6-PMP_Project Time Management_PMBOK_V4.pdf
-
Upload
shamim-sarwar-pappu -
Category
Documents
-
view
216 -
download
0
Transcript of 6-PMP_Project Time Management_PMBOK_V4.pdf
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 1/72
PMP Examination Preparation Course
Topic: Project Time Management
Version 4.0
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 2/72
©2009 Capgemini - All rights reserved 1
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Project Time Management
Hot Topics
Precedence diagramming method/ AON
Dependencies
Duration compression
Fast Track / Crash
Analogous estimating
Critical PathCritical Path
Float/Slack/Lag/Lead
Resource Leveling
Monte Carlo Simulation
Variance Analysis
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 3/72
©2009 Capgemini - All rights reserved 2
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Project Time Management (Cont’d.)
Processes required to deliver project on schedule
• Define Activities – Identifying specific actions to be performed to produceproject deliverables
• Sequence Activit ies – Identifying and documenting relationship amongproject activities.
• Estimate Activity Resource – Estimating type and quantities of material,people, equipment or supplies required.
• Estimate Activity Duration – Number of work periods required to completeindividual activities with estimated resources.
• Develop Schedule – Analyzing activity sequences, durations, resourcerequirements and schedule constraints to create project schedule.
• Control Schedule – Monitoring the status of project to update projectprogress and managing changes to schedule baseline.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 4/72
©2009 Capgemini - All rights reserved 3
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Project Time Management (Cont’d.)
Control Schedule Define Activities
SequenceActivities
Estimate Activity
Resources
Estimate ActivityDurations
Develop
Schedule
ClosingClosing
ProcessProcess
GroupGroup
Monitoring &Monitoring &
ControllingControlling
Process GroupProcess Group
ExecutingExecuting
ProcessProcess
GroupGroup
Planning ProcessPlanning Process
GroupGroup
InitiatingInitiating
ProcessProcess
GroupGroup
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 5/72
©2009 Capgemini - All rights reserved 4
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Define Activities
Identify the specific schedule activities that need be performed toproduce various project deliverables
Involves:
• Documenting the specific action or work to be performed
• Identify deliverables at the lowest level i.e. Work Packages
• Work packages are further decomposed into schedule activities
Defining and planning the schedule activities such that the projectobjectives are met
Defining and planning the schedule activities such that the projectobjectives are met
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 6/72
©2009 Capgemini - All rights reserved 5
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Define Activities
Decomposition
Rolling wave planning
Templates
Expert judgment
Tools and TechniquesTools and Techniques
Activity Lists
Activity attributes
Milestone list
Scope Baseline
Enterpriseenvironmental factors
Organizationalprocess assets
OutputsOutputsInputsInputs
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 7/72
©2009 Capgemini - All rights reserved 6
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Define Activities
1.Scope Baseline
Project deliverables, constraints and assumptions documented in project scopebaseline are considered explicitly while defining activities
2. Enterprise environmental factors
Availability of project management information systems and schedulingsoftware tools
3. Organizational process assets Formal / informal policies, procedures and guidelines for activity definitions
Lessons learned / Historical information on activity lists from previous similar
projects
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 8/72
©2009 Capgemini - All rights reserved 7
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Define Activities (Cont’d.)
1. Decomposition
Subdividing project work packages into smaller, manageable componentscalled activities
Define Activities process defines final outputs as activities rather thandeliverable
WBS and WBS dictionary are basis of development of activity list (they can bedeveloped in parallel as well)
Involving team members in decomposition can lead to more accurate results.
Each work package in the WBS is decomposed into the scheduleactivities required to produce the work package deliverables
Each work package in the WBS is decomposed into the scheduleactivities required to produce the work package deliverables
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 9/72
©2009 Capgemini - All rights reserved 8
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Define Activities (Cont’d.)
2. Rolling wave planning
Form of progressive elaboration planning . As scope is evolved, WBS and WBSdictionary items are more detailed
Work to be accomplished in near term is detailed at low level of WBS whilework to be accomplished in future is at a higher level of WBS
During early strategic planning, activities can be defined at milestone level,when less information is less defined, later it can be decomposed into activities
3.Templates Standard activity list or portion of activity list from a previous project
Can contain resource skills, required hours of effort, identification of risks,expected deliverables, can be used to identify typical milestones
4. Expert judgment
Consulting experts
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 10/72
©2009 Capgemini - All rights reserved 9
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Define Activities
1.Activi ty lists
It’s a comprehensive list including all schedule activities required on theproject
Activities are discrete components of project schedule, but NOT a part of WBS
Verified against WBS for completeness
Only contains the activities required as a part of project scope
Includes descriptions (activity identifier, scope of work) of activities for the
team to understand
Are used in the schedule model and is part of the project management plan
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 11/72
©2009 Capgemini - All rights reserved 10
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Define Activities (Cont’d.)
2. Activity Attributes Extend the description of activity by identifying attributes associated with each
activity.
Attributes – Activity identifier, Activity codes, Activity description, Predecessor
activities, Successor activities, Logical relationships, Leads and Lags, resourcerequirements, imposed dates, constraints and assumptions, person responsiblefor executing the work, geographic area where the work will be performed,Schedule activity type – level of effort, discrete effort and apportioned effort
Used for schedule development, for selecting, ordering & sorting plannedactivities within report.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 12/72
©2009 Capgemini - All rights reserved 11
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Define Activities (Cont’d.)
3. Milestone listsMilestone is a significant point or event in project
It identifies all the milestones
Indicates whether the milestone is mandatory (required by contract) or optional(based on project requirements or historical information)
Milestones – Have no duration, indicate start or completionof an activity
Milestones – Have no duration, indicate start or completionof an activity
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 13/72
©2009 Capgemini - All rights reserved 12
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Question?
Which of the following is an activity attribute:
•Activity code
•Lead and lag
•Constraints and assumptions
•Person responsible
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 14/72
©2009 Capgemini - All rights reserved 13
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Sequence Activities
Identifying and documenting the logical relationships among theschedule activities
Sequencing can be performed by using project management softwareor by using manual or automatic technique.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 15/72
©2009 Capgemini - All rights reserved 14
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Sequence Activities (Cont’d.)
Precedence
diagramming method(PDM)
Dependencydetermination
Applying leads andlags
Schedule Networktemplates
Tools and TechniquesTools and Techniques
Project schedule
network diagrams Project document
updates
Activity list
Activity attributes
Milestones List
Project scopestatement
OrganizationalProcess Asset
OutputsOutputsInputsInputs
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 16/72
©2009 Capgemini - All rights reserved 15
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Sequence Activities
1. Activity lists (described earlier)
2. Activity attributes (described earlier)
3. Milestone lists (described earlier)4. Project Scope statement
Product characteristics described in scope description may impact activitysequencing. These are often apparent in activity lists
This is reviewed to ensure accuracy
5.Organizational Process Assets
Organizational Process Asset can influence the sequence activities process.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 17/72
©2009 Capgemini - All rights reserved 16
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Sequence Activities (Cont’d.)
1.Precedence diagramming method (PDM)
A method of critical path methodology for constructing a project schedulenetwork diagram
This technique is also called Activity-On-Node (AON).
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 18/72
©2009 Capgemini - All rights reserved 17
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Activi ty Activi ty
Tools & Techniques – PDM
START
A
D E
B
FINISH
C
F
Precedence Diagramming method (PDM)Precedence Diagramming method (PDM)
FS/SS/FF/SF
No Dummies
Commonly used
Relationship
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 19/72
©2009 Capgemini - All rights reserved 18
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Dependency /logical Relationship
PDM includes four types of logical relationships
A B
A B
BA
BA
FINISH TO START
START TO START
FINISH TO FINISH
START TO FINISH
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 20/72
©2009 Capgemini - All rights reserved 19
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Sequence Activities (Cont’d.)
2. Dependency determination
Three types of dependencies are used to define the sequence among theactivities.
Mandatory
Discretionary
External
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 21/72
©2009 Capgemini - All rights reserved 20
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Dependency determination
TYPETYPE DESCRIPTIONDESCRIPTION EXAMPLE(S)EXAMPLE(S) !REMEMBER!!REMEMBER!
Task DependenciesTask Dependencies
MandatoryMandatory Logical dependencies due to
nature of work Often involve physical
limitations
The code must be completed
before it can be reviewed Foundation must be complete
before building floor
DiscretionaryDiscretionary Dependencies defined by the
project management team An additional level of review
before delivery to the client Also called as SOFT
LOGIC, PREFERRED
LOGIC
Should be used with care
Should be fully documented
ExternalExternal Dependencies on eventsoutside the project
Software licenses mustbe supplied by Clientbefore development
A dependency can be bothexternal and mandatory
Also called as HARDLOGIC
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 22/72
©2009 Capgemini - All rights reserved 21
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Sequence Activities
3. Applying Leads and Lags
Lag is the amount of wait time before the successor activity can be started
Lead allows the acceleration of the successor activity
4. Schedule Network templates
Portions of project schedule network diagram are referred as sub-network orfragment network
Useful as templates when project includes several identical deliverables e.g.,floors on high rise buildings
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 23/72
©2009 Capgemini - All rights reserved 22
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Sequence Activities
1. Project schedule network diagram
Schematic display of projects schedule
Includes either full project details or one or more summary activities
2. Project document updates
Project documents that may be updated include, but not limited to:
Activity list
Activity attributes
Risk Register
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 24/72
©2009 Capgemini - All rights reserved 23
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Question?
Identify the type of dependency:
• Building plan to be cleared by the local municipal department beforeconstruction can start
• Testing to be done before product can be put into the market
• Marketing and legal department to clear RFP prior to submission
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 25/72
©2009 Capgemini - All rights reserved 24
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Estimate Activity Resources
Estimating the type and quantities of resources required to performeach schedule activity
Estimate Activity Resource process is closely coordinated with
Estimate Cost process.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 26/72
©2009 Capgemini - All rights reserved 25
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Estimate Activity Resources (Cont’d.)
Expert judgment
Alternative analyses
Published estimatingdata
Bottom-up estimating
Project managementsoftware
Tools and TechniquesTools and Techniques
Activity resourcerequirements
Resourcebreakdown structure
Project Document
updates
Activity lists
Activity attributes
Resource Calendars
Enterpriseenvironmentalfactors
Organizational
process assets
OutputsOutputsInputsInputs
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 27/72
©2009 Capgemini - All rights reserved 26
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Estimate Activity Resources
1.Activity l ist
Activity List identifies the activities which will need resources.
2. Activity attributes Developed during the define activities and sequence activities processes
3. Resource Calendar
Provides information on which resources are potentially available duringplanned activity period and is used for estimating resource utilization
Specify when and how long identified project resource will be availableduring project.
Includes availability, capabilities, and skills of human resources.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 28/72
©2009 Capgemini - All rights reserved 27
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Estimate Activity Resources
4.Enterprise environmental factors
Can influence the Estimate Activity Resources process
5. Organizational process assets
Policies regarding staffing, purchase and rental of supplies and equipments
Available historical information regarding what type of resources were requiredfor similar projects in past
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 29/72
©2009 Capgemini - All rights reserved 28
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Estimate Activity Resources
1.Expert judgment
People or group with specialized knowledge in resource planning andestimating
2. Alternatives analysis
Alternative methods for accomplishing schedule activities
Various levels of resource capabilities or skills
Different size or type of machines
Hand operated tools versus automated tools
Make or buy decisions regarding resource (equipment, supplies)
3. Published Estimating data
Published updated production rate and unit costs of resources for an extensivearray of labor trades, material, and equipment for different countries andgeographical locations within a country
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 30/72
©2009 Capgemini - All rights reserved 29
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Estimate Activity Resources (Cont’d.)
4. Bottom-up Estimating
If project team does not have adequate confidence in the estimates at theschedule activity level, it needs to be further decomposed
Resource needs at these decomposed levels are estimated and quantities arerolled up to the scheduled activities resources
Dependencies between these activities may impact application and use of resources and such pattern of resource usage is documented
5. Project Management Software
Helps planning, organizing, managing resource pools and develop resourceestimates
Sophisticated tools have capabilities to define resource breakdown structures,resource availabilities, resource rates and resource calendars
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 31/72
©2009 Capgemini - All rights reserved 30
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Estimate Activity Resources
1. Activity resource requirements
Description of type and quantities of resources required for each scheduleactivity in work package
Aggregated to determine resource estimates for each work package
Supporting documentation – basis of estimate for each resource, assumptionsmade while determining type, availability and quantity of resources
2. Resource breakdown structure
Hierarchical structure of identified resources by resource category and type
3. Project Documents updates
Project documents that may be updated include, Activity list, Activity attributes
and Resource calendars.
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 32/72
©2009 Capgemini - All rights reserved 31
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Question?
Which of the following is not a tool and technique for
activity resource estimating?
•Published estimating data•Bottom-up estimating
•Alternative analysis
•Parametric estimating
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 33/72
©2009 Capgemini - All rights reserved 32
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Estimate Activity Durations
Estimate activity durations is the process of approximating the number of workperiods needed to complete individual activities with estimated resources.
Uses information on activity scope of work, required resource types, estimated
resource quantities and resource calendars.
Estimating the number of work periods required to complete eachschedule activity
Estimating the number of work periods required to complete eachschedule activity
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 34/72
©2009 Capgemini - All rights reserved 33
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Estimate Activity Durations (Cont’d.)
Expert J udgment
Analogous estimating
Parametric estimating
Three-point estimate
Reserve analysis
Tools and TechniquesTools and Techniques
Activity durationestimates
Project Documentupdates
Activity list
Activity attributes
Activity ResourceRequirements
Resource calendars
Project scope statement
Enterprise environmentalfactors
Organizational processassets
OutputsOutputsInputsInputs
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 35/72
©2009 Capgemini - All rights reserved 34
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Estimate Activity Durations
1. Activity list (described earlier)2. Activity attributes (described earlier)
3. Activity Resource requirements
Duration of activities will depend on the resources available to work onactivities
Availability of skilled resources will significantly influence the duration of mostactivities.
Project experience communication overload as more resources are addedthus reducing productivity
Output improves proportionally less than the increase in resources
I E i A i i D i (C ’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 36/72
©2009 Capgemini - All rights reserved 35
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Estimate Activity Durations (Cont’d.)
4. Resource calendars
Developed as part of Estimate activity resource process.
Type of resource assigned, quantity, availability, capability of both equipment &material resources could significantly influence the activity duration
For example senior staff members are expected to complete the activity inlesser time as compared to junior staff members
5. Project scope statement
Constraints and assumptions are considered when estimating activitydurations.Example of constraints are available skilled resources, contract terms andrequirements.
Example of assumptions are existing conditions, availability of information andlength of reporting periods.
I t E ti t A ti it D ti (C t’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 37/72
©2009 Capgemini - All rights reserved 36
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs – Estimate Activity Durations (Cont’d.)
6. Enterprise environmental factors
Duration estimating databases and other reference data.
Published commercial information
Productivity metrics
7. Organizational process assets
Historical duration information
Project calendars
Scheduling methodology
Lessons learned.
T l & T h i E ti t A ti it D ti
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 38/72
©2009 Capgemini - All rights reserved 37
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Estimate Activity Durations
1. Expert judgment
Should be used along with historical information
Can also be used to determine whether to combine methods of estimating and how toreconcile differences between them
2. Analogous estimate Also called as ‘Top-Down’estimates
Form of expert judgment
Uses performance results of similar past activities
Used when there is only limited amount of detailed information about project.
3. Parametric estimating
Uses a statistical relationship between historical data and other variable to calculate anestimate for activity parameter such as cost, budget & duration.
Can produce higher levels of accuracy depending upon sophistication and underlyingdata built into the model.
Tools & Techniq es Estimate Acti it D rations (Cont’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 39/72
©2009 Capgemini - All rights reserved 38
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques – Estimate Activity Durations (Cont’d.)
4. Three point estimate Most likely – Duration of the schedule activity, given the resources likely to be assigned,
their productivity, realistic expectations of availability for the schedule activity,dependencies on other participants, and interruptions
Optimistic – Duration is based on a best-case scenario of what is described in the mostlikely estimate
Pessimistic – Duration is based on a worst-case scenario of what is described in the mostlikely estimate
Activity duration estimates can be constructed by taking an average of 3 estimated
durations which will often provide more accurate estimates than a single point estimate5. Reserve Analysis
Incorporating additional time referred to as contingency, time reserves, buffers
Can be percentage of estimated activity duration, fixed number of work periods, or
developed by quantitative risk analysis Can be used completely or partially, can be reduced or totally eliminated later on
Outputs Estimate Activity Durations
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 40/72
©2009 Capgemini - All rights reserved 39
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Outputs – Estimate Activity Durations
1. Activity duration estimates
Quantitative assessments of likely number of work periods that will be requiredto complete a schedule activity
Generally expressed as a range 2 months +/- 5 days or 90% probability of finishing in 2 weeks
2. Project Document updates
Project Document updated may include
Activity attributes, and assumption made in developing the activity durationestimate such as skill levels and availability.
Question?
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 41/72
©2009 Capgemini - All rights reserved 40
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Question?
Identify the kind of estimation technique used in each of the
following:
• (27000 use case points) / (27 use case points/ hr) = 1000 hrs
• Aggressive = 10 days; Pessimistic = 20 days; Most likely = 16 days
• Similar functionality in an earlier project took 15 person days tocomplete
Develop Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 42/72
©2009 Capgemini - All rights reserved 41
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Develop Schedule
Develop schedule is the process of analyzing activity sequences,duration, resource requirements and schedule constraints to create theproject schedule.
Developing an acceptable project schedule is often an iterativeprocess.
Serves as a baseline against which project progress can betracked
Serves as a baseline against which project progress can betracked
Develop Schedule(Cont’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 43/72
©2009 Capgemini - All rights reserved 42
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Develop Schedule(Cont d.)
Schedule network analysis
Critical path method
Critical chain method
Resource leveling What-if scenario analysis
Adjusting leads and lags
Schedule compression
Scheduling tool
Tools and TechniquesTools and Techniques Project schedule
Schedule baseline
Schedule Data
Project DocumentUpdates
Activity lists
Activity attributes
Project schedule Networkdiagrams
Activity Resourcerequirements
Resource Calendars
Activity duration estimates
Project scope statement
Enterprise environmentalfactors
Organizational process
assets
OutputsOutputsInputsInputs
Inputs – Develop Schedule (Cont’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 44/72
©2009 Capgemini - All rights reserved 43
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs Develop Schedule (Cont d.)
1. Activity list (described earlier)
2. Activity attributes (described earlier)
3. Project schedule network diagrams (described earlier)
4. Activity Resource requirements (described earlier)
5. Resource calendars (described earlier)
6. Activity duration estimates (described earlier)
Inputs – Develop Schedule (Cont’d )
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 45/72
©2009 Capgemini - All rights reserved 44
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Inputs Develop Schedule (Cont d.)
7. Project scope statement
Assumptions and constraints – Imposed dates, market window ontechnology project
Commonly used constraints in PM software – “Start No Earlier Than”and“Finish NO Later Than”
Major milestones dictated by Project sponsor, customer
8. Organizational process assets
Scheduling methodology
Project calendars
9. Enterprise environmental factors
Can influence the develop schedule process include a scheduling tool that can beused in developing the schedule
Tools & Techniques – Develop Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 46/72
©2009 Capgemini - All rights reserved 45
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques Develop Schedule
1. Schedule network analysis
Used to calculate early and late start and finish dates
Network loops and open ends are adjusted before applying any techniques
Analytical techniques – critical path method, critical chain method, what-if analysis, and
resource leveling
Points of path convergence and path divergence can be identified and used in schedulecompression analysis
2. Critical path method
Calculates theoretical early start and finish dates and late start and finish dates byperforming forward pass and backward pass analysis
It is called as theoretical as resource limitations are not considered
Measure of flexibility in a schedule is FLOAT – If difference between early and late datesis positive, schedule is flexible. Critical path has ZERO or NEGATIVE float and activitieson critical path are termed as critical activities
(More details are provided later on)
Tools & Techniques – Develop Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 47/72
©2009 Capgemini - All rights reserved 46
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Tools & Techniques Develop Schedule (Cont d.)
3. CRITICAL CHAIN Method (scheduling & managing uncertainty by):
Schedule network analysis technique that modifies project schedule to account for limitedresources.
Resource-constrained critical path is known as critical chain. Adds duration buffers that are non-work schedule activities to manage uncertainty.
One buffer is known as project buffer. Additional buffers are known as feeding buffers.
Size of buffer should account for uncertainty in the duration of chain of dependant tasks.
Tools & Techniques – Develop Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 48/72
©2009 Capgemini - All rights reserved 47
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
q p ( )
4. Resource leveling
Often cause original critical path to change and is necessary when resources are overallocated.
Allocate scarce resources to the critical activities first It lets the cost and schedule slip infavor of having stable number of resources per month
Sacrificing schedule for having resource stability is called as resource-based scheduling
Scheduling of finite or critical resource from project ending date is known as reverseallocation scheduling
Uneven Resource loading
160
80100
200225
180
0
50
100
150
200
250
J an Feb Mar April May J une
Hours
157 157 157 157 157 157
0
50
100
150
200
J an Feb Mar Apr May J une
Levelled Resources
Hours
Tools & Techniques – Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 49/72
©2009 Capgemini - All rights reserved 48
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
q p ( )
5. What-if Scenario analysis
Consideration of different scenarios of event occurrence and their impact on the projectschedule. These events could be external to the project or integral part of project
Examples – What will happen if there is a change in process? What will happen if aspecific component gets delayed
Out come of scenario analyses helps to assess the feasibility of schedule under adverseconditions and in preparing contingency/response plan to mitigate the impact of unexpected situations
Most common technique is Monte Carlo analysis used to calculate a distribution of possible outcome for the total project.
6. Leads and lags
Adjustments to leads and lags to come up with a viable project schedule.
Tools & Techniques – Develop Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 50/72
©2009 Capgemini - All rights reserved 49
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
q p ( )
7.Schedule compression
Shortening of schedule without changing the project scope, to meet the scheduleconstraints, imposed dates, or other schedule objectives
Crashing
• Maintain scope and add more resources to the critical path activities
• Almost always associated with increase in cost
• Not all activities can be executed faster by adding resources
Fast tracking
• Performing critical path activities in parallel
• Increases the probability of rework
• Increases risks
8. Scheduling tool Can be used in conjunction with other project management Software application as well
as manual methods.
Outputs – Develop Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 51/72
©2009 Capgemini - All rights reserved 50
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Project schedule
Contains milestone schedule, summary schedule and detailed schedule withlogical relationships.
Remains preliminary until resource assignments are confirmed
This process is completed on or before the completion of projectmanagementplan
Can be at summary level – master schedule or at a detailed level
Can be presented in tabular or graphical format
• Project schedule network diagram
• Bar charts or
• Milestone charts
Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 52/72
©2009 Capgemini - All rights reserved 51
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Definitions of key terms
Free Slack/Free float/Slack/Float : The amount of time the activity can bedelayed without affecting the start of successor activity
Total Slack/Total Float : The amount of time the activity can be delayedwithout affecting the project completion date
Project Slack/Project Float : The amount of time the project can be delayedwithout delaying the externally imposed completion date imposed by thecustomer or Sr. Management
Crit ical path is the longest sequence of activities on the network diagram and ischaracterized by zero float or slack for activities. There is no slack along the
critical path
Any delay in critical path delays the project
Sometime multiple critical paths can exist
In practice, apart from the critical activities, activities thathave small amount of float are also closely monitored
Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 53/72
©2009 Capgemini - All rights reserved 52
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Critical Path Method (CPM)
• Deterministic method
• Single estimate (most likely)
• Focus on float to identify the least flexible activities• Does not allow for looping in network and shows only one path
Scheduling Techniques / Mathematical Analysis• Calculate Theoretical early/late start and finish dates
• These dates are subject to change after resource leveling and durationcompression
Develop Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 54/72
©2009 Capgemini - All rights reserved 53
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Building Network Diagrams
3,105K 11
9,820 J10
510I9
74H8
630G7
215F6
43E5
24D4
24C3
15B2
-15A1
FloatFloatLFLFLSLSEFEFESESPredecessor Predecessor DurationDurationDescriptionDescription Activi ty Activ ity
STEP1: Create Activity List
STEP2: Assign duration
STEP3: Determine predecessor
Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 55/72
©2009 Capgemini - All rights reserved 54
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Scheduling Conventions
• 1st Activity is always scheduled tostart on project start date
• Each activity starts at the beginning of the start period and finishes at theend of the finish period
− A one day activity starting on J an1st has end date of J an 1st
• Early Finish date (EF) = Early startdate (ES) + duration - 1
• The successor activity starts in thenext available time period. If anactivity finishes on Day 3, successoractivity will start on Day 4
STEP4: Forward PassSTEP4: Forward Pass – – Calculate EarlyCalculate Early
schedule activitiesschedule activities
Early Start Duration Early Finish
Task Name
Late Start Slack/Float Late Finish
Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 56/72
©2009 Capgemini - All rights reserved 55
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Mon 6/12
A
15 Fri 6/30
Mon 6/12 0 Fri 6/30
Mon 7/3
B
5 Fri 7/7
Mon 7/3 0 Fri 7/7
Mon 7/10
C
4 Thu 7/13
Mon 10/9 65 Thu 10/12
Mon 7/10
D
4 Thu 7/13
Mon 8/23 32 Mon 8/28
Mon 7/10
F
15 Fri 7/28
Mon 7/10 0 Fri 7/28
Fri 7/14
E
3 Tue 7/18
Mon 8/29 32 Mon 8/31
Mon 7/31
G
30 Fri 9/8
Mon 7/31 0 Fri 9/8
Mon 9/11
H
4 Thu 9/14
Mon 9/11 0 Thu 9/14
Wed 7/19
I
10 Tue 8/1
Fri 9/1 32 Thu 9/14
Fri 9/15
J
20 Thu 10/12
Fri 9/15 0 Thu 10/12
Fri 10/13
J
5 Thu 10/19
Fri 10/13 0 Thu 10/19
STEP7: Determine Critical PathSTEP7: Determine Critical Path
Outputs – Develop Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 57/72
©2009 Capgemini - All rights reserved 56
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Bar chart that shows activitystart and finish dates withexpected duration
Generally do not depictinterdependencies
Weak planning tool
Effective for progressreporting and control
Gantt (Bar) ChartGantt (Bar) Chart
Shows interdependenciesof all tasks and activitydates information
Shows workflows and canidentify the critical path
Can aid in effectiveplanning, organizing andcontrol of project
Shows start/finish dates of major deliverables and keyexternal dependencies
Similar to bar chart but canalso be represented in atabular form
Good for management andcustomer reporting
Schedule Network DiagramSchedule Network DiagramMilestone ChartMilestone ChartMethods of presenting Project Schedule
Outputs – Develop Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 58/72
©2009 Capgemini - All rights reserved 57
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
2. Schedule baseline
Specific version of the project version developed from the schedule networkanalysis of the schedule model
Approved and accepted by project management team as schedule baseline
Contains baseline start and finish dates
3. Schedule data
Supporting data – schedule milestones, schedule activities, activity attributes,
assumptions and constraints Resource requirements by time periods – resource histograms
Alternative schedules – best case, worst case schedules etc
Scheduling of contingency reserves
Outputs – Develop Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 59/72
©2009 Capgemini - All rights reserved 58
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
4. Project Documents updates
Include but not limited to
Activity Resource Requirements
Activity Attributes
Calendar
Risk Register
Question?
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 60/72
©2009 Capgemini - All rights reserved 59
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
A critical project is running behind schedule and the resources arebeing overworked everyday. What option should the project managerchoose:
• Fast tracking• Crashing
• None of these
Control Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 61/72
©2009 Capgemini - All rights reserved 60
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Control Schedule is concerned with
• Determining current project status
• Influencing factors that cause schedule changes
• Determining that project schedule has changed
• Managing the actual changes as they occur
This is the process necessary for controlling changes to theproject schedule
This is the process necessary for controlling changes to theproject schedule
Control Schedule(Cont’d.)
T l d T h i OI
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 62/72
©2009 Capgemini - All rights reserved 61
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Performance Reviews
Variance analysis
Project Managementsoftware
Resource leveling What-if scenario analysis
Adjusting leads and lags
Schedule compression
Scheduling tool
Tools and TechniquesTools and Techniques
Work Performancemeasurements
Organizational processassets (updates)
Change Request
Project management plan(updates)
Project Document(updates)
Project Management Plan
ProjectSchedule
Work PerformanceInformation
Organizational processassets
OutputsOutputsInputsInputs
Inputs – Control Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 63/72
©2009 Capgemini - All rights reserved 62
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
1. Project Management Plan
Contains schedule management plan and schedule baseline, which is used tocompare with actual results to determine if change, corrective action or preventiveaction is necessary.
2. Project Schedule
Most recent version of the project schedule with notations to indicate updates,completed activities and started activities as of the indicated data date.
Inputs – Control Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 64/72
©2009 Capgemini - All rights reserved 63
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
3. Work Performance Information
Information about the project progress such as which activities have started theirprogress and which activities have finished
4 Organizational process assets Existing formal informal schedule control related policies, procedures and guidelines;
Schedule control tools; and
Monitoring and reporting method to be used
Tools & Techniques – Control Schedule
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 65/72
©2009 Capgemini - All rights reserved 64
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
1. Performance Reviews
Measure, compare and analyze schedule performances such as actual startand finish date, percent complete and remaining duration of work in progress
An important part of Schedule Control is to decide if the schedule variationrequires corrective action.
2. Variance analysis
Schedule performance measurements (SV,SPI) are used to asses magnitude
of variation to the original schedule baseline.
Identifying which variance would call for corrective actions
Mainly focused on critical activities / sub-critical activities (less float)
3. Project Management Software
Ability to track planned versus actual, ability to forecast effects of schedulechanges
4. Resource leveling
Tools & Techniques – Control Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 66/72
©2009 Capgemini - All rights reserved 65
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
5. What-if scenario analysis
6. Project Management Software
Ability to track planned versus actual, ability to forecast effects of schedule
changes
7. Adjusting leads and lags
8. Schedule compression
9. Scheduling toolScheduling tool and supporting data are used in conjunction with manualmethods or other PM SW to perform schedule network analyses to generate anupdated project schedule.
Outputs – Control Schedule (Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 67/72
©2009 Capgemini - All rights reserved 66
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
1. Work Performance measurements
Schedule variance (SV) and Schedule performance index (SPI) at workpackage and control account level are communicated to stakeholders
2. Organizational Process assets (updates) Feeding the organizational database with lessons learned – causes of schedule
variance and reasoning behind corrective actions taken. Any other lessonslearned during schedule control
3. Change Requests
Requested changes to the schedule baselines
May require adjustments to other components of the project management plan
Processed for review and disposition through Perform Integrated changecontrol process
Outputs – Control Schedule(Cont’d.)
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 68/72
©2009 Capgemini - All rights reserved 67
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
4. Project Management Plan Updates
Elements of project management plan that may be updated but are not limitedto: Schedule baseline, Schedule management plan, Cost baseline.
5. Project Document Updates
Schedule Data
Project Schedule
Question?
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 69/72
©2009 Capgemini - All rights reserved 68
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Which of the following are tools and techniques of
schedule control?
Variance analysis
Schedule comparison bar charts
Progress reporting
Performance measurement
Recap
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 70/72
©2009 Capgemini - All rights reserved 69
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Arrow diagramming method
Precedence diagramming method
Dependencies
Duration compression
Fast Track / Crash
Analogous estimating
Critical PathCritical Path
AON/ADM/GERT
Float/Slack/Lag/Lead
Resource Leveling
Monte Carlo Simulation
Variance Analysis
Review Questions Time
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 71/72
©2009 Capgemini - All rights reserved 70
PMP Workshop | Financial Services All work described was performed by Capgemini or a Capgemini affiliate
Review Questions
7/30/2019 6-PMP_Project Time Management_PMBOK_V4.pdf
http://slidepdf.com/reader/full/6-pmpproject-time-managementpmbokv4pdf 72/72
www.capgemini.com/financialservices
Thank You