6 J 5 Jllll.1977 ©¢Snr¤—svs-·RRF Q4-)!6 J 5 Jllll.1977 ©¢Snr¤—svs-·RRF Q4-)! FIGURES OCR...
Transcript of 6 J 5 Jllll.1977 ©¢Snr¤—svs-·RRF Q4-)!6 J 5 Jllll.1977 ©¢Snr¤—svs-·RRF Q4-)! FIGURES OCR...
SCAN -9909024 OCR Output
7|\1|1|!||\EINXIIIIHIIIIIWlfllIINIIUIJIIIIIIMIIIIIIIIIHIIICERN LIBRARIES, GENEVA
Geneva - May 1977
P0O030187
September 14-17, l976
Conference, Chalk River, Ontario, Canada.Paper presented at the l976 Proton Linear Accelerator
practical solutions are described.the design of such a structure are explained, andenergy gain around O.1 MeV/m. The guide·lines foroperated almost CW with a travelling wave giving anquency swing during the acceleration cycle. It ishigh-energy proton linac, except for a small fre
The SPS accelerating structure is essentially a
SUM ARY
G. Dome
TRAVELLING WAVE DRIFT—TUBE STRUCTURE FOR THE CERN SPS
THE SPS ACCELERATION SYSTEM
CERN-SPS/ARF/77-11
'cf p OXXCERN - SPSO A f. "
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH+E 7Q U 6
©¢Snr¤—svs-·RRF Q4-)!6 J 5 Jllll.1977
FIGURES OCR Output
REFE RENCE S 1 9
ACKNOWLEDGEMENTS 18
MANUFACTURERSll. 18
POWER AMPLIFIERS10. 16
FEEDER LINES I5
TERMINATING LOAD I5
13INPUT AND OUTPUT COUPLERS
IlBEAM LOADING AND RF POWER
HIGHER MODES OF THE ACCELERATING STRUCTURE Il
TECHNOLOGY
CHOICE OF THE ACCELERATING STRUCTURE
REQUIREMNTS FOR THE ACCELERATING STRUCTURE
INTRODUCTION
.*252
Table 0f contents
in the SPS ring. OCR Outputb) This value corresponds to 1 X 10protons circulating13
a) At the present time, a 3rd cavity is being ordered.
tion easily provides the required bandwidth without any variable tuning
at a reasonable power level. On the other hand, travelling wave opera
necessitate variable tuning for a cavity operated with a standing wave
Although the relative frequency swing is only 4.4 X 10"°, it would
power is needed during most of the acceleration cycle.
The last requirement in Table I stems from the fact that the RF
close to 1Duty factor
UID = 89 kWBeam power per cavity (at ¢_ = 45°)
ID = 70 mAAverage be m current
eU = 1.27 MeV(at ¢_ = 45U)Energy gain per cavity for one traversal
Synchronous phase angle (from crest of the wave) ]¢S| Z 45
Peak accelerating voltage per cavity VI = 1.8 MV
Number of cavities
to 200.396 MHzto top energy (400 GeV)
199.526 MHzFrequency swing from injection energy (10 Ggv)
200.222 MHzFrequency at transition energy (24 GeV)
Specifications for the SPS Acceleration System
Table I
specificationsl’ shown in Table I.
June 17, 1976. The RF accelerating system was designed to meet the
ground near Geneva. It reached its design energy for the first time on
The SPS is the European proton synchrotron of 400 GeV built under—
velocity is v, the electric field induced by the beam along the axis of OCR Output
If the RF component of the be m current is IL and the particle
El.
peak value of the effective accelerating voltage per cavity is essentially
(several hundreds m); therefore, in the absence of beam loading, the
attenuation constant. At 200 MHz, the attenuation length lk! is large
where vn is the group velocity of the travelling wave, and u is the field
v_ Q c3>R = AL EL = 2uR 2 1
is related to the series impedance by the equation
of the structure
(2)R1 (in E-) = EZ/power loss per unit length
defined as
The effective shunt impedance R1 per unit length of the structure,
travelling wave.
(including the transit time factor), and P is the power flux of the
where E is the peak value of the effective accelerating field on the axis
(1). R2 (ln 55) — En E2
as
parameter for RF power is the series impedance R2 of the structure, defined
terminated in a matched load for travelling wave operation. The important
Each accelerating cavity is essentially a loaded waveguide of length 2,
2. REQUIREMENTS FOR THE_ACCELERATING STRUCTURE
the cavities are in a tunnel, 60 m underground.
important when the power amplifiers are located at the surface, whereas
matched load even with varying frequency and beam loading. This is very
a long feeder line to the power amplifier, and continues to appear as a
It also presents another major advantage: the cavity may be connected by
operating mode approaches the edge of a passband, where vg vanishes. OCR Outputperfect synchronism with the bea . It is no longer valid when thespace—harmonic of the beam induced field, which is closest to
a) It should be mentioned that Eq. (4) represents only that particular
Vrf
_ i b T ji ·7T — sin T ·1;·— I (6). S].n_ 2 S]..II_ _ Jo 2 _ RZR I ER. Q ······I·····. T2 _ 2 i· 2traversal of the cavity is
With Eq. (4), the effective voltage V seen by the beam upon one
the particles leave the cavity.
the particles enter; in the second case, z is taken from the end where
first case, the distance z in Eq. (4) is taken from the cavity end where
acceleration is of the forward wave or of the backward wave type. In the
as positive or negative according to whether the passband used for
as positive. The particle velocity v, on the other hand, should be taken
In all formulae, the group velocity vc should be taken essentially
finite velocity (or energy) Of the particles.
synchronism between the wave and the particles; it corresponds to a de
In Equation (5), wo is the angular RF frequency at which there is perfect
(5)T=;"*—(w·wg)
travelling wave and the proton bunches along the cavity:
the middle of the cavity. The angle T is the total phase slip between the
where z is the distance from one cavity end. All phases are referred to
b b 4onE:-I?-%s‘2}—?£
_.w _&—]T—· JT(z)2
the cavity is given by
limit for the filling time 2/vg of the cavity: OCR Output
i.e. at injection. According to Eq. (5), this condition sets an upper
it was decided that Irl should not exceed w radians in the worst case,
In order to limit the voltage reduction due to T at other energies,
the acceleration cycle.
transition. In this case, T and ¢_ have always the same sign throughout
RF amplitude |E2| but only the RF phase ¢, then r must be zero at
while ]V| is kept constant. If this is to be done without changing the
¢h must abruptly change sign (going from a negative to a positive value)
Fig. l shows the phasor diagram for Eq. (6). At transition energy,
than in normal proton linacs.
to work with a rather low accelerating field E, about l0 times lower
"linac". On the other hand, this recirculation allows the latter linac
in order to recirculate the beam some l00 000 times through the SPS
which does not apply in a normal linac, is the small price to be paid
accelerating voltage is given by Eqs. (5) and (6). Such a reduction,
travelling wave and the particles; the corresponding reduction in
cannot be maintained throughout the acceleration cycle between the
Because of this slight change in RF frequency, perfect synchronism
frequency of the particles.
order to maintain an exact harmonic relationship with the revolution
cycle; this is the reason why the RF frequency must also increase, in
cumulative increase in the revolution frequency during the acceleration
hand, the small increase of velocity from turn to turn produces a
structure to be exactly periodic, as for an electron linac. On the other
traversal of the cavity is very small, which allows the loaded waveguide
For relativistic particles, the velocity increase during one
very close to 2IO.
sents the beam—induced voltage VL. For tightly bunched beams, IL isrf
Eq. (6) is the RF impressed voltage V, while the last term repre
axial electric field in the middle of the cavity. The first term in
where ¢ is the phase of the bunches with respect to the crest of the
value of E2 and of the RF power. OCR Output
Fig. 1 that T = 0 corresponds to a larger |Vrf|, i.e. to a maximuma) Because T and ¢S have always the same sign? it is clear from
<12>P = KVI2 + |V.|2 + 2IVI |vI¤¤s ¢1 Q [ bS]
or, from Fig. 1 when T = O:
_ "rf
The RF power is given by Eq. (1) as
is the beam—cavity coupling impedance.
c 8_ r (11)
Rzmzwhere
c b(10)V = E2·ej¢— r I
to
For simplicity“”, we now assume r = O in Eq. (6), which then reduces
Optimization for power efficienc
straight section of the SPS ring.
which is the maximum length available for a single cavity in a long
R 5 22.5 m (9)
To this condition should be added
(8)2 5 (215 m) v_/c
which may be rewritten as
(7)R/vn 5 0.718 ps or E4 903£
identical cells. OCR Output
1. The structure should be a wave—guide periodically loaded with
Summary
the relatively small nominal beam current I0 in Eq. (16).
which is an extremely large value at 200 MHz. This large value comes from
(17)R1/Q 2. 5000 S2/m
(9):
Inserting |V| = 1.8 MV and I0 = 70 mA, this yields with the condition
Q 903 903 I0(16)R 2. 11 mz 4 .L 2, .Z.... = ..... i
or with Eq. (15):
R22.2 = -5 .,5 903 RN
But condition (7) yields, with Eq. (3):
I(15)V Rom? = aLl: 4i
power efficiency at the nominal values of]V\ and I0:
hence with Eq. (ll), there is an optimum R25} which provides maximum
cb b(14)vl = ris lv
s bFor IV\Ȣand Ifixed, P is minimum when
r lv c b(13)V r I P=l|Vll —-L-l-+—Q+2cos¢» 8 b I
This may be rewritten as
currents, the cavities should be shortened. OCR Outputyielding maximum power efficiency; while for still higher beambeam current, the final cavities described in Table II come close tothe SPS by a factor 5, when multipulsing its CPS-injector. For such a
a) Already at present it is contemplated to increase the beam current in
increased"’.
power efficiency, it could do so in the future, if the beam current is
and energy gain per turn; but according to condition (15) for maximum
choice do) optimum power efficiency at the design values of beam current
this choice of accelerating structure does not provide (nor could any other
parallel, and to optimize it for maximum series impedance R2. Obviously,
Therefore, it was decided to use the simpler structure with all bars
times the nominal value.
while condition (16) can still only be met with a beam current several
practically unchanged. Conditions (8) and (9) are then easily fulfilled,g g
parallel to the first one, reduces vto v/c = 0.1 while R1/Q remains
other hand, going to a simpler structure where the second set of bars is
violates condition (9) and still fails to verify condition (16). On the
n/2 mode between adjacent bars. The maximum length 2 allowed by Eq. (8)
Orders of magnitude are R1/Q = 500 Q/m at 200 MHz and vn/c = 0.2 at
The bar passband is of the backward wave type.
the structure is operated in w mode (i.e. H/2 between adjacent bars).
and to provide a resonant coupling between each set of parallel bars when
envelope. The second set of bars is used to produce a large bandwidth,
alternately by horizontal and vertical bars placed across a circular
bandwidth. This structure contains two sets of drift tubes, supported
the cross—bar structure appears to have the largest R1/Q and the largest
Among all structures suitable for accelerating relativistic protons,a)
CHOICE OF THE ACCELERATING STRUCTURE
and (16).
turn and beam current, 2 and R1/Q should verify conditions (8), (9)
3. For optimum power efficiency at the design values of energy gain per
the transition frequency (200.222 MHz).
The travelling wave should be exactly synchronous with the beam at
7.
flowing. The surface finish of the copper is better than 5 um. OCR Output
line is turned to the top of the cavity, where no electric current is
a cylinder and welded longitudinally. In the final assembly, the weld
clad with copper by hot rolling. Afterwards, the sheets were rolled to
copper: 5 mm of copper on 20 mm of steel. The flat steel sheets were
The cylindrical envelope is made of ordinary steel clad with OFHC
Manufacturing of the cavities
4. TECHNOLOGY
the optimum is very flat.
has led to the set of parameters shown in Table II (p. l0). As usual,
0.067& and condition (8) was not fulfilled. For n/2 mode, optimization
and 2v/3 modes were investigated; in the latter case v_/c was at most
Once 2 is determined, R2 is optimized under condition (8). Both n/2
therefore the matching of the couplers is less critical.
is no impedance transformation by the cavity between these drift tubes, and
between the two extreme drift tubes be a multiple of H; in that case there
total number of drift tubes is chosen in such a way that the phase shift
at least five identical sections made of an integral number of cells. The
than Q.5 m. With a maximum allowed length of 22.5 m, this corresponds to
For manufacturing, the cavity had to be divided into sections shorter
tunnel.
to accommodate the cavity and all the ancillary equipment in the SPS
impedance, the inner cavity diameter had to be limited to 750 mm in order
a somewhat larger cavity diameter would yield a slightly better series
aperture), drift tube length, stem dia eter, cavity diameter. Although
have been varied: drift tube diameter (determined by the necessary beam
using a classical bead perturbation technique. All geometrical dimensions
Many reduced scale (1:5) models of the structure have been measured,
drift tube assembly (Fig. 3) can easily be taken out and replaced.
by horizontal bars (Fig. 2). It was designed in such a way that each
taining a set of identical and equally spaced drift tubes, all supported
Consequently, the structure is made of a cylindrical envelope con
the regulation of the cooling water temperature to within i7.5°C. OCR Output
assemblies at CERN. An overall, fine tuning of f25 kHz is provided by
the spacing between pedestals before brazing of the final drift tube
was measured. The frequency error was corrected by carefully adjusting
ll drift tubes especially used for this purpose, and the w/2 mode frequency
each section individually. The section envelope was fitted with a set of
tuned to the transition frequency at r/2 mode. This was achieved by tuning
to avoid any variable tuning in the cavities. Nevertheless, they must be
As mentioned, the original purpose of travelling wave operation was
Tuning of the cavity sections
than 2 X l0-G Torr.
Under normal working conditions, the vacuum in the cavities is better
resonator.
tested successfully under a peak current of 30 A/cm in a A/4 coaxial
holes: they normally carry a peak current of 3 A/cm, but they have been
case, for example, of the contacts between the pedestals and the envelope
inserted in grooves which are machined in the OFHC copper. This is the
All RF contacts are provided by silver-plated copper-beryllium springs,
system is made of copper or stainless-steel parts.
to it by an epoxy resin with good thermal conductivity. The whole cooling
waterpipes (with l20 mm! bore) running all along the structure and glued
O.&°C along a stem. The envelope itself is cooled sufficiently by 8
the temperature difference along a pedestal radius is l.1°C; it is only
the matched load at the end of the cavity. At the nominal field level,
circuits being connected in parallel; the same waterflow then cools
The total waterflow per cavity is 550 litres/minute, all cooling
by stainless steel flanges.
electron-beam welded. On their outside ends, the stems are terminated
perfect tightness against water, both ends of the stems have been
stems, these are cooled by a high speed waterflow. In order to ensure
together under vacuum. Since half of the power dissipation occurs on the
The drift tube assemblies are made of OFHC copper pieces brazed
9.
bea loading. OCR Outputb) The power dissipated in the cavities increases only slightly with
the stem diameter has been increased from 85 um to 86.5 nm.
a) For practical reasons during brazing of the drift tube assemblies,
13 kWPower dissipation per cavity
293 kwPower flux without beam loading PO = E5/R2
89 kV/mAxial electric field (without beam loading) E0 = lv/zlPower attenuation Zol = m2/(vgQ) 0.0é56 neper
1.h MQBea cavity coupling impedance TP = RZZZ/8
0.712 usFilling time 2/v
20.196 mInteraction length 2 = SQ cells
20.570 m2 half-cells for the input and output couplersCavity length: 5 sections of 11 cells, including
27.1 kQ/mSeries impedance R2
0.0946vg/c
19650Q (measured on the final, full scale cavity)
611 QmR1/Q
85 mmStem diameter
150 mmDrift tube length
170 mmDrift tube outer diameter
130 mmDrift tube inner diameter
750 mmCavity inner diameter
376 nmCell length (BA/4)
to 191.2 MHzto w mode)
221.6 MHzLower bar passband (0 mode
w/2Operating mode at transition frequency (200.222 MHz)
Parameters of the SPS travellinz wave structure
Table II
10.
being fitted with a 200 MHZ rejecting filter. OCR Outputa number of cells; they couple as strongly as possible to 629 MHz whileprobes with resistive loads have been designed to be put at the top ofprovide insufficient coupling to the 629 MHz mode. Therefore, damping
a) Since the time of the conference, these end-plate loops have proven to
maximum value for the RF power which is required in the presence of beam loading:
cAssuming again T = 0, we get from Eq. (l2) with |Vb| = rlb, the following
the same cavity voltage V against beam loading, as shown clearly by Fig. 1.
Nevertheless, the amplifiers must deliver more power in order to maintain
would otherwise go into the terminating load.
of the beam, and the beam power is merely subtracted from the power which
the bea towards the feeder line: the power amplifiers ignore the presence
sign as the particle velocity. Therefore, there is no RF power induced by
(of the synchronous space—harmonic) of the travelling wave be of the same
cavity end which must be fed by RF power in order that the phase velocity
From Eq. (4), the beam induced field vanishes at z = O, i.e. at the
6. BEAM LOADING AND RF POWER
once the da ping loops are installed“’.
dinal mode (with E_ # 0 on the cavity axis) and will hopefully be suppressed
ing in the cavities. This instability seems to be driven by a longitu
observed at high energy in the SPS, together with a 629 MHz signal grow
Bunch-to-bunch dipole oscillations of the beam have already been
rating mode, and as much as possible to all other modes.
are designed in order to couple as little as possible to the main accele
end-plate; they are terminated by 600 W, air—co0led loads. These loops
Therefore, two special coupling loops have been foreseen on each cavity
to the higher modes, they do not provide sufficient damping for them.
verse instabilities. Since the main couplers are not intended to couple
a mode is large enough,it can drive the beam into longitudinal or trans
synchronous with the beam. If the beam-cavity coupling impedance for such
In the higher passbands of the accelerating structure, many modes are
5. HIGHER MODES OF THE ACCELERATING STRUCTURE
ll.
1.06 MV. OCR Output
From Eq. (21), the peak accelerating voltage per cavity would then be
value; from Eq. (20), the corresponding power efficiency would be 0.828.
with the actual cavities. This current is 5.4 times the present nominal
I0 = 0.377 A for the beam current which would yield maximum power efficiency
The nominal P = 340 kW inserted in Eq. (21) gives IL = 0.754 A or
factor, it was decided to specify a power level of 500 kW per amplifier.
the possible increase of beam current in the future, and for some safety
I0 = 70 mA. With provision made for the losses in the feeder lines, for
power required at the input of the cavity, for an average beam current
(19) gives P = 340 kW with a power efficiency PL/P = 0.261. This is theSInserting now the nominal values of lvl, ¢and Ib in Eq. (18) and
b rn(1 + COS ¢n) ° = 2 with |V| rclb . ( l)4P I2 =-—-—-——-—
c Sto maximum power efficiency for given values of P, rand ¢
condition inserted in Eq. (18) determines the beam current which corresponds
cbwhen |V| = rl, which is exactly the sa e condition as Eq. (14). This
(Z0)(Pb) 2 cos ¢ r max
For a given ¢_, the power efficiency reaches its maximum value
E? = 4 cos ¢S ;rE-+ ——~—- + 2 cos (19)vl rllcb c b lvl
deduced from Eq. (13), which yields for the power efficiency
SThe power Pk = % ]V|Ib cos ¢delivered to the beam is most easily
8 r cb b s+x "+2|V|I ¤¤s¢ l (18)P=—¥|E-E
I2!
the usual ceramic disc, resulting in more uniform dielectric losses. OCR Output
field is roughly parallel to the cera ic, but it is more uniform than in
radially in order to form a big A/4 stub on the air side. The electric
formed into a short ceramic cylinder, by expanding the coaxial line
breakdown. Instead of the usual cera ic disc, the window has been trans
The basic design principle was to have it easily replaceable in case of
The most remarkable part of the couplers is probably the RF window.
this is very important to prevent beam instabilities.
adjacent modes, thus reducing their coupling impedance with the beam:
edges. Consequently, the terminating load of the cavity also damps the
the w/2 operating mode, just because the latter is far from the passband
It was possible to make the matching of the couplers broadband around
up to outlets at the bottom of the big stubs (Fig. 5).
This air is forced down and flows along the coaxial lines of the couplers,
four high·speed fans (working with 400 Hz A.C.) blow air into the line.
the window into 100 Q at the T—junction. Just above the T—junction,
cascade of two A/4 transformers which transforms the 50 Q impedance at
Each piece of line from the windows to the T—junction is essentially a
practically loaded with their 50 Q characteristic impedance by the structure.
The two short coaxial lines from the windows to the coupling loops are
measurements on the first two sections of the first cavity hith 22 cells).
reduced scale model with 16 cells; the final adjustments were made by
The shape of the couplers was determined by measurements on a l:5
drift tube assembly (Fig. 4).
end up into two coupling loops connected to the pedestals of the first
T-junction into two smaller ones, the central conductors of which eventually
matched load at the other end. The big 50 Q coaxial line splits at a
which connect the cavity to the power amplifier at one end, and to a
provide a matched transition between the cavity and the big coaxial lines
Both ends of the cavity are equipped with identical couplers. They
7. INPUT AND OUTPUT COUPLERS
I3.
at the end of each acceleration cycle. OCR Outputreconditioning pulse of 600 kW during 300 us is now being inserted
a) In order to avoid this periodic reconditioning of the cavities, a
to the 550 kW level
of hard conditioning are then necessary in order to bring the cavity back
the maximum level steadily goes down to 350 kW after one week. Two hours
level up to 550 kW; but even when the cavity is being used for acceleration,
tube assembly. Progressive conditioning of the cavity pushes this maximum
to be limited by multipactoring between the end plate and the first drift
On the other hand, the maximum power which can be fed into a cavity seems
very fast during the acceleration cycle, with no noticeable RF reflection.
Once the cavity has been conditioned, this power range is being traversed
still occurs on the windows, at a power level ranging from 10 to 50 kW.
As shown by the temperature rise at the window rings, multipactoring
disappeared.
yield. with the titanium coated window assemblies, sputtering has totally
chosen for its low secondary emission coefficient and its low sputtering
resistance being at least 500 MQ measured in vacuum). Titanium has been
the inner side of the ceramic was vacuum flashed with titanium (the D.C.
layer of 0.5 um which was also applied to the inner conductor of the line;
Afterwards, the gold coating was replaced by a vacuum—deposited titanium
resulted in a nicely conducting window and a large reflection of RF power.
stainless steel, and progressively reaching the other end. This process
line and onto the ceramic, starting from the end close to the coated
RF power, this gold coating was sputtered onto the inner conductor of the
deposited gold layer of 2 um, and the ceramic was left uncoated. Under
the early windows, the first copper layer was coated with an electro
layer of 10 pm, then with a vacuum-deposited copper layer of 2 um. In
exposed to RF fields are coated, first with an electro—deposited copper
cooled (Fig. 6). The caps and that stainless steel cylinder which is
a Fe—Ni-Co alloy, which are brazed to the ceramic; these caps are water—
metallic pieces of stainless steel are covered at their ends by caps of
ductivity (roughly 10 times higher than alumina). The neighbouring
The ceramic itself is beryllium oxide, because of its good thermal con
lh.
Rosenthal-Stemag). OCR Output
This ceramic is basically a magnesium silicate ("Frequenta", made by
moulded with a uniform hydrostatic pressure applied from all sides.
losses; but in order to achieve this performance, the ceramic must be
power level of 3 MW (travelling wave) before cracking under dielectric
which is radiation resistant. With this shape, the ceramic can stand a
both ends also, the inner conductor is supported by a triangular ceramic,
contacts on the inner conductor at both ends of each line section. At
expansions between inner and outer conductor are compensated by sliding
The line is made of sections 5.55 m long. The different thermal
under natural cooling by air convection and by heat radiation.
aluminium. It can transport a CW travelling wave of 750 kW at 200 MHz,
normal air, The inner conductor is copper, the outer conductor is
The feeder lines are big 3&5 mm, 50 0 coaxial lines, containing
9. FEEDER LINES
A/A transformer is water cooled; in the second case, it is air—cooled.
dielectric of which can be either alumina or air. In the first case, the
30 mm thick, while the matching element is a A/é coaxial transformer, the
separated: the window which stands the water pressure is an alumina disk,
50 Q coupler on the other side. Finally, the two problems have been
15 atm), and which provides a transition from the 5.8 Q water line to the
on one side (the water column is 60 m high, and the test pressure is
problem is to produce an input window which stands the static water pressure
is increased by addition of a small amount of sodium nitrite). The main
line; it is heated by dielectric and conduction losses (the conductivity
(Fig. 7). Water is both the dissipative and the cooling element of the
with a uniform 6Ug" coaxial line, 6 m long, filled with water as dielectric
200 MHz, and capable of dissipating 500 kW of RF power. This is achieved
The output coupler must be terminated by a load which is matched at
8. TERMINATING LOAD
l5.
a) In fact, the amplifier interlock switches it off at a VSWR of 1.4. OCR Output
ting voltage.
be stepped up in power so as to compensate for the reduced accelera
interruption, provided the remaining tubes of all amplifiers can
faulty acceleration cycle, and acceleration can continue without
Switching to the new operation mode may be done at the end of the
cavity is reduced in proportionality to the number of tubes left.
three other tubes. ln such a case, the accelerating voltage in the
2. lf one out of the four tubes fails, operation may continue with the
matched load when looking towards the amplifier.
1. If the four tubes have the s me output impedance, the cavity sees a
ones:
Among other advantages, the use of hybrids presents the following
shown in Fig. 8 and Fig. 9.
by using three coaxial hybrids (which are 3 dB directional couplers) as
the 500 kW level. The final solution combines the output of four tubes
necessary to combine the output power of several tubes in order to reach
on the market, the choice fell on high—power tetrodes. Still it was
power of 500 kW at 200 MHz. Because 200 MHz klystrons were not available
Each cavity is fed by an amplifier capable of delivering a CW output
l0. POWER AMPLIFIERS
the VSWR as measured at the a plifier output is always less than 1.25
For the complete system, including feeder line, couplers, cavity and load,
during acceleration, the VSWR of both lines is always smaller than 1.05.
are about 95 m and 110 m, respectively). In the frequency range used
0.037 neper for one line and 0.043 neper for the other (the line lengths
The total attenuation between the power amplifier and the cavity is
1 MHz. OCR Output
bandwidth of the whole amplifier chain, from the low level to 500 kW, is
The bandwidth of one unit, measured at the 3 dB points, is 3 MHz. The
deliver a CW power of 140 kW, that is 10% more than the nominal 125 kW.
Finally, it should be mentioned that the amplifier units can safely
50 Q loads.
by 8 small coupling loops resonating at 840 MHz and terminated by small
840 MHz, which killed the first tubes. This mode was selectively damped
this circuit also showed a most dangerous oscillation on a H1] mode at
ferrite in order to prevent breakdown at the output coupling loop. But
value for all frequencies. The anode circuit was fitted with U-17
line, as seen between the control grid and the screen grid, at a low
by the very lossy Eccosorb ZN, which keeps the input impedance of this
U—l7. The screen—grid circuit is a very low impedance line tenninated
range from 30 MHz to 50 GHz. The control grid circuit is fitted with
and Cuming, which has large electric and magnetic losses in the full
range from 400 to 2000 MHz; the other is the Eccosorb ZN from Emerson
losses at 200 MHz but presents a large peak of magnetic losses in the
respect: one of them is the Siferrit U—l7 from Siemens, which has low
vent higher mode oscillations. Two kinds of ferrite were used in this
usual in high power amplifiers, they had to be damped in order to pre
tubes (Fig. l0). They use a grounded screen-grid configuration. As
The a plifier units themselves allow a quick replacement of the
of six tubes.
time as guaranteed by the manufacturer is a total of 30,000 hours per set
type RS 2004 J, in order to meet the SPS specifications. The tube life
hybrids. The tubes were especially developed by Siemens as tetrode
the 50 kW output of which is divided into four parts by using smaller
The four tubes of 125 kW each are driven by another identical tube,
17.
a) On leave from Brookhaven National Laboratory. OCR Output
charge, G. Rogner.
a visitor in the SPS for one year in 1972-73, and to our engineer-in
The mechanical design of the cavities is due to P. Grandu”, who was
amplifiers, and the author was responsible for the accelerating cavities.
touched upon here). H.P. Kindermann was responsible for the power
D. Boussard was responsible for the low—level system (which was not
RF group of the CERN SPS Division, under the leadership of C. Zettler.
The present paper describes the work which has been done by the
Acknowledgements
Colorado), but which are now delivered by Quartex (Paris).
which were first ordered directly from the U.S.A. (Coors, Golden,
The couplers were made at CERN except for the beryllium oxide windows,
Germany). The terminating load was made by Varian (Palo Alto, California).
(Munich). The accelerating cavities were made by Leybold—Heraeus (Hanan,
and Munich). The hybrids and the feeder lines were made by Spinner
The power amplifier plant was made by Siemens (Berlin, Erlangen
ll. MANUFACTURERS
18.
North*Holland Publishing Company, Amsterdam, 1970, p. 707-709. OCR Output"Linear Accelerators" (Edited by P.M. Lapostolle and A.L. Septier),
3. G. D6me: "Review and survey of accelerating structures", in
Energy Accelerators, Frascati, September 1965, p. 38-41.300 GeV proton synchrotron", V International Conference on High
2. W. Schnell: "A wide band travelling wave accelerating method for a
cram/1050, Geneva, 14 January 1972, p. 65-79.1. C. Zettler: "The Acceleration System", in "The 300 GeV Program e",
REFERENCES
19.
Fig. 1 Phaser diagram for Eq. (6)
9; \€P
Vrf OCR Output