system to match the actual req
Space Temperatures: The heating system is designed to maintain space temperatures in occupied rooms at 21 C (70 F)
during occupied periods. Space temperatures in occupied areas should be monitored regularly to notice any significant
change from normal.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
3
Filters The air handling system filters should be changed on a regular basis, eg about every eight to ten weeks throughout the year
when the building is being used. Otherwise, the outdoor air volumes will decrease and there will not be adequate air supply
for ventilation and free cooling in the rooms.
The dirt loading of air filters varies according to the cleanliness of the air being handled through the system. This may vary
from one season to another. The actual pressure drop through the filters may be determined by using the installed static
pressure gauges. As the filter bank loads with dirt over several weeks, the air pressure drop through the filters gradually
increases. Following are guidelines for the pressure drops for clean and loaded (dirty) filters. These are based on the
assumption that the air volume across the filter bank is equal to the peak design airflow rate.
Type of Filter Pressure Drop (Clean) Pressure Drop (Dirty) Inches w.c. Inches w.c.
50-mm thick Pleated Panel Filters 245 Pa (1.0
305-mm thick Cartridge Filters 367 Pa (1.5
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
4
Troubleshooting Procedures
The following schedule of suggested Troubleshooting Procedures is provided to assist in identifying the source of mechanical
system problems and taking corrective action.
TROUBLESHOOTING PROCEDURES FOR AIR HANDLING UNITS
PROBLEM MOST LIKELY CAUSES RECOMMENDED ACTION Air Handling Unit Fails To Operate
1. Electrical starting switch or disconnect switched off
2. Circuit breaker has tripped 3. Software setting on DDC system
changed 4. Low temperature control
1. Determine reason for shutdown and
2. Reset breaker and check motor current (starting and operating)
3. Change software setting to restart fan
4. Push manual reset button to restart supply fan
Entire area served by air handling system is too cold
1. Heating coil has lack of heating water flow
2. Heating water supply temperature is too cold
1. Check heating coil pump flow and restore flow
2. Raise temperature of heating water supply
Individual room temperature is too cold (Winter)
1. Hot water reheat coil control valve failure
2. Incorrect control setting for space temperature setpoint.
1 Determine cause of control valve failure and correct
2 Change control setting
Individual room temperature is too hot
1. Incorrect control setting (space temperature)
2. Inadequate air flow (during warmer weather conditions).
3. Lack of water flow in cooling coil.
1. Change control setting for space temperature
2. Determine cause of air flow shortage and correct
3. Check cooling coil control valve.
Poor air quality (general) and lack of air flow yet AHU is operating
1. Filters are plugged 2. Heating coil or cooling coil plugged
with dirt 3. Fire damper is closed
1. Check filter pressure drop and change filters
2. Clean the coils 3. Check fire damper position and
reopen Poor air quality in an individual room or area, yet other areas on same system are okay
1. Fire damper has tripped, blocking airflow
2. Balancing damper has been partially or fully closed
1. Check fire damper linkage and replace if necessary
2. Reopen balancing damper to marked position (or contact air balancing company)
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
5
TROUBLESHOOTING PROCEDURES FOR WATER CHILLER /CHILLED WATER SYSTEM
PROBLEM MOST LIKELY CAUSES RECOMMENDED ACTION Compressor Does Not Run 1. Electrical starting switch or
disconnect switched off 2. High Pressure Switch has tripped 3. Tripped motor overload 4. Compressor motor defective 5. Seized compressor 6. Pre-lubrication unsuccessful
1. Determine reason for shutdown
2.
3. Find cause of overload and reset 4. Check motor winding and repair 5. Replace compressor 6. Check oil pump operation
Compressor Cycles Off On Low Pressure
1. Loss of refrigerant charge 2. Bad transducer 3. Low refrigerant charge 4. Failed expansion device
1. Repair leak and recharge 2. Replace transducer 3. Add refrigerant 4. Repair/replace device
Compressor Shuts Down on High Pressure Control
1. Faulty high pressure switch 2. Compressor discharge valve partially
closed 3. Condenser coil plugged or dirty 4. Circuit overcharged 5. Liquid valve closed
1. Replace switch 2. Open valve or replace if it is
Defective 3. Clean coil 4. Clean condenser 5. Open valve and replace if
necessary Unit Operates Too Long Or Continuous
1. Low refrigerant charge 2. Control contacts fused 3. Partially plugged expansion valve or
filter drier 4. Service load exceeds capacity
1. Add refrigerant 2. Replace control 3. Clean expansion valve or replace
filter 4. Take measures to reduce loads
System is Unduly Noisy 1. Piping vibration 2. Expansion valve hissing 3. Compressor noisy
1. Support pipe 2. Add refrigerant and check for
plugged liquid line filter drier 3. If bearings are worn replace
compressor. Check for loose bolts
TROUBLESHOOTING PROCEDURES FOR CIRCULATING PUMPS
PROBLEM MOST LIKELY CAUSES RECOMMENDED ACTION Pump inoperative
1. Control problem e.g. temperature settings incorrect
2. Electrical supply problem 3. Motor failure
1. Check control operation 2. Check and restore power 3. Repair / replace motor
Low Flow 1. Dirty strainer 2. Air in system
1. Clean strainer 2. Remove air from piping
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
6
TROUBLESHOOTING PROCEDURES FOR SUMP PUMP (SEWAGE OR STORM SUMP PUMPS)
PROBLEM MOST LIKELY CAUSES RECOMMENDED ACTION
Pump fails to operate 1. Pump power cord disconnected 2. Circuit breaker tripped 3. Defective motor 4. Impeller blocked 5. Clogged screen or pump inlet
1. Reconnect power cord 2. Reset circuit breaker 3. Repair/replace motor 4. Unblock impeller 5. Unclog screen/inlet
Pump operates with reduced delivery
1. Impeller loose on shaft 2. Clogged or damaged impeller 3. Bearings frozen 4. Defective/inoperative check valve
1. Tighten impeller connection 2. Unclog/repair impeller 3. Replace bearings 4. Repair/replace check valve
Pump operates for short time then stops
1. Floats or weights incorrectly adjusted
2. Bearings worn
1. Modify float and/or weight adjustment
2. Replace bearings
Pump operates continually 1. Defective level control switch 2. Clogged pump or screen inlet
1. Repair/replace control switch 2. Unclog pump inlet/screen
Pump cycles too frequently 1. Defective check valve 1. Repair/replace check valve
Pump operation is very noisy (Squealing, hammering, grinding)
1. Impeller rubbing inlet plate or pump housing
2. Loose shaft coupling 3. Obstructed rotating parts 4. Gravel or stones at bottom of sump
1. Repair pump 2. Repair/replace shaft coupling 3. Remove obstruction 4. Clean sump pit/remove gravel
Pump turn on and off points have changed
1. Float operation obstructed or restrained
2. Float rod bent or obstructed by debris
1. Readjust float control or weights 2. Repair/replace rod or remove debris
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA OPERATING DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
7
Mechanical Equipment Starting Procedures
For normal operation, the mechanical equipment is started and stopped automatically by the DDC direct digital control
system. Major items of equipment have magnetic starting switches with Hand/Off Automatic selector switches. These
ies, the
.
Refer to applicable Safety Procedures before working on any equipment with electrical power supply.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
1
1.4 MAINTENANCE AND LUBRICATION DIVISION
MONTHLY ROUTINES EQUIPMENT TASKS TO BE PERFORMED Air Cooled Chiller Check that filters are clean and in place
Check that blower/bearing shaft assembly turns freely
Check conformance to temperature setpoints
Check lubrication system and observe oil level
Check for refrigerant leaks and repair as necessary
Check refrigerant level and system operation
Check electrical components and ensure correct Amperage draw
Check safety and operating controls
Air Handling Units Observe units for any change in running condition and any unusual noise.
Check filter condition (pressure drop) and replace if necessary
Exhaust Fans Observe monthly for any change in running condition and any unusual noise.
Steam to Water Heat Exchangers
Check for leaks around piping connections to heat exchanger
Check hot water supply temperature and compare to set point temperature (varies with outdoor air temperature).
Valves and Piping Observe for leaks, damage and condition.
Disclaimer: Building Owners are responsible to develop maintenance programs that reflect their own corporate policies regarding comfort conditions, energy consumption, safety, applicable legislation, bylaws, codes and other considerations. Any maintenance procedures and routines provided herein are generic and are to be considered as suggestions only for typical items to be included when developing a detailed maintenance program. These guidelines provide one source of information to be used when developing such programs for buildings. We recommend that the operating and maintenance staff become fully familiar with all the equipment supplier data included in Section 3 of these guidelines and in case of any data that is missing or incomplete contact all equipment suppliers to obtain more detailed information to improve their understanding of all system components and controls when developing a detailed maintenance program. The building Owner is responsible for complying with all safety codes, bylaws and other applicable legislation pertaining to any and all mechanical or plumbing or drainage or fire protection systems regardless of whether any mention is made herein. We recommend that only qualified and experienced operating and maintenance personnel be authorized to work on any of the equipment, systems or controls referred to in these guidelines. In case of any apparent disagreement between information provided directly from any specific supplier and what is listed anywhere in these guidelines, assuobtain clarification.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
2
1.4 MAINTENANCE AND LUBRICATION DIVISION
QUARTERLY ROUTINES EQUIPMENT TASKS TO BE PERFORMED Air Cooled Chiller Check operational and safety controls.
Check refrigerant charge, leak test and repair as necessary.
Air Handling Units Check operational and safety controls.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
3
1.4 MAINTENANCE AND LUBRICATION DIVISION
SEMI-ANNUAL ROUTINES EQUIPMENT TASKS TO BE PERFORMED Air Cooled Chiller Drain chilled water lines at end of cooling season and refill at beginning of
cooling season
Inspect evaporator and clean as required.
Inspect refrigerant lines for any evidence of oil leaks.
Check compressor crankcase heater operation.
Check that condensate drain is clear and pan is clean.
Air Handling Units Check all wiring for loose connections.
Check motor voltage and check amperage draws and compare to nameplate data.
Check contactors and replace contactor points if abnormally pitted or burned
Clean coils using low-pressure water spray.
Check setscrews on blower wheels, blower bearings and motor pulleys for looseness on the shaft
Belts Inspect and replace belts as required.
Exhaust Fans Check electrical connections and tighten
Ensure fan wheels rotate freely and easily
Lubricate fan and motor bearings (refer to lubrication schedule)
Heating and Cooling Coils Prior to each heating and cooling season check coils for debris and clean off if necessary.
Motorized Dampers Check operation of dampers to ensure tight close off without binding.
Check for loose linkages and adjust as necessary.
Pumps Lubricate pump and motor as recommended by the manufacturer.
Clean motor and housing and check glands, seals and couplings for wear, damage or leaks.
Ensure sheaves and pulleys run true, correct as necessary.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
4
1.4 MAINTENANCE AND LUBRICATION DIVISION
ANNUAL ROUTINES
EQUIPMENT TASKS TO BE PERFORMED Air Cooled Chiller Prior to each season, shut down inspect and clean.
Inspect piping for cracks or other damage.
Air Handling Units Check operation of all controls and adjust as necessary.
Check electrical connections and retighten
Controls Check to ensure proper operation and set points, service as necessary by controls specialist.
Cooling Coils Clean coil, inspect blank-off plates to ensure no air is bypassing coil.
Fire / Smoke Dampers Check fusible links for signs of fatigue or damage and replace with link of similar temperature rating if damaged.
Fire Protection System Inspect and test all components of the fire system to ensure proper operation.
Grilles, Registers, Diffusers, Louvres Clean with soapy cloth and remove any debris.
Motorized Dampers Clean and lubricate linkages.
Valves Clean valve and actuator, check to ensure proper movement of valve.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
5
1.4 MAINTENANCE AND LUBRICATION DIVISION
EVERY TWO YEAR ROUTINES EQUIPMENT TASKS TO BE PERFORMED
Fire Dampers Visual check of each fire damper to ensure it is not rusted or blocked
EVERY FOUR YEAR ROUTINES EQUIPMENT TASKS TO BE PERFORMED
Fire Dampers
Replace fusible links on all fire dampers
Test each fire damper to verify it closes and check latches where applicable
Lubricate moving parts of all fire dampers
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
6
LUBRICATION GUIDE
Conditions
The following information provides general guidelines for obtaining optimum performance from the various types of fan and
motor bearings. Because there are unique operating conditions for each individual system it is up to the building operators to
determine what is best for each situation.
The following conditions influence the required frequency of lubricating fan and motor bearings:
1. Cleanliness: Fan systems that are located in areas exposed to dirt-laden air require more frequent lubrication.
2. Moisture: If the ambient air has high humidity levels or if there is any direct water splash, the bearings require
more frequent lubrication.
3. Temperature: Higher temperature conditions require more frequent lubrication.
4. Load Conditions: Abnormally high load conditions have an effect on the recommended lubrication procedures.
Higher speed fans and motors require more frequent lubrication.
5. Hours of Operation: The frequency of lubricating bearings depends on the average weekly hours of operation.
Obviously a system that operates continually requires more frequent lubrication compared to a system that is
operated periodically according to a time schedule.
6. Types of Bearings: Fan bearings may be permanently lubricated sealed type, Ball bearing type, solid pillow block
spherical roller bearings or split pillow block spherical roller bearings. Motor bearings may be grease or oil
lubricated.
In some cases the equipment manufacturer provides specific recommendations for lubricating bearings and these may be
Equipment Survey Identification of Equipment Types
The first step in establishing a project specific lubrication schedule is to survey all of the fan and motor equipment in the
building to identify the types of fan and motor bearings, whether each is grease or oil lubricated and the system conditions
that influence lubrication requirements. Once this has been completed, a specific lubrication schedule may be developed
using the general lubrication guide on the following page.
Permanently Lubricated Sealed Fan Bearings For most normal operating conditions, pre-lubricated ball bearings require no lubrication for at least 7 to 10 years of
operation.
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
7
Grease Lubricated Ball Type Fan Bearings For clean, dry operating conditions, and operating temperatures between 30 ºC and 60 ºC change grease at 3 to 6 month
intervals, (or as per chart below) using Shell Alvania No 2 grease or equivalent. Add grease using low pressure grease gun,
with the fan wheel slowly rotated manually (if possible) until some purging occurs at the seals. Note the condition of the old
grease that appears and adjust lubrication schedule accordingly. Do not over grease.
Following is a general guide for re-lubricating based on fan speed and shaft size.
LUBRICATION SCHEDULE - MONTHS
500 1000 1500 2000 2500 3000 3500 4000 4500
6 6 5 3 3 2 2 2 1
6 5 4 2 2 1 1 1 1
5 4 3 2 1 1 1
4 3 2 1 1 1
Grease Lubricated Split Pillow Block Spherical Roller Fan Bearings For clean, dry operating conditions, and operating temperatures between 30 ºC and 60 ºC change grease at 3 to 6 month
intervals, (or as per chart below) using Shell Alvania No 2 grease or equivalent. Add grease using low pressure grease gun,
with the fan wheel slowly rotated manually (if possible) until some purging occurs at the seals. Note the condition of the old
grease that appears and adjust lubrication schedule accordingly. Do not overgrease.
Following is a general guide for relubricating based on fan speed and shaft size.
LUBRICATION SCHEDULE - MONTHS
Shaft
500 750 1000 1500 2000 2500 3000 3500 4000
6 5 4 4 3 2 2 1 1
5 4 4 3 2 1 1
4 4 4 2 1
4 4 3 1
BCCAA CYCLOTRON ADDITION VANCOUVER CANCER CENTRE 610 - 10TH AVENUE VANCOUVER, BRITISH COLUMBIA
MAINTENANCE AND LUBRICATION DIVISION
WESTERN MECHANICAL SERVICES (1977) LTD. Field Engineering and Quality Assurance of Building Mechanical Systems and Automatic Controls
8576 Fraser Street, Vancouver, BC, V5X 3Y3, Phone (604) 324-1434, Fax (604) 324-8263
8
Grease Lubricated Solid Pillow Block Spherical Roller Fan Bearings For clean, dry operating conditions, and operating temperatures between 30 ºC and 60 ºC change grease at 3 to 6 month
intervals, (or as per chart below) using Shell Alvania No 2 grease or equivalent. Add grease using low pressure grease gun,
with the fan wheel slowly rotated manually (if possible) until some purging occurs at the seals. Note the condition of the old
grease that appears and adjust lubrication schedule accordingly. Do not overgrease.
Following is a general guide for relubricating based on fan speed and shaft size.
LUBRICATION SCHEDULE - MONTHS
500 1000 1500 2000 2500 3000 3500 4000 4500
6 4 4 2 1 1 1 1 0.5
4 2 1 1 1 1/2 1/2 1/2 1/2
3 2 1 1/2 1/2
2 1 1/2
Grease Lubricated Ball Bearing Motors For clean, dry operating conditions, and operating temperatures between 30 ºC and 60 ºC change grease at 6 to 12 month
intervals, (or as per chart below) using Shell Alvania No 3 grease or equivalent.
Up To 7.5 H.P. 10 H.P. to 40 H.P. 50 to 150 H.P.
Up to 16 hours, clean and dry 5 Years 3 Years 1 Year
12 to 24 hours Moderate dirt or moisture 2 Years 1 Year 6 Months
Severe dirty or very hot 6 Months 3 Months 2 Months
Oil Lubricated Sleeve Bearing Motors For clean, dry operating conditions, and operating temperatures between 30 ºC and 60 ºC lubricate using SAE 10 non-
detergent oil at intervals between 6 months to one year.