5 th Edition Regional Road Impact Fee Update Capital Improvements Advisory Committee July 18, 2019

Transcript of 5th Edition Regional Road Impact Fee Update › wp-content › uploads › 2019 › 07 ›...

Page 1: 5th Edition Regional Road Impact Fee Update › wp-content › uploads › 2019 › 07 › 20119-07-1… · NORTH Prater Way @ Lillard Dr Intersection Improvements - Complete NORTH

5th Edition Regional Road Impact FeeUpdate

Capital Improvements Advisory CommitteeJuly 18, 2019

Page 2: 5th Edition Regional Road Impact Fee Update › wp-content › uploads › 2019 › 07 › 20119-07-1… · NORTH Prater Way @ Lillard Dr Intersection Improvements - Complete NORTH

5th Edition RRIF Capital Improvement Plan

Sparks Area

Page 3: 5th Edition Regional Road Impact Fee Update › wp-content › uploads › 2019 › 07 › 20119-07-1… · NORTH Prater Way @ Lillard Dr Intersection Improvements - Complete NORTH

SA Roadway Limits Description

NORTH 4th St/Prater Way (Multimodal) I-80 to Vista BlvdMultimodal Improvements and Bus Rapid Transit - Complete

NORTH La Posada Dr Roundabout @ Cordoba BlvdIntersection Improvements – Under design/ROW acquisition (City of Sparks)

NORTH Oddie Blvd/Wells Ave (Multimodal) US 395 to Pyramid Way - Phase 1 Multimodal Improvements - Under Design

NORTH Prater Way @ Lillard Dr Intersection Improvements - Complete

NORTH Pyramid Hwy @ McCarran Blvd Intersection Improvements - Complete

NORTH Sparks Blvd (4 to 6 lanes) I-80 to Baring Blvd Widen from 4 to 6 lanes; Multimodal Improvements - Scoping

SOUTH 4th St/Prater Way (Multimodal) Keystone Ave to I-80 Multimodal Improvements and Bus Rapid Transit - Complete

SOUTH Kietzke Ln (Multimodal) Virginia St to Galletti Way Multimodal Improvements - Under Construction (NDOT)

SOUTH McCarran Blvd (4 to 6 lanes) Mira Loma Dr to Greg St Widen from 4 to 6 lanes; Multimodal Improvements - Complete

SOUTH SouthEast Connector (6 lanes) South Meadows Pkwy to Greg St New 6 lane roadway - Complete

SOUTH Sparks Blvd (4 to 6 lanes) Greg St to I-80 Widen from 4 to 6 lanes - Scoping

5th Ed RRIF CIP – Sparks Area

Page 4: 5th Edition Regional Road Impact Fee Update › wp-content › uploads › 2019 › 07 › 20119-07-1… · NORTH Prater Way @ Lillard Dr Intersection Improvements - Complete NORTH

Roadway Improvements 1996-2019

Regional Road Capacity Improvements through the

RRIF Program

4

Capacity Relief Projects 1996 - 2019

$ 204 M Developer Built

$ 95 M RTC Built RRIF Revenue

$ 299 M Capacity Improvements