6 AP HTS Transformer Technology
-
Upload
joao-monteiro -
Category
Documents
-
view
220 -
download
0
Transcript of 6 AP HTS Transformer Technology
-
7/29/2019 6 AP HTS Transformer Technology
1/25
HTS Transformerv
c wen er y
Oak Ridge National Laboratory
Ed PlevaWaukesha Electric Systems
June 30, 2010
Team:
- c wen er y, ona an em o, v n s,Robert Duckworth, Randy James, Isidor Sauers, EnisTuncer
WES- Ed Pleva, Sam Mehta, Vinay Mehrotra, Bob
1 Managed by UT-Battellefor the Department of Energy
Del Vecchio
-
7/29/2019 6 AP HTS Transformer Technology
2/25
Project Purpose
To establish the technical and economic benefits ofHTS Transformers of >10-MVA ratings.
To carry out materials studies in support of thisdevelo ment.
Supports DOE-OE Mission and Subprogram goals:Modernize electric grid; Smart Grid Program.
Enhance security, reliability and efficiency of energyinfrastructure.
Develop revolutionary power equipment using HTS wires.
Characterize dielectric materials and establish design rules.
2 Managed by UT-Battellefor the Department of Energy
2
.
-
7/29/2019 6 AP HTS Transformer Technology
3/25
Program Historyase : , , an
1 MVA 1- prototype tested 199813.8kV HV/6.9kV LV; Bi-2212; 25 K
HV, vacuum, ac loss testing, cold mass assy at ORNL
rea own cause y ;
later reached 13.8 kV in airPhase 2: 2000 2005 (WES, SuperPower, ORNL and Energy East)
5/10 MVA 3- prototype tested 2003-4. . -
HV, ac loss testing, cooling system design/fab at ORNL
Transformer failed HV dielectric tests; cracked epoxy
insulation; root cause & lessons learned analysis done
ase : resen ,
WES using internal funds; DOEbase program funding to ORNL
Conceptual design rework; 70-K YBCO;
cryogen c e ec r c ac oss es ng,composite dewar development at ORNL
Simplify manufacturing process
Phase 4: Future (WES, SP, SCE, ORNL)
3 Managed by UT-Battellefor the Department of Energy
3
Construct 28-MVA FCL Smart Grid Demo Transformer for SCE
-
7/29/2019 6 AP HTS Transformer Technology
4/25
Why HTS Transformers? HTS transformer develo ment is underwa worldwide.
Projects in Japan, Korea, China, India, Australia.
Many transformers in the grid are aging, creating a ready HTS market.
2 .
Conventional transformer losses are 40% of total grid loss because they are sonumerous
If HTS transformer is 0.2% more efficient, losses are reduced by 1/3
~ 107 ton annual CO2 reduction
Transformer size, weight, fire hazard, and environmental impact reduced.
Overload o eration is ossible with no loss of lifetime.
Fault current limiting (FCL) capability is possible supports Smart Grid.THIS IS UNDER DEVELOPMENT IN A NEW COLLABORATION WITH SUPERPOWER
AND SOUTHERN CALIFORNIA EDISON.
FCL transformer development helps other FCL projects
High-voltage insulation, dewar development
Conductor cooling, YBCO properties
4 Managed by UT-Battellefor the Department of Energy
4
-
7/29/2019 6 AP HTS Transformer Technology
5/25
Fault Limiting Equipment is
Enabler of Smart GridWithout limiter
Fault currents are growing
inexorably in expanding urban grids
With HTS limiter
Need fast limiting of fault currents avoid damage to grid and equipment
avoid power interruptions
Smart Grid vision of re-configurable networks
re uires connectivit
Fault currentlimitinge ui ment
5 Managed by UT-Battellefor the Department of Energy
5
-
7/29/2019 6 AP HTS Transformer Technology
6/25
OUTLINE Research plan
Summary of new 28-MVA FCL Smart GridTransformer project
Specifications Ed Pleva
Overall configuration
Windin details
Composite dewar long-term testing
AC Loss testing and calculation
550-kV BIL flashover test coil Bill Schwenterly
Bushing tests
Technology Transfer/Collaborations
Future Plans
6 Managed by UT-Battellefor the Department of Energy
6
-
7/29/2019 6 AP HTS Transformer Technology
7/25
Overall Research Planon nuous y evo ve concep ua es gns or rans ormers us ng
YBCO immersed in pressurized, subcooled nitrogen.
Near-term, develop FCL HTS analog for conventional unit.
- .
Far-term, with low-cost conductor and refrigeration, develop HTSunit that exceeds conventional performance at same cost insmaller envelope.
Carry out high-voltage tests to qualify electrical insulationsystems up to 115-138 kV operating voltage and 650 kV BIL.
Perform ac loss, stabilit , and fault handlin tests on sub-scaletest coils.
Support development of suitable dewar vessels.
Perform other materials tests as needed.
NEW PHASE In FY2010, WES/ORNL team joined withSuperPower and Southern Calif. Edison in a successfulproposal to develop a 28-MVA superconducting FCL
7 Managed by UT-Battellefor the Department of Energy
7
transformer for SCEs Smart Grid site in Irvine, California.
-
7/29/2019 6 AP HTS Transformer Technology
8/25
FY 2010 activity has centered on securing new
, ,losses, and high-voltage insulation.
Funding Action DOE Smart Grid RegionalDemonstration funding has been approved for 28-MVA
.
Milestone Open-top composite dewar successfully
passed four-month long-term test.
Milestone Further ac loss tests on YBCO simulatedHV coils were carried out.
550-kV BIL.
Long-term testing will begin on epoxy resin bushing.
8 Managed by UT-Battellefor the Department of Energy
8
-
7/29/2019 6 AP HTS Transformer Technology
9/25
DOE Smart Grid Regional
for a 28-MVA HTS FCL transformer.
Rating: 28-MVA; 70.5 kV / 12.47 kV; 132 A / 1296 A
13.1% impedance to match existing conventional units.
Increase to 26% im edance in HTS uench ives 50% reductionof fault current.
Continuous operation at 40.6 MVA (145% of rated load) withextra liquid nitrogen supply.
Normal operation at 70 K, 3.4 bar.
HTS is sized for sufficient margin on 40.6-MVA current.
.
Current leads are sized for 125% of 28-MVA current.
Maximum current lead temperature rises to
-
7/29/2019 6 AP HTS Transformer Technology
10/25
Conceptual Design
manufacturing techniques wil lutil ize experienced WES coilwinders.
Uses WES design software &
ORNL design spreadsheet.
70-K pressurized, subcooled
for oil.
HTS tape with parallel resistive
conductor for stability andau an ng.
Coil dewar surrounds warmsteel core.
- .
Proof of concept with single-phase Alpha-1 (normalconductor) and Alpha-2 (HTS)
10 Managed by UT-Battellefor the Department of Energy
10
un s.
-
7/29/2019 6 AP HTS Transformer Technology
11/25
2G-HTS Conductor Architecture Under
Original design used parallel copper.Motivated b ANSI re uirement for a conventional non-FCL
transformer to recover normal operation after a 2-sec fault.
This had disadvantages:Re uired amount of co er is nearl as much as in a
conventional unit.
Copper produces high eddy current losses.
Evaluatin allo o tions for re lacin co er.High resistance after HTS quenches reduces fault current to
about half that of conventional unit.
Eddy current losses are reduced.
SCE substation has type CO-8 distribution breakers.Opening t ime is ~1 sec in area of interest for 28 MVA.
11 Managed by UT-Battellefor the Department of Energy
11
.
Few-minute re-cool time.
-
7/29/2019 6 AP HTS Transformer Technology
12/25
The windings will be similar to WESs
. HV Continuous disc winding;
single conductor, 8-12 turns/disc.
crew w n ng; - con uc ors n
parallel. Transposed to give uniformcurrent sharing.
individually-tested modules to limitamount of conductor at risk in a testfailure.
Standard 6 or 12 mm 2G HTS tape withhigh resistance alloy strip.
Provides robust conductor that can be
insulated on high-speed machine.
High-resistance
alloy
12 Managed by UT-Battellefor the Department of Energy
12
InsulationHTS
-
7/29/2019 6 AP HTS Transformer Technology
13/25
28-MVA unit will be proof-tested at SCE
- , .
13 Managed by UT-Battellefor the Department of Energy
13
-
7/29/2019 6 AP HTS Transformer Technology
14/25
Technical Progress
S. W. Schwenterly, ORNL
14 Managed by UT-Battellefor the Department of Energy
14
-
7/29/2019 6 AP HTS Transformer Technology
15/25
The open-top composite dewar
- . Dewar performed well in vacuum and thermal cycling tests in
FY2009. Paper at 2009 Cryo.Eng. Conference.
-
maintain10-3 torr warm,
-
7/29/2019 6 AP HTS Transformer Technology
16/25
Test coils help predict ac loss.- - .
HTS tape is bare, insulation is only around co-wound conductor to preventbuckling. 4-mm disc spacers machined from clear plastic.
Simulated high voltage winding 26 six-turn discs, continuously wound by, . -mm ape, . cm , . cm eng , m o ape, -
measured Ic (equivalent to 50 A rms).
Electronic loss measurement with lockin amplifier external toroidal air-core bucking transformer to cancel inductive signal has been added.
Validation third coil with only copper showed the expected resistive losses, atboth RT and 77 K.
New cryostat in the composite dewar with pumped LN bath allows testingat reduced tem erature, with no effect b nearl metal wall.
16 Managed by UT-Battellefor the Department of Energy
16
Coil with co-wound copper was tested at reduced temperature and
several frequencies in this dewar.
-
7/29/2019 6 AP HTS Transformer Technology
17/25
Losses in HV prototype coils exhibit non-linearcurrent dependence
Losses (Ipeak/Ic)n. Losses are similar for
co-woun u an
Stainless. ForIpeak/Ic < 0.4, n ~
. .
Consistent with
ferromagnetic Ni-W
ForIpeak/Ic > 0.4, n ~ 2.
Eddy or coupling
mec an sm
17 Managed by UT-Battellefor the Department of Energy
17
-
7/29/2019 6 AP HTS Transformer Technology
18/25
Losses in HTS/Cu coil varied as square of
fre uenc and were tem erature inde endent. Dividing ac loss by square
of frequency collapses the.
Loss proportional to squareof the frequency alsosuggests coupling or eddymec an sm.
Very l itt le change in losswhen temperature is lowered
rom o sugges smost of loss from Cu or HTSsubstrate.
HTS/SS coil will et similar
18 Managed by UT-Battellefor the Department of Energy
18Presentation_name
tests.
-
7/29/2019 6 AP HTS Transformer Technology
19/25
Losses are higher at the coil ends
Each VT pair covers 2 discs.
19 Managed by UT-Battellefor the Department of Energy
19
a a e s a en s ncrease osses.
-
7/29/2019 6 AP HTS Transformer Technology
20/25
Insulation studies for 550 kV BIL
. Similar 350-kV BIL coi l
passed all tests in FY2008Flashover
New WES Test Coil
Standard WES designpressboard structure
Copper conductor withWES polymerinsulation
LVHV
LV & HV disc windings
HV Tests in LN in Fall2009
Bushin Test
Commercial 650 kVBIL bushingsuccessfully testedshor t-term in FY09
Long-term testplanned for smaller28-kV model
20 Managed by UT-Battellefor the Department of Energy
20
-
7/29/2019 6 AP HTS Transformer Technology
21/25
Test Results - 550-kV Coil
HV coil was impulsed from topwith bottom & LV coil grounded.
-
1.8 bar absolute to stop boiling.Passed 3 impulse shots at -550 kV
.
Warmed up and un-grounded the
HV coil.Test with ac voltage showed 2.2 pC
partial discharge at 102 kVac.
Passed 1-min withstand at 201
kVac.650-kV impulse tests planned if
fundin available.
21 Managed by UT-Battellefor the Department of Energy
21
-
7/29/2019 6 AP HTS Transformer Technology
22/25
FY 2010 Plans FY 2010 Performance Seek new funding options DOE Smart Grid Regional
Demonstration funding has been
MilestoneYBCO ac loss andIc testing
approved for 28-MVA FCL unit.
Carried out further Ic and ac loss testson YBCO sample coils with co-wound
Carry out further dielectrictesting
.
New 115 KV/550 kV BIL coil passed550kV impulse / 200 kV withstand;
long-term bushing tests started.es one ompos e ewar
testing and procurement
Modify WES transformer
Long-term tests on small open-topdewar completed successfully; newprocurement under consideration.
WES ro rams are now in use for HTS
design programs for HTS Begin 5/7-MVA single-phase
prototype substation
unit designs. Replaced by new 28-MVA FCL unit
project.
22 Managed by UT-Battellefor the Department of Energy
22
-
7/29/2019 6 AP HTS Transformer Technology
23/25
Technology Transfer, Collaborations
New collaboration with SuperPower and SCE on a Smart Gridproposal for fault current limiting transformers has receivedDOE funding approval.
Team possesses strong complementary abili ties in research,engineering, manufacturing, & utility operation.
. ,2X WES to ORNL, Smart Grid FCL transformer team meetingsat WES and SP. Communication several t imes a week by phoneand E-mail.
Team is working with suppliers to develop dewars and qualifybushings. A 650-kV commercial bushing was used for impulse
Paper on composite dewar was presented at 2009 CEC/ICMC.
23 Managed by UT-Battellefor the Department of Energy
23
Applied Superconductivity Conference.
-
7/29/2019 6 AP HTS Transformer Technology
24/25
FY 2011 Plans
Su ort 28-MVA FCL unit conce tual desi n and en ineerinanalysis.
Cryogenic, electrical, mechanical issues
Support detail design of single-phase Alpha-1 unit with
Qualify YBCO materials for the reference design.Support SuperPower and WES in specification and
roduction of HTS FCL conductor laminated to a resist ivemetallic strip
Test sample coils with SP conductor wound by WES in
subcooled liquid nitrogen: -multiple-tape coils
Critical current and stability under operating conditions
Fault current handling, recovery, and load restoration after
Address Technology Issues.
Continue long-term bushing tests in LN.
24 Managed by UT-Battellefor the Department of Energy
24
of single-phase test dewar for proof of concept.
-
7/29/2019 6 AP HTS Transformer Technology
25/25
WES and ORNL continue to be committed
to the development of HTS transformers.
We welcome the
artici ation of
SuperPower
and SCE!
QUESTIONS?
25 Managed by UT-Battellefor the Department of Energy
25