6 AP HTS Transformer Technology

download 6 AP HTS Transformer Technology

of 25

Transcript of 6 AP HTS Transformer Technology

  • 7/29/2019 6 AP HTS Transformer Technology

    1/25

    HTS Transformerv

    c wen er y

    Oak Ridge National Laboratory

    Ed PlevaWaukesha Electric Systems

    June 30, 2010

    Team:

    - c wen er y, ona an em o, v n s,Robert Duckworth, Randy James, Isidor Sauers, EnisTuncer

    WES- Ed Pleva, Sam Mehta, Vinay Mehrotra, Bob

    1 Managed by UT-Battellefor the Department of Energy

    Del Vecchio

  • 7/29/2019 6 AP HTS Transformer Technology

    2/25

    Project Purpose

    To establish the technical and economic benefits ofHTS Transformers of >10-MVA ratings.

    To carry out materials studies in support of thisdevelo ment.

    Supports DOE-OE Mission and Subprogram goals:Modernize electric grid; Smart Grid Program.

    Enhance security, reliability and efficiency of energyinfrastructure.

    Develop revolutionary power equipment using HTS wires.

    Characterize dielectric materials and establish design rules.

    2 Managed by UT-Battellefor the Department of Energy

    2

    .

  • 7/29/2019 6 AP HTS Transformer Technology

    3/25

    Program Historyase : , , an

    1 MVA 1- prototype tested 199813.8kV HV/6.9kV LV; Bi-2212; 25 K

    HV, vacuum, ac loss testing, cold mass assy at ORNL

    rea own cause y ;

    later reached 13.8 kV in airPhase 2: 2000 2005 (WES, SuperPower, ORNL and Energy East)

    5/10 MVA 3- prototype tested 2003-4. . -

    HV, ac loss testing, cooling system design/fab at ORNL

    Transformer failed HV dielectric tests; cracked epoxy

    insulation; root cause & lessons learned analysis done

    ase : resen ,

    WES using internal funds; DOEbase program funding to ORNL

    Conceptual design rework; 70-K YBCO;

    cryogen c e ec r c ac oss es ng,composite dewar development at ORNL

    Simplify manufacturing process

    Phase 4: Future (WES, SP, SCE, ORNL)

    3 Managed by UT-Battellefor the Department of Energy

    3

    Construct 28-MVA FCL Smart Grid Demo Transformer for SCE

  • 7/29/2019 6 AP HTS Transformer Technology

    4/25

    Why HTS Transformers? HTS transformer develo ment is underwa worldwide.

    Projects in Japan, Korea, China, India, Australia.

    Many transformers in the grid are aging, creating a ready HTS market.

    2 .

    Conventional transformer losses are 40% of total grid loss because they are sonumerous

    If HTS transformer is 0.2% more efficient, losses are reduced by 1/3

    ~ 107 ton annual CO2 reduction

    Transformer size, weight, fire hazard, and environmental impact reduced.

    Overload o eration is ossible with no loss of lifetime.

    Fault current limiting (FCL) capability is possible supports Smart Grid.THIS IS UNDER DEVELOPMENT IN A NEW COLLABORATION WITH SUPERPOWER

    AND SOUTHERN CALIFORNIA EDISON.

    FCL transformer development helps other FCL projects

    High-voltage insulation, dewar development

    Conductor cooling, YBCO properties

    4 Managed by UT-Battellefor the Department of Energy

    4

  • 7/29/2019 6 AP HTS Transformer Technology

    5/25

    Fault Limiting Equipment is

    Enabler of Smart GridWithout limiter

    Fault currents are growing

    inexorably in expanding urban grids

    With HTS limiter

    Need fast limiting of fault currents avoid damage to grid and equipment

    avoid power interruptions

    Smart Grid vision of re-configurable networks

    re uires connectivit

    Fault currentlimitinge ui ment

    5 Managed by UT-Battellefor the Department of Energy

    5

  • 7/29/2019 6 AP HTS Transformer Technology

    6/25

    OUTLINE Research plan

    Summary of new 28-MVA FCL Smart GridTransformer project

    Specifications Ed Pleva

    Overall configuration

    Windin details

    Composite dewar long-term testing

    AC Loss testing and calculation

    550-kV BIL flashover test coil Bill Schwenterly

    Bushing tests

    Technology Transfer/Collaborations

    Future Plans

    6 Managed by UT-Battellefor the Department of Energy

    6

  • 7/29/2019 6 AP HTS Transformer Technology

    7/25

    Overall Research Planon nuous y evo ve concep ua es gns or rans ormers us ng

    YBCO immersed in pressurized, subcooled nitrogen.

    Near-term, develop FCL HTS analog for conventional unit.

    - .

    Far-term, with low-cost conductor and refrigeration, develop HTSunit that exceeds conventional performance at same cost insmaller envelope.

    Carry out high-voltage tests to qualify electrical insulationsystems up to 115-138 kV operating voltage and 650 kV BIL.

    Perform ac loss, stabilit , and fault handlin tests on sub-scaletest coils.

    Support development of suitable dewar vessels.

    Perform other materials tests as needed.

    NEW PHASE In FY2010, WES/ORNL team joined withSuperPower and Southern Calif. Edison in a successfulproposal to develop a 28-MVA superconducting FCL

    7 Managed by UT-Battellefor the Department of Energy

    7

    transformer for SCEs Smart Grid site in Irvine, California.

  • 7/29/2019 6 AP HTS Transformer Technology

    8/25

    FY 2010 activity has centered on securing new

    , ,losses, and high-voltage insulation.

    Funding Action DOE Smart Grid RegionalDemonstration funding has been approved for 28-MVA

    .

    Milestone Open-top composite dewar successfully

    passed four-month long-term test.

    Milestone Further ac loss tests on YBCO simulatedHV coils were carried out.

    550-kV BIL.

    Long-term testing will begin on epoxy resin bushing.

    8 Managed by UT-Battellefor the Department of Energy

    8

  • 7/29/2019 6 AP HTS Transformer Technology

    9/25

    DOE Smart Grid Regional

    for a 28-MVA HTS FCL transformer.

    Rating: 28-MVA; 70.5 kV / 12.47 kV; 132 A / 1296 A

    13.1% impedance to match existing conventional units.

    Increase to 26% im edance in HTS uench ives 50% reductionof fault current.

    Continuous operation at 40.6 MVA (145% of rated load) withextra liquid nitrogen supply.

    Normal operation at 70 K, 3.4 bar.

    HTS is sized for sufficient margin on 40.6-MVA current.

    .

    Current leads are sized for 125% of 28-MVA current.

    Maximum current lead temperature rises to

  • 7/29/2019 6 AP HTS Transformer Technology

    10/25

    Conceptual Design

    manufacturing techniques wil lutil ize experienced WES coilwinders.

    Uses WES design software &

    ORNL design spreadsheet.

    70-K pressurized, subcooled

    for oil.

    HTS tape with parallel resistive

    conductor for stability andau an ng.

    Coil dewar surrounds warmsteel core.

    - .

    Proof of concept with single-phase Alpha-1 (normalconductor) and Alpha-2 (HTS)

    10 Managed by UT-Battellefor the Department of Energy

    10

    un s.

  • 7/29/2019 6 AP HTS Transformer Technology

    11/25

    2G-HTS Conductor Architecture Under

    Original design used parallel copper.Motivated b ANSI re uirement for a conventional non-FCL

    transformer to recover normal operation after a 2-sec fault.

    This had disadvantages:Re uired amount of co er is nearl as much as in a

    conventional unit.

    Copper produces high eddy current losses.

    Evaluatin allo o tions for re lacin co er.High resistance after HTS quenches reduces fault current to

    about half that of conventional unit.

    Eddy current losses are reduced.

    SCE substation has type CO-8 distribution breakers.Opening t ime is ~1 sec in area of interest for 28 MVA.

    11 Managed by UT-Battellefor the Department of Energy

    11

    .

    Few-minute re-cool time.

  • 7/29/2019 6 AP HTS Transformer Technology

    12/25

    The windings will be similar to WESs

    . HV Continuous disc winding;

    single conductor, 8-12 turns/disc.

    crew w n ng; - con uc ors n

    parallel. Transposed to give uniformcurrent sharing.

    individually-tested modules to limitamount of conductor at risk in a testfailure.

    Standard 6 or 12 mm 2G HTS tape withhigh resistance alloy strip.

    Provides robust conductor that can be

    insulated on high-speed machine.

    High-resistance

    alloy

    12 Managed by UT-Battellefor the Department of Energy

    12

    InsulationHTS

  • 7/29/2019 6 AP HTS Transformer Technology

    13/25

    28-MVA unit will be proof-tested at SCE

    - , .

    13 Managed by UT-Battellefor the Department of Energy

    13

  • 7/29/2019 6 AP HTS Transformer Technology

    14/25

    Technical Progress

    S. W. Schwenterly, ORNL

    14 Managed by UT-Battellefor the Department of Energy

    14

  • 7/29/2019 6 AP HTS Transformer Technology

    15/25

    The open-top composite dewar

    - . Dewar performed well in vacuum and thermal cycling tests in

    FY2009. Paper at 2009 Cryo.Eng. Conference.

    -

    maintain10-3 torr warm,

  • 7/29/2019 6 AP HTS Transformer Technology

    16/25

    Test coils help predict ac loss.- - .

    HTS tape is bare, insulation is only around co-wound conductor to preventbuckling. 4-mm disc spacers machined from clear plastic.

    Simulated high voltage winding 26 six-turn discs, continuously wound by, . -mm ape, . cm , . cm eng , m o ape, -

    measured Ic (equivalent to 50 A rms).

    Electronic loss measurement with lockin amplifier external toroidal air-core bucking transformer to cancel inductive signal has been added.

    Validation third coil with only copper showed the expected resistive losses, atboth RT and 77 K.

    New cryostat in the composite dewar with pumped LN bath allows testingat reduced tem erature, with no effect b nearl metal wall.

    16 Managed by UT-Battellefor the Department of Energy

    16

    Coil with co-wound copper was tested at reduced temperature and

    several frequencies in this dewar.

  • 7/29/2019 6 AP HTS Transformer Technology

    17/25

    Losses in HV prototype coils exhibit non-linearcurrent dependence

    Losses (Ipeak/Ic)n. Losses are similar for

    co-woun u an

    Stainless. ForIpeak/Ic < 0.4, n ~

    . .

    Consistent with

    ferromagnetic Ni-W

    ForIpeak/Ic > 0.4, n ~ 2.

    Eddy or coupling

    mec an sm

    17 Managed by UT-Battellefor the Department of Energy

    17

  • 7/29/2019 6 AP HTS Transformer Technology

    18/25

    Losses in HTS/Cu coil varied as square of

    fre uenc and were tem erature inde endent. Dividing ac loss by square

    of frequency collapses the.

    Loss proportional to squareof the frequency alsosuggests coupling or eddymec an sm.

    Very l itt le change in losswhen temperature is lowered

    rom o sugges smost of loss from Cu or HTSsubstrate.

    HTS/SS coil will et similar

    18 Managed by UT-Battellefor the Department of Energy

    18Presentation_name

    tests.

  • 7/29/2019 6 AP HTS Transformer Technology

    19/25

    Losses are higher at the coil ends

    Each VT pair covers 2 discs.

    19 Managed by UT-Battellefor the Department of Energy

    19

    a a e s a en s ncrease osses.

  • 7/29/2019 6 AP HTS Transformer Technology

    20/25

    Insulation studies for 550 kV BIL

    . Similar 350-kV BIL coi l

    passed all tests in FY2008Flashover

    New WES Test Coil

    Standard WES designpressboard structure

    Copper conductor withWES polymerinsulation

    LVHV

    LV & HV disc windings

    HV Tests in LN in Fall2009

    Bushin Test

    Commercial 650 kVBIL bushingsuccessfully testedshor t-term in FY09

    Long-term testplanned for smaller28-kV model

    20 Managed by UT-Battellefor the Department of Energy

    20

  • 7/29/2019 6 AP HTS Transformer Technology

    21/25

    Test Results - 550-kV Coil

    HV coil was impulsed from topwith bottom & LV coil grounded.

    -

    1.8 bar absolute to stop boiling.Passed 3 impulse shots at -550 kV

    .

    Warmed up and un-grounded the

    HV coil.Test with ac voltage showed 2.2 pC

    partial discharge at 102 kVac.

    Passed 1-min withstand at 201

    kVac.650-kV impulse tests planned if

    fundin available.

    21 Managed by UT-Battellefor the Department of Energy

    21

  • 7/29/2019 6 AP HTS Transformer Technology

    22/25

    FY 2010 Plans FY 2010 Performance Seek new funding options DOE Smart Grid Regional

    Demonstration funding has been

    MilestoneYBCO ac loss andIc testing

    approved for 28-MVA FCL unit.

    Carried out further Ic and ac loss testson YBCO sample coils with co-wound

    Carry out further dielectrictesting

    .

    New 115 KV/550 kV BIL coil passed550kV impulse / 200 kV withstand;

    long-term bushing tests started.es one ompos e ewar

    testing and procurement

    Modify WES transformer

    Long-term tests on small open-topdewar completed successfully; newprocurement under consideration.

    WES ro rams are now in use for HTS

    design programs for HTS Begin 5/7-MVA single-phase

    prototype substation

    unit designs. Replaced by new 28-MVA FCL unit

    project.

    22 Managed by UT-Battellefor the Department of Energy

    22

  • 7/29/2019 6 AP HTS Transformer Technology

    23/25

    Technology Transfer, Collaborations

    New collaboration with SuperPower and SCE on a Smart Gridproposal for fault current limiting transformers has receivedDOE funding approval.

    Team possesses strong complementary abili ties in research,engineering, manufacturing, & utility operation.

    . ,2X WES to ORNL, Smart Grid FCL transformer team meetingsat WES and SP. Communication several t imes a week by phoneand E-mail.

    Team is working with suppliers to develop dewars and qualifybushings. A 650-kV commercial bushing was used for impulse

    Paper on composite dewar was presented at 2009 CEC/ICMC.

    23 Managed by UT-Battellefor the Department of Energy

    23

    Applied Superconductivity Conference.

  • 7/29/2019 6 AP HTS Transformer Technology

    24/25

    FY 2011 Plans

    Su ort 28-MVA FCL unit conce tual desi n and en ineerinanalysis.

    Cryogenic, electrical, mechanical issues

    Support detail design of single-phase Alpha-1 unit with

    Qualify YBCO materials for the reference design.Support SuperPower and WES in specification and

    roduction of HTS FCL conductor laminated to a resist ivemetallic strip

    Test sample coils with SP conductor wound by WES in

    subcooled liquid nitrogen: -multiple-tape coils

    Critical current and stability under operating conditions

    Fault current handling, recovery, and load restoration after

    Address Technology Issues.

    Continue long-term bushing tests in LN.

    24 Managed by UT-Battellefor the Department of Energy

    24

    of single-phase test dewar for proof of concept.

  • 7/29/2019 6 AP HTS Transformer Technology

    25/25

    WES and ORNL continue to be committed

    to the development of HTS transformers.

    We welcome the

    artici ation of

    SuperPower

    and SCE!

    QUESTIONS?

    25 Managed by UT-Battellefor the Department of Energy

    25